Beruflich Dokumente
Kultur Dokumente
DATOS
Longitud: 16 m
Base: 10 m
Patio(Area libre):
l1= 7 m
b1= 5 m
l2= 3.25 m
b2= 5 m
5.00 5.00
3.25
5.75
16.00
7.00
5.05 5.00
10.00
Datos Generales:
Calculo de Predimensionamiento:
1.- reas:
rea Total:
AT= 160 m2
At= 51.25 m2
t= Hpt/20
t= 0.13 m
Lmc= 2*hpt
Lmc= 5.2 m
e= (Lcr.col.)/25
e= 0.15 m
e= 0.2 m
5- rea de columnas(Ac):
t= 0.13 m
a= 0.46154 m
01.00.00.00 ESTRUCTURAS
AT= 160 m2
Profundidad:
Cimiento 0.9 m
Area de cimentacin(Ac):
Tramo 1-7
Tramo A-B
Tramo B - C
Profunidad= 0.9 m
Altura= 0.3 m
Tramo 1-7
A. eje A-A= 2.243 m2
A. eje C-C= 2.4 m2
EJE B-B
TRAMO 2-4= 0.908 m2
TRAMO 4-5= 0.303 m2
TRAMO 6-7= 0.51 m2
EJE A'-A'
EJE 1-1
TRAMO A-B= 0.525 m2
EJE 3-3
TRAMO A-A'= 0.345 m2
TRAMO A'-B= 0.225 m2
EJE 4-4
TRAMO A-B= 0.525 m2
TRAMO B -C= 0.57 m2
EJE 5-5
TRAMO A-B= 0.705 m2
TRAMO B-C= 0.413 m2
EJE 6-6
TRAMO B-C= 0.593 m2
EJE 7-7
TRAMO A-B= 0.728 m2
TRAMO B-C= 0.728 m2
altura= 0.3 m
Longitud:
Tramo 1-7
A. eje A-A- izq.= 14.95 m
A. eje A-A-der.= 14.8 m
A. eje A-A-arib.= 0.15 m
A. eje C-C-izq= 16 m
A. eje C-C-Abaj.= 0.15 m
EJE B-B
EJE A'-A'
EJE 1-1
TRAMO A-B-arrib.= 3.5 m
TRAMO A-B-abaj.= 3.65 m
TRAMO A-B-der.= 0.15 m
EJE 3-3
TRAMO A-A'-arrib.= 2.15 m
TRAMO A-A'-abaj.= 2.15 m
EJE 4-4
TRAMO A-B-arrib.= 3.5 m
TRAMO A-B-abaj.= 3.5 m
TRAMO A-B-der.= 0.15 m
EJE 5-5
TRAMO A-B-arrib.= 4.85 m
TRAMO A-B-abaj.= 4.7 m
EJE 6-6
TRAMO B-C-arrib.= 3.95 m
TRAMO B-C-abaj.= 4.1 m
TRAMO B-C-der.= 0.15 m
TRAMO B-C-izq.= 0.15 m
EJE 7-7
TRAMO A-B-abaj.= 4.85 m
TRAMO A-B-izq.= 0.15 m
Afp= 152.922 m2
COLUMNAS RECTANGULARES
Datos: col. 01
ALTURA(m) 10.8
espesor(m) 0.15
ancho(m) 0.15
N columnas 24
Vol. Col. (m3) 5.832
Datos: Col. 02
ALTURA(m) 2.43
espesor(m) 0.15
ancho(m) 0.15
N columnas 2
Vol. Col. (m3) 0.10935
Encofrado
Primer Piso 11.1555 m2
Segundo Piso 17.8305 m2
Tercer Piso 12.7575 m2
TOTAL 41.7435 m2
0.3
3/4" 2.24 4
9
0.3
0.3
2.24 4
5/8"
3.73
0.3
Peso N
Decripcion/Diagrama
kg/m Elem.
Estrivos Columnas estructura
0.105
0.11
Estrivos Patio
0.105
0.105
01.04.02.00 Vigas
01.04.02.01 Concreto f'c = 210kg/cm2
Vigas
REFERNCIA N VIG. alto(m)
TRAMO A-B 7 0.20
TRAMO B-C 3 0.20
PRIMER TRAMO 1-2 2 0.20
SEGUNDO Y TRAMO 2-3 2 0.20
TERCER PISO TRAMO 3-4 3 0.20
TRAMO 4-5 5 0.20
TRAMO 5-6 4 0.20
TRAMO 6-7 2 0.20
SEGUNDO PISO
2 0.20
TRAMO 2-3
SEGUNDO PISO 1 0.20
2 0.20
TRAMO 3-4
1 0.20
2 0.20
TRAMO 4-5
1 0.20
2 0.20
TRAMO 5-6
1 0.20
2 0.20
TRAMO 6-7
1 0.20
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo A-B
4.9
3/4'' 2.24 4
0.15 0.15
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo B-C
4.95
3/4'' 2.24 4
0.15 0.15
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo 1-7: EJE A-A y B-B
17.1
3/4'' 2.24 4
0.15 0.15
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo A-B
0.125
0.125
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo B-C
0.125
0.125
Peso N
Decripcion/Diagrama
kg/m Elem.
Viga Tramo 1-2
0.125
0.125
Viga Tramo 2-3
0.125
0.125
Viga Tramo 3-4
0.125
0.125
Viga Tramo 4-5
0.125
0.125
Viga Tramo 5-6
0.125
0.125
Viga Tramo 6-7
0.125
0.125
Losa
Numero Area # Lozas
Losa 01 4.465 3
Losa 02 17.625 3
Losa 03 3.978 3
Losa 04 4.44 3
Losa 05 6.177 3
Losa 06 6.895 3
Losa 07 7.326 3
Losa 08 6.177 3
Losa 09 11.387 3
Losa 10 6.178 1
Losa 11 5.209 3
Losa 12 14.591 3
TOTAL=
Peso N
Decripcion/Diagrama
kg/m Elem.
