Sie sind auf Seite 1von 7

PROCEEDINGS OF INTERNATIONAL SYMPOSIUM ON GEOTECHNICAL ASPECTS OF UNDERGROUND CONSTRUCTION IN SOFT

GROUND IS-TOKYO99 / JAPAN 7 19-21 JULY 1999

Design of Bored Tunnel Linings Installed within Partially Excavated Cut & Cover Station Boxes

Dr. Friedrich Prinzl


Geoconsult Consulting Engineers, Salzburg, Austria

Alexandre R.A. Gomes


Geoconsult Consulting Engineers, Salzburg, Austria

ABSTRACT: According to the construction programme of the MRTA ISP Underground Structures North, in
Bangkok, Thailand, four cut & cover station boxes will be tunnelled through by earth-pressure-balance
shield machines. The excavation works inside these stations will be in different stages of progress when the
temporary precast concrete tunnel linings are installed. The tunnels will be used for construction operational
works, such as the transport of muck from the excavation face, and the lining removed when the excavation
within the station is finalised. For the design of the temporary precast concrete tunnel linings, a detailed
finite difference analysis was carried out to assess the interaction between the tunnel linings, the soil and
diaphragm walls as the excavation within the station proceeds. The paper outlines the criteria utilised in the
analysis and summarises the relevant conclusions obtained from the assessment.

1. INTRODUCTION

The Initial System Project (ISP) Underground


Structures, North Contract, is the northern section
of the Blue Line, which is the first stage of the
major underground mass rapid transit system
being implemented by the Metropolitan Rapid
Transit Authority (MRTA) in Bangkok, Thailand.
In this contract, nine cut & cover station boxes
will be connected by twin single track bored
tunnels in a total length of about 16 km.
Owing to the construction schedule, the shield
machines will drive through four cut & cover
station boxes after the installation of the
diaphragm walls and at different stages of station
excavation. A temporary tunnel will be installed
and removed after the excavation inside the
station is finalised.
Figure 1 shows a section through a typical
station box, after the installation of the tunnel
linings.
The excavation inside the station will cause a
continuous change in the ground stresses around
the tunnels. Vertical loads will decrease whilst the
horizontal loads will increase with the passive
earth pressure.
The magnitude of the stresses required a
detailed modelling of the ground-tunnel
diaphragm wall interaction with respect to the
tunnel lining section forces and overall lining
stability. Figure 1 Typical section through a station box
2. DESCRIPTION OF THE STRUCTURES station will penetrate the stiff clay and the
underlying sand layer.
2.1 Bored Tunnel Precast Concrete Lining A section through a typical station box,
including the soil profile and the piezometric
The temporary tunnel lining consists of precast profile, is shown in Figure 1. Soil Parameters are
concrete rings of six segments plus one keystone. shown in Table1.
The nominal inner diameter is 5700 mm and the
segment thickness is 300 mm. The design strength 4. GROUND-STRUCTURE MODELLING
of the segments is 40MPa.
Segments will be installed in a staggered The two-dimensional explicit finite difference
arrangement and will be connected in longitudinal analysis (FLAC code, Cundall et al 1993) was
and radial direction by curved steel bolts. used for the modelling of the interaction between
The top of the bored tunnel linings will be soil and structure. With this method, a complete
generally located at approximately 14.5m below modelling of the structure and ground, including
the ground surface. stress and strain distribution in the ground,
deformation and section forces of the lining was
2.2 Other Structural Elements possible.

