Beruflich Dokumente
Kultur Dokumente
Stations:
Length:
MARK-UPS IN
TOTAL - MARK
ESTIMATED PERCENT
ITEM NO. DESCRIPTION QUANTITY UNIT
DIRECT COST
OCM PROFIT %
(1) (2) (3) (4) (5) (6) (7) (8)
Prepared/Submitted by:
TOTAL - MARK-UPS
TOTAL
VAT TOTAL COST UNIT COST
INDIRECT COST
VALUE
(9) (10) (11) (12) (13)
(5) x (8) 5%[(5)+(9)] (9) + (10) (5) + (11) (12)/ (3)
Approved by:
LORETO B. DACOROON
Assistant District Engineer
(Caretaker)
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Cordillera Administrative Region
Office of the District Engineer
Bangued, Abra
PROGRAM OF WORK
100.00%
ESTIMATED COST OF PROP
ITEM DESCRIPTION
UNIT QUANTITY
PART I FACILITIES FOR ENGINEER
PART A FACILITIES FOR ENGINEER
A.1.1 (13) Provision of Furnitures/Fixtures & Appliances for the living Quarters for the Engineers l.s. 1.00
PART II OTHER GENERAL REQUIREMENTS
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard l.s. 1.00
B.7 Occupational Safety and Health Program month 2.00
PART F BRIDGE CONSTRUCTION
403 (4) Structural Steel, furnished, and fabricated - Purlins kgs. 339.00
403 (5) Structural Steel, furnished, fabricated, and erected - Truss kgs. 1,824.19
404 (1) a Reinforcing Steel kgs. 418.10
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY PLUMBING WORKS
DIVISION I GENERAL
PART A EARTHWORK
801(1) Removal of Actual Structures/Obstruction (Windows & Roof Framing) l.s. 1.00
803 (1) a Structure Excavation cu.m. 48.00
PART B PLAIN AND REINFORCED CONCRETE WORKS
900 Reinforced Concrete (Column) cu.m. 1.12
903(2) Forms and Falseworks l.s 1.00
DIVISION IIBUILDINGS
PART C FINISHING
1001 (1) a Pipe - 50mm diameter PVC ln.m. 2.00
1001 (1) a2 Pipe - 75mm diameter PVC ln.m. 5.00
1001 (2) a1 Fittings- 50mm diameter PVC 45deg. Elbow pcs. 4.00
1001 (2) a2 Fittings- 75mm diameter PVC 45deg. Elbow pcs. 3.00
1001 (2) b2 Fittings- 75mm diameter PVC 90deg. Elbow pcs. 1.00
1001 (2) c2 Fittings- 75mm diameter PVC Cleanout with Plug pcs. 2.00
1001 (2) g2 Fittings- 75mm dia. PVC Sanitary Wye pcs. 2.00
1001 (2) k1 Fittings- 75mm dia. X 50mm dia. PVC Reducer - Sanitary Tee pcs. 3.00
1001 (8) Three Chamber Septic Vault ls 1.00
1002 (1) e1 Fittings- 50mm diameter P-Trap pcs. 1.00
1002 (1) e2 Fittings- 75mm diameter P-Trap pcs. 2.00
1002(2)a1 Galvanizes Iron Pipes (13mm dia.) pcs. 6.00
1002(2)a2 Galvanizes Iron Pipes (25mm dia.) pcs. 1.00
1002(2)b2 Fittings - Galvanized Iron (13mm dia elbow 1/4 bend; 90 deg. ) pcs. 6.00
1002(2)c1 Fittings - Galvanized Iron (13mm dia tee equal ) pcs. 7.00
1002(2)e1 Fittings - Galvanized Iron (13mm dia socket/coupling) pcs. 6.00
1002(2)f2 Fittings - Galvanized Iron (25mm dia. x 13mm reducer coupling) pcs. 1.00
1002(5)a1 Water Closet, Elongated, Complete set 1.00
1002(5)q Faucet pcs. 3.00
1002(5)q Hose Bibb pcs. 1.00
1201(4)h3 Floor Drain pcs. 3.00
1002 (5)g3 Lavatory, Wall Hung Complete set 1.00
1002 5) c1 Kitchen Sink Complete set 1.00
1003(1) c2 Ceiling (6.0mm Wood Frame Marine Plywood) sq.m. 162.25
1008 (1)a Residential Casement sq.m. 23.06
1010(1)b Wooden Doors - Flush sq.m. 13.65
1013(1) Corrugated Metal Roofing - Guage 26 sq.m 181.74
1013(2)a Fabricated Metal Roofing Accessory -Ridge Roll ln.m. 13.00
1013(2) b Fabricated Metal Roofing Accessory -Flashings ln.m. 27.96
1013(2)c Fabricated Metal Roofing Accessory - Gutters ln.m. 26.00
1013(3) Roof Ventilators each 0.48
1018(2) Unglazed Tiles - Vitrified Floor Tile sq.m. 2.02
1032(1)a Painting Works - Masonry and Fiber Cement Painting sq.m. 431.31
1032(1)b Painting Works - Metal Painting sq.m. 23.06
1032(1)c Painting Works - Wood Paint sq.m. 162.25
PART D ELECTRICAL
1100(14) Octagonal Junction Box PVC pcs. 9.00
1100(15) Utility Boxes PVC pcs. 27.00
1100(22) Grounding Rod Copperweld length 2.00
1101(1)b2 Electrical Wire - 2.0mm TWG/THHN mtr. 250.00
1101(1)b4 Electrical Wire - 3.5mm TWG/THHN mtr. 200.00