Viguetas Losa 01
0.9 0.9
0.15 0.15 3/4'' 2.24 2
1.15
Viguetas Losa 02
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.95
Viguetas Losa 03
3/4'' 2.24 2
0.9 0.9
0.15 0.15 3/4'' 2.24 2
2.05
Viguetas Losa 04
0.9 0.9
0.15 0.15 3/4'' 2.24 2
2.05
Viguetas Losa 05
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.07
Viguetas Losa 06
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.07
Viguetas Losa 07
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.07
Viguetas Losa 08
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.07
Viguetas Losa 09
3/4'' 2.24 2
0.9 0.9
0.15 0.15 3/4'' 2.24 2
2.62
Viguetas Losa 10
0.9 0.9
0.15 0.15 3/4'' 2.24 2
2.62
Viguetas Losa 11
0.9 0.9
0.15 0.15 3/4'' 2.24 2
2.62
Viguetas Losa 12
0.9 0.9
0.15 0.15 3/4'' 2.24 2
3.53
01.04.04.00 Escalera
01.04.04.01 Concreto f'c = 210kg/cm2
Losa de escalera
TIPO Largo (m) espesor(m) ancho(m)
Larga 4.58 0.15 1.2
2.22 0.15 1.2
En U
1.2 1.15 1.2
Escalones de escalera
TIPO Largo (m) Area (m^2) ancho(m)
Larga 0.02125 1.2
En U 0.02125 1.2
Losa de escalera
TIPO Largo (m) ancho(m) # de veces
Larga 4.58 1.2 1
2.22 1.2 2
En U
1.2 1.2 4
Total=
Escalones de escalera
TIPO altura (m) ancho(m) # de veses
Larga 0.17 1.2 16
En U 0.17 1.2 32
Total=
0.7
1/2'' 2.24 3
0.3
Escalera 1 - Va al 2 piso
Acero positivo 0.2
0.7
0.3
Escalera 1 - Va al 2 piso
Acero positivo 0.2
Escalera 2 - Va al 3 y 4 piso
Acero anclaje
0.7
Escalera 2 - Va al 3 y 4 piso
Acero positivo 1.2
Tramo 1
2.22 1/2'' 2.24 3
0.6
Escalera 2 - Va al 3 y 4 piso
Acero positivo 0.3
Tramo 2
2.22 1/2'' 2.24 3
0.3
1.2
Escalera 2 - Va al 3 y 4 piso
Acero Negativo 0.3
Tramo 1 1.2
0.8 1/2'' 2.24 3
Escalera 2 - Va al 3 y 4 piso
Acero Negativo
Tramo 1
0.8 1/2'' 2.24 3
0.3
1.2
Escalera 2 - Va al 3 y 4 piso
Acero Negativo
Tramo 2 0.3
1/2'' 2.24 3
2.22
Acero de Temperatura
1/2'' 2.24 12
1.2
02.00.00.00 ARQUITECTURA
02.01.00.00 Albaileria
02.01.01.00 Muro de ladrillo asentado de soga e= 0.13
Vigas
altura(m) Largo(m)
0.2 16
0.2 5
0.2 7
0.2 4.85
0.2 5
02.02.02.00 Tarrajeo en Interiores con Cemento-Arena 1:4
Muros
altura(m) Largo(m)
