Beruflich Dokumente
Kultur Dokumente
5 No 2 J u n e 1970 Contents
THEARUP
Published by
Ove Arup Et Partners Consulting Engineers
Arup Associates Architects and Engineers
1 3 Fitzroy Street. London. W1 P 6BQ
T h e background to
the modern design
of w i n d - s e n s i t i v e
st J itures.
r
by K. Anthony
G l a s g o w Airport 10
Development,
by H Stears
S o n i c booms 14
and ancient buildings,
by P. B e c k m a n n
West Norwood 1 7
Library and Public Hall,
by J . Morrison
Surface finishes, 22
by T. O'Brien
been a d v a n c e d and generally accepted. All
that is required of the engineer is the substitu-
tion into these expressions of constants appro- Fig. 3
priate to the w i n d re'gime, the site and the W i n d speed versus return period
structure. Almost, that is, for although the
manner in w h i c h the w i n d may be thus des-
cribed is fairly w e l l established, some degree of
judgement and intuition is needed in applying probability distributions more than adequately still existing among some engineers, that the
it to one's o w n particular design problem. well. 'highest recorded gust' is a meaningful
Although the principles described in this criterion to adopt.
It is in this description of the w i n d that some
article may apply equally w e l l to other Mention should be made of a promising
difficulty may be experienced in understand-
averaging durations, the mean hourly w i n d development by Thorn w h o has found that
ing some of the concepts and terminology
speed will be used as the basis from w h i c h to extreme w i n d distributions may w e l l have
used in the statistical approach. It may be use-
start. particular characteristics w h i c h enable pre-
ful, therefore, to provide some background
before proceeding further. Firstly, let us look H o w is the mean hourly w i n d speed predicted? dictions to be made on the basis of m a x i m u m
at some of the characteristics of the mean The m e c h a n i c s of determining this have been mean monthly w i n d speeds. T h e significance
wind. dealt with in the past by several authors, of this is that it may not be necessary to
notably Shellard, Thorn and Davenport, but accrue many years of annual extreme data.
The mean wind
again, it may be useful to outline the concepts The readily available monthly means may be
Why, for instance, should the one hour mean used in assessing annual probabilities.
here. Basically, the highest mean hourly w i n d
be an appropriate basis to u s e ? Apart from So for any particular location w h e r e annual
speed occurring each year is recorded at the
certain meteorological significances, there are extreme data is available, the w i n d speeds
observation station to provide a set of m a x i -
structural implications. relating to any chosen probability can be
mum values w h i c h can then be analyzed
If the mean w i n d speed is to represent the using extreme value statistics. determined. If this exercise is carried out for a
source of the static load on the structure, then A minimum of about 15 annual v a l u e s is large number of observation stations
the choice of the averaging time to be used for necessary for reasonably accurate estimates to throughout a country, a set of contours or
the mean must depend upon several f a c t o r s : isotachs can be drawn for e a c h probability.
be made. Naturally, the greater the number,
1 T h e c h o s e n period should result in a the more reliable are the estimates. Extreme T h i s w a s done several years ago by Thorn for
reasonably constant mean speed. values behave statistically s o m e w h a t dif- the U S A and more recently in this country by
2 T h e period should be short enough to c o n - ferently from the population from w h i c h they Shellard and Helliwell of the M e t e o r o l o g i c ^ ^ ^
tain the w o r s t effects of a short duration are derived. Rather than fitting the Normal Office. T h e w i n d map in B R S Digest 99 a n l ^ F
storm. distribution, they may conform to a number of the n e w draft code is an example. In these
other l a w s s u c h as the Fisher-Tippett T y p e s . cases, the map indicates not mean hourly
3 It should be long enough for the structure to
I, II (Frechet) and III (Weibull) probability values, but three second gust speeds associat-
attain steady state conditions.
distributions. These are basically logarithmic ed w i t h an annual probability of 0 . 0 2 . Naturally,
4 Data for the chosen period should be as time goes by and more data is collected,
transformations of each other.
readily available.
W h i c h e v e r distribution is found suitable there these maps need to be revised.
