Sie sind auf Seite 1von 15

HAIL SURFACE FACILITIES EPS

PROJECT

INSTRUMENTATION LOOP TEST

INDEX LIST

Included
DOCUMENT REMARK
YES NO
ICAPS Form - Loop Test Report
Drawings:
- PID
- Loop Diagram
- Wiring Diagram
- Hook-up Drawing
- Vendor drawing
Data Sheets
Alarm & Trip List
Reports:
- Instrument Calibration Report
- Instrument Check List
- Cable Testing (single/multicore)
- Junction Box Check List
(only copy)
Punch List
Other Certificates/Reports

Accepted by CONTRACTOR COMPANY


SIGNATURE :
NAME :
DATE :
Instrument Loop Test
*H10002996*
*H10002996*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0137 - Instrument Loop REV 0
BF : P-5000T DWG/PID: HD-EC-TF-YZDA-0001/HD-EC-TF-BQDA-0001
V-5600-HF TO V-5110-TF Task Location: MUBARRAZ User Group: TR
Sub-system : M-PR-001 - Oil Slug Catcher Sub-system
ASSOCIATED ITEMS
JBNPA-5004T, JBNPA-5004T-C, PAH-5000T, PAL-5000T, PI-5000T, PT-5000T, PT-5000T-C

TEST RESULTS
(Record ICSS values for inputs and field values for outputs)
TAG:
Segment:
Device address:
Range & units:
I/O type:
0%/OFF:
25%:
50%:
75%:
TEST

100%/ON:
75%:
50%:
25%:
0%/OFF:
LL:
ALARMS/
TRIPS

L:
H:
HH:
Normal state versus faulty process conditions: OK NOT OK N/A
VALVE TEST AIR SUPPLY (bar) OPEN/CLOSE TIME (s) FAIL POSITION (O/C/H) DISCREPANCY TIMER**

** Adjust (when required) timer value for discrepancy alarm (case ON/OFF valves & MOV).

CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


GENERAL NOTES:
V-5602-TF
OIL PIG RECEIVER 1. PRESSURE INSTRUMENT DBB WILL BE MONO BLOCK DBB VALVE
ASSEMBLY.
SIZE : MAJOR BARREL : 22 INCH NOTE 16 2500# 300# A59AN 2. ALL INSTRUMENT TAG NUMBERS WILL BE SUFFIXED WITH `T' FOR
SIZE : MINOR BARREL : 18 INCH SP=3500 psig MUBARRAZ ISLAND.
LENGTH : 6635 mm (NOTE 23) 3. SMALL BORE PIPING BRANCHES UNDER ASME B31.3 CODE WELDED TO
112"D3" DNV-OS-F101 PIPELINE WILL BE TESTED JOINTLY WITH THE PIPELINE
DESIGN PRESS. : 3500 psig FIRE CASE SLOPE 1:500 ACCORDING TO DNV CODE REQUIREMENTS UP TO THE FIRST FLANGED
PSV TO FLARE HEADER
DESIGN TEMP. : 200/-2.2 F FB,LO 6"X3" JOINT AVAILABLE AS STATED IN 8598-TQ-0101-PIPELINE HYDROTEST.
5000 6"-FL-A59AN-5005

F19AN 2500#
TRIM : F19AN HD-EC-TF-BQDA-0018
3" NOTE 5
3/4"
3"X112" NOTES:
F19AN A59AN 1. NITROGEN PURGING CONNECTION/WATER FLUSHING CONNECTION.
2. QUICK OPENING END CLOSURE DOOR WILL BE EQUIPPED WITH A
SLOPE 1:500 PRESSURE LOCKING DEVICE TO PREVENT OPENING OF DOOR
NOTE 2 TO FLARE HEADER WHEN THE PIG TRAP IS PRESSURIZED. THE VALVES DESIGNATED
2"-FL-A59AN-5007 WITH THIS NOTE WILL BE PROVIDED WITH MECHANICAL KEY TYPE
HD-EC-TF-BQDA-0018
2"I.K I.K 2" NOTE 5 INTERLOCK. FOR ADDITIONAL INFORMATION ABOUT INTERLOCKING
SEQUENCE REFER TO OPERATION AND MAINTENANCE MANUAL DOC
NO. HD-EC-CM-BZ0M-0001.
RO

3"-P-F19AN-5081
3. VALVE INTERNAL DIAMETER TO BE IDENTICAL TO PIPELINE

2"-P-F19AN-5082
NOTE 1 5000
SLOPE 1:500 INTERNAL DIAMETER.
TO FLARE HEADER 4. ALL PIPE LINE VALVES WITH DNV-OS-F101 SPEC. TO BE TOP
ENTRY.
NC 2" HD-EC-TF-BQDA-0018 5. NO LOW POINT/NO POCKET.
2" 6. AVOID DEAD LEG.
7. PRESSURE INDICATOR TO BE VISIBLE FROM PIG LAUNCHER

600MM
MIN.
/RECEIVER DOOR SCALE OF PRESSURE INDICATOR FROM 0 TO
NOTE 2 2" 15 psig BUT PRESSURE RATED TO LINE PRESSURE.
PI 8. CORROSION COUPON, CORROSION PROBE WILL BE RETRACTABLE
5001A/B UNDER PRESSURE. THE ACCESS FITTINGS WILL BE LOCATED AT