1101(1)b8 Electrical Wire - 8.0mm TWG/THHN roll 50.00
1101(7)a1 Single Pole Wall Switch on one Switch Plate set 8.00
1101(7)a2 Duplex(2 Single Pole Wall Switch on one Switch Plate) set 1.00
1101(8)a2 Duplex Convenience Receptacles/Outlets set 18.00
1102(1)a1 Panelboard Circuit Breaker Type - Main Distribution Panel (MDP) set 1.00
1103(2)a33 Flourescent Lighting Fixture with/ HPF-NCPF Ballast (Boxtype Surface Mounted) sets 6.00
1103(7)a5 Led Bulb w/ Medium Base, Keyless Type, porcelain Receptacle/Outlet sets 10.00
Prepared : Checked :
Submitted : Approved :
GRAM OF WORK
n/a
n/a
n/a
n/a
:
:
No. of Span : ____na____ No. of Piers : n/a
1
n/a
65 c.d.
EQUIPMENT
DESCRIPTION NEEDED
Backhoe (1.04 cu.m. Capacity) 1
Dumptruck (10 cu.m. Capacity) 1
Minor Tools 10% of Labor Cost 1
1
1
1
ESTIMATED COST OF PROPOSED WORK
UNIT COST TOTAL COST
133,134.54 133,134.54
4,578.78 4,578.78
4,792.10 9,584.19
76.59 25,965.64
89.82 163,843.09
52.89 22,113.19
16,436.23 16,436.23
320.75 15,395.81
7,087.18 7,937.64
26,048.70 26,048.70
327.91 655.82
296.98 1,484.88
124.09 496.36
167.42 502.26
353.29 353.29
167.46 334.92
254.18 508.36
183.17 549.51
60,716.63 60,716.63
1,764.30 1,764.30
1,014.15 2,028.30
418.95 2,513.69
1,452.19 1,452.19
200.90 1,205.38
167.25 1,170.72
160.65 963.88
240.97 240.97
9,706.78 9,706.78
724.96 2,174.89
724.96 724.96
536.97 1,610.90
5,170.87 5,170.87
7,579.30 7,579.30
579.99 94,102.75
2,749.20 63,396.59
2,205.04 30,098.86
468.85 85,208.14
327.92 4,263.02
300.17 8,392.72
296.94 7,720.53
22,469.90 10,785.55
1,383.71 2,795.08
605.91 261,334.04
1,159.75 26,743.73
125.23 20,317.95
86.68 780.09
126.91 3,426.55
687.76 1,375.53
39.30 9,824.52
39.62 7,924.56
58.11 2,905.33
439.18 3,513.47
568.08 568.08
497.69 8,958.48
17,987.48 17,987.48
1,375.85 8,255.12
627.73 6,277.29
I. BUDGET RESERVE
J. YOUTH & INFRA DEVELOPMENT
K. APPROPRIATION P 1,241,000.00
LORETO B. DACOROON
Assistant District Engineer
(Caretaker)
SUMMARY OF ESTIMATES
Prepared by:
ERNESTO B. BELMES
Engineer ll
Checked by:
Submitted by:
EDWIN T. BRINGAS
Chief, Maintenance Section
Name of Project: : Repair and Maintenance of DPWH - Old Constructions Building
Location: : Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
No. of
Name and Capacity No. of Hours Hourly Rate Amount
Units
2. Equipment:
ITEM 403 (5) : Structural Steel, furnished, fabricated, and erected - Truss
Unit of Measurement= kgs. Quantity= 1,824.19
Output= 17 kgs./hr. Duration= 107.31 hours
Say 107.00 hours
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
No. of
Name and Capacity No. of Hours Hourly Rate Amount
Units
2. Equipment:
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
No. of
Name and Capacity No. of Hours Hourly Rate Amount
Units
2. Equipment:
No. of
Designation No. of Hours Hourly Rate
1. Labor: Person
Foreman 1 1 71.95
Skilled 2 1 52.06
Unskilled 2 1 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Unskilled 2 1 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1001 (2) c2 : Fittings- 75mm diameter PVC Cleanout with Plug
Unit of Measurement= pcs. Quantity= 2.00
Output= 7 pcs./hr. Duration= 1.00
Say 1.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 2 71.95
Skilled 1 2 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1001 (2) k1 : Fittings- 75mm dia. X 50mm dia. PVC Reducer - Sanitary Tee
Unit of Measurement= pcs. Quantity= 3.00
Output= 7 pcs./hr. Duration= 0.50
Say 1.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1002 (1) e1 : Fittings- 50mm diameter P-Trap
Unit of Measurement= pcs. Quantity= 1.00
Output= 7 pcs./hr. Duration= 1.00
Say 3.00
1. Labor:
Foreman 1 3 78.12
Skilled 2 3 56.64
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1002 (1) e2 : Fittings- 75mm diameter P-Trap
Unit of Measurement= pcs. Quantity= 2.00
Output= 7 pcs./hr. Duration= 1.00