2.4 14.5
2.4 7.08
2.4 13.48
2.4 14.05
2.4 13.15
PRIMER PISO 2.4 18.93
1.5 1.2
1.5 1
1.5 0.7
1.7 1
0.7 0.15
1.7 0.7
2.4 33.83
2.4 4.74
2.4 15.88
2.4 11.84
SEGUNDO PISO
2.4 16.27
1.5 1.2
1.5 2.55
1.7 0.8
2.4 41.05
2.4 18
2.4 34.22
2.4 5.62
1.5 1.2
TERCER PISO
1.7 0.8
1.5 0.97
0.7 0.15
0.9 0.15
1.2 0.15
02.03.00.00 Cielo Raso
02.03.01.00 Cielo Rasos: con cemento - Arena 1:4
Cielo Razo
Numero Area # Lozas
Losa 01 4.465 3
Losa 02 17.625 3
Losa 03 3.978 3
Losa 04 4.44 3
Losa 05 6.177 3
Losa 06 6.895 3
Losa 07 7.326 3
Losa 08 6.177 3
Losa 09 11.387 3
Losa 10 6.178 1
Losa 11 5.209 3
Losa 12 14.591 3
TOTAL=
Area # Habitaciones
Dormitorio 1 16.25 1
Dormitorio 2 11.95 1
Sala 21.85 1
comedor 10.49 1
PRIMER PISO
Cocina 7.43 1
Pasadisos 12.22 1
Cochera 29.1 1
Lavanderia 15.16 1
Dormitorio 1 14.57 1
Dormitorio 2 9.74 1
Sala 15.39 1
SEGUNDO PISO comedor 13.93 1
Cocina 5.54 1
Pasadisos 12.79 1
Lavanderia 6.26 1
Gerencia 14.71 1
Sub Gerencia 8.73 1
Administracion 8.36 1
secretaria 6.35 1
TERECER PISO
Logistica 4.78 1
Oficiana 5.36 1
TERECER PISO
Alamacen 4.05 1
Pasadisos 24.27 1
Total=
PARA MUROS
Area(m^2) # de veces
10.5 1
7.22 1
11.64 1
PRIMER PISO
12.99 1
20.29 1
11.19 1
11.7 1
12.7 1
8.75 1
6.74 1
SEGUNDO PISO
5.18 1
11.1 1
3.6 1
9.6 1
35.8425 1
8.65 1
10 1
TERCER PISO
11.25 1
6.94 1
5.45 1
5.94 2
TOTAL
02.05.02.00 Contrazcalos
PARA MUROS
Area(m^2) # de veces
10.5 1
7.22 1
11.64 1
PRIMER PISO
12.99 1
20.29 1
11.19 1
11.7 1
12.7 1
8.75 1
6.74 1
SEGUNDO PISO
5.18 1
11.1 1
3.6 1
9.6 1
35.8425 1
8.65 1
10 1
TERCER PISO
11.25 1
6.94 1
5.45 1
5.94 2
TOTAL
# puertas
Puerta para Baos 6
Puerta para Dormitorios 4
Puerta para Sala 2
Puerta para Comedor 3
Puerta para Cocina 2
Puerta de entrada al piso 4
Puerta hacia lavanderia 3
Puerta para oficinas 6
TOTAL=
# Ventanas
Ventana para Baos 6
Ventanas para Dormitorios 7
Ventanas para Sala 6
Ventanas para Comedor 4
Ventanas para Cocina 2
Puerta para oficinas 13
TOTAL=
02.07.00.00 VIDRIOS.
02.07.01.01 Vidrios dobles transparentes.
# Ventanas
Ventanas para Dormitorios 7
Ventanas para Sala 6
1
Ventanas para Comedor
3
Ventanas para Cocina 2
2
Ventanas para oficinas
11
# Ventanas
4
Ventana para Baos 1
1
02.08.00.00 PINTURA
02.08.01.00 pintura base 2 capas, blanco: Base y la superficie melon
Pintado interior
altura(m) Largo(m)
2.4 14.5
2.4 7.08
2.4 13.48
2.4 14.05
2.4 13.15
PRIMER PISO 2.4 18.93
1.5 1.2
1.5 1
1.5 0.7
1.7 1
0.7 0.15
1.7 0.7
2.4 33.83
2.4 4.74
2.4 15.88
2.4 11.84
SEGUNDO PISO
SEGUNDO PISO
2.4 16.27
1.5 1.2
1.5 2.55
1.7 0.8
TERCER PISO 2.4 41.05
2.4 18
2.4 34.22
2.4 5.62
1.5 1.2
1.7 0.8
1.5 0.97
0.7 0.15
0.9 0.15
1.2 0.15
Pintado exterior
altura(m) Largo(m)
2.4 7.61
1.5 1.2
2.4 2.5
PRIMER PISO 1.5 1
2.4 1.2
2.4 4.9
2.4 1.75
2.4 4.03
2.4 6.58
1.5 1.2
2.4 0.15
2.4 2.7
SEGUNDO PISO
2.4 1.1
2.4 5.4
1.7 0.8
2.4 2.42
2.4 8.88
1.5 1.2
1.5 0.97
1.7 0.8
TERCER PISO
2.4 2.6
2.4 7
2.4 3.45
1.5 1.2
Pintado exterior vigas
altura(m) Largo(m)
0.2 16
0.2 5
0.2 7
0.2 4.85
0.2 5
Cielo Razo
Numero Area # Lozas
Losa 01 4.465 3
Losa 02 17.625 3
Losa 03 3.978 3
Losa 04 4.44 3
Losa 05 6.177 3
Losa 06 6.895 3
Losa 07 7.326 3
Losa 08 6.177 3
Losa 09 11.387 3
Losa 10 6.178 1
Losa 11 5.209 3
Losa 12 14.591 3
TOTAL=
Niveles N Luminarias
Primer Piso 14
Segundo Piso 14
Tercer Piso 20
Total= 48
03.01.02.00 Tomacorrientes
Niveles N Tomacorrienes
Primer Piso 21
Segundo Piso 23
Tercer Piso 33
Total= 77
Longitud Conductor
Niveles Tuberia
(m) N 14
10.68 3/4" /
4.39 3/4" /
5.05 3/4" /
Primer Piso 12.75 3/4" /
12.02 3/4" /
5.62 3/4" /
6.17 3/4" /
TOTAL= 56.68
Longitud Conductor
Niveles Tuberia
(m) N 14
3.68 3/4" /
15.69 3/4" /
4.17 3/4" /
Segundo Piso 10.68 3/4" /
5.48 3/4" /
6.35 3/4" /
10.4 3/4" /
TOTAL= 56.45
Longitud Conductor
Niveles Tuberia
(m) N 14
5.75 3/4" /
6.98 3/4" /
8.48 3/4" /
Tercer Piso
11.86 3/4" /
6.02 3/4" /
8.12 3/4" /
TOTAL= 47.21
03.02.02.00 Tomacorrientes/ 5/8" PVC SEL
Longitud Conductor
Niveles Tuberia
(m) N 12
7.26 5/8" /
5.97 5/8" /
4.85 5/8" /
Primer Piso
4.96 5/8" /
11.88 5/8" /
10.78 5/8" /
TOTAL= 45.7
Longitud Conductor
Niveles Tuberia
(m) N 12
3.26 5/8" /
26.196 5/8" /
3.354 5/8" /
Segundo Piso 10.28 5/8" /
9.34 5/8" /
8.39 5/8" /
5.82 5/8" /
TOTAL= 66.64
Longitud Conductor
Niveles Tuberia
(m) N 12
9.34 5/8" /
7.5 5/8" /
7.95 5/8" /
9.99 5/8" /
Tercer Piso
13.8 5/8" /
7.93 5/8" /
9.82 5/8" /
17.8 5/8" /
TOTAL= 84.13
03.03.00.00 Conductores y cables de energa en tuberas
03.03.01.00 Alumbrado Interior / N14 TW-AWG
Longitud Conductor
Niveles
(m) N 14
10.68 /
4.39 /
5.05 /
Primer Piso 12.75 /
12.02 /
5.62 /
6.17 /
TOTAL= 56.68
Longitud Conductor
Niveles
(m) N 14
3.68 /
15.69 /
4.17 /
Segundo Piso 10.68 /
5.48 /
6.35 /
10.4 /
TOTAL= 56.45
Longitud Conductor
Niveles
(m) N 14
5.75 /
6.98 /
8.48 /
Tercer Piso
11.86 /
6.02 /
8.12 /
TOTAL= 47.21
Longitud Conductor
Niveles
(m) N 12
7.26 /
5.97 /
4.85 /
Primer Piso
4.96 /
11.88 /
10.78 /
TOTAL= 45.7
Longitud Conductor
Niveles
(m) N 12
3.26 /
26.196 /
3.354 /
Segundo Piso 10.28 /
9.34 /
8.39 /
5.82 /
TOTAL= 66.64
Longitud Conductor
Niveles Tuberia
(m) N 14
9.34 5/8" /
7.5 5/8" /
7.95 5/8" /
9.99 5/8" /
Tercer Piso
13.8 5/8" /
7.93 5/8" /
9.82 5/8" /
17.8 5/8" /
TOTAL= 84.13
os
TRAMO 4-5-izq.= 1.87 m
TRAMO 4-5-der.= 2.02 m
TRAMO 4-5-abaj.= 0.15 m
Total 2314.01
Total 417.1776
Largo(m) Ancho(m) Vol (m3)
4.7 0.13 0.8554
4.85 0.13 0.3783
0.95 0.13 0.0494
3.75 0.13 0.195
1.85 0.13 0.1443
2.85 0.13 0.3705
2.42 0.13 0.25168
3.1 0.13 0.1612
Total 2.40578
TOTAL 141.12
TOTAL 470.5792
TOTAL 232.064
TOTAL 99.456
TOTAL 596.736
0.15
Losa
N Ladrillos # Lozas UND. Lad.
