Sie sind auf Seite 1von 17

EXPLOTACION DE GLORY HOLE

PLANEAMIENTO SEMANAL

SEMANA 23
03 09 de Junio, 2016
IDS
Consumo de explosivos

CANTIDAD TOTAL DE EXPLOSIVO


EMULSION GASIFICADA SAN-G

FACTOR DE POTENCIA (kg/TM)


EMULEX REAL (kg) 1 1/2"x12"

EMULEX REAL (kg) 4" X 16"

FACTOR DE CARGA (kg/m3)


(m)
(m)

DE TALADRO (Pulg.)

EXAMON REAL (kg)


VOLUMEN (m3)
ALTURA PROMEDIO
N VOLADURA

N TALADROS
BURDEN (m)

ESPACIAMIENTO
RAMPA

BANCO
FECHA

FASE
MES

27/05/2016 5 86 F0_ F3 4294_4318 4.2 4.8 6.90 27613.91 225 5 0 0 11308 0 11308 0.41 0.15

28/05/2016 5 87 Laquia 2.5 3 3.80 622.88 26 4 0 0 0 200 200 0.32 0.12


29/05/2016 5 88 Fase 2 Sur 4294 4.17 4.8 6.90 19255.81 140 5 0 0 8049 0 8049 0.42 0.15
1/06/2016 6 89 Fase 2 Sur 4294 4.17 4.8 6.83 20834.09 268 5 0 0 8447 0 8447 0.41 0.15
Total 6.11 68326.69 5 27804 28004 0.14

Factor de Carga (Kg/m3) Factor de Potencia (Kg/TM)


0.15 0.15 0.15
0.50 0.41 0.42 0.41 0.16
0.14 0.12
0.40 0.32
0.12
0.30 0.10
0.08
0.20 0.06
0.10 0.04
0.02
0.00 0.00
Material aportado (Tn)

TRANSPORTE DE MATERIAL

DESMONTE 17233Tn
18000.0 17121.0
16199.8
16000.0 15330.8
14934.6
14430.6
14000.0 13340.9 13148.4

12000.0

10000.0
TN

8000.0

6000.0

4000.0 3240.0
2400.0 2400.0 2400.0 2400.0 2400.0 2400.0
2000.0
Mineral 2400 Tn
0.0
27/05/2016 28/05/2016 29/05/2016 30/05/2016 31/05/2016 1/06/2016 2/06/2016
Desmonte (Tn) 13340.9 15330.8 17121.0 16199.8 14430.6 13148.4 14934.6
Mineral (Tn) 2400.0 2400.0 2400.0 2400.0 2400.0 3240.0 2400.0
Cumplimiento de extraccin de material (Tn)
Semanal (23)

Tn Material Programado Programado Cumplimiento Cumplimiento


Mineral Total general
Fecha Desmonte Desmonte Mineral Desmonte (%) Mineral (%)
27/05/2016 13,341 2,400 15,741 17,233 2,400 77% 100%
28/05/2016 15,331 2,400 17,731 17,233 2,400 89% 100%
29/05/2016 17,121 2,400 19,521 17,233 2,400 99% 100%
30/05/2016 16,200 2,400 18,600 17,233 2,400 94% 100%
31/05/2016 14,431 2,400 16,831 17,233 2,400 84% 100%
1/06/2016 13,148 3,240 16,388 17,233 2,400 76% 135%
2/06/2016 14,935 2,400 17,335 17,233 2,400 87% 100%
Total general 104,506 17,640 122,146 120,631 16,800 87% 105%

Mensual - Mayo

Programado % Cumplimiento % Cumplimiento


Material Tn
Mineral la Fecha al Mes
Desmonte 443,872 534,000 83% 83%
Mineral 76,331 66,000 116% 116%
Total general 520,202 600,000 87% 87%
Tn Desmonte
600000 20000
17233
18000
500000
16000
14000
400000
12000
Tn