Say 3.00
1. Labor:
Foreman 1 3 78.12
Skilled 2 3 56.64
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: : Repair and Maintenance of DPWH Resthouse Along Abra - Kalinga Road
Location: : Macanogcog, Malibcong, Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1001 (8) : Three Chamber Septic Vault
Unit of Measurement= ls Quantity= 1.00
Output= Duration= 24.00
Say
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 24 78.12
Skilled 2 48 56.64
Unskilled 4 48 43.65
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
80.30
P 256.37
Amount
25.64
P 25.64
Amount
166.67
51.00
P 217.67
P 499.67
P 124.92
P 31.23
P 655.82
P 327.91
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
80.30
P 256.37
Amount
25.64
P 25.64
Amount
723.33
126.00
P 849.33
P 1,131.34
P 282.84
P 70.71
P 1,484.88
P 296.98
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
P 176.07
Amount
17.61
P 17.61
Amount
84.00
100.50
P 184.50
P 378.18
P 94.54
P 23.64
P 496.36
P 124.09
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
P 176.07
Amount
17.61
P 17.61
Amount
114.00
75.00
P 189.00
P 382.68
P 95.67
P 23.92
P 502.26
P 167.42
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
P 176.07
Amount
17.61
P 17.61
Amount
50.00
25.50
P 75.50
P 269.18
P 67.29
P 16.82
P 353.29
P 353.29
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
P 176.07
Amount
17.61
P 17.61
Amount
36.00
25.50
P 61.50
P 255.18
P 63.79
P 15.95
P 334.92
P 167.46
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
143.90
104.12
P 248.02
Amount
24.80
P 24.80
Amount
89.00
25.50
P 114.50
P 387.32
P 96.83
P 24.21
P 508.36
P 254.18
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
71.95
104.12
P 176.07
Amount
17.61
P 17.61
Amount
150.00
75.00
P 225.00
P 418.68
P 104.67
P 26.17
P 549.51
P 183.17
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
234.36
339.84
P 574.20
Amount
57.42
P 57.42
Amount
107.00
450.00
P 557.00
P 1,188.62
P 297.16
P 74.29
P 1,560.06
P 1,560.06
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
234.36
339.84
P 574.20
Amount
57.42
P 57.42
Amount
214.00
450.00
P 664.00
P 1,295.62
P 323.91
P 80.98
P 1,700.50
P 850.25
ntenance of DPWH Resthouse Along Abra - Kalinga Road
hours
hours
Amount
1,874.88
5,437.44
8,380.80
P 15,693.12
Amount
1,569.31
P 1,569.31
Amount
42,878.52
P 42,878.52
P 60,140.95
P 15,035.24
P 3,758.81
P 78,935.00
P 78,935.00
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 2 26.47
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 1 9.22
ITEM 1002(2)b2 : Fittings - Galvanized Iron (13mm dia elbow 1/4 bend; 90 deg. )
Unit of Measurement= pcs. Quantity= 6.00
Output= 1.72 pcs./hr. Duration= 3.49 hours
Say 4.00 hours
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 4 52.94
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 5 66.18
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 4 52.94
ITEM 1002(2)f2 : Fittings - Galvanized Iron (25mm dia. x 13mm reducer coupling)
Unit of Measurement= pcs. Quantity= 1.00
Output= 1.72 pcs./hr. Duration= 0.58 hours
Say 1.00 hours
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools
10% of Labor Cost 1 1 13.24
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Lavatory Wall Hung including fittings and acc. set 1.00 3,000.00 3,000.00
American Standard or Equivalent
Solvent Cement sealant 100cc can 1 165.00 165.00
No. of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor:
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 2 71.95
Skilled 2 2 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 4 71.95
Skilled 2 4 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1100(22) : Grounding Rod Copperweld
Unit of Measurement= length Quantity= 2.00
Output= Duration= 2.00
Say 2.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 2 71.95