2"-FL-A59AN-5006
LL 2" THE HORIZONTAL LINE AT 6 O'CLOCK POSITION.
2"-P-F19AN-5080 NOTE 7 9. VALVE TO BE PROVIDED WITH INCHING FACILITY & MECHANICAL
1oo2 1" STOP.
VOTING PG 10. INTRUSIVE TYPE PIG SIGNALER.
ESD 5002 11. CORROSION COUPON, CORROSION PROBE TO BE PROVIDED ON
2T 2" REMOVABLE SPOOL PIECE.
NOTES 10,24 NOTE 2 12. PAVED AREA WITH LOCAL PIT.
TSO
XI 13. FOR INITIAL PRESSURIZATION.
2" 14. LOW DIFFERENTIAL PRESSURE OPEN PERMISSIVE FOR MAIN SDV

ASME SEC. VIII DIV2


5010 PG NOTE 2
TSO FROM PCS.

BY PIG SIGNALER
5001 NOTE 10 2" 15. DELETED.
PT PT

DNV-OS-F101

RS
16. WARE HOUSE SPARE TO BE PROVIDED. TAG NAME PSV-5000SH.
2"-P-F19AN-5141

XI
2"-P-F19AN-5140

5001A 5001B ASME B31.3

BY PIG SIGNALER

VENDOR
5001 17. PIPING SUPPORTS WILL BE DESIGNED FOR SLUG FLOW.
ESD
2H XS 2" 3/4" 3" 2" 2" ASME SEC. VIII DIV2 18. REFER OPERATING & CONTROL PHILOSOPHY (DOC. NO.

VENDOR
2T
3.1T 5010 N7 N6 N9 HD-EC-CM-BDBE-0006) AND OPERATION AND MAINTENANCE
7.1T NOTE 26 1500# 1500# 1500#
FB MANUAL DOC NO. HD-EC-CM-BZ0M-0001 FOR DETAILS OF
18" MULTIPHASE PIPELINE MOV MOV 2" LO 2" PIGGING SEQUENTIAL STEPS.
API 5L GR X65, 1500#
2" 2" FB 2" 5001 5002 2" 2" 2" V-5602-TF 19. TELL-TALE CONNECTION.
SDV LO N5 N10 N8
NOTE 28 A2 NOTE 2 20. LINE PROVIDED TO RECOVER OIL FROM OIL PIPELINE IN CASE OF
FROM OIL PIG LAUNCHER 5000 MIN. M MIN. M 1500# 1500# 1500#
(REF.DOC.3)
22" EMERGENCY.
(V-5600-HF) NOTES 21,27 1500# 21. OIL PIPELINE (18"), GAS INJECTION PIPELINE (6") AND GAS LIFT
HD-EC-HF-BQDA-0009
IJ
A1 1500#
1500# N2 N1 PIPELINE (8") INCLUDING HOT INDUCTION BENDS (EXCEPT FOR
U/G A/G API 5L GR X65 FC API 5L GR X65 18" 18" 18" 1:100
DNV-OS-F101 1500# FB,TSO FB,TSO,FL FB,TSO,FL 1500# 4" 8" 1500# BARRED TEES, PIPING FLANGES AND INSULATION JOINTS) ARE
TYPE 01 DNV-OS-F101 1500# N3 N4 CONSIDERED AS MATERIALS ORDERED BY ADOC (PRIOR TO EPC
F19AN TYPE 04 TYPE 04
ASME B31.3 F19AN
MIN 4" 4"
NOTES 3,4,14,25 ASME B31.3 NOTES 2,3,4 NOTES 2,3,4 ASME SEC. VIII DIV2 EXECUTION).
ASME B31.3 F19AN 22. DELETED.
2"-P-F19AN-5139

DNV-OS-F101 API 5L GR X65, 1500# ASME B31.3


DNV-OS-F101 API 5L GR X65, 1500# 8"-P-F19AN-5078 23. PIG RECEIVER LENGTH BASED ON AN EXPECTED MAXIMUM PIG
F19AN 4"
NOTE 2 TSO MIN DRAIN TRAY LENGTH OF 1500mm FOR CLEAN OPERATION ONLY ACCORDING TO
API 5L GR X65 ESD ASME B31.3
DNV-OS-F101 1500# 2T LC LC 1"-DL-A59AN-5119 LETTERS HDS-EPC-L-T-025 MODIFICATION TO DESIGN OF PIG
3.1T LAUNCHER/RECEIVER, HDS-EPC-L-T-093 MODIFICATION TO PIG
ASME B31.3 F19AN BALANCE LINE

2"-DL-A59AN-5144
4" 4"-P-F19AN-5079 1" 1" TRAP DIMENSIONS AND 8598-TRAD-ADOC-LET-PM-131
NOTE 21
2" NOTE 2 TSO 4"-P-F19AN-5110
SDV NOTE 19 MODIFICATION TO PIG TRAP DIMENSIONS.
2" F19AN 4" F19AN A59AN 24. HAZOP RECOMMENDATION NO.15: RELOCATE PIG SIGNALLER
5001 2"-P-F19AN-5109 NOTE 2 8" NOTE 2 TSO XS-5010 DOWNSTREAM SDV-5000 TO FACILITATE MAINTENANCE.
A59AN TSO

600 MM
2" 1" 25. CLOSING OF SDV WILL GENERATE AN ALARM IN PCS.

MIN.
NOTE 26 26. VALVE TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070
TSO,FC CORRECTION OF INSTRUMENTATION TAG NO. OF MOV & SDV.
TYPE 01 MOV 4"-P-F19AN-5077 1"
5000 F19AN A59AN 27. PERSONNEL PROTECTION INSULATION ONLY FOR ONSHORE AG

