Beruflich Dokumente
Kultur Dokumente
1 2 3
Iamara Rossi Bulhes , Flavio Augusto Picchi and Ariovaldo Denis Granja
ABSTRACT
This research focuses on the use of concepts and tools of Lean Thinking seeking the implementation of
continuous flow in construction. An exploratory case research approach was used in the work. Such
study was carried out in a construction site of a resort in the northeast region of Brazil. Taking as a ba-
sis literature and successful implementation path used in other industries, a combined analysis was
used, first in value stream level and second in processes level. As result of this research, Value Stream
Maps (VSM) of the execution of the standard apartment was drawn for a sample of services, including
dry wall and ceramic tiling. The maps made possible an organized discussion about the applicability
of important lean concepts, such as: takt time, cell production, etc. Line of Balance, Operator Balance
Charts and Standardized Work Combination Table were analysed to improve flow. As conclusion, the
path of implementation suggested in lean literature and used in several other industries presented in-
teresting potential considering this case study and encourages future studies using and detailing this
approach.
KEY WORDS
Continuous flow, Value stream maps, Operator balance chart, Standardized work combination table
1 PhD student, Architecture and Construction Department, School of Civil Engineering, Architecture and Urban
Design, Univ. of Campinas, Campinas/SP, Brazil, iamara@fec.unicamp.br
2 Professor, Architecture and Construction Department, School of Civil Engineering, Architecture and Urban
Design, and Director, Lean Institute Brazil. Av. Albert Einstein, 951, Caixa Postal 6021, Univ. of Campinas,
Campinas/SP, Brazil, CEP 13084-971, Phone +55 19/3788-2082, fpicchi@fec.unicamp.br
3 Professor, Architecture and Construction Department, School of Civil Engineering, Architecture and Urban
Design. Av. Albert Einstein, 951, Caixa Postal 6021, Univ. of Campinas, Campinas/SP, Brazil, CEP 13084-971,
Phone +55 19/3788-2082, FAX 19/3788-2411, adgranja@fec.unicamp.br
Santos et al. 2002; Ballard and Tommelein 1999), Rother and Shook (2000) point out the impor-
and on tools to support flow, such as production tance of starting in the value stream level (a whole
control (Ballard 2000), mechanisms to pull pro- factory or a whole construction site), and just after
duction (Ballard and Howell, 1998; Tommelein that going into details in processes level (each task
and Li, 1999), visual devices to increase transpar- level), avoiding isolated improvements without a
ency (Formoso and Santos 2002), reduction of the system view. Most implementations, in construc-
cycle time (Ballard 2001; Elfving et al. 2002), tion or even in other industries, start directly ana-
poka-yoke (mistake-proof) devices (Santos and lyzing the process level, with limited results
Powell 1999), batch size reduction (Santos and (Picchi and Granja 2004; Rother 1997).
Powell 2001). This approach has been used successfully by
In spite of all these efforts, the application of several companies in different industries4, and
continuous flow in construction is still understood could be summarized by the following steps:
in a fragmented way (Picchi and Granja 2004), Value Stream Mapping and designing a fu-
resulting in implementation difficulties. In other ture-state value stream map proposing neces-
industries, approaches for integrating continuous sary improvements to reduce waste,
flow achieving with other lean concepts, such as represented by non value-adding activities;
value stream improvement, have helped compa- after that, action plan establishment to guide
nies to obtain better results (Rother and Shook implementation;
2000). Implementation of continuous flow, balanc-
The main objective of this research is to analyse ing workers activities, implementing work
if the approach for lean combination and imple- cells, etc., and establishing pulled production
mentation used in manufacturing has the same were necessary;
potential of usefulness in construction, for achiev- Use of standardized work for the definition
ing continuous flow. of rhythm and sequence;
A case study approach was adopted in this Continuous improvement of standardized
exploratory research, carried out in a project site work by successive kaizens.
in the city of Natal, Brazil. The project is a Resort This approach is supported by some analysis
with 396 rooms, owned by an international group. tools, described below.
The first research phase consisted of data collec-
tion and the second one of results analysis and dis- VALUE-STREAM MAPPING (VSM)
cussion. Data was collected by interactions with
job site managers and took as a framework the The VSM shows graphically every step involved
path proposed by Rother and Shook (2000). The in the material and information flows from orders
suggestions were partially implemented, due to reception to delivery. Generally, two maps are
project phase restrictions, but important insights conceived: one current-state VSM, representing
could be obtained. Based on that, a preliminary present value stream and its wastes, and a future-
analysis model for achieving continuous flow in state VSM, representing the design of improve-
construction is proposed. ments in the value stream, towards lean imple-
mentation. Rother and Shook (2000) list eight key
A COMBINED ANALYSIS OF VALUE questions that drive the current state analysis
STREAM LEVEL AND PROCESS LEVEL towards a lean future state.