5 T h e data should conform reasonably to It is common practice to use the terms recur-
are various w a y s of handling the data. A
appropriate probability theory. rence interval or return period w h e n talking of
particularly easy method, attributable to
The ideal averaging period has been given as Lieblein, is by means of order statistics, but annual probabilities. T h e relationship is
between 10 and 1 5 minutes. This is b e c a u s e : w h i c h e v e r method is adopted, the final result simple. If F ( V ) is the probability of the extreme
i T h i s period lies w e l l within the meteorolo- of interest for any particular location is a set of w i n d _NOT exceeding the value V . then
gical 'spectral gap', meaning that values of w i n d speeds w i t h their associated probabilities 1-F(V) is the probability of it being
w i n d speed averaged over different periods (Fig. 3 ) . T h e concept is rather like that of exceeded at least once in any given year. T h e
of time w i t h i n this range w o u l d not be very Olympic G a m e s records. There exists n o w a return period, expressed in years is then.
different from each other. record for the long-jump. In some years the
ii S o u r c e s of high w i n d s s u c h as thunder- record is not broken but w h e n it is, the length
storms and squalls w h i c h usually last from jumped is greater than the previous one. H e n c e
R
= 1 _ F(V) ( 1 )
5 to 10 minutes w o u l d be contained within as time passes, the record distance can only
the period. increasenever decrease. It may be w o n - There still exists some misunderstanding of the
iii S i n c e the natural periods of structures are dered w h e t h e r there is some physical limit meaning of the return period. In effect, it is the
usually less than 10 s e c o n d s . 1 0 - 1 5 beyond w h i c h it is impossible to j u m p . average interval of time b e t w e e n o c c u r r e n c e s
minutes is ample time for steady state c o n - Similarly, there may be some physical limit to of a particular w i n d speed being reached or
ditions to develop. w i n d speed, but it is clear that even if s u c h a exceeded at least once during an infinite
However, very f e w meteorological organiza- limit should exist, it w o u l d be too high to be of period of time. There is no periodicity implicit
tions use s u c h a period for recording data, but interest in structural design. A s far as the in this definition. One cannot say that a par-
most do have data on the one hour mean. T h e theory of extremes is c o n c e r n e d there is no ticular value w i l l occur every 5 0 years, 1 0 0
above three conditions apply equally w e l l to upper boundonly lower and lower proba- years, or whatever. One cannot say when it
this period w h i c h has statistical reasons for bility for higher and higher w i n d speeds. will occur. It could be today, it could be
being a most acceptable parameter, not least of T h e s e considerations apply equally w e l l to entirely outside the return period, or it c o u l d
w h i c h is that its data has been found to fit other time averages and highlight the fallacy. happen any number of times w i t h i n the period.
Although it may not a l w a y s be consciously variable behaves in a random manner. In other W e must then, have some knowledge of the
considered, buildings have an anticipated life- w o r d s , no 'trends' are displayed during the power spectrum and correlation functions in
time. Some structures are designed to a period under consideration. T h e significance order to describe these sequential and spatial
specific length of service. In N e w York, this is of the term 'stationary' can be appreciated if it actions of the w i n d . It is w e l l k n o w n that
often as l o w as 3 0 years. T h e only really is remembered that our basic physical model however random a continuous time series may
meaningful statement that can be made is that of a high w i n d is a mean f l o w stirred m e c h a n i - be. it is theoretically possible by Fourier
a given w i n d speed has a certain c h a n c e of cally by the roughness of the ground over analysis to break d o w n the series into separate
occurring or being exceeded w i t h i n a specified w h i c h it passes. A laboratory analogue of this sine or c o s i n e forms of differing frequencies
number of years. It is clear that this c h a n c e model is a w i n d tunnel w i t h a roughened and amplitudes. One w a y of visualizing the
must become greater as the specified number floor. In s u c h a tunnel, the mean f l o w is deter- power spectrum is to think of it as a means of
of years is increased. mined by the fan setting and the turbulent describing the manner in w h i c h the total w i n d
fluctuations superimposed on the mean are energy is distributed over the entire range of
As this principle is of the utmost importance to
generated by the floor roughness. S u p p o s e these frequencies contained in the f l u c t u a -
a probabilistic approach, it is w o r t h w h i l e
that in such a tunnel, the fan setting and the tions. In order to arrive at a fuller understand-
looking at it a little closer. T h e question a
floor roughness w e r e maintained and a ing of the meaning of the spectrum, it is c o n -
designer may ask himself is 'What return
venient to consider the fundamental properties
period, R, should I use in designing my struc- number of records w e r e obtained in the form
referred to previously. In fact, if the power
ture w h i c h has an anticipated life of n years if I of traces of w i n d speed against time, all the
spectrum w e r e to be estimated theoretically,
am willing to accept a risk, P, of a w i n d speed, records w o u l d be different but simple averages
the step by step procedure w o u l d be to make
V, being e x c e e d e d during the n y e a r s ? ' T h e s u c h as the standard deviation and the root
separate estimates of these fundamental
risk or probability, P , may be given by mean square w o u l d be almost identical for all
n
parameters.