Skilled 1 2 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 3 71.95
Skilled 4 4 52.06
Unskilled 2 2 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 2 71.95
Skilled 4 3 52.06
Unskilled 2 2 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 1 71.95
Skilled 4 1 52.06
Unskilled 2 1 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Skilled 2 6 71.95
Unskilled 2 6 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
3. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1101(7)a2 : Duplex(2 Single Pole Wall Switch on one Switch Plate)
Unit of Measurement= set Quantity= 1.00
Output= 1.25 set/hr. Duration= 0.80
Say 1.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Skilled 2 1 71.95
Unskilled 2 1 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
3. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Skilled 2 14 71.95
Unskilled 2 14 52.06
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1102(1)a1 : Panelboard Circuit Breaker Type - Main Distribution Panel (MDP)
Unit of Measurement= set Quantity= 1.00
Output= 0.3 set/hr. Duration= 4.00
Say 4.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 2 71.95
Skilled 2 4 52.06
Unskilled 1 2 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1103(2)a33 : Flourescent Lighting Fixture with/ HPF-NCPF Ballast (Boxtype Surface Mounted)
Unit of Measurement= sets Quantity= 6.00
Output= 1.0 set/hr. Duration= 6.00
Say 6.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 3 71.95
Skilled 2 6 52.06
Unskilled 2 3 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
DETAILED UNIT PRICE ANALYSIS
ITEM 1103(7)a5 : Led Bulb w/ Medium Base, Keyless Type, porcelain Receptacle/Outlet
Unit of Measurement= sets Quantity= 10.00
Output= 1.0 set/hr. Duration= 10.00
Say 10.00
No. of
Designation No. of Hours Hourly Rate
Person
1. Labor:
Foreman 1 5 71.95
Skilled 2 10 52.06
Unskilled 2 5 40.15
Sub-Total for 1
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
3. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
208.24
P 352.14
Amount
35.21
P 35.21
Amount
99.00
108.00
P 207.00
P 594.35
P 148.59
P 37.15
P 780.09
P 86.68
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
287.80
416.48
P 704.28
Amount
70.43
P 70.43
Amount
864.00
972.00
P 1,836.00
P 2,610.71
P 652.68
P 163.17
P 3,426.55
P 126.91
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
104.12
P 248.02
Amount
P -
Amount
500.00
300.00
P 800.00
P 1,048.02
P 262.01
P 65.50
P 1,375.53
P 687.76
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
215.85
832.96
160.60
P 1,209.41
Amount
120.94
P 120.94
Amount
6,000.00
155.00
2,660.00
P 6,155.00
P 7,485.35
P 1,871.34
P 467.83
P 9,824.52
P 39.30
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
161.89
624.72
120.45
P 907.06
Amount
90.71
P 90.71
Amount
4,800.00
240.00
62.00
P 5,040.00
P 6,037.76
P 1,509.44
P 377.36
P 7,924.56
P 39.62
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
53.96
208.24
40.15
P 302.35
Amount
30.24
P 30.24
Amount
1,850.00
31.00
P 1,881.00
P 2,213.59
P 553.40
P 138.35
P 2,905.33
P 58.11
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
863.40
624.72
P 1,488.12
Amount
148.81
P 148.81
Amount
1,040.00
P 1,040.00
P 2,676.93
P 669.23
P 167.31
P 3,513.47
P 439.18
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
104.12
P 248.02
Amount
24.80
P 24.80
Amount
160.00
P 160.00
P 432.82
P 108.21
P 27.05
P 568.08
P 568.08
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
2,014.60
1,457.68
P 3,472.28
Amount
347.23
P 347.23
Amount
3,006.00
P 3,006.00
P 6,825.51
P 1,706.38
P 426.59
P 8,958.48
P 497.69
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
416.48
80.30
P 640.68
Amount
64.07
P 64.07
Amount
900.00
700.00
400.00
1,000.00
10,000.00
P 13,000.00
P 13,704.75
P 3,426.19
P 856.55
P 17,987.48
P 17,987.48
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
215.85
624.72