600MM
NOTE 13

MIN.
PORTABLE BARREL PIPELINE IN HAIL (IN MUBARRAZ AG PIPELINE PERSONNEL
DNV-OS-F101 API 5L GR X65 1500# NOTE 2 4" F19AN 2" PROTECTION IS NOT REQUIRED, THE MAXIMUM OPERATIONAL
A59AN NOTE 12 CATCH BASIN TEMPERATURE IS 150F).
2" 2" ASME B31.3 M 18"
FL
F19AN CB-04 28. FOR DETAILED INFORMATION SEE REFERENCE DOCUMENT 3.
NOTE 9 TYPE 04

DPT
NOTE 2 8"
TSO NOTE 2 4" F19AN HOLDS:
5000 A59AN 1. DELETED.
2. DELETED.
3. DELETED.
NNF RECEIVER LINE 8" NOTE 6

4"-DC-A59AN-5062
2"-DC-A59AN-5158
ESD
7.1T
NOTE 14 REFERENCE DOCUMENTATION (REF.DOC.):

A59AN 1 PIPING AND INSTRUMENT DIAGRAM HD-EC-CM-BQDA-0001


SYMBOLS LEGEND
H 2" F19AN P&ID SYMBOLS & LEGENDS-PIPING/INSTRUMENT
DPI 4"-DC-A59AN-5061 NOTE 6 2 HD-EC-CM-BQDA-0002
INTERFACE
5000 RO GA WITH DIMENSIONS AND LOADING DATA
I.K 3 HD-EC-TF-VR0A-3001
5003 I.K (V-5602-TF)
3" 2" NOTE 2
1"
2"-DC-A59AN-5059 2 14/10/16 ISSUED FOR CONSTRUCTION MPL VVD PSC
3" MPL VVD PSC
2" 2" 1 09/08/16 ISSUED FOR CONSTRUCTION
2"-DC-A59AN-5111
PI H MPL VVD PSC

600 MM
0 26/04/16 ISSUED FOR CONSTRUCTION

MIN.
5000 L
F19AN A59AN TI C 18/03/16 ISSUED FOR DESIGN MPL VVD PSC
5000
B ISSUED FOR HAZOP MPL VVD PSC
4"-DC-A59AN-5062
1" 04/01/16
PT 2"
RO RO 5000
5010 I.K
I.K
I.K
I.K
5011 2" PG TT 2" A 30/11/15 ISSUED FOR REVIEW MPL VVD PSC
5000 5000 REV DATE DESCRIPTION DR`N CH'D AP`D
3" 2" F19AN
A59AN TG TE SP SCALE: LOCATION: MUBARRAZ PROJECT No.: 8598
5000 5000 001
TO SLUG CATCHER
2" 2" (V-5110-TF)
18"-P-F19AN-5076
HD-EC-TF-BQDA-0002
NOTE 20

NOTE 20

NOTE 17
TW TW
5000G 5000 CP CC
NNF 2"-DC-A59AN-5115
NOTES 8,11 TO PRODUCTION SEPARATOR
NNF 3"-P-F19AN-5105
(V-5120-TF) PROJECT HAIL SURFACE FACILITIES
HD-EC-TF-BQDA-0003 EPS PROJECT
SLOPE 1:300
DRG. TITLE: PIPING AND INSTRUMENT DIAGRAM
TO CLOSED DRAIN HEADER HAIL OIL PIG RECEIVER

SHT. SIZE: A1
4"-DC-A59AN-5062
HD-EC-TF-BQDA-0017
REV
DWG. NO. HD-EC-TF-BQDA-0001 SH.- 1 OF 1NO. 2
CAD FILE: HD-EC-TF-BQDA-0001.DWG
FIELD TECHNICAL ROOM
INSTRUMENT JUNCTION BOX / LOCAL PANEL MARSHALLING CABINET SYSTEM CABINET

CABINET NODE SLOT


PRIM PCS-SYS-103 01 02

TF-PAR-512 PCS-IFP-601
TAG: PT -5000 T F2
PT-5000T JBNPA-5004T PCS-IFP-601 PCS-SYS-103
TS TS JBNPA-5004T-C pos: 9 A1BA4D

PR1 PT-5000T-C PR1 PR7 JBNPA-5004T-C PR7 CS TAG: PT5000T


+ +7 13 9A CN1 INA
BLK BLK BLK BLK BLK BLK BLK BLK IO TYPE: AI CH.: 9
- -7 14 9B CN2
WHT WHT WHT WHT WHT WHT

P&ID. HD-EC-TF-BQDA-0001
P&ID Description HAIL OIL PIG RECEIVER
NOTES: DRAWING NO.