300000 10000
8000
200000
6000
4000
100000
2000
0 0

Fecha

Tn Mineral
90000 2400 2500

80000

70000 2000

60000
1500
50000
Tn

40000
1000
30000

20000 500
10000
0
0 0

Fecha
Rendimiento de Equipos
EXCAVADORAS Tn/hr

MODELO CAT 336 DL CAT 336 DL CAT 336 DL CAT 385


CAPACIDAD 2.4 m3 2.4 m3 2.4 m3 6.0 m3
FECHA AT-PVX EXC-1 AT-PVX EXC-2 AT-PVX EXC-3 AT-PVX EXC-6 Total (Tn/hr)
27/05/2016 298.6 368.9 325.5 - 331.0
28/05/2016 324.8 252.4 382.5 557.5 379.3
29/05/2016 292.7 116.7 97.5 700.7 301.9
30/05/2016 247.2 202.7 - 686.4 378.8
31/05/2016 333.5 223.0 - 655.8 404.1
01/06/2016 - 156.4 370.6 539.8 355.6
02/06/2016 - 221.5 313.7 635.4 390.2
Total (Tn/hr) 299.3 220.2 298.0 629.3 363.0

VOLQUETES
Fecha Tn Tn/hr
27/05/2016 15,740.9 57.3
28/05/2016 17,730.8 57.8
29/05/2016 19,521.0 56.0
30/05/2016 18,599.8 55.0
31/05/2016 16,830.6 56.1
01/06/2016 16,388.4 54.6
02/06/2016 17,334.6 57.8
Total general 122,146.2 56.2
Disponibilidad Mecnica - Excavadoras
D.M. PROMEDIO EXCAVADORAS
N Exc MARCA PROPIETARIO MODELO D. M Promedio UTI Promedio D.M.Programada
Exc 1 CAT 01 PEVOEX 336 D2L 69.58% 75% 85%
Exc 2 CAT 02 PEVOEX 336 D2L 88.00% 80% 85%
Exc 3 CAT 03 YARUSYACAN 336 DL 84.03% 76% 85%
Exc 6 CAT 04 PEVOEX 385 85.00% 82% 85%
PROMEDIO
81.65% 78.25%
REAL
PROMEDIO
85.0% 85.00%
PROGRAMADO

DISPONIBILIDAD DE EXCAVADORAS
REAL VS PROGRAMADA UTILIZACIN PROMEDIO
100.00%
85%
80.00%
60.00% 80%
40.00%
20.00% 75%
0.00%
70%
336 D2L 336 D2L 336 DL 385
336 D2L 336 D2L 336 DL 385
D. M Promedio D.M.Programada
UTI Promedio
Disponibilidad Mecnica Perforadoras

D. M. PROMEDIO PERFORADORAS
N Perf MARCA PROPIETARIO MODELO D. M Promedio UTI Promedio D.M.Programada
Perf 1 SANDVIK PEVOEX DP1500i 72% 74% 85%
Perf 3 ATLAS COPCO CMA ROC L8 84% 80% 85%
Perf 4 SANDVIK PEVOEX DX 800 80% 69% 85%
PROMEDIO REAL 78.67% 74.33%