the records. It follows then that the average
Pn=1-[F(7)]" ..(2) properties determined from one record yield It has already been explained that the struc-
information about the average properties of tural engineer need not concern himself w i t h
= 1-[1-1/R] n
-..(3)
the entire collection of records. In statistical the theoretical determination of these para-
= 1-e~ n , R
(approx.) .. .. (4)
terminology, any one of the records is called a meters to design his structure. T h e f o l l o w i n g
~ n / R (approx. for small sample or realization taken from an infinite brief descriptions of the statistical properties
values of n) ....(5) collection or statistical ensemble of records. of the stationary process w h i c h constitutes the
S u c h an ensemble is stationary if the external fluctuations in w i n d speed are offered as a n
from w h i c h R and hence the design w i n d controlling factors, the fan setting and the aid to the understanding of the concepts and
speed may be calculated or read off an appro- floor roughness, remain the same. terminology commonly used.
priate graph s u c h as Fig. 3.
In the case of our model of atmospheric To simplify the explanations, a single w i n d
t is often thought that the probability of, say, turbulence, it is assumed that a record, record will be considered. T h i s restricts us to
I 50 year return period w i n d occurring within obtained in high w i n d conditions w i t h given the study of the properties of the fluctuations
any given interval of 50 years must be unity. mean hourly w i n d speed and ground rough- in the time sense and in the direction of the
Application of equation ( 3 ) will reveal thatthe ness, is one sample from the stationary mean w i n d , but the concepts apply equally
c h a n c e is, in fact. 0.63. This is w h a t is meant ensemble of records w h i c h could be obtained w e l l to the other w i n d speed vectors implicit in
by the 0.63 probability level in the B R S Digest at the site. Deductions about the average the turbulence. The considerations are illus-
101 and n e w draft C P 3 Chapter V in choosing properties of gusts contained in the sample trated in Figs. 4 to 11 w h e r e the mathematical
the S factor. Whether or not this 2 in 3 c h a n c e
3 are assumed, therefore, to be generally expressions will also be f o u n d for each para-
can be considered as an acceptable risk is a applicable to all s u c h records, meter. It should also be made clear that, as the
question of load factors. b statistics of the mean w i n d speed have already
Equations ( 3 ) and ( 5 ) are also useful w h e n It has already been inferred that a structure been dealt w i t h , w e are c o n c e r n e d n o w w i t h
determining suitable loadings for components will be responsive to the time sequential fluctuations only. That is, the random variable
as opposed to entire structures. It might be manner in w h i c h the fluctuating load is applied n o w in question is the w i n d speed relative to
reasonable, for instance, to consider replacing and that the pulsating nature of gusts can give the meannot the absolute value.
a f e w damaged w i n d o w s or light cladding rise to magnifications in levels of stress and The variance, o (v)
2
panels every f e w years rather than overdesign deflection,etc. I t w a s also implied that, should
all of them. In assessing the acceptable risk, the structure be large, long or high, then The variance of the random function may be
the c o n s e q u e n c e s of failure call for consider- because of the turbulent nature of the w i n d , physically derived from a w i n d record by
able thought. T h e principle of acceptable risk gusts will not occur simultaneously over the summing the squares of a large number of
and length of service is valid for a multitude of face, length or height of the structure. That is, gust speeds and dividing by the number_of
problems associated w i t h variable loadings the gusts will not be fully correlated over the values taken. T h e result is the mean square, v . 2
and strengths. The portion of the w i n d loading structure. of the gust speed. Fig. 4.
w h i c h gives rise to the static response of the
structure can thus be dealt w i t h , having
chosen a probability suitable to the risk one
'ishes to take for the design of the structure
' element in question.