HAIL SURFACE FACILITIES


EPS PROJECT
HD-EC-TF-YZDA-0001
LOOP NUMBER: P -5000 T
B 23/02/2017 ISSUE FOR REVIEW
LOOP DIAGRAM (INSTRUMENT & F&G) LOOP SERVICE:
P- 4203 .S 1
A 08/07/2016 ISSUE FOR REVIEW
Area No.: MUBARAZ_ISLAND
V-5600-HF TO V-5110-TF
Rev Date Description Unit No.: 200_MUBARAZ ISLAND Rev: B
3DQHO &DEOH :LUH7DJ :LUH7DJ &DEOH 3DQHO
7HUPLQDO 7HUPLQDO 7HUPLQDO
7HUPLQDO6WULS &DEOH6HW &RORU &RORU &DEOH6HW 7HUPLQDO6WULS
JBHCV-5000T HCV-5000T-C HCV -5000 T HCV -5000 T JBNPA-5004T-C PCS-IFP-601
+1 +1 1
TS PR1 BLK BLK PR1 JBNPA-5004T-C
JBHCV-5000T HCV-5000T-C HCV -5000 T HCV -5000 T JBNPA-5004T-C PCS-IFP-601
-1 -1 2
TS PR1 WHT WHT PR1 JBNPA-5004T-C
Shield JBNPA-5004T-C
Sh1
Metal PR1
JBHCV-5000T HCV-5000T-C ZT -5000 T ZT -5000 T JBNPA-5004T-C PCS-IFP-601
+2 +2 3
TS PR2 BLK BLK PR2 JBNPA-5004T-C
JBHCV-5000T HCV-5000T-C ZT -5000 T ZT -5000 T JBNPA-5004T-C PCS-IFP-601
-2 -2 4
TS PR2 WHT WHT PR2 JBNPA-5004T-C
Shield JBNPA-5004T-C
Sh2
Metal PR2
PT-5004T PT-5004T-C PT -5004 T PT -5004 T JBNPA-5004T-C PCS-IFP-601
+ +3 5
TS PR1 BLK BLK PR3 JBNPA-5004T-C
PT-5004T PT-5004T-C PT -5004 T PT -5004 T JBNPA-5004T-C PCS-IFP-601
- -3 6
TS PR1 WHT WHT PR3 JBNPA-5004T-C
PT-5004T-C Shield Shield JBNPA-5004T-C
Sh3
PR1 Metal Metal PR3
PCV-5005AT PCV-5005AT-C PCV -5005AT PCV -5005AT JBNPA-5004T-C PCS-IFP-601
+ +4 7
TS PR1 BLK BLK PR4 JBNPA-5004T-C
PCV-5005AT PCV-5005AT-C PCV -5005AT PCV -5005AT JBNPA-5004T-C PCS-IFP-601
- -4 8
TS PR1 WHT WHT PR4 JBNPA-5004T-C
PCV-5005AT-C Shield Shield JBNPA-5004T-C
Sh4
PR1 Metal Metal PR4
PCV-5005BT PCV-5005BT-C PCV -5005BT PCV -5005BT JBNPA-5004T-C PCS-IFP-601
+ +5 9
TS PR1 BLK BLK PR5 JBNPA-5004T-C
PCV-5005BT PCV-5005BT-C PCV -5005BT PCV -5005BT JBNPA-5004T-C PCS-IFP-601
- -5 10
TS PR1 WHT WHT PR5 JBNPA-5004T-C
PCV-5005BT-C Shield Shield JBNPA-5004T-C
Sh5
PR1 Metal Metal PR5
ZT-5005BT ZT-5005BT-C ZT -5005BT ZT -5005BT JBNPA-5004T-C PCS-IFP-601
+ +6 11
TS PR1 BLK BLK PR6 JBNPA-5004T-C
ZT-5005BT ZT-5005BT-C ZT -5005BT ZT -5005BT JBNPA-5004T-C PCS-IFP-601
- -6 12
TS PR1 WHT WHT PR6 JBNPA-5004T-C
ZT-5005BT-C Shield Shield JBNPA-5004T-C
Sh6
PR1 Metal Metal PR6
PT-5000T PT-5000T-C PT -5000 T PT -5000 T JBNPA-5004T-C PCS-IFP-601
+ +7 13
TS PR1 BLK BLK PR7 JBNPA-5004T-C
PT-5000T PT-5000T-C PT -5000 T PT -5000 T JBNPA-5004T-C PCS-IFP-601
- -7 14
TS PR1 WHT WHT PR7 JBNPA-5004T-C
PT-5000T-C Shield Shield JBNPA-5004T-C
Sh7
PR1 Metal Metal PR7
TT-5000T TT-5000T-C TT -5000 T TT -5000 T JBNPA-5004T-C PCS-IFP-601
+ +8 15
TS PR1 BLK BLK PR8 JBNPA-5004T-C
TT-5000T TT-5000T-C TT -5000 T TT -5000 T JBNPA-5004T-C PCS-IFP-601
- -8 16
TS PR1 WHT WHT PR8 JBNPA-5004T-C

Plant Name: HAIL_DEVELOPMENT

Panel Strip With Adjacent Connections


1 MAP 07/02/2017 ISSUE FOR DESIGN RGP Panel: JBNPA-5004T Page 1 of 3
0 MAP 24/06/2016 ISSUE FOR DESIGN RPG Strip: TS
A MAP 24/02/2016 ISSUE FOR REVIEW RPG P- 006
No. By Date Description Sign. By Doc. No: HD-EC-TF-YZDA-0004 Rev: 1
NEW