240.90
P 1,081.47
Amount
108.15
P 108.15
Amount
5,100.00
P 5,100.00
P 6,289.62
P 1,572.40
P 393.10
P 8,255.12
P 1,375.85
ETAILED UNIT PRICE ANALYSIS
hours
hours
Amount
359.75
1,041.20
401.50
P 1,802.45
Amount
180.25
P 180.25
Amount
2,800.00
P 2,800.00
P 4,782.70
P 1,195.67
P 298.92
P 6,277.29
P 627.73
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Skilled 1 10 52.06
Labor 1 10 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 10%
VAT 5%
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Sub-Total for 1
2. Equipment:
NONE
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM 10%
VAT 5%
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
ITEM A.1.1 (13) : Provision of Furnitures/Fixtures & Appliances for the living Quarters for the Engineers
Unit of Measurement= l.s. Quantity= 1.00
Output= Duration=
Say -
1. Labor:
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
uratex mattress w/ thin cotton cover (3x30x75
green) pcs. 6.00 1,800.00
monoblock chair pcs. 10.00 200.00
kitchen accessories set 1.00 1,500.00
double burner stove set. 1.00 1,500.00
L.P.G. pcs. 1.00 1,000.00
Air Con(1.5 HP) pcs. 4.00 22,867.00
Hanging Cabinet l.s. 1.00 7,000.00
Sub-Total for 3
Direct Cost
OCM/CP 10%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 40 71.95
Skilled 1 40 52.06
Unskilled 4 40 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 2 71.95
Skilled (Equipment Operator) 2 2 52.06
Skilled (Mason) 6 21 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 0 71.95
Skilled 4 0 52.06
Unskilled 6 0 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 6 71.95
Skilled 4 11 52.06
Unskilled 4 6 40.15
Sub-Total for 1
2. Equipment:
Minor Tools
10% of Labor Cost 1 11
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 26 71.95
Skilled 4 26 52.06
Unskilled 4 13 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
Name and Specification Unit Quantity Unit Cost
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 16 71.95
Skilled 2 32 52.06
Unskilled 1 16 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Skilled 2 22 52.06
Unskilled 2 22 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
1. Labor:
Foreman 1 33 71.95
Skilled 4 44 52.06
Unskilled 2 33 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 2 71.95
Skilled 2 2 52.06
Unskilled 2 2 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Skilled 2 6 52.06
Unskilled 2 6 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Skilled 2 5 52.06
Unskilled 2 5 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Skilled 4 2 52.06
Unskilled 2 2 40.15
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 17 78.12
Skilled 6 34 56.64
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 26 78.12
Skilled 4 6 56.64
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
Name of Project: Repair and Maintenance of DPWH - Old Constructions Building
Location: Zone 7, Bangued Abra
1. Labor:
Foreman 1 56 78.12
Skilled 2 56 56.64
Sub-Total for 1
2. Equipment:
Sub-Total for 2
2. Materials:
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
520.60
401.50
P 922.10
Amount
92.21
P 92.21
Amount
1,600.00
950.00
80.00
320.00
P 2,950.00
P 3,964.31
P 396.43
P 218.04
TAILED UNIT PRICE ANALYSIS
P 4,578.78
P 4,578.78
TAILED UNIT PRICE ANALYSIS
Amount
2,343.60
416.48
321.20
P 3,081.28
Amount
P -
Amount
3,742.96
122.00
1,351.76
P 5,216.72
P 8,298.00
P 829.80
P 456.39
TAILED UNIT PRICE ANALYSIS
P 9,584.19
P 4,792.10
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
-
-
P -
Amount
P -
Amount
10,800.00
2,000.00
1,500.00
1,500.00
1,000.00
91,468.00
7,000.00
P 115,268.00
P 115,268.00
P 11,526.80
P 6,339.74
P 133,134.54
P 133,134.54
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
2,878.00
2,082.40
6,424.00
P 11,384.40
Amount
1,138.44
P 1,138.44
Amount
P -
P 12,522.84
P 3,130.71
P 782.68