38 3 114
147 3 441
34 3 102
37 3 111
52 3 156
58 3 174
62 3 186
52 3 156
95 3 285
52 1 52
44 3 132
122 3 366
TOTAL= 2275
Area (m^2)
13.395
52.875
11.934
13.32
18.531
20.685
21.978
18.531
34.161
6.178
15.627
43.773 15.666667
270.988
4.8
a
# de veses Vol (m3)
15 0.3825
28 0.714
Total= 1.0965
Area (m2)
5.496
5.328
5.76
16.584
Area (m2)
3.264
6.528
9.792
Area(m^2)
2.28
1.8
15.48
11.28
2.52
3.6
4.776
5.76
1.56
1.05
3.96
2.28
1.8
5.16
2.28
1.8
2.28
12
2.016
4.896
1.8
7.488
2.76
1.19
2.448
1.968
3.96
1.8
3.12
4.488
5.088
6.888
11.616
3.648
2.016
2.4
1.815
5.16
2.76
1.7
1.425
7.44
16.44
11.64
199.636
Area(m^2)
5.16
3.225
1.8
9.12
8.352
17.28
3.84
3.36
3.168
3.825
3.168
2.28
1.8
2.28
1.8
2.64
1.36
6.12
9
1.8
7.488
1.56
1.36
2.28
1.8
3.96
1.83
4.008
4.608
6.888
2.88
1.8
3.672
3.672
3.648
5.832
6.072
1.8
4.56
1.8
162.896
Area(m^2)
2.28
1.8
12
5.16
9.12
1.8
8.4
2.88
5.4
5.76
6.72
3.24
1.83
3.96
6.12
2.28
1.8
3
2.76
5.16
4.56
1.425
2.88
1.36
7.44
9
2.88
1.36
2.52
8.88
1.68
3.255
4.56
9.456
6.888
2.928
1.8
5.904
3.6
5.832
9.12
3.6
192.398
554.93
s
# de veses Area(m^2)
1 18.264
2 3.6
1 6
2 3
1 2.88
1 11.76
1 4.2
1 9.672
1 15.792
9 16.2
1 0.36
1 6.48
1 2.64
1 12.96
2 2.72
1 5.808
1 21.312
5 9
2 2.91
2 2.72
1 6.24
1 16.8
1 8.28
2 3.6
TOTAL 193.198
Vigas
# de veses Area(m^2)
3 9.6
3 3
3 4.2
4 3.88
1 1
TOTAL= 21.68
s
# de veses Area(m^2)
1 34.8
1 16.992
1 32.352
1 33.72
1 31.56
1 45.432
5 9
2 3
1 1.05
1 1.7
9 0.945
1 1.19
1 81.192
1 11.376
1 38.112
1 28.416
1 39.048
10 18
2 7.65
2 2.72
1 98.52
1 43.2
1 82.128
1 13.488
11 19.8
2 2.72
2 2.91
11 1.155
11 1.485
11 1.98
Total 705.641
Area (m^2)
13.395
52.875
11.934
13.32
18.531
20.685
21.978
18.531
34.161
6.178
15.627
43.773
270.988
Area (m^2)
16.25
11.95
21.85
10.49
7.43
12.22
29.1
15.16
14.57
9.74
15.39
13.93
5.54
12.79
6.26
14.71
8.73
8.36
6.35
4.78
5.36
4.05
24.27
279.28
Area(m^2)
10.5
7.22
11.64
12.99
20.29
11.19
11.7
12.7
8.75
6.74
5.18
11.1
3.6
9.6
35.8425
8.65
10
11.25
6.94
5.45
11.88
233.2125
Area(m^2)
10.5
7.22
11.64
12.99
20.29
11.19
11.7
12.7
8.75
6.74
5.18
11.1
3.6
9.6
35.8425
8.65
10
11.25
6.94
5.45
11.88
233.2125
Puertas
6
4
2
3
2
4
3
6
30
adera de Cedro.