GENERAL
1 Tag No. PT -5000 T 7 Area Classification ZONE 1, IIB, T3
2 Service HAIL FLUID TO V-5110-TF 8 Ambient Temperature 40F to 185F
3 Line No. 18"-P-F19AN-5076 9
4 Line Size Line Schedule 18 in 160 10
5 Equipment No. 11
6 PID No. HD-EC-TF-BQDA-0001 12
TRANSMITTER BODY ELECTRONIC
13 Instrument Function Gauge Pressure 55 Mounting Yoke 2" Pipe
14 Element Type MFR Standard 56 Power Supply / From 24 VDC PCS
15 Element Material Hastelloy C276 57 Accuracy % Repeatibility 0.1% span
16 Body Material 316 SS 58 Output Signal 4-20 mA Hart
17 Material Detail 316 59 Electrical Protection Ex'd'
18 Body Rating 1500 lbs 60 IP Rating IP 66
19 Overrange Protection 150% of calibrated range 61 Zero Adjustment External
20 Vent Drain No Yes 62 Electrical Connections M20 x 2uds plugged
21 Fill Fluid Silicone oil 63 Span Adjustable External
22 Wetted O-Rings Material PTFE or equivalent 64 Calibrated Range psi 0 - 720
23 Bolts Material 316 SS 65 DCS Range psi 0 - 720
24 Housing Material 316L SS 66
25 Process Connection 1/2" NPTF 67
26 Instrum. Range Limits psi -14.5 - 7200 68
27 Static Pressure Rating 1500 lbs 69
28 70
29 71
DIAPHRAGM SEALS ACCESSORIES
30 Seal Type NA Without Seal 72 Indicator Digital Local Indicator
31 Flange Size / Rating NA NA 73 Integral Meter Scale Yes
32 Flange Facing / Finish NA NA 74 Mounting Bracket Yes
33 Capillary Type / Length NA NA 75 Integral Manifold Yes
34 Capillary Material NA 76 Manifold Type 2 Valve Block/Bleed
35 Fill Fluid NA 77 Manifold Material Incoloy 825
36 Flushing Connection NA 78 Manifold Process Connection 1/2" NPT(F)
37 Diaphragm Material - 79 Manifold Model 2050CDADAOAA
38 Model NA 80 Sunshade Yes
39 Process Connection NA 81
40 Upper Housing Material NA 82
41 Lower Housing Material NA 83
PROCESS DATA REQUIREMENTS AND TEST
42 Fluid Name CRUDE OIL/GAS 84 NACE Requirements Yes
43 Fluid Phase N/A or other 85 Material Certificate Yes
44 Operating Conditions Min Norm Max 86 Test Requirements Yes
45 Pressure (upstream) psig 130 130 300 87 Factory Configuration Yes
46 Temperature F 150 88 Factory Calibration Yes
47 Corrosive Agents Yes 89 SIL Requirement SIL - 2
48 Toxic Agents Yes 90
49 Design Press. Min / Max psig 3500 91
50 Design Temp. Min / Max F -2.2 260 92
51 93
52 94
53 95
54 96
PURCHASE DATA NOTES
97 Manufacturer YOKOGAWA 103 See notes
98 Model Number EJA530EJDS4N02DEL/KU22/D1/C2/T08/M15+QIC
99 Mtr. Requisition HD-EC-CM-YZIR-1041
100 Smart Plant Code KB1301
101 Order No. 0859810410
102 Item Number
INSTRUMENT SPECIFICATION
1 JGV 24/10/2016 ISSUED FOR DESIGN
0 CFT 17/05/2016 ISSUED FOR DESIGN Pressure Transmitter
A JGV 19/01/2016 ISSUE FOR REVIEW Sheet S-65.1 of 208
No. By Date Revision Spec: 203 Dwg. No.: HD-EC-CM-YZIH-0009 Rev.: 1
L-YC-I203-B, Rev 1 Print Date: 10/24/2016 Project Rev. 0
Tag Number : PT -5000 T

1. All the wetted part materials shall be in accordance with NACE requirement as per NACE MR0175/ISO15156 (latest edition).
2. Type 3.1 Certificate of Material Certification (Standard EN 10204:2004) shall be provided.
3. Positive Material Identification shall be provided.
4. Test inspection shall be performed and provided.

INSTRUMENT SPECIFICATION

1 JGV 24/10/2016 ISSUED FOR DESIGN Pressure Transmitter


0 CFT 17/05/2016 ISSUED FOR DESIGN
A JGV 19/01/2016 ISSUE FOR REVIEW Sheet S-65.2 of 208
No. By Date Revision Code: 203 Dwg. No.: HD-EC-CM-YZIH-0009 Rev.: 1
Project N: 8598 REV. DATE DESCRIPTION PREPARED CHECKED APPROVED PROJ.
Doc N: HD-EC-CM-BQIB-0001 A 08/01/2016 ISSUED FOR REVIEW MPL VVD PSC HAIL SURFACE FACILITIES EPS PROJECT
Rev: 1 0 21/04/2016 ISSUED FOR DESIGN 
MPL VVD PSC MUBARRAZ ISLAND


ABU DHABI OIL CO., LTD (JAPAN) 1 09/08/2016 ISSUED FOR DESIGN MPL VVD PSC

ALARM AND TRIP SUMMARY

NORMAL
ALARMS / TRIPS (SET POINT)
REV. INSTRUMENT TAG NO. SERVICE LOCATION OPERATING ACTION P&ID REMARKS
VALUE LL L H HH
18" MULTIPHASE
TOTAL PRODUCTION SHUTDOWN FOR EPS FACILITY AT
PT-5001A 18" MULTIPHASE PIPELINE PRESSURE PIPELINE 130 psig 95 psig - - - HD-EC-TF-BQDA-0001
MUBARRAZ
API 5L GR X65, 1500#
18" MULTIPHASE
TOTAL PRODUCTION SHUTDOWN FOR EPS FACILITY AT
PT-5001B 18" MULTIPHASE PIPELINE PRESSURE PIPELINE 130 psig 95 psig - - - HD-EC-TF-BQDA-0001
MUBARRAZ
API 5L GR X65, 1500#

OIL PIG RECEIVER (V-5602-TF) MAIN LINE


1 PT-5000
PRESSURE
18"-P-F19AN-5076 130 psig - 105 psig 150 psig - ALARM HD-EC-TF-BQDA-0001

18" MULTIPHASE PIPELINE OPERATING PRESSURE. PRESSURE DROP ACROSS SDV-5000 (BALL VALVE FB TYPE) AND ITS
130 psig LOW DIFFERENTIAL PRESSURE OPEN PERMISSIVE FOR SDV-
DPT-5000 DIFFERENTIAL PRESSURE IN SDV-5000/1 PIPELINE - - 100 psi - HD-EC-TF-BQDA-0001 BY-PASS VALVE SDV-5001 (FOR INITIAL PRESSURIZATION) IS MEASURED BY DPT-5000. NORMAL
(SEE REMARKS) 5000
API 5L GR X65, 1500# OPERATING DIFFERENTIAL PRESSURE WILL REMAIN BELOW HIGH PRESSURE ALARM SET POINT.
OIL SLUG CATCHER (V-5110-TF) INLET LINE
PT-5004 PRESSURE 18"-P-F19AN-5076 130 psig - - 150 psig 185 psig ALARM HD-EC-TF-BQDA-0002
(BEFORE CHOKE)