Following concepts, among others, are useful to
Womack and Jones (1996) have proposed five understand VSM data (Lei 2003; Rother and
principles for Lean Thinking: value, value stream, Shook 2000; Rother and Harris 2002): Cycle
flow, pull, perfection. In fact, these principles are Time (C/T): measures how often a part or produc-
presented by the authors as steps of implementa- tion actually is completed by a process, and Takt
tion: understanding customer requirements, ana- Time (TT): related to the rhythm of consumption,
lysing waste through all steps, implementing flow or customer demand.
and pull and improving continuously. This
approach is detailed by Rother and Shook (2000), OPERATOR BALANCE CHART (OBC)
who describe value stream mapping as a primary
tool for planning lean transformation. Rother and The operator balance chart is a graphic tool that
Harris (2002) complement this approach present- assists the creation of continuous flow in a multi-
ing tools for work cell design, enabling step, multi-operator process by distributing opera-
continuous flow.
4 Several cases are described in literature, for example in www.lean.org; some of the authors of this paper have
experienced this approach in different industries.
tor work elements in relation to takt time (Lei Although generally not used in manufacturing,
2003, p.53). the Line of Balance (LOB) is regarded as an
An OBC uses vertical bars to represent the total useful tool in the value stream level, helping the
amount of work each operator must do compared analysis of construction tasks rhythm and interfer-
to takt time. Creating an OBC helps the critical ences, and aiming at continuous flow (Seppnen
task of redistributing work elements among oper- and Junnone 2004; Kenley 2004; Seppnen and
ators. This is essential for minimizing the number Kankainen 2004).
of operators needed by making the amount of
work for each operator nearly equal to, but CASE STUDY RESULTS
slightly less than takt time (Lei 2003). Rother and
Harris (2002) give examples of practical use of The case study data collection was developed in a
this tool to improve work design. three weeks interaction of researchers with the job
site managers. During this time, the main related
STANDARDIZED WORK COMBINATION TABLE lean concepts and tools, presented previously,
(SWCT) were introduced to the team, and tools were
applied, starting with a value stream analysis. The
This form shows the combination of manual work structure and external masonry were almost fin-
time, walk time and machine processing time for ished at that time and the work focused on the
each operator in a production sequence. It pro- future tasks from that stage to the end of
vides more details and is a more precise process construction.
design tool than the OBC. This table is a support The starting point of analysis was the existing
to Standardized Work, a key concept in lean computer based long term plan, elaborated by the
thinking, based on three elements: 1) takt time; companys planning department. Several prob-
2) the precise work sequence in which an opera- lems could be identified, such as tasks interfer-
tor performs tasks within takt time; 3) the stan- ence and restrictions due to design and materials
dard inventory (Lei 2003). delivery. The environment was requiring several
stabilization actions, taken by the managers and
OTHER TOOLS not focused on by this research. The proposal was
to analyze lean tools implementation, aiming con-
Several other tools can be used to support the tinuous flow creation, as part of the overall
analyses, most of them described by Lei (2003), improvement effort..
Rother and Harris (2002) and other authors.
Line of balance - LOB (block C)
7 46
45
44
43
6 42
41
40
39
38
5 37
36
35
34
33
4 32
31
30
29
28
27
26
25
3 24
23
22
21
20
19
18
17
16
15
2 14
13
12
11
10
9
8
7
1 6
5
4 Loop 1
3
2 Loop 2
1
19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
The pathway described previously was tested, visual analysis; b) definition of work pace for
directing the analysis from value stream level to each task; c) identification of groups of tasks that
process level, using in a logical sequence the fol- occur in a same project phase and that could be
lowing tools: LOB, VSM, OBC, SWCT. The clustered for flow implementation.
VSM was drawn in two levels: whole project and
group of tasks. VALUE-STREAM MAP (VSM)PROJECT
Production schedule
Suppliers Control Customer
Duration of project:
17 months
20.000 m2
Number of
Apartment: 397
I I I I I I I
Ceramics Aluminum Wood Wares and Delivery
Dry Wall Paint Cleaning
I tiling I doors I I doors I metals I
I
2 29d 4 33d 1 11d 1 1 1 8d 1 8d 1
C/T = 70,4 h C/T = 61,6 h C/T=1,5 h C/T=1,5 h C/T=1,5 h C/T=1,5 h C/T=1,5 h C/T=1,5 h
Batch =1 ap Batch =1 ap Batch =1 ap Batch =1 ap Batch =1 ap Batch=1 ap Batch=1 ap Batch=1 ap
1 shift 1shift 1shift 1 shift 1 shift 1 shift 1 shift 1 shift
Loop 1
Loop 2
141 h
61,6 h 1,5h 1,5h 1,5h 1,5h 1,5h 1,5h
70,4 h
194d
11d 8d 8d
29d 33d
From Figure 1 one can observe a total available time of 18 days (8,8h eachbrazilians
1. What is the takt time?
day work) or 158,4 h, to produce 46 apartments. Takt time is 3,44 h for each apartment.