Let us n o w turn our attention to the fluctuating
part of the w i n d load.
The fluctuations (gusts)
It w a s stated earlier that the fluctuating part of
the w i n d regime could be fully described by
the probability distribution, the power s p e c - * a
trum and the cross-correlation functions.
Before an insight into the meaning of these
terms may be gained, it is necessary firstly to
U
5 ^
/
term intensity of turbulence which is
measured by the ratio of the root mean square
of the gust speeds to the mean value of the -v(t).v(t*T)
w i n d speed.
random process itself. It is clear, however, that other in some respects, but as the separation T o gain an insight into the meaning of the
similar operations may be carried out on the distance increases, any such influence power spectrum, let us return briefly to the
fluctuations occurring at t w o different points decreases until the distance is so great that no autocovariance function. Let us also consider
in space. In this case, the pairs of values are effect is felt at all. a very simple fluctuating velocity function
formed from the t w o separate records. Extending the concept further, it is possible, ( F i g . 9 ) , of the cosine form,
Correlations, then, may be defined in space as between t w o points in space, to evaluate
well as time. It is convenient to mention space spatial correlations between different c o m - v = a cos 2rcnt (6)
correlations at this juncture, before turning to ponents of the gust velocities. Furthermore,
the power spectrum, because the concepts one is not restricted to cross-correlations at w h e r e a is the amplitude, n is the frequency,
f o l l o w directly from those previously d i s - zero time lag. One could correlate one c o m - t is time and T ( = 1 / n ) is the period. If the
cussed. ponent at one point w i t h another component autocovariance w e r e to be calculated by
Instead of considering, as w e have done, the at another point at various intervals of time taking N pairs of v a l u e s of v separated by a
time correlation between a down-wind later. In all, as there are three components at time lag x = T , the result w o u l d be
(longitudinal) component of w i n d speed w i t h each of the t w o points in space, there must be
respect to time lags, one could evaluate the nine different cross-correlations that could be
performed. W h i c h of these is of interest to a C (T) =
V
. (7)
correlation between the same components
recorded at t w o different points in space but structural designer depends on the geometry
w i t h respect to the distance between the t w o of the structure and on the mode of behaviour S i n c e the values of v are equal to a for r = T .
points. One could visualize doing this in under consideration. The designer of a tall 2T. 3T, etc.. it is clear that v = a at T = 0 . It
practice by setting up one anemometer in a slender building w o u l d be interested in the will be remembered that for zero lag, the auto-
fixed position and another capable of being vertical correlations of longitudinal and trans- covariance becomes equal to the variance,
verse components because he w o u l d be c o n - w h i c h in this case of a cosine form will also be
moved to any location in space. Simultaneous
cerned with the d o w n - w i n d and a c r o s s - w i n d a 2
correlation function since the spatial separa- to simplify the considerations, and therefore
tions are equivalent to time lags consistent r*(v) C (0) -
v
^ (8)
the design procedure, greatly.