The cut & cover station boxes will be typically 4.1 Ground Modelling
200 m long and 23 m wide. Retaining walls
consist of 1.0m thick diaphragm walls. The toe The constitutive model was based on an ideal
level of the walls will be slightly different for each elasto-plastic (Mohr-Coloumb) failure criterion.
station, ranging from 32.5m to a maximum depth Regarding stress conditions for the design of
of 37.5m. the tunnel lining, full ground stresses were used.
The construction will follow a top-down Stress-release (ground relaxation) due to tunnel
excavation method with the bracing support excavation was neglected as preliminary
provided by the installation of temporary steel investigation had shown that it has minor
struts and the definitive concrete slabs. The influence due to the particular load conditions.
stations will have a roof, a retail, a concourse and Considering that the interaction of the tunnels
a base concrete slab. with the walls will occur in short-term conditions,
Steel arch supports, consisting of H joists and undrained parameters were assumed for the
longitudinal stiffeners, were also considered for cohesive soil layers. The effect of ground water
strengthening of the precast concrete lining at flow and consolidation was not considered in the
critical excavation stages. model.
Strength and deformation soil parameters were
3. GEOTECHNICAL CONDITIONS assumed isotropic and defined as a function of the
depth, as shown in the Table 1 and Equations (1)
Soil conditions correspond to the typical to (3).
Bangkok subsoil. It is constituted of a first layer of
man made ground of about 2.5m, followed by the Table 1. Soil parameters
soft clay layer 9 to 15m thick and the stiff clay
SOIL LAYERS
layer with thickness ranging from 6 to 14m. PARAMETER MADE
Below these clay layers is the Bangkok aquifer, GROUND
SOFT CLAY STIFF CLAY SAND
which is constituted of dense to very dense sand Cu [kPa] - (1) (2) -
interlayered by thin layers and lenses of stiff to E'c (1.0%)* [kPa] 20000 200Cu 350Cu 2000N60
hard clays. E'c (0.1%)* [kPa] - 430Cu 850Cu 2500N60
Regarding ground water conditions, deep well E'r (1.0%)* [kPa] - 3E'c 2E'c 3E'c
pumping has led to a drop of the water pressure of Eu,c (1.0%)* [kPa] - 225Cu 400Cu -
Eu,c (0.1%)* [kPa] - 500Cu 1000Cu -
the various aquifers and an under drainage of the Eu,r (1.0%)* [kPa] - 3Eu,c 2Eu,c
clay layers. The ground water level of the ' [-] 0.30 0.30 0.30 0.25
Bangkok aquifer, which was originally at the [-] 0.50 0.50 0.50 0.50
ground surface, has dropped by more than 20m. k'0 [-] 0.75 0.75 0.65 0.50
The present reference water table along the k0 [-] 1.00 1.00 1.00 -
* Correspondent shear strains
contract alignment is about 23.0m below the
surface. Long-term monitoring shows that this Cu 2 Dp 5 (15 Cu 50) (1)
water table is consistent for already several years. (2)
Cu 50 7.8(15 Dp )
Bored tunnels will be mainly located in the stiff
clay layer whereas the diaphragm wall of the
N 60 20 0.78(16 Dp ) (3)
Where: To avoid an unrealistic heave and to consider
Cuundrained shear strength (kPa) the elastic behaviour of the ground due to the
N60Standard Penetration Test Value unloading from the tunnel excavation, an
Ec / Eu,cdrained / undrained Youngs modulus unloading Youngs modulus (correspondent to 1%
for loading-reloading (MPa) shear strain) was used for the area below the
Er / Eu,rdrained / undrained Youngs modulus tunnel invert.
for unloading (MPa) The Stiffness-Shear Strain Model is shown in
drained / undrained Poissons ratio Figure 3.
ko / kodrained / undrained lateral earth pressure
coefficient
Dpdepth with relation to the ground surface level
(m).

The standard ground model used for the design


of station retaining walls and tunnels made use of
different stiffness parameters. For these analyses,
stiffness correspondent to 0.1 and 1.0% shear
strains were applied for the retaining wall design
and tunnel design, respectively. The assumption is
accordance to the typical range of strains involved
in the construction of the respective structures.
Figure 2 shows the form of the relationship
between ground stiffness and shear strains and the
approximate range of strains associated with the
construction of the structures.

Figure 3 Stiffness-Shear Strain Model.

