Sie sind auf Seite 1von 11

Cost Estimation

Cost of the plant

Cost of cumene plant of capacity 100 Million pound TPA in 1990 is Rs.

58000000

Therefore cost of 800 TPA in 1990 is:


0.6
C1 = C2 (Q1/Q2)^ 0.6 = 580000000 x (800/100) = Rs. 3060000000

Chemical Engineering Plant Cost Index: Cost index in 1990 = 357.6

Cost index in 2015 = 560.7 (James R. Couper, 2003)

Thus, Present cost of Plant = (original cost) ( (present cost index)/(past cost index))^0.6

0.6
= (3060000000) (560.7/357.6)
= Rs. 4009000000

i.e., Fixed Capital Cost (FCI) = Rs 4009000000

Cost of Equipment: (Robert H. Perry, 1997)

Table 7.1

Number Equipment Capacity/power Total Cost (Rs.)


(range)

15 Pumps 1-22 kW 9000000

1 Fired Heater 2800kW 1500000

3
6 Reactor 6.5m 120989900

2
15 Heat exchanger equipment* 20- 400m 7985734

2
4 Flash Drums 4-6 m 450000

3
2 Storage tank 450m 5000000

2 columns 8000 gallon 56900400

3 Conveyer Belt 10 m2 800000

2 Crystalizer 5.5 m3 1200000

2
0
Purchased equipment cost(PEC) =Rs. 947000000

Estimation of Capital Investment Cost:

I. Direct Costs: material and labour involved in actual installation of complete facility (70-85% of fixed-
capital investment)

a) Equipment + installation + instrumentation + piping + electrical + insulation + painting (50- 60% of


Fixed-capital investment)

1. Purchased equipment cost (PEC):

PEC = 25% of Rs 4009000000 ~= 947000000

2
0
2. Installation, including insulation and painting:

Installation cost = 40% of Purchased equipment cost = 40% of 947000000 = Rs 378000000

3. Instrumentation and controls, installed:

Installation cost = 20% of Purchased equipment cost = 0.20 947000000= Rs 189400000

4. Piping installed:

Piping Cost= 40% of Purchased equipment cost = Rs 378000000

5. Electrical, installed:

Electrical cost = 25% of Purchased equipment cost = 0.25 = Rs 236750000

B. Buildings, process and Auxiliary:

Buildings, process and auxiliary cost = 40% of PEC = 0.40 947000000= Rs 378000000

C. Service facilities and yard improvements: = 60% of 947000000 = Rs 568200000

D. Land:

Cost of land = 6% PEC = 0.06 947000000= Rs 56820000

Thus, Direct cost = Rs 790000000----- (82%of FCI)

II. Indirect costs: Expenses which are not directly involved with material and labour of actual
installation of complete facility (15-30% of Fixed-capital investment)

A. Engineering and Supervision:


Cost of engineering and supervision = 10% of Direct costs
= 10% of 790000000 = Rs 79000000

B. Construction Expense and Contractors fee: = 10% of Direct costs


= 10% of 790000000 = Rs79000000

C. Contingency: = 10% of Fixed-capital investment Contingency


cost = 0.1 947000000 = Rs 94700000
Thus, Indirect Costs = Rs 1042340000 --- (26.75% of FCI)

III. Fixed Capital Investment:

Fixed capital investment = Direct costs + Indirect costs


= (Rs790000000) + (Rs1042340000)

IV. Fixed capital investm Working Capital:

Working Capital = 15% of Fixed-capital investment


= 0.15 4009000000= Rs 601000000

V. Total Capital Investment (TCI):

Total capital investment = Fixed capital investment + Working capital


= (4009000000) + (601000000)
Total capital investment = Rs 4610000000

Estimation of Total Production cost:


1. Manufacturing Cost
= Direct production cost + Fixed charges + Plant overhead cost.

A. Fixed Charges: (10-20% total product cost)

i. Depreciation: (13% of FCI for machinery and equipment and 2-3% for Building Value for
Buildings)
Depreciation = (0.134009000000) + (0.034009000000) = Rs 641440000

ii. Local Taxes:


Local taxes = 3% of fixed capital investment
Local Taxes = Rs0.03*4610000000=138300000
iii. Insurances:
Insurance = 0.0074610000000= Rs 322700000

Thus, Fixed Charges = Rs 1105100000


D. Direct Production Cost: (about 60% of total product cost)

Fixed charges = 15% of total product cost

Total product charge =1105100000 /0.15


Total product charge(TPC) = Rs 7367300000

i. Raw Materials:

Raw material cost = Rs =Rs. 174661

ii. Operating Labour (OL):

Operating labour cost = 12% of Operating


7367300000
labour cost = Rs 884076000

iii. Utilities:

Utilities cost= 0.127367300000


Utilities cost = Rs 884076000

iv. Laboratory Charges:

Laboratory charges = 1.5% of OL


Laboratory charges = Rs 13261140

v. Patent and Royalties:

Patent and Royalties = 0.04 7367300000


Patent and Royalties cost = Rs 294600000

Thus, Direct Production Cost = Rs 3315285000 ----- (45% of TPC)

E. Plant overhead Costs


I. Plant overhead cost = 60% of Direct production cost
Plant overhead cost = Rs 4420380000

Thus, Manufacture cost = Direct production


cost + Fixed charges + Plant overhead costs.
Manufacture cost = (3315285000) +
(1105100000)+ (4420380000 )
Manufacture cost = Rs 8840765000

II. General Expenses = Administrative costs + distribution and selling costs + research and
development costs

A. Administrative costs= 5% of total product cost


Administrative costs = Rs 165764250
B. Distribution and Selling costs= 15% of total product cost
Distribution and Selling costs = Rs 497292700
C. Research and Development costs= 5% of total product cost
Research and Development costs = Rs 165764250
D. Financing (interest):
Interest = 5% of total capital investment
Interest = Rs 230500000

Thus, General Expenses = Rs 1059321200

III. Total Production cost = Manufacture cost + General Expenses


= (8840765000) + (1059321200)
Total production cost = Rs9900086200

IV. Gross Earnings/Income:


Wholesale Selling Price of TPA per kg = Rs 42
Total Income = Selling price Quantity of product manufactured Total
Income = Rs. 45*361600000=Rs 16272000000

Gross income = Total Income Total Product Cost =16272000000 (9900086200)


Gross Income = Rs 6371913800

Let the Tax rate be 45%


Net Profit = Gross income - Taxes = Gross income (1- Tax rate) Net
profit = 6371913800 *(1-0.45) = Rs 3504552590
Rate of Return:

Rate of return = Net profit100/Total Capital Investment Rate of


Return = 3504552590100/ (4610000000)
Rate of Return = 75 %

Pay Out Period=FCI/(net profit after tax per year+ Depreciation)


=601000000/(3504552590+ 641440000)
POP = 1.4 years

Das könnte Ihnen auch gefallen