Ventanas
6
7
6
4
2
13
38
ALTURA (m) Ancho(m) Area (m^2)
0.9 1.2 7.56
0.9 1.22 6.588
0.9 0.7 0.63
0.9 1.2 3.24
0.9 1.2 2.16
0.9 0.97 1.746
0.9 1.2 11.88
TOTAL= 33.804
terior
# de veses Area(m^2)
1 34.8
1 16.992
1 32.352
1 33.72
1 31.56
1 45.432
5 9
2 3
1 1.05
1 1.7
9 0.945
1 1.19
1 81.192
1 11.376
1 38.112
1 28.416
1 39.048
10 18
2 7.65
2 2.72
1 98.52
1 43.2
1 82.128
1 13.488
11 19.8
2 2.72
2 2.91
11 1.155
11 1.485
11 1.98
Total 705.641
xterior
# de veses Area(m^2)
1 18.264
2 3.6
1 6
2 3
1 2.88
1 11.76
1 4.2
1 9.672
1 15.792
9 16.2
1 0.36
1 6.48
1 2.64
1 12.96
2 2.72
1 5.808
1 21.312
5 9
2 2.91
2 2.72
1 6.24
1 16.8
1 8.28
2 3.6
TOTAL 193.198
ntado exterior vigas
# de veses Area(m^2)
3 9.6
3 3
3 4.2
4 3.88
1 1
TOTAL= 21.68
Area (m^2)
13.395
52.875
11.934
13.32
18.531
20.685
21.978
18.531
34.161
6.178
15.627
43.773
270.988
Tees Grif. Lav Grf. Bao Val. Globo
3 0 0 3
6 4 2 5
8 4 2 4
2 2 2 3
19 10 6 15
Y Sumideros CODO 45
8 5 1
6 4 2
5 2 1
19 11 4
PLANILLA DE METRADOS
Trabajo metrados
PROVINCIA: CAJAMARCA
DISTRITO: CAJAMARCA
CONSTRUCCIN DE VIVIENDA
01.00.00.00ESTRUCTURAS
01.01.00.00TRABAJOS PROVISIONALES
01.01.01.00 Nivelacin Trazo y replanteo 1
01.02.00.00MOVIMIENTO DE TIERRAS
01.02.01.00 Excavacin de Cimentacin 1
01.02.02.00 Acarreo y eliminacin de material excedente 1
m3 5.94135 5.941
m 2
41.7435 41.7435 41.744
Kg 2731.1872 2731.187
m3 2.40578 7.217
m2 44.04488 44.045
kg 5598.2976 5598.298
m3 43.22 43.223
Pz 2275 2275.000
m2 270.988 270.988
Kg 5247.3792 5247.379
m3 6.8313 6.831
m2 26.376 26.376
Kg 348.768 348.768
PRESUPUESTO
SUBPRESUPUESTO
CLIENTE
LUGAR
FECHA
ITEM
01.00.00.00
01.01.00.00
01.01.01.00
01.02.00.00
01.02.01.00
01.02.02.00
01.03.00.00
01.03.01.00
01.03.01.01
01.03.02.00
01.03.02.01
01.03.03.00
01.03.03.01
01.03.03.02
01.03.04.00
01.03.04.01
01.04.00.00
01.04.01.00
01.04.01.01
01.04.01.02
01.04.01.03
01.04.02.00
01.04.02.01
01.04.02.02
01.04.02.03
01.04.03.00
01.04.03.01
01.04.03.02
01.04.03.03
01.04.03.04
01.04.04.00
01.04.04.01
01.04.04.02
01.04.04.03
02.00.00.00
02.01.00.00
02.01.01.00
02.02.00.00
02.02.01.00
02.02.02.00
02.03.00.00
02.03.01.00
02.04.00.00
02.04.01.00
02.04.02.00
02.05.00.00
02.05.01.00
02.05.02.00
02.06.00.00
02.06.01.00
02.06.02.00
02.07.00.00
02.07.01.01
02.07.01.02
02.08.00.00
02.08.01.00
03.00.00.00
03.01.00.00
03.01.01.00
03.01.02.00
03.02.00.00
03.02.01.00
03.02.02.00
03.03.00.00
03.03.01.00
03.03.02.00
03.04.00.00
03.04.01.00
03.04.02.00
04.00.00.00
04.01.00.00
04.01.01.00
04.01.02.00
04.01.03.00
04.01.04.00
04.01.05.00
04.01.06.00
04.02.00.00
04.02.01.00
04.02.02.00
04.02.03.00
04.02.04.00
04.02.05.00
PRESUPUESTO
CONSTRUCCION DE VIVIENDA VIVIENDA MULTIFAMILIAR
CONSTRUCCION DE VIVIENDA VIVIENDA MULTIFAMILIAR
GUEVARA GONZALES KELVIN
CAJAMARCA-CAJAMARCA-CAJAMARCA
7/5/2012
DESCRIPCIN Unidad
CONSTRUCCIN DE VIVIENDA
ESTRUCTURAS
TRABAJOS PROVISIONALES
Nivelacin Trazo y replanteo m2
MOVIMIENTO DE TIERRAS
Excavacin de Cimentacin m3
Acarreo y eliminacin de material excedente m3
ARQUITECTURA
Albaileria
Muro de ladrillo asentado de soga e= 0.13 m2
Cielo Raso
Cielo Rasos: con cemento - Arena 1:4 m2
Pisos, Paredes y Veredas
Cermico 20*30 en SS.HH m2
Cermico 20*30 m2
ZCALOS Y CONTRAZCALOS
Zcalo de pintura m2
Contrazcalos m2
CARPINTERA DE MADERA.
Puertas de Cedro m2
Ventanas Batientes y/o Corredizas de Marco en Madera de Cedro. m2
VIDRIOS.