SPLIT RANGE PRESSURE CONTROLLER ACTING ON PCV-


PT-5005 OIL SLUG CATCHER PRESSURE V-5110-TF 90 psig 70 psig 75 psig 95 psig - HD-EC-TF-BQDA-0002
5005A/B TO REGULATE VESSEL PRESSURE

PT-5006A OIL SLUG CATCHER PRESSURE V-5110-TF 90 psig - - - 100 psig OIL SLUG CATCHER SHUTDOWN HD-EC-TF-BQDA-0002

PT-5006B OIL SLUG CATCHER PRESSURE V-5110-TF 90 psig - - - 100 psig OIL SLUG CATCHER SHUTDOWN HD-EC-TF-BQDA-0002

SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG


LT-5000A OIL SLUG CATCHER LEVEL V-5110-TF 1000 mm 300 mm - - - CLOSE SDV-5004 HD-EC-TF-BQDA-0002
NO. OF MOV & SDV. PREVIOUS SDV TAG NUMBER (IFD) WAS SDV-5002

SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG


LT-5000B OIL SLUG CATCHER LEVEL V-5110-TF 1000 mm 300 mm - - - CLOSE SDV-5004 HD-EC-TF-BQDA-0002
NO. OF MOV & SDV. PREVIOUS SDV TAG NUMBER (IFD) WAS SDV-5002

SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG


LT-5008A OIL SLUG CATCHER LEVEL V-5110-TF 1000 mm - - - 3450 mm CLOSE SDV-5002 AND SDV-5003 HD-EC-TF-BQDA-0002 NO. OF MOV & SDV. PREVIOUS SDV-5004 AND SDV-5005 TAG NUMBERS (IFD) WERE SDV-5002 AND SDV-
5003, RESPECTIVELY
SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG
LT-5008B OIL SLUG CATCHER LEVEL V-5110-TF 1000 mm - - - 3450 mm CLOSE SDV-5002 AND SDV-5003 HD-EC-TF-BQDA-0002 NO. OF MOV & SDV. PREVIOUS SDV-5004 AND SDV-5005 TAG NUMBERS (IFD) WERE SDV-5002 AND SDV-
5003, RESPECTIVELY

LEVEL CONTROLLER ACTING ON FCV-5002 HAZOP RECOMMENDATION NO. 31: REDUCE SET VALUE OF LAH-5002 TO PROVIDE MORE TIME FOR
LT-5002 OIL SLUG CATCHER LEVEL V-5110-TF 1000 mm - 450 mm 2600 mm - HD-EC-TF-BQDA-0002
TO CONTROL LIQUID LEVEL IN THE SLUG CATCHER OPERATOR RESPONSE

SLUG CATCHER (V-5110-TF) OIL OUTLET LINE FLOW CONTROLLER ACTING ON FCV-5002 TO STEADY THE
FT-5002
FLOW
14"-P-A59AN-5083 8201 ft3/h - - 9841 ft3/h -
FLOW AND AVOID OVERLOAD
HD-EC-TF-BQDA-0002

SLUG CATCHER (V-5110-TF) GAS OUTLET LINE


FT-5001
FLOW
12"-G-A59AN-5035 198408 ft3/h - - 238720 ft3/h - ALARM HD-EC-TF-BQDA-0002

SPLIT RANGE PRESSURE CONTROLLER ACTING ON


PT-5007 PRODUCTION SEPARATOR PRESSURE V-5120-TF 55 psig 45 psig 50 psig 75 psig - HD-EC-TF-BQDA-0003
PCV-5007A/B TO REGULATE VESSEL PRESSURE

PT-5008A PRODUCTION SEPARATOR PRESSURE V-5120-TF 55 psig - - - 100 psig PRODUCTION SEPARATOR SHUTDOWN HD-EC-TF-BQDA-0003

PT-5008B PRODUCTION SEPARATOR PRESSURE V-5120-TF 55 psig - - - 100 psig PRODUCTION SEPARATOR SHUTDOWN HD-EC-TF-BQDA-0003

SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG


PRODUCTION SEPARATOR LEVEL CLOSED DRAIN SYSTEM AND FLARE KOD SYSTEM SHUTDOWN
LT-5005A V-5120-TF 2500 mm - - - 2750 mm HD-EC-TF-BQDA-0003 NO. OF MOV & SDV. PREVIOUS SDV-5010A/B, SDV-5004, SDV-5005 AND SDV-5006 TAG NUMBERS (IFD)
(OIL COMPARTMENT) OPEN SDV-5010A/B, CLOSE SDV-5004, SDV-5005 AND SDV-5006
WERE SDV-5014A/B, SDV-5002, SDV-5007 AND SDV-5008 AND RESPECTIVELY
SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG
PRODUCTION SEPARATOR LEVEL CLOSED DRAIN SYSTEM AND FLARE KOD SYSTEM SHUTDOWN
LT-5005B V-5120-TF 2500 mm - - - 2750 mm HD-EC-TF-BQDA-0003 NO. OF MOV & SDV. PREVIOUS SDV-5010A/B, SDV-5004, SDV-5005 AND SDV-5006 TAG NUMBERS (IFD)
(OIL COMPARTMENT) OPEN SDV-5010A/B, CLOSE SDV-5004, SDV-5005 AND SDV-5006
WERE SDV-5014A/B, SDV-5002, SDV-5007 AND SDV-5008 AND RESPECTIVELY