with the mean f l o w velocity. In a turbulent It will be recalled that the statistical method of i=1
airstream having a mean speed of. say. 4 0 m / design being described is concerned w i t h w h e r e N is the number of c o s i n e w a v e s
second (1 31 f t . / s e c o n d | . a spatial separation of both time and spatial correlations. T h e first present. The variance of a time series c o n t a i n -
4 0 m is equivalent to a time lag of one s e c o n d . enables us to take a c c o u n t of the repetitive ing a mixture of cosine w a v e s c a n , therefore,
T h e turbulent w i n d regime is assumed to be nature of gust loading and the second to allow be regarded as being made up of c o m p o n e n t s
carried d o w n - w i n d at the mean w i n d velocity. for the non-uniform manner in w h i c h w i n d of the average power or variance at the various
T h i s assumption, k n o w n as Taylor's H y p o - acts over a tall or extended structure and/or individual frequencies. All the frequencies
thesis, does not apply vertically, because mean across the faces of a large building. Both forms contribute to make up the w h o l e spectrum of
^ ^ w i n d speeds increase generally w i t h height. of correlation have been discussed but the variance or power. There will be so many
individual frequencies in a random function
that one can talk of there being a continuous
range of frequencies. T h e power spectrum
may. then, be defined by
ff (v)
2
= C (0) =
v
S (n) dn. . .(9)
v
^ ^ A A 4
velocity t force response
CO
r\ A
1 V V f y
otv) olv off off oiy] oly
Fig. 14
Graphical representation of the design procedure (after Davenport)
Glasgow a w a y , the site of the then existing airport. T h e
same design team w a s therefore c o m m i s -
ing removing a door and its frames from the
building, handrails from the escalator, and air
/
>
h
)
it,
D /
L
\ /
/
n o *
9 )
:
:
; -
i 8
o
y
Fig. 1
Airport development plan
Fig. 2
Section/elevation of proposed satellite building
V
0>*
i I
Fig. 4
Model of satellite building
( P h o t o : A . L. Hunter of Edinburgh)
11
lighting is contained between the t w i n booms during and after construction, to prevent the main building and the aircraft access
of the prestressed concrete trusses. T h i s form flotation, and s u c h proposals as permanent bridges. T h i s w o r k will generally be carried out
of construction also caters easily for the over- sub-soil drainage, tension piles, and dead as structural steel trusses of spans in the order
hang required for solar shielding purposes. weight at basement slab level are being c o n - of 2 4 - 3 0 m ( 8 0 - 1 0 0 ft.) to provide for future
T h e lower boom and all vertical supporting sidered. A g a i n , due to soil conditions, it will be flexibility and to keep the apron as clear as
steelwork are exposed and the external w a l l s necessary to design basement and ground possible for service vehicle movement.
are glazed at the passenger level. floor slabs as suspended. In addition to these n e w buildings, phase II
A s the building is completely sealed against T h e basic planning of the building results in includes the provision of some 10 hectares
noise, mechanical ventilation is required and columns at 6.1 m ( 2 0 ft.) centres along four ( 2 5 acres) of concrete to the w e s t of the
the ducts are carried from the ground floor longitudinal lines giving rise to floor spans of existing apron (job no. 3 4 1 9 ) . T h e design is
plant rooms vertically through the central 9 m ( 3 0 ft.) and 1 5 m ( 5 0 ft.) w i t h cantilevers based on the requirements of the k n o w n air-
duct, and then distributed by threading their up to 4.6 m (1 5 ft.) on the north side at first craft w i t h a small amount of reserve for any
w a y through the roof grid trusses. In addition, floor level to provide cover for the baggage future possibilities.
further extract facilities are available within the unloading bays. The structural depth at first The very low bearing strength of the subgrade
roof space only, to discharge air through floor is restricted to that adopted in the original on this site necessitates the use of a rigid
sound filters housed in the roof overhangs. building w h i c h is 6 1 0 mm (2 ft.) overall, and pavement to minimize both depth of c o n -
T h e contract for the w h o l e of phase I (job nos. it has been decided that the most economic struction and cost. For the pavement c o n -
3 4 1 5 - 6 ) w e n t out to tender in September solution will be, therefore, to continue with the struction proposed this gives a Load Classifi-
1969, and w a s awarded to J o h n Laing C o n - same form of construction, i.e. a ribbed floor, cation Number of 90. T h e pavement required
struction Ltd.. in November. Phase la w a s spanning across the building on to short span on grassed areas will be 3 0 0 mm ( 1 2 in.)
substantially complete in May 1 9 7 0 . At the beams on the column lines. T h i s will be inter- 'pavement quality' concrete, on 1 0 0 mm
same time as the apron construction, further rupted in certain areas w h e r e there will exist a (4 in.) 'dry lean' concrete, on a minimum of
nose loader bridges and waiting areas w e r e mezzanine w a l k w a y access to the baggage
6 1 0 mm (2 ft.) of compacted infill. T h e 3 0 0
constructed in order that eight aircraft bays reclaim areas. Where this occurs, a 2 5 0 mm
mm ( 1 2 in.) concrete slab will be dowelled.