Vidrios dobles transparentes. m2
Vidrios Catedral translucido m2
PINTURA
pintura base 2 capas, blanco: Base y la superficie melon m2
INSTALACIONES ELECTRICAS
Salida
Alumbrado Interior UND
Tomacorrientes UND
Canalizaciones,conductos o tuberias
Alumbrado Interior/ 3/4" PVC SEL m
Tomacorrientes/ 5/8" PVC SEL m
INSTALACIONES SANITARIAS
INSTALACIONES DE AGUA POTABLE
Tubera de PVC 1/2" m
Codos de PVC 1/2" 90 UND
Tees de PVC 1/2" UND
Grifos para lavandera UND
Grifos para bao UND
Vlvulas de Globo 1/2" UND
INSTALACIONES DE DESAGE
Tubera de PVC 4" m
Tubera de PVC 2" m
Codos de PVC 2" 45 UND
"Y " De PVC UND
Sumideros UND
COSTO DIRECTO
GASTOS GENERALES
UTILIDAD
SUB TOTAL
IGV
VALOR REFERENCIAL
EXPEDIENTE TECNICO
GASTOS DE SUPERVISIN
TOTAL
Metrado Precio Parcial SUB TOTAL
175699.13 175699.13
3890.0864
160 24.31 3890.0864
3588.1711
45.81 53.41 2446.52886
64.13 17.80 1141.64226
63162.569
105058.3
132277.66 132277.66
49782.65
554.93 89.71 49782.6504
33414.998
214.878 39.56 8500.49031
705.641 35.31 24914.5078
8287.5244
270.988 30.58 8287.52438
19556.499
4843.4691
233.2125 10.38 2421.73457
233.2125 10.38 2421.73457
6121.3872
30 62.51 1875.252
38 111.74 4246.1352
3817.9074
6453.221
1191.507 5.42 6453.22098
3689.4663 3689.4663
1188
48 10.12 485.76
77 9.12 702.24
980.75844
160.34 3.02 484.86816
196.47 2.52 495.89028
1346.1319
160.34 4.05 649.05632
196.47 3.55 697.07556
174.576
3 34.10 102.288
3 24.10 72.288
5058.411 5058.411
2088.7581
65.56 13.79 903.894077
44 3.10 136.312
19 4.40 83.562
10 26.29 262.9
6 51.29 307.74
15 26.29 394.35
2969.6529
30.2 26.53 801.167344
89.26 21.53 1921.65355
4 4.60 18.392
19 5.60 106.362
11 11.10 122.078
S/, 316724.66
22% S/, 69679.4259
6% S/, 19003.4798
S/, 405407.57
18% S/, 72973.3624
S/, 478380.93
3.5% S/, 16743.3326
S/, 18000
S/, 513124.26
ANALISIS DE COSTOS UNITARIOS
PRESUPUESTO CONSTRUCCION DE VIVIENDA VIVIENDA MULTIFAMILIAR
SUBPRESUPUESTO CONSTRUCCION DE VIVIENDA VIVIENDA MULTIFAMILIAR
CLIENTE
LUGAR CAJAMARCA-CAJAMARCA-CAJAMARCA
FECHA 7/5/2012
01.00.00.00 ESTRUCTURAS
01.01.01.00 N
RENDIMIENTO 500
Descripcin de Recurso
MANO DE OBRA
OFICIAL
PEON
MATERIAL
YESO DE 10KG
MADERA TORNILLO
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
WINCHA DE 50 M
01.02.01.00 E
RENDIMIENTO 4
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
PEON
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
01.02.02.00 Acarreo y
RENDIMIENTO 6
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
PEON
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
REGLA DE MADERA
01.03.02.00 Cimiento Corrido: cemento - hormigon+%P.G.
01.03.02.01 Cim
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
PIEDRA GRANDE
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
PIEDRA MEDIANA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
01.03.03.02 Encofrado
RENDIMIENTO
Habilitacin: 40
Encofrado: 14
Desencofrado: 28
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
MADERA TORNILLO
CLAVOS DE 3''
ALAMBRE NEGRO N8
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
01.03.04.00 Falso Piso (e=0.10 m)
01.03.04.01 C
RENDIMIENTO
PREP. Y VACEADO: 100
CURADO: 200
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
REGLA DE MADERA
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
VIBRADOR DE 2'', 4HP
WINCHE ELECTRONICO DE 2 TAM
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
MADERA TORNILLO
CLAVOS DE 3''
ALAMBRE NEGRO N8
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
01.04.01.03 Acero 3/4" Y Estribo de 1/4'' con Fy=4200kg/cm2
RENDIMIENTO
HABILITACION: 250
COLOCACION: 250
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
MATERIAL
FIERRO CORRUGADO
ALAMBRE NEGRO N 16
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
CIZALLA
01.04.02.00 Vigas
01.04.02.01 Concreto f'c = 210kg/cm2
RENDIMIENTO
PREP. Y VACEADO: 20
CURADO: 40
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
HORMIGN
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
VIBRADOR DE 2'', 4HP
WINCHE ELECTRONICO DE 2 TAM
01.04.02.02 Encofrado y desencofrado
RENDIMIENTO
Habilitacin: 40
Encofrado: 9
Desencofrado: 36
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
MADERA TORNILLO
CLAVOS DE 3''
ALAMBRE NEGRO N8
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
01.04.02.03 Acero 3/4" Y Estribo de 1/4'' con Fy=4200kg/cm2
RENDIMIENTO
HABILITACION: 250
COLOCACION: 250
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
MATERIAL
FIERRO CORRUGADO
ALAMBRE NEGRO N 16
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
CIZALLA
RENDIMIENTO
PREP. Y VACEADO: 25
CURADO: 50
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
PIEDRA CHANCADA DE 1/2''
ARENA GRUESA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
VIBRADOR DE 2'', 4HP
WINCHE ELECTRONICO DE 2 TAM
RENDIMIENTO 2000
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
LADRILLO DE ARCILL HUECO
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
01.04.03.03 Encofrado y desencofrado
RENDIMIENTO
Habilitacin: 75
Encofrado: 12
Desencofrado: 36
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
MADERA TORNILLO
CLAVOS DE 3''
ALAMBRE NEGRO N8
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO
HABILITACION: 250
COLOCACION: 250
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
MATERIAL
FIERRO CORRUGADO
ALAMBRE NEGRO N 16
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
CIZALLA
01.04.04.00 Escalera
01.04.04.01 Concreto f'c = 210kg/cm2
RENDIMIENTO
PREP. Y VACEADO: 12
CURADO: 30
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
OPERADOR DE EQIP. LIV.
MATERIAL
CEMENTO PORTLAN T-1
PIEDRA CHANCADA DE 1/2''
ARENA GRUESA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
MEZCLADORA DE 9-11P3
VIBRADOR DE 2'', 4HP
WINCHE ELECTRONICO DE 2 TAM
01.04.04.02 Encofrado y desencofrado
RENDIMIENTO
Habilitacin: 28
Encofrado: 6
Desencofrado: 18
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
MATERIAL
MADERA TORNILLO
CLAVOS DE 2 1/2''
ALAMBRE NEGRO N16
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO
HABILITACION: 250
COLOCACION: 250
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
MATERIAL
FIERRO CORRUGADO
ALAMBRE NEGRO N 16
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
CIZALLA
02.00.00.00 ARQUITECTURA
02.01.00.00 Albaileria
02.01.01.00 Muro de ladrillo asentado de soga e= 0.13
RENDIMIENTO
COLOCACION: 6.45
ACARREO: 16.13
6.45=400LAD/DIA
16.13=1000LAD/DIA
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA GRUESA
LADRILLO
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
CLAVOS DE 3''
RENDIMIENTO
PAETEO: 25
TARRAJEO 12
ARMAR ANDAMIO: 32
DESARMAR ANDAMIO: 120
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA FINA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
CLAVOS DE 3''
REGLA DE MADERA
RENDIMIENTO
PAETEO: 34
TARRAJEO 20
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA FINA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
CLAVOS DE 3''
REGLA DE MADERA
RENDIMIENTO
PAETEO: 34
TARRAJEO 20
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA FINA
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
CLAVOS DE 3''
REGLA DE MADERA
02.04.00.00 Pisos, Paredes y Veredas
02.04.01.00 Cermico 20*30 en SS.HH
RENDIMIENTO 12
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA FINA
CERAMICOS
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
RENDIMIENTO 12
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
MATERIAL
CEMENTO PORTLAN T-1
ARENA FINA
CERAMICOS
AGUA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
ANDAMIO DE MADERA
02.05.00.00 ZCALOS Y CONTRAZCALOS
02.05.01.00 Zcalo de pintura
RENDIMIENTO
IMPRIMACION: 45
PINTURA: 40
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PINTURA AL TEPLE
PINTURA IMPRIMANTE
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
02.05.02.00 Contrazcalos
RENDIMIENTO
IMPRIMACION: 45
PINTURA: 40
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PINTURA AL TEPLE
PINTURA IMPRIMANTE
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 2
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
MADERA CEDRO
MADERA DE TRIPLAY
COLA SINTETICA
CLAVOS 2''
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 4
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
MADERA CEDRO
COLA SINTETICA
CLAVOS 2''