P 16,436.23
P 16,436.23
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
208.24
5,058.90
P 5,411.04
Amount
3,074.00
2,704.00
541.10
P 6,319.10
Amount
P -
P 11,730.14
P 2,932.54
P 733.13
P 15,395.81
P 320.75
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
35.82
103.66
119.91
P 259.39
Amount
3,275.36
25.94
P 25.94
Amount
5,762.40
P 5,762.40
P 6,047.73
P 1,511.93
P 377.98
P 7,937.64
P 7,087.18
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
395.73
2,290.64
883.30
P 3,569.67
Amount
356.97
P 356.97
Amount
4,480.00
10,000.00
1,440.00
P 15,920.00
P 19,846.63
TAILED UNIT PRICE ANALYSIS
P 4,961.66
P 1,240.41
P 26,048.70
P 26,048.70
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
1,841.92
5,330.94
2,055.68
P 9,228.54
Amount
922.85
P 922.85
Amount
19,717.88
41,399.71
428.34
P 61,545.93
P 71,697.33
P 17,924.33
P 4,481.08
P 94,102.75
P 579.99
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
1,151.20
3,334.73
642.40
P 5,128.33
Amount
512.83
P 512.83
Amount
42,661.00
P 42,661.00
P 48,302.17
P 12,075.54
P 3,018.89
P 63,396.59
TAILED UNIT PRICE ANALYSIS
P 2,749.20
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
2,290.64
1,766.60
P 4,057.24
Amount
405.72
P 405.72
Amount
5,050.50
9,639.00
3,780.00
-
P 18,469.50
P 22,932.46
P 5,733.12
P 1,433.28
P 30,098.86
P 2,205.04
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
2,374.35
9,162.56
2,649.90
P 14,186.81
Amount
1,418.68
P 1,418.68
Amount
45,435.00
2,960.00
920.00
P 49,315.00
P 64,920.49
P 16,230.12
P 4,057.53
P 85,208.14
P 468.85
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
143.90
208.24
160.60
P 512.74
Amount
51.27
P 51.27
Amount
2,184.00
500.00
345.00
P 2,684.00
P 3,248.01
P 812.00
P 203.00
P 4,263.02
P 327.92
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
624.72
481.80
P 1,106.52
Amount
110.65
P 110.65
Amount
4,697.28
300.00
180.00
P 5,177.28
P 6,394.45
P 1,598.61
P 399.65
P 8,392.72
P 300.17
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
520.60
401.50
P 922.10
Amount
92.21
P 92.21
Amount
4,368.00
500.00
P 4,868.00
P 5,882.31
P 1,470.58
P 367.64
P 7,720.53
P 296.94
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
49.98
38.54
P 88.52
Amount
8.85
P 8.85
Amount
2,600.00
P 2,600.00
P 2,697.37
P 674.34
P 168.59
P 3,540.30
P 7,375.63
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
416.48
160.60
P 577.08
Amount
57.71
P 57.71
Amount
1,494.80
P 1,494.80
P 2,129.59
P 532.40
P 133.10
P 2,795.08
P 1,383.71
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
1,328.04
11,554.56
P 12,882.60
Amount
1,288.26
P 1,288.26
Amount
62,167.00
123,753.00
58,315.00
1,230.00
19,525.00
1,200.00
675.00
5,500.00
1,200.00
6,750.00
P 244,235.00
P 258,405.86
P 64,601.47
P 16,150.37
P 339,157.69
P 786.35
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
2,031.12
1,359.36
P 3,390.48
Amount
101.71
P 101.71
Amount
6,245.75
9,877.00
1,200.00
1,750.00
P 19,072.75
P 22,564.94
P 5,641.24
P 1,410.31
P 29,616.49
P 1,284.32
TAILED UNIT PRICE ANALYSIS
hours
hours
Amount
4,374.72
6,343.68
P 10,718.40
Amount
1,071.84
P 1,071.84
Amount
2,324.00
1,230.00
550.00
750.00
1,750.00
540.00
P 7,144.00
P 18,934.24
P 4,733.56
P 1,183.39
P 24,851.19
P 153.17
STRUCTURE EXCAVATION
septic tank= 48 cu.m. Area= 2.42 sq.m. H=
48 cu.m.
wall 1
W-1
net area of wall= 61.66 sq.m.
factor= 11 m./sq.m.
length of bars for masonry wall= 678.26 m.
MASONRY WORKS
W-1
area of W 61.66 sq.m.
height of wall= m.
length of wall= m.
area of ramp= sq.m.
area of doors= sq.m.
net area of wall= 61.66
REINFORCED CONCRETE
Note: use Class A concrete mix (1:2:4)
COLUMN
column
Heigth= 4.05
width= 0.25
thickness= 0.25
#= 4
Volume= 1.12
STEEL TRUSS
(3/16"x2-1/2''x2-1/2''x20'Angle bar)
TOP CHORD(2-3/16"x2''x2''x20'Angle bar)
EFF. L NO. NO OF TRUSS LENGTH
6.99 2 5 69.9
6.99 2 5 69.9
TOTAL LENGTH= 139.8 m.
