1 Material Estimation for Renovation of Pati

Brick Works
S. Total Wastage Required Total
Particulars Rate / Pcs
No Quantity Quantity Quantity Amount

Danchi Appa (Bricks)


1 4000 60% 2400 18 43200
2x4x8.5
2 Kun Appa (Bricks) 140 70% 98 24 2352
3 Normal Brick 2x4x9 820 80% 656 15 9840
4 Jhingati roof tiles 6000 50% 3000 20 60000
TOTAL (A) 115392

Cement, Sand and Mud


Works
S. Required
Particulars Rate / Qty Total Amount
No Quantity

Cement For Laying Bricks


1 18 935 16830
(Bags)
Sand For laying bricks (Cu.
2 58 6000
Ft.)
Mud For laying Jhingati
3 56 5000
Roof Tiles (Cu. Ft.)
TOTAL (B) 27830

Wood
Works
Total
S. Length (in Breadth (in Height (in Volume (in Rate /
Particulars No. Amoun
No Feet) Feet) Feet) Cu. Ft.) Volume
t
Wooden
1 8.5 0.33 0.5 4 5.61 6000 33660
Beam

33,66
TOTAL (C)
0
Labor Rate Estimation for renovation
2
of Pati

S. Total Rate/Perso
Particulars Unit Total Amount
No Quantity n

Brick Works ( 4" Inner Brick Wall in


1 Sq. ft. 153
cement Mortar) 1200 * 20
24000
Brick Works (Brick face Works with DAYS
2 Sq. ft. 466
Danchi Appa)
Carpente Carpenter 1500 * 5
3 Wooden Works 7500
rs cost s cost DAYS
3000 * 2
4 Jhingati Works Sq. ft. 350 6000
DAYS
TOTAL 37500

3 Total Rate Estimation for renovation of Pati

S.
Particulars Total Amount
No

Material Cost Estimation for renovation of Pati


1 179222
(A+B+C)
2 Labor Cost Estimation for renovation of Pati 37500

TOTAL 2,16,722