DISPONIBILIDAD DE PERFORADORAS UTILIZACIN PROMEDIO


REAL VS PROGRAMADA 85%
90% 80%
85%
75%
80%
70%
75%
70% 65%

65% 60%
DP1500i ROC L8 DX 800 DP1500i ROC L8 DX 800

D. M Promedio D.M.Programada UTI Promedio


Disponibilidad Mecnica - Volquetes
DISPONIBILIDAD DE VOLQUETES
N Vol MARCA PLACA PROPIETARIO MODELO D. M Promedio UTI Promedio D.M.Programada
Vol 1 AT-PVX CV-001 D10-745 PEVOEX FMX 81.94% 74.67% 85%
Vol 2 AT-PVX CV-002 D9S-899 PEVOEX FMX 7.71% 80.00% 85%
Vol 3 AT-PVX CV-003 AFP-894 PEVOEX FMX 83.33% 87.21% 85%
Vol 4 AT-PVX CV-004 D1F-731 PEVOEX FMX 83.33% 85.43% 85%
Vol 5 AT-PVX CV-005 D9T-776 PEVOEX FMX 78.47% 82.00% 85%
Vol 6 AT-PVX CV-006 D1H-775 PEVOEX FMX 83.33% 83.67% 85%
Vol 7 AT-PVX CV-007 AEW-719 SAN JUAN DE MILPO FMX 83.33% 87.82% 85%
Vol 8 AT-PVX CV-008 ADX-704 SAN JUAN DE MILPO FMX 83.33% 72.74% 85%
Vol 10 AT-PVX CV-011 D9S-874 PEVOEX FMX 74.17% 84.47% 85%
Vol 11 AT-PVX CV-012 B8V-797 PEVOEX FMX 78.47% 77.09% 85%
Vol 12 AT-PVX CV-015 B3A-843 PEVOEX FMX 80.30% 85.00% 85%
Vol 13 AT-PVX CV-016 C91-895 PEVOEX FMX 83.33% 82.28% 85%
Vol 14 AT-PVX CV-017 D9J-942 PEVOEX FMX 73.20% 84.83% 85%
Vol 15 AT-PVX CV-019 T6A-865 PEVOEX FMX 60.00% 75.00% 85%
Vol 16 AT-PVX CV-021 T5X-939 PEVOEX FMX 83.33% 80.00% 85%
Vol 17 AT-PVX CV-024 D9H-809 PEVOEX FMX 83.33% 79.00% 85%
Vol 18 AT-PVX CV-026 T5Y-804 PEVOEX FMX 83.33% 77.09% 85%
Vol 19 AT-PVX CV-027 ACH-875 PEVOEX FMX 80.56% 86.00% 85%
Vol 20 AT-PVX CV-032 AKL-703 PEVOEX FMX 83.33% 79.00% 85%
Vol 21 AT-PVX CV-033 ALW-740 PEVOEX FMX 83.33% 82.00% 85%
Vol 22 AT-PVX CV-034 ALV-892 PEVOEX FMX 83.33% 83.00% 85%
Vol 23 AT-PVX CV-035 C8O-967 PEVOEX FMX 83.33% 82.00% 85%
Vol 24 AT-PVX CV-036 C9D-705 PEVOEX FMX 72.00% 80.64%
PROMEDIO REAL 77% 81%
PROMEDIO PROGRAMADO 85.0% 85.0%
Disponibilidad Mecnica Equipos Auxiliares

D. M. EQUIPOS AUXILIARES
N Trac MARCA PROPIETARIO MODELO D. M Promedio UTI Promedio D.M.Programada
Trac 1 CAT PEVOEX D8T 80% 82% 85%
Trac 2 KOMATSU PEVOEX D65EX 88% 84% 85%
Trac 3 KOMATSU PEVOEX D65EX 89% 85% 85%
Rod 1 JCB PEVOEX VM-115 53% 51% 85%
Ret 1 JCB PEVOEX 83% 74% 85%
Pic 1 DOOSAN PEVOEX 33% 20% 85%
PROMEDIO REAL 71.06% 66.00%

DISPONIBILIDAD DE EQUIPOS AUXILIARES UTILIZACIN PROMEDIO


REAL VS PROGRAMADA 90%
80%
100% 70%
80% 60%
60% 50%
40%
40% 30%
20% 20%
0% 10%
Trac 1 Trac 2 Trac 3 Rod 1 Ret 1 Pic 1 0%
Trac 1 Trac 2 Trac 3 Rod 1 Ret 1 Pic 1
D. M Promedio D.M.Programada
UTI Promedio
Plano stock de materiales
Plan de perforacin y voladura
Plan de Minado
STOCK DE MATERIALES
DESMONTE (Tn.) MINERAL (Tn.)
TOTAL 128,601 38,823
Plano de Laquia

VOLADURA LA LAQUIA 1+520

CARRETERA A LA LAQUIA
PROGRESIVA
1+440

BRAZO LA LAQUIA 0+090


Plano de Rutas
ORIGEN DESTINO MATERIAL DISTANCIA (Km)
FASE 2S B4294 OP2 MINERAL 0.89
FASE 00 B4294 LA LAQUIA DESMONTE 2.50
FASE 3N B4312 LA LAQUIA DESMONTE 2.25