BOTTOM CHORD(2-3/16"x2-''x2''x20'Angle bar)
EFF. L NO. NO OF TRUSS LENGTH
13.4 2 5 134
TOTAL LENGTH= 134 m.
VERTICAL MEMBER(3/16"x1-3/4''x1-3/4''x20'Angle bar)
EFF. L NO. NO OF TRUSS LENGTH
0.39 2 5 3.9
0.79 2 5 7.9
1.19 2 5 11.9
1.6 2 5 16
2 2 5 20
0.39 2 5 3.9
0.79 2 5 7.9
1.19 2 5 11.9
1.6 2 5 16
FOR TRUSS
(1.0x2"x6"x20' C-Purlins)
C-PURLINS
EFF. L NO. LENGTH
13 24 312
FACIA BOARD
EFF. L NO. LENGTH
54 2 108
K.G.
418.1
Screening: Capacity of Loader at 200 cu.m. per day is reduced to 50% due to double handling
= 250 CU.M. = 2.5 DAYS
100 CU.M. / DAY
Equipment rental:
Payloader = P 13,864.00 /day x 2.5 DAYS
225 CU.M.
= P 154.04
Total Cost of Aggregates at Quarry Site = 227.61
TOTAL TIME =
NO OF HRS./TRIP = 33 =
60 MINS./HR.
Travel Velocity:
Loaded: 15.00 Kph
Unloaded: 20.00 Kph
Distance: 56.60 Km.
Loaded: 5.00 km. X 60.00 Min./hour
20.00 Kph
= 15.00 minutes
= P 6.11 /bag
= P 160.60 /CU.M.
LOADING TIME = 30
UNLOADING TIME = 1
SLACK TIME = 8
39
TOTAL TIME = 74
O OF HRS./TRIP = 74 = 1.23
60 MINS./HR.
TOTAL = P 1,133.14
/cu.m.
/cu.m.
8 MINS.
15 MINS
10 MINS
33 MINS
0.55 HOURS
P 443.85
P 326.24 /CU.M.
P 326.00 /CU.M.
/hour
/day
/hour
/day
P 281.05
P 941.50
P 1,222.55 per trip
P 1,222.55
per trip
pcs.
1 DUMPTRUCK WITH A CAPACITY OF 4.5 CU.M.
MINS.
MINS.
MINS.
MINS.
MINS
MINS
MINS
HOURS
/CU.M.
/CU.M.
Name of Material Unit DepED Price Unit
#REF! #REF!
Php 150.00
Php 850.00
Php 41.03
Php 50.00
Php 209.00
Php 800.00
Php 850.00
Php 13.00
Php 60.00
Php 354.75
Php 9.50
Php 30.00
Php 31.00
Php 900.00
Php 70.00
Php 50.00
Php 49.00
Php 280.00
Php 70.00
Php 352.50
Php 245.00
311a Portland Cement Concrete Pavement (Conventional Method) sq.m. 0.39 kgs.
Pavement (Conventional Method) 0.285 liters
0.12 liters
0.45 l.m.
0.1265 cu.m.
0.23 cu.m.
9.5 bags
Foreman 60 cu.m./hr.
Laborer
Foreman 80 cu.m./hr.
Laborer
Foreman 20 cu.m./hr.
Laborer
Foreman 50 cu.m./hr.
Unskilled
Foreman 50 cu.m./hr.
Unskilled
Foreman 50 cu.m./hr.
Unskilled
Foreman 50 cu.m./hr.
Unskilled
Foreman 50 cu.m./hr.
Unskilled
Cycle Time
Ave. Hauling Distance = 90.00 kms.
Distance from Source to Project Site = 90.00
paved road = 72.00
unpaved road (National) = 18.00
unpaved road (Local) = -
Capacity of Cargo Truck = 150.00 bags
No. of Laborers = 6.00 Laborers
A) Paved Road
72.00 kms x 60 min/hr
Loaded Trip = = 216.00 mins
20 kms/hr
72.00 kms x 60 min/hr
Unloaded Trip = = 144.00 mins
30 kms/hr
B) UnPaved Road (National)
18.00 kms x 60 min/hr
Loaded Trip = = 72.00 mins
15 kms/hr
18.00 kms x 60 min/hr
Unloaded Trip = = 43.20 min.
25 kms/hr
C) UnPaved Road (Local) 18.00 kms.
0.00 kms x 60 min/hr
Loaded Trip = = 0.00 mins
5 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = = 0.00 min.
10 kms/hr
F) Slack Time
= 6.00 min.