4.2 Modelling of the Structural Elements

The diaphragm wall was modelled by


continuum elements with an ideal linear elastic
behaviour. The interaction between the walls and
the adjacent soil was simulated by interface
elements (springs) in normal and tangential
direction.
Figure 2 Stiffness-shear strain relationship by The normal springs were defined as very stiff so
Menzies (1997) that the transfer of forces between the soil and the
wall would be controlled by their relative
stiffness. Tangential (shear) parameters were
For the assessment of the interaction between defined by the soil cohesion and friction angle
the tunnels and the diaphragm walls, a combined according to the geotechnical parameters.
ground model was used. Ground stiffness Permanent concrete slabs and temporary steel
correspondent to 0.1% shear strain was generally props were simulated by compression-only beam
applied to the model and the higher shear strain elements connected to the diaphragm wall grid
associated with the tunnel construction was points.
considered by the definition of a zone of larger The steel arch support used for the
strains (1.0%) within a distance of approximately strengthening of the tunnel lining was simulated
3.0m measured radially from the periphery of the by beam elements with the correspondent flexural
tunnel linings. At this distance, shear strains due and axial stiffness per linear metre.
to the tunnel construction will already be reduced
to less than 0.1% shear strains (Prinzl and Gomes
1998).
4.3 Bored Tunnel Precast Concrete Lining for the assessment of the lining overall stability
under the changing load conditions.
Two different approaches were used for the Since the effect of the longitudinal bolts and
modelling of the precast concrete tunnel lining friction between the rings were considered, this
structural behaviour. These models were applied model should provide a worst-case stability
in dependence of the purpose of the assessment, assessment.
i.e., for the assessment of the section forces in the
lining (Structural Design) or the analysis of the
overall lining stability (Stability Analysis).

4.3.1 Structural Design

The assessment of section forces for the design


of the temporary precast concrete lining was
carried out with the assumption of a continuous
lining of beam elements with reduced lining Figure 4 Detail of the longitudinal joint between the
flexural stiffness. segments
The decrease in the lining flexural stiffness is
caused by the joints and their reduced lining 5. ANALYSIS AND DESIGN
thickness. The reduced moment of inertia can be
back calculated from the number of segments per 5.1 Analysis Cases and Construction programme
ring (excluding the key-stone) and the moments of
inertia at the joint and at the standard lining According to the construction programme,
section in accordance to Muir Wood, 1975. bored tunnels will be driven through the station
The results obtained from this assumption, boxes when the excavation works are in different
which was the basic approach used for the design stages. The timing of bored tunnel drive through
of the tunnel linings along the route, provided the the stations can be affected by changes in the
critical section forces for the structural design of construction programme during the execution of
the tunnel lining at station sections. the works.
The detailed methodology used for the As to cope with these conditions, four different
structural design of the precast concrete tunnel scenarios were analysed with regard to the time of
linings is described by Prinzl and Gomes (1999). the passage of the bored tunnels and lining
installation as shown in Table 2:
4.3.2 Stability Analysis
Table 2. Analysis Cases - Percentage of excavation
For the assessment of the overall lining
stability, the lining was simulated by means of % of excavation with respect to the distance
continuum elements with detailed consideration of Analysis
of the tunnel top from the ground surface
the geometry and the layout of segments and Cases
level
joints, as shown in Figure 4. a 0.0%
The precast concrete tunnel lining was defined b 16%
as a very dense radial grid with interface elements c 29%
at the joints. A linear elastic behaviour was d 65%
assumed, with exception of the areas close to the * The distance of tunnel top to the ground surface level
radial joints, where the Mohr-Coulumb failure is approximately 14.5m
criterion was applied to simulate the possible completed at the moment of lining installation
plastic behaviour of the joints.
The effect of the radial connecting bolts, which As an additional analysis, the installation of
connects the segments of the rings, were simulated steel arch supports inside the precast concrete
lining was also considered to ensure the lining
by tension-only cable elements.
overall stability at critical stages of excavation.
The boundary between segments and ground Excavation and constructions steps were
was established by interface elements, which detailed simulated with the finite difference
should allow a quasi friction-free movement of the analysis. For illustration purposes, the main
tunnel lining. construction stages for the Lat Phrao station are
This model, which is more flexile than the shown in Figure 5.
continuous lining previously described, was used
yielding of the radial connections bolts. The
general criteria for the definition of critical lining
deformations are shown in Figure 6.

Figure 5 Main construction stages of the Lat Phrao


Station Figure 6 General criteria for the definition of
critical lining deformations

5.2 Design of the Precast Concrete Lining 6. RESULTS AND CONCLUSIONS

The following criteria was used for the For illustration purposes, the results obtained
assessment of the lining performance: from the analysis of lining section forces at the
Lat Phrao station is presented.
5.2.1 Structural Design
6.1.1 Structural Design
Segments were designed for the ultimate limit
state in accordance with the BS 8810 based on the Figure 7 shows a plot of the required
results obtained from the beam model with reinforcement (ReqReinf) normalised with the
continuous lining and reduced lining flexural Standard Lining Reinforcement (StandReinf) in
stiffness. relation to the excavation depth (He) inside the
Due to the temporary character of the lining, the station normalised with the distance from the
structural capacity was checked for a reduced load tunnel top to the ground surface (Ho).
factor (1.2) and reduced partial safety factors for
the materials (1.3 and 1.05 for the concrete and
steel respectively)
Serviceability limit states, such as allowable
crack widths, were not considered as a criterion
for the lining design.