PRODUCTION SEPARATOR LEVEL P-5120A/B-TF SHUTDOWN SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG
LT-5006A V-5120-TF 2500 mm 500 mm - - - HD-EC-TF-BQDA-0003
(OIL COMPARTMENT) CLOSE SDV-5009 NO. OF MOV & SDV. PREVIOUS SDV TAG NUMBER (IFD) WAS SDV-5011

PRODUCTION SEPARATOR LEVEL P-5120A/B-TF SHUTDOWN SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG
LT-5006B V-5120-TF 2500 mm 500 mm - - - HD-EC-TF-BQDA-0003
(OIL COMPARTMENT) CLOSE SDV-5009 NO. OF MOV & SDV. PREVIOUS SDV TAG NUMBER (IFD) WAS SDV-5011

PRODUCTION SEPARATOR INTERFACE LEVEL


LT-5004 V-5120-TF 1500 mm - 600 mm 1600 mm 1800 mm LEVEL CONTROLLER ACTING ON LCV-5004 HD-EC-TF-BQDA-0003
(WATER COMPARTMENT)

SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG


PRODUCTION SEPARATOR INTERFACE LEVEL INTERFACE LOW LEVEL TRIP TO AVOID OIL GAS BLOW-BY
LT-5009A V-5120-TF 1500 mm 300 mm - - - HD-EC-TF-BQDA-0003 NO. OF MOV & SDV. PREVIOUS SDV-5008 AND SDV-5007 TAG NUMBERS (IFD) WERE SDV-5009 AND SDV-
(WATER COMPARTMENT) CLOSE SDV-5008 AND SDV-5007
5010, RESPECTIVELY
SDV TAG NUMBER ACCORDING TO LETTER HDS-EPC-L-T-070 CORRECTION OF INSTRUMENTATION TAG
PRODUCTION SEPARATOR INTERFACE LEVEL INTERFACE LOW LEVEL TRIP TO AVOID OIL GAS BLOW-BY
LT-5009B V-5120-TF 1500 mm 300 mm - - - HD-EC-TF-BQDA-0003 NO. OF MOV & SDV. PREVIOUS SDV-5008 AND SDV-5007 TAG NUMBERS (IFD) WERE SDV-5009 AND SDV-
(WATER COMPARTMENT) CLOSE SDV-5008 AND SDV-5007
5010, RESPECTIVELY

HD-EC-CM-BQIB-0001 Rev. 1
Sheet 1 of 7
Instrument Check List
*H10001626*
*H10001626*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0041 - Electrical instrument REV 0
Item : PT-5000T DWG/PID: HD-EC-TF-BQDA-0001
PRESSURE TRANSMITTER Task Location: MUBARRAZ User Group: TARGET
Sub-system : M-PR-001 - Oil Slug Catcher Sub-system
1 Check for mechanical damage.
2 Check installed equipment is suitable and conforms to specification.
3 Check installation conforms to P&ID and hook-up drawing.
4 Check tube fittings manufacturer is the one chosen for the plant.
5 Check piping connections provide required block & bleed facility.
6 Check insulation and heat-tracing.
7 Check identification (tag number, tag plates).
8 Check supporting and protection against vibrations.
9 Check the continuity of the I.E earth (since interconnection is achieved through junction boxes and instruments)
10 Check calibration certificate.
11 Check electrical connections.
12 Check cable conformity and identification at instrument side.
13 Check cable gland conformity and mounting.
14 Check earthing connections (cable armour and screen).
15 Check ATEX certificate.
16 Flush instrument pipework with dry air.

17 Check equipment is correctly preserved.


18 Produce marked-up documents in accordance with installation.
NA Not Applicable X Checked & not accepted O Checked & accepted
Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


Instrument Test Sheet
*H10010470*
*H10010470*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0095 - Analogue O/P REV 0
Item : PT-5000T DWG/PID: HD-EC-TF-BQDA-0001
PRESSURE TRANSMITTER Task Location: MUBARRAZ User Group: TR
Sub-system : M-PR-001 - Oil Slug Catcher Sub-system

DATA
MODEL N : SERIAL N :
VENDOR CALIBRATION MANUAL N :
CALIBRATION/TEST PROCEDURE N :
DATA SHEET N : Rev :
TEST EQUIPMENT : SERIAL N :

TEST DETAILS
CALIBRATION FIGURES
INPUT RISING INPUT FALLING
SPAN ACTUAL UNITS ACTUAL %SPAN mA %ERROR SPAN ACTUAL UNITS ACTUAL %SPAN mA %ERROR

0% 100%

25% 75%

50% 50%

75% 25%

100% 0%

TESTED LABEL AFFIXED DATA SHEET ATTACHED

Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


Instrument Check List
*H10009923*
*H10009923*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0043 - Multi/Single-core instrument control cable REV 0
Item : PT-5000T-C DWG/PID: HD-EC-TF-YZDL-0001
01x2x1.5/XLPE/OA.SCR/SWA/LSZH Task Location: MUBARRAZ User Group: TR
Sub-system : M-PR-001 - Oil Slug Catcher Sub-system
1 Check cable is as specified in project cable schedule.
2 Check relevant documents are at the latest revision.
3 Check cable is routed in accordance with cable layout drawings.
4 Check cable for any physical damage.
5 Check cable is adequately supported and correctly fixed to rack according to Project specification.
6 Check bending radius is within the specified limits.
7 Check cable is correctly loomed and segregated in accordance with specification.
8 Check cable and core marking are in accordance with specification.
9 Check cable labelling is in accordance with specification.
10 Check glands, shrouds, MCTU and earthing are in accordance with specification.
11 Check terminations are in accordance with termination diagram, and produce "AS BUILT" terminations drawings.
12 Check gland plate for single core cables is non ferrous.
NA Not Applicable X Checked & not accepted O Checked & accepted