2. Will finished goods be built to One option would be keeping an established number of apartments with dry-wall
replenish a supermarket from which finished, and another one would be prepared just if next process demands
customers pull, or will them be built (supermarket); the option adopted was to build and deliver to next process execution
and directly shipped to clients? immediately.
3. Where to use continuous flows To achieve continuous flow two work cells were proposed, for the execution of tasks
process? Positioning + Dry wall 1, and studs installation + Dry Wall 2.
4. Where pulled systems should be A supermarket was planned between processes and suppliers, regulating materials
used? delivery on demand.
Just the first cell (positioning + dry wall 1) should be planned; cell 2 (studs+dry wall 2)
5. At what single point will production
would work in a FIFO (first in first out) with a maximum of two apartments between
be scheduled?
cells.
6. How to level the production mix at This question is related to different products mix. In construction a parallel would be
the pacemaker process? different size apartments mixing, planned by production control.
ning of the project. The total duration of the trated in a period of time, considering each apart-
project was seventeen months. ment execution (Figure 2). In fact these task
The discussion of a whole project future state grouping is one improvement obtained in the
was not an objective of this research, but should analysis of LOB and VSM in the project level,
be the following step after the current state draw- seeking continuous flow. Most projects planned
ing. According to job sites priorities, the future in a traditional way do not show clearly these
state was drawn just for loops 1 and 2, identified groups, presenting tasks with different rhythms
in Figure 1 and 2. and interferences (Seppnen. and Junnone 2004;
This representation shows us: a) the sense of Kenley 2004; Seppnen and Kankainen 2004).
wastes in the form of waiting, inventories, etc., for Group of tasks level VSMs were drawn for both
a typical apartment; b) cycle times for each activ- loops 1 and 2. As an example, the analysis for loop
ity, making clear eventual unbalanced work; c) 1 (dry-wall) is presented in Figure 3. The dry wall
Total lead time versus total processing time; d) installation was divided into following sub-pro-
The relationship between information flow and cesses: positioning, dry-wall 1 (structure, floor
materials flow, showing opportunities for the perforations for services, first side closing), studs
elimination of several programming points, which installation, dry-wall 2 (second side closing and
generally generate conflict and flow interruptions. finishing). Current State map shows us four
sequential processes, each one with a day of work
VALUE-STREAM MAP (VSM)GROUP OF TASKS (8,8h) duration, and a waiting of 4 days between
Dry-wall 1 and Studs installing. The total process
Line of Balance (Figure 1) shows us groups of time (PT) is 4 days and total lead time (LT) 8 days.
tasks that happen in sequence and that are concen- For the elaboration of the future VSM the eight
key questions proposed by Rother and Shook
Suppliers
PC (2000) have been used. The discussion referring
schedule
1 2 4d
inside cell between combined activities resulted
2 2
LT=8 d
4d apartments. This level of inventory reflects uncer-
Figure 3: Current State Mapprocess level - Dry Wall tainties evaluated by job site managers, such as
Suppliers
and optimize operators time. This analysis is sup-
PC schedule
Customers
ported by the OBC (Rother and Harris 2002). To
exemplify this application, ceramic tiling (loop 2)
Dry Wall 1 Dry Wall 2 is discussed; previously, a value stream map in
Setting
Positions DW1
Max. 2 apt
Studs
DW2
group of tasks was drawn, not presented in this
FIFO
3
installing
4
paper.
C/T = 8,8 h C/T = 8,8 h
Before OBC analysis in a traditional way, the
Batch=1 ap
1 shift
Batch =1 ap
1 shift
job site managers had planned to use 6 teams of 3
workers each working in parallel, to accomplish
8,8 h 8,8 h PT= 2d the 46 apartments of Block C in 48 days as
2d
LT=4 d
required in the LOB (Figure 1). Data was gathered
Figure 4: Future-state map of the Dry Wall.
interviewing the foreman, collecting times for
ceramic tiling sub-tasks, occurred during the exe-
cution of a pilot apartment. The total work content
positioning changes, and could be reduced in the was 69 hs (Figure 5a), representing the total sum
future, improving reliability of design and previ- of work elements as if one apartment were done
ous works. The use of just in time, represented by by just one worker. In this Figure the sub-tasks
a supermarket between site and suppliers, could included in the ceramic tiling can be seen, as bath-
reduce the inventory of raw materials, not quanti- room floor, bathroom wall, etc. Figure 5b shows
fied in current state map. The final lead time (LT) the division of work among 3 workers, as planned
would be 4 days, against 8 days in current state originally by the foreman.