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
02.07.00.00 VIDRIOS.
02.07.01.01 Vidrios dobles transparentes.
RENDIMIENTO 15
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
VIDRIO DOBLE
SILICONA FRIA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
VIDRIO DOBLE
SILICONA FRIA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
02.08.00.00 PINTURA
02.08.01.00 pintura base 2 capas, blanco: Base y la superficie melon
RENDIMIENTO
IMPRIMACION: 33
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PINTURA INTERIORES
PINTURA IMPRIM.
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 20
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
SUMINISTRO
03.01.02.00 Tomacorrientes
RENDIMIENTO 20
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
SUMINISTRO
03.02.00.00 Canalizaciones,conductos o tuberias
03.02.01.00 Alumbrado Interior/ 3/4" PVC SEL
RENDIMIENTO 100
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
TUBERIA PVC
RENDIMIENTO 100
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
TUBERIA PVC
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
CABLE
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
CABLE
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
TUBERIA PVC
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
TUBERIA PVC
04.00.00.00 INSTALACIONES SANITARIAS
04.01.00.00 INSTALACIONES DE AGUA POTABLE
04.01.01.00 Tubera de PVC 1/2"
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
MATERIAL
TUBERIA PVC 1/2''
PEGAMENTO
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
CODO
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
TEES
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
GRIFO
RENDIMIENTO 10
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
GRIFO
RENDIMIENTO 10
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
GRIFO
04.02.00.00 INSTALACIONES DE DESAGE
04.02.01.00 Tubera de PVC 4"
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
MATERIAL
PEGAMENTO
TUBERIA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 25
Descripcin de Recurso
MANO DE OBRA
CAPATAZ
OPERARIO
MATERIAL
PEGAMENTO
TUBERIA
EQUIPOS Y HERRAMIENTAS
HERRAMIENTAS MANUALES
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
CODO
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
CODO
04.02.05.00 Sumideros
RENDIMIENTO 50
Descripcin de Recurso
MANO DE OBRA
OPERARIO
MATERIAL
PEGAMENTO
CODO
Nivelacin Trazo y replanteo
M2/DIA COSTO UNITARIO m2
Excavacin de Cimentacin
M3/DIA COSTO UNITARIO m3
M2/DIA
COSTO UNITARIO m2
M2/DIA
M2/DIA
P2 4.83 1.50
KG 0.13 5.00
KG 0.26 4.62
M2/DIA
COSTO UNITARIO m2
M2/DIA
M2/DIA
P2 5.16 1.50
KG 0.17 5.00
KG 0.3 4.62
KG 1.07 2.49
KG 0.06 2.62
P2 6.71 1.50
KG 0.24 5.00
KG 0.21 4.62
KG 1.07 2.49
KG 0.06 2.62
Pz 1.05 0.50
P2 5.15 1.50
KG 0.11 5.00
KG 0.1 4.62
KG 1.07 2.49
KG 0.06 2.62
P2 5.74 1.50
KG 0.1 5.00
KG 0.08 2.62
KG 1.07 2.49
KG 0.06 2.62
M2/DIA
M2/DIA COSTO UNITARIO m2
M2/DIA
M2/DIA
KG 0.20 17.00
GAL 0.13 15.00
KG 0.20 17.00
GAL 0.13 15.00
de Cedro.