CONTINUITY INSULATION
TEST ALL CORES AND RECORD LOWEST VALUE
CORES CORE to EARTH
SCREEN CORE to CORE
EARTH CORE to SCREEN
ARMr CORE to ARMr
SCREEN to EARTH
TEST VOLTS
SCREEN to ARMr
TESTING INSTRUMENTS USED
TYPE / SERIAL N : Calibration date

TYPE / SERIAL N : Calibration date

Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


Instrument Check List
*H10000992*
*H10000992*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0145 - Junction & marshalling box REV 0
Item : JBNPA-5004T DWG/PID: HD-EC-TF-YZPA-0001
JUNCTION BOX Task Location: MUBARRAZ User Group: TARGET
Sub-system : M-IN-010 - Multicable and Junction Boxes Sub-system
1 Check equipment is de-energized and safe.
2 Check available documents are at the latest revision.
3 Check nameplate data/certification is in accordance w ith project data.
4 Check all flange faces are clean and greased w ith approved lubicants, and that all bolts are fitted and correctly tight (Exd only).
5 Check all gaskets and bolts are fitted in covers and gland plates w here applicable.
6 Check enclosure is correctly tagged as per draw ing.
7 Check enclosure is correctly earthed in accordance w ith project data.
8 Check all unused entries are plugged w ith approved blanks.
9 Check that terminals are approved and that the correct numbers are fitted (refer to manufacturer's certificates).
10 Check segregation barriers are fitted w here necessary.
11 Check enclosure is correctly mounted and easily accessible.
12 Produce a set of marked-up draw ings w hich are in accordance w ith the installation.
13 Review of the FAT punch list.
NA Not Applicable X Checked & not accepted O Checked & accepted
Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


Instrument Check List
*H10008239*
*H10008239*
ABU DHABI OIL CO., LTD (JAPAN)
HD-EC-CM-BPGB-0043 - Multi/Single-core instrument control cable REV 0
Item : JBNPA-5004T-C DWG/PID: HD-EC-TF-YZDL-0001
20x2x1.0/XLPE/OA.SCR+IND.SCR/SWA/LSZH Task Location: MUBARRAZ User Group: TARGET
Sub-system : M-IN-010 - Multicable and Junction Boxes Sub-system
1 Check cable is as specified in project cable schedule.
2 Check relevant documents are at the latest revision.
3 Check cable is routed in accordance with cable layout drawings.
4 Check cable for any physical damage.
5 Check cable is adequately supported and correctly fixed to rack according to Project specification.
6 Check bending radius is within the specified limits.
7 Check cable is correctly loomed and segregated in accordance with specification.
8 Check cable and core marking are in accordance with specification.
9 Check cable labelling is in accordance with specification.
10 Check glands, shrouds, MCTU and earthing are in accordance with specification.
11 Check terminations are in accordance with termination diagram, and produce "AS BUILT" terminations drawings.
12 Check gland plate for single core cables is non ferrous.
NA Not Applicable X Checked & not accepted O Checked & accepted

CONTINUITY INSULATION
TEST ALL CORES AND RECORD LOWEST VALUE
CORES CORE to EARTH
SCREEN CORE to CORE
EARTH CORE to SCREEN
ARMr CORE to ARMr
SCREEN to EARTH
TEST VOLTS
SCREEN to ARMr
TESTING INSTRUMENTS USED
TYPE / SERIAL N : Calibration date

TYPE / SERIAL N : Calibration date

Remarks :

SUBCONTRACTOR CONTRACTOR COMPANY

Signature

Name

Date

PRINTED ON 05/05/2017 SHEET 1 OF 1


HAIL SURFACE FACILITIES
MEC. COMPLETION
PRE-COMMISSIONING
EPS PROJECT
RFC WALKDOWN
COMM. ASSISTANCE
ABU DHABI OIL CO., LTD (JAPAN) PUNCH LIST ENTRY FORM
AREA: 1 - CATEGORY: 2 - DISCIPLINE: 3 - TO BE ACTIONED BY: PUNCH LIST ENTRY
A - TO BE RESOLVED PRIOR TO COMMENCEMENT OF B - BUILDING O - OPERATION ENG - ENGINEERING FORM No.:
MODULE: PRE-COMMISSIONING ACTIVITIES C - CIVIL WORK P - PIPING & VESSEL CONS - CONSTRUCTION (to be filled by ICAPS eng.):
B - TO BE RESOLVED PRIOR TO COMMENCEMENT OF E - ELECTRICAL S - SAFETY COMM - COMMISSIONING
COMMISSIONING AND START-UP / HANDOVER H - HVAC T - TELECOM VEN - VENDOR
EWP / CWP: C - TO BE RESOLVED AGREED WITH COMPANY I - INSTRUMENTATION X - SUBSEA SUB - SUBCONTRACTOR
APPROVED PROGRAM M - MECHANICAL Z - MISCELLANEOUS COMP - COMPANY

SUBSYSTEM:
Engineering Material Originator
Item Number Cat. Fault description Discipline Action required required Corrective action
YES / NO YES / NO CONTRACTOR COMPANY

SUBCONTRACTOR CONTRACTOR COMPANY

DATE

NAME

SIGNATURE
HD-EC-CM-ZQGB-0014, Rev.3

Das könnte Ihnen auch gefallen