Total Cycle Time = 531.20 min.
Hauling Cost
Equipment Cost = 1 Cargo Truck x 6,248.00 /day x 0.40 days =
Labor Cost = 6 Laborers x 312.24 /day x 0.40 days =
Cycle Time
Ave. Hauling Distance = 31.00 kms.
Distance from Source to Project Site = 31.00
paved road = 13.00
unpaved road (National) = 18.00
unpaved road (Local) = -
Capacity of Dump Truck = 3.00 cum.
A) Paved Road
13.00 kms x 60 min/hr
Loaded Trip = = 39.00 mins
20 kms/hr
13.00 kms x 60 min/hr
Unloaded Trip = = 26.00 mins
30 kms/hr
B) UnPaved Road (National)
18.00 kms x 60 min/hr
Loaded Trip = = 72.00 mins
15 kms/hr
18.00 kms x 60 min/hr
Unloaded Trip = = 43.20 min.
25 kms/hr
C) UnPaved Road (Local) (31.00) kms.
0.00 kms x 60 min/hr
Loaded Trip = = 0.00 mins
5 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = = 0.00 min.
10 kms/hr
D) Loading Time
= 6.00 min.
E) Unloading Time
= 3.00 min.
F) Slack Time
= 6.00 min.
Total Cycle Time = 195.20 min.
Hauling Cost
Equipment Cost = 1 Dump Truck x 5,944.00 /day x 1.25 days =
1 Payloader x 7,464.00 /day x 1.25 days =
Cycle Time
Ave. Hauling Distance = 31.00 kms.
Distance from Source to Project Site = 31.00
paved road = 13.00
unpaved road (National) = 18.00
unpaved road (Local) = -
Capacity of Dump Truck = 3.00 cum.
A) Paved Road
13.00 kms x 60 min/hr
Loaded Trip = = 39.00 mins
20 kms/hr
13.00 kms x 60 min/hr
Unloaded Trip = = 26.00 mins
30 kms/hr
B) UnPaved Road (National)
18.00 kms x 60 min/hr
Loaded Trip = = 72.00 mins
15 kms/hr
18.00 kms x 60 min/hr
Unloaded Trip = = 43.20 min.
25 kms/hr
C) UnPaved Road (Local) (31.00) kms.
0.00 kms x 60 min/hr
Loaded Trip = = 0.00 mins
5 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = = 0.00 min.
10 kms/hr
D) Loading Time
= 6.00 min.
E) Unloading Time
= 3.00 min.
F) Slack Time
= 6.00 min.
Total Cycle Time = 195.20 min.
Hauling Cost
Equipment Cost = 1 Dump Truck x 5,944.00 /day x 0.47 days =
1 Payloader x 7,464.00 /day x 0.47 days =
Unit Cost of Hauling 1,826.60 /cum.
Cost at Source 400.00
Cycle Time
Ave. Hauling Distance = 31.00 kms.
Distance from Source to Project Site = 31.00
paved road = 13.00
unpaved road (National) = 18.00
unpaved road (Local) = -
Capacity of Dump Truck = 3.00 cum.
A) Paved Road
13.00 kms x 60 min/hr
Loaded Trip = = 39.00 mins
20 kms/hr
13.00 kms x 60 min/hr
Unloaded Trip = = 26.00 mins
30 kms/hr
B) UnPaved Road (National)
18.00 kms x 60 min/hr
Loaded Trip = = 72.00 mins
15 kms/hr
18.00 kms x 60 min/hr
Unloaded Trip = = 43.20 min.
25 kms/hr
C) UnPaved Road (Local) (31.00) kms.
0.00 kms x 60 min/hr
Loaded Trip = = 0.00 mins
5 kms/hr
0.00 kms x 60 min/hr
Unloaded Trip = = 0.00 min.
10 kms/hr
D) Loading Time
= 6.00 min.
E) Unloading Time
= 3.00 min.
F) Slack Time
= 6.00 min.
Total Cycle Time = 195.20 min.
No. of Trips/day 480 / 195.20 = 2.46 trips/day
Hauling Cost
Equipment Cost = 1 Dump Truck x 5,944.00 /day x 0.52 days =
1 Payloader x 7,464.00 /day x 0.52 days =
bags/trip
2,499.20
749.38
3,248.58
trips/day
cum./trip
7,430.00
9,330.00
16,760.00
/cum.
/cum.
trips/day
cum./trip
2,793.68
3,508.08
6,301.76
/cum.
/cum.
trips/day
cum./trip
3,090.88
3,881.28
6,972.16
/cum.
/cum.
Tuba NHS (Nangalisan)