5.2.2 Stability Analysis

Of relevance for the analysis of the tunnel lining


stability, was the relative displacement between
segments and the yielding of the radial connection
bolts, which could indicate likely unstable joints.
It is important to notice that the results of the
analysis based on the continuum elements shall be
understood as indicative only, as it does not Figure 7 Normalised required reinforcement
consider the stiffening effect of the friction (ReqReinf/StandReinf) versus Normalised excavation
between the adjacent rings, the longitudinal depth (He/Ho).
connection bolts and the staggered lining
arrangement. According to the results, the earlier the tunnel
As a general criteria, the deformations of the is installed with respect to the progress of the
lining were considered to become critical when excavation works inside the station, the larger will
the maximum relative displacement between be the stresses on the tunnel lining. This situation
adjacent segments would achieve values higher will occur due to the redistribution of stresses
than 10mm, which corresponds to the gap between during the station excavation, which are partially
the bolts and the bolt holes, and the start of transferred to the tunnel lining.
Critical section forces in the lining (maximum earlier stage of excavation. Results show that the
required reinforcement) will occur at a He/Ho of stress released by the tunnel excavation does not
approximately 1.0 (top of the tunnel) decrease considerably the stresses in the tunnel
lining at the final stages of excavation.
6.1.2 Stability Analysis Further, the installation of steel arch supports
when the ration He/Ho achieved 0.6 proved to be a
Regarding lining stability, critical conditions satisfactory solution for the increase of the tunnel
(relative segment displacements higher than lining stability and the limitation of the required
10mm and bolt yielding) occurred generally for a reinforcement below the standard lining
He/Ho of approximately 0.8 (80% of the tunnel reinforcement. For the fulfilment of this purpose,
cover excavated). a minimum of one arch per concrete ring had to be
It is also important to notice that although installed.
section forces and lining displacements obtained As a result of this analysis, an extensive
from the two different structural models were of monitoring programme was established for the
different order, they followed the same basic control of the actual lining behaviour during the
patterns as shown by the moment distributions excavation works in the stations. The
shown in Figures 7 and 8. observational method shall provide information
for the back-analysis of the tunnel lining and
allow the establishment of the actual necessity of
installing the strengthening steel arch supports.
The monitoring programme will include
convergence measurements, strain gauges for
measurement of strains at the lining
reinforcement rebars and at the steel connection
bolts, and joint gauges for the monitoring of the
joint widths and rotation.

Figure 8 Continuous Lining (Beam Elements) -


Moment Distribution at Stage X

Figure 10 Steel arch support for lining strengthening

7. ACKNOWLEDGEMENTS

The authors would like to express their


gratitude to the Metropolitan Rapid Transit
Authority (MRTA), the ION Joint Venture and
Figure 9 Segmented Lining (Continuum Elements) - Ove Arup and Partners for the possibility of
Moment Distribution at Stage X publishing this paper.

6.1.3 Additional Analyses


8. REFERENCES
The effect of the stress released by the ground
relaxation due to the closure of the shield tail void Cundall P.A., Coetze M.J., Hart R.D., Varona
was also analysed and shown to be of less P.M. (1993) Flac Users Manual. Itasca
relevance for the lining design than the effect Consulting Group. U.S.A.
induced by the installation of the lining in an
Menzies B. (1997). Applying modern measures.
Ground Engineering pp 22-23.
Muir Wood A.M. (1975). The circular tunnel in
elastic ground. Geotechnique 25, No. 1.
Prinzl F. and Gomes A.R.A (1998). The effect of
the non-linear relationship between ground
stiffness and shear strains in the design of
tunnel linings (internal calculations). Not
published
Prinzl F. and Gomes A.R.A (1999). Structural
Design of Precast Concrete Linings for Bored
Tunnels Example from the Design of an
Urban Mass Rapid Transit System. 10th
Australian Tunnelling Conference 1999,
Melbourne VIC, Australia.

Das könnte Ihnen auch gefallen