P2 15.00 5.40
GAL 0.5 8.00
KG 0.052 4.70
P2 12.00 8.00
UND 0.07 12.00
P2 12.00 8.00
UND 0.07 12.00
M 1.00 2.00
M 1.00 1.50
M 1.00 2.00
M 1.00 1.50
M 1.00 30.00
M 1.00 20.00
M/DIA COSTO UNITARIO m
M 1.00 3.00
GAL 0.3 3.50
Parcial
0.54
0.19
0.35
23.40
0.90
22.50
0.37
0.02
0.35
53.41
Parcial
51.60
7.60
44.00
1.81
1.81
17.80
Parcial
17.20
2.53
14.67
0.60
0.60
201.74
Parcial
11.64
0.38
2.56
1.20
6.60
1.28
180.69
83.25
94.50
2.94
9.41
0.41
7.00
2.00
236.67
Parcial
44.03
0.61
4.10
7.68
28.16
4.10
168.69
60.75
68.25
36.75
2.94
23.94
1.54
22.40
358.50
Parcial
110.08
1.52
10.24
19.20
70.40
10.24
188.57
82.13
72.75
30.75
2.94
59.85
3.85
56.00
34.94
Parcial
24.97
1.09
7.31
10.29
6.29
9.10
7.25
0.65
1.20
0.87
0.87
260.82
Parcial
9.14
0.30
2.05
0.48
5.28
1.02
247.36
157.73
86.25
3.39
4.32
0.32
2.80
1.20
608.04
Parcial
146.12
3.80
20.48
19.20
92.40
10.24
304.81
218.93
82.50
3.39
157.11
5.11
56.00
40.00
56.00
39.12
Parcial
28.16
1.52
10.24
12.00
4.40
9.98
7.74
0.85
1.39
0.99
0.99
4.17
Parcial
1.24
0.06
0.41
0.77
2.82
2.66
0.16
0.11
0.04
0.06
419.29
Parcial
73.06
1.90
10.24
9.60
46.20
5.12
267.68
218.93
39.00
9.75
78.56
2.56
28.00
20.00
28.00
44.62
Parcial
31.29
1.69
11.38
13.33
4.89
12.24
10.07
1.20
0.97
1.10
1.10
4.17
Parcial
1.24
0.06
0.41
0.77
2.82
2.66
0.16
0.11
0.04
0.07
445.71
Parcial
74.86
2.13
12.29
7.68
40.48
12.29
307.43
218.93
39.00
39.75
9.75
63.42
2.62
22.40
16.00
22.40
1.04
Parcial
0.50
0.01
0.05
0.05
0.40
0.53
0.53
0.02
0.02
34.98
Parcial
25.36
1.27
8.53
10.67
4.89
8.74
7.73
0.55
0.46
0.89
0.89
4.17
Parcial
1.24
0.06
0.41
0.77
2.82
2.66
0.16
0.11
0.04
0.07
559.23
Parcial
120.91
3.04
17.07
16.00
76.27
8.53
307.43
218.93
39.00
39.75
9.75
130.90
4.23
46.67
33.33
46.67
61.81
Parcial
50.71
2.53
17.07
21.33
9.78
9.32
8.61
0.50
0.21
1.77
1.77
4.65
Parcial
1.71
0.12
0.82
0.77
2.82
2.66
0.16
0.12
0.06
0.06
89.71
Parcial
30.51
2.36
15.88
12.28
56.28
9.18
4.35
33.00
9.75
2.92
1.07
1.74
0.11
39.56
Parcial
27.36
2.36
16.69
8.32
4.16
2.63
1.20
0.33
8.03
0.96
2.55
0.13
4.40
35.31
Parcial
23.26
11.97
8.13
3.16
4.16
2.63
1.20
0.33
7.89
0.81
2.55
0.13
4.40
30.58
Parcial
23.26
11.97
8.13
3.16
4.16
2.63
1.20
0.33
3.16
0.81
1.74
0.11
0.50
51.35
Parcial
13.48
1.27
8.58
3.63
35.66
2.63
1.20
31.50
0.33
2.21
0.47
1.74
51.35
Parcial
13.48
1.27
8.58
3.63
35.66
2.63
1.20
31.50
0.33
2.21
0.47
1.74
10.38
Parcial
4.86
4.86
5.35
3.40
1.95
0.17
0.17
10.38
Parcial
4.86
4.86
5.35
3.40
1.95
0.17
0.17
62.51
Parcial
51.20
51.20
9.52
0.63
0.40
8.40
0.08
1.79
1.79
111.74
Parcial
25.60
25.60
85.24
81.00
4.00
0.24
0.90
0.90
103.91
Parcial
6.83
6.83
96.84
96.00
0.84
0.24
0.24
103.91
Parcial
6.83
6.83
96.84
96.00
0.84
0.24
0.24
5.42
Parcial
3.10
3.10
2.21
0.52
1.69
0.11
0.11
10.12
Parcial
5.12
5.12
5.00
5.00
9.12
Parcial
5.12
5.12
4.00
4.00
3.02
Parcial
1.02
1.02
2.00
2.00
2.52
Parcial
1.02
1.02
1.50
1.50
4.05
Parcial
2.05
2.05
2.00
2.00
3.55
Parcial
2.05
2.05
1.50
1.50
34.10
Parcial
4.10
4.10
30.00
30.00
24.10
Parcial
4.10
4.10
20.00
20.00
13.79
Parcial
9.41
1.22
8.19
4.05
3.00
1.05
0.33
0.33
3.10
Parcial
2.05
2.05
1.05
1.05
4.40
Parcial
2.05
2.05
2.35
1.05
1.30
26.29
Parcial
10.24
10.24
16.05
1.05
15.00
51.29
Parcial
10.24
10.24
41.05
1.05
40.00
26.29
Parcial
10.24
10.24
16.05
1.05
15.00
26.53
Parcial
8.19
1.22
8.19
18.05
1.05
17.00
0.29
0.29
21.53
Parcial
8.19
1.22
8.19
13.05
1.05
12.00
0.29
0.29
4.60
Parcial
2.05
2.05
2.55
1.05
1.50
5.60
Parcial
2.05
2.05
3.55
1.05
2.50
11.10
Parcial
2.05
2.05
9.05
1.05
8.00
INSUMOS Y CANTIDADES REQUERIDAS
02.01.00.00 Albaileria
02.01.01.00 Muro de ladrillo asentado de soga e= 0.13
02.07.00.00 VIDRIOS.
02.07.01.01 Vidrios dobles transparentes.
02.08.00.00 PINTURA
02.08.01.00 pintura base 2 capas, blanco: Base y la superficie melon
03.01.02.00 Tomacorrientes
04.02.05.00 Sumideros
12
11
4.5
1.5
3.50%
70
Cantidad Precio
19
Cantidad Precio
12.8
22.5
75
18.4
70
20
cantidad Precio
5
4.62
cantidad Precio
50
70
cantidad Precio
2.49
2.62
cantidad Precio
0.5
cantidad Precio
75
0.5
cantidad Precio
75
cantidad Precio
30
cantidad Precio
17
15
cantidad Precio
5.4
25
8
4.7
cantidad Precio
8
12
cantidad Precio
13
13
cantidad Precio
cantidad Precio
cantidad Precio
cantidad Precio
1.5
cantidad Precio
2
cantidad Precio
1.5
cantidad Precio
30
cantidad Precio
20
cantidad Precio
3
3.5
cantidad Precio
0.8
cantidad Precio
1.3
cantidad Precio
15
cantidad Precio
40
cantidad Precio
15
cantidad Precio
17
cantidad Precio
12
cantidad Precio
1.5
cantidad Precio
2.5
cantidad Precio
8
01.00.00.00ESTRUCTURAS
01.01.00.00TRABAJOS PROVISIONALES
01.01.01.00 Nivelacin Trazo y replanteo
160 2.56
160 5.12
160 32
160 2400
160 5.6
160 0.8