(Figure 3). OBC is useful to compare workers time to each
Similarly as the application in project level, other and to compare Cycle Time (C/T) against
VSM in the level of group of tasks has brought Takt Time (TT). Takt time can be calculated as:
interesting insights regarding flow creation, in a total available time (48 days x 8.8hs = 422.4 hs)
more detailed scale. The systematic application of divided by the number of apartments (46), result-
the questions directs the use of lean tools, such as ing in a TT of 9.18 hs, meaning the average time to
cell work, pulled system, FIFO, in an integrated deliver one apartments ceramic tiling.
vision. Figure 5b shows us some wastes: a) the division
of work among workers is unbalanced, so some of
OPERATOR BALANCE CHART (OBC) them wait for others; b) The cycle time (34hs) is
much lower than 6xtakt time (55.08hs), so the
After VSM analysis identified opportunities to crews definition was overestimated (in Figure 5b
create flow among tasks, a detailed analysis in the C/T of one team was compared to 6xTT, since 6
process level must be done, in order to balance
61 Bathroom wall
40
45 Balcony floor
C/T = 34 h 34 h
39 30
Bedroom floor and
skirting board
24 h
20
11 h
11
10
Balcony granite details
3 Balcony door-sill
1 Bathroom door-sill
0
1 2 3
Figure 5a: Work content Figure 5b: Operator Balance Chart
Line of Balance
Project Value Stream Map for the whole project present and future
Value Stream
Value Stream Map by groups of tasks present and future
interactions
Group of tasks
Lillrank, P (1995). The transfer of management construction. Proceedings of the 7th Confer-
innovations from Japan. Organization Stud- ence of the International Group for Lean Con-
ies, 16(6) 971989. struction, Berkeley/CA.
Nakagawa, Y & Shimizu, Y. (2004). Toyota Pro- Santos, A. & Powell, J.A. (2001). Reduction of
duction System adopted by building construc- cycle-time through smaller batch sizes in eng-
tion in Japan. Proceedings of the 12th Annual lish and brazilian construction sites. Pro-
Conference of the International Group for ceedings of the CIB World building congress,
Lean Construction,Elsinore, Denmark. Wellington/New Zealand.
OBrien, W.J.; london, K. & Urijhoef, R. (2002). Santos, A., Moser, L. & Tookey, J.E. (2002).
Construction supply chain modeling: a Applying the concept of mobile cell manu-
reseach review and interdisciplinary research facturing on the drywall process. Proceed-
agenda. Proceedings of the 10th Conference ings of the 10th Annual Conference on lean
of the International Group for Lean Construc- construction, Gramado/RS.
tion, Gramado, Brazil. Seppnen, O. & Junnone, J. (2004). Task plan-
Picchi, F.A. & Granja, A. D. (2004). Contruction ning as part of production control. Proceed-
Sites: Using Lean Principles To Seek Broader ings of the 12th Annual Conference of the
Implementations Proceedings of the 12th International Group for Lean Construc-
Annual Conference of the International tion,Elsinore, Denmark.
Group for lean Construction, Elsinore, Seppnen, O. & Kankainen, J. (2004). Empirical
Denmark. Research on Deviations in Production and
Rother, M. (1997). Crossroads: wich way will Current State of Project Control. Proceed-
you turn on the road to lean? in: Liker, J.K. ings of the 12th Annual Conference of the
(Editor) Becoming lean: inside stories of U.S. International Group for Lean Construc-
manufacturers Productivity press. Portland, tion,Elsinore, Denmark.
Oregon, USA. Tommelein, I.D. & Li, A.E.Y. (1999). Just-in-
Rother, M. & Shook, J. (2000). Learning to see. time concrete delivery: mapping alternatives
Brookline, Massachusetts, USA, 100 pp. for vertical supply chain integration. Pro-
Rother, M. & Harris, R. (2002). Creating continu- ceedings of the 7th Annual Conference of the
ous flow. Brookline, Massachusetts, USA, International Group for Lean Construction,
104 pp. Berkeley/CA/USA.
Santos, A. (1999). Application of flow principles Womack, J.P. & Jones, D.T. (1996). Lean think-
in the production management of construction ing: banish waste and create wealth in your
sites. Thesis (Ph.D.), School of Construction corporation. Simon and Schuster, New York.
and Property Management, The University of Womack, J.P. & Jones, D.T. ; Roos, D. (1991).
Salford. The machine that changed the world: the story
Santos, A. & Powell, J. (1999). Potential of of lean production. Harper Perennial, New
poka-yoke devices to reduce variability in York.