w o u l d be available to B E A during construction ( 1 0 in.) solid slab will be substituted,
Where there is existing concrete immediately
of the West Pier extension. together w i t h a subsidiary r o w of column ties,
under the n e w pavement, the specification
P h a s e II to prevent excessive deflection of the adjacent
for the latter may be reduced according to
cantilevers. In order to achieve maximum
Unfortunately, the time of submission of the results from bearing tests.
economy of use. the same ribbed floor c o n -
development plan and instruction to proceed Longitudinal and transverse falls at the air-
struction will be adopted for the ground floor
with phase I c a m e at the same time as the craft bays will be, in no instance, greater than
over the basement, and in those areas of the
financial report on the airport, w h i c h included second floor w h e r e suitable. To provide a 0.9% and 0.4% respectively. Collection of
such factors as a major industrial dispute and visual unity to the complete building, the surface water will be by continuous gutter o n i
the collapse of British Eagle, so w e w e r e not second floor office structure used in the the perimeter of the satellite pier aircraft bays.
instructed to proceed w i t h working drawings original building will be extended to the Phase III
of phase II. This instruction has not yet been section of offices in the n e w part, and to the The third phase of the development (job no.
given and is not unconnected with the delay in southern bay at the w e s t end. 3 4 2 0 ) consists of providing large areas of
decision on an extension of the main r u n w a y .
car parking and re-routing service roads on the
T h e extension is, I understand, necessary, in It is proposed to continue w i t h the same form
landside of the airport, and this will probably
the v i e w of the airlines, to allow them to of double skin construction for the roof, using
take place as and w h e n required.
operate the larger aircraft (Trident 3) intended precast concrete arch units spanning between
for the major trunk routes in 1 9 7 1 . Recent trusses. The original form of concrete truss is This completes the k n o w n picture of the
parliamentary a n s w e r s indicate the r u n w a y anticipated but alternative proposals for developments at G l a s g o w Airport w i t h the
length required to operate this aircraft in structural steelwork have been prepared. exception of the hotel w h i c h is at present on
compliance w i t h Board of Trade safety regula- site. T h i s is a joint F o r t e s / B E A project and is
In the n e w satellite pier (job no. 3 4 1 8 ) the being constructed by M a c A l p i n e s . T h e
tions to be 2 , 5 0 0 m ( 8 , 2 0 0 ft.), and another
principle of amalgamating forward assembly remaining future developments are very hazy,
airport operator is understood to require a
areas has been carried to the ultimate. In this but could well include cargo-handling
r u n w a y length of that order before considering
section of the project, 1 2 aircraft bays have facilities.
to operate an airport some 64 km ( 4 0 miles) to
been positioned round a single 61 m ( 2 0 0 ft.)
the east. The proposals for the main terminal The problem w i t h airport development has
diameter building, thus giving minimum
extension (job no. 3 4 1 7 ) are generally to a l w a y s been the rate of growth. In the past the
passenger w a l k i n g distance on final call, and
provide space to deal w i t h an annual capacity actual growth rate has a l w a y s been in excess
minimum apron extent. T h e segregation of
of up to 5m. passengers. T h e original of that predicted and present planners state
arriving and departing passengers has been
philosophy of design, a VA level building that 1 2 % is the minimum, but any figure up to
obtained by the provision of a second floor
concept, is maintained, but the earlier dis- 20% could easily occur at isolated points.
perimeter g a n g w a y connected by ramps to the
advantages of the e c o n o m y - e n f o r c e d , narrow Adopting 12%, it w o u l d appear that the 5 m.
various aircraft bays.
c h e c k - i n hall has been overcome by providing passengers per annum, w h i c h w e have
a c h e c k - i n hall the full depth of the building, The requirement at the perimeter of the build- designed for, w o u l d be reached by 1 9 7 9 . T h e ^
giving space for a total of 50 desks. The ing to provide future flexibility of aircraft present programme for the development p r o - |
ground floor of the existing building will be dispersal will necessitate support at close vides that, w i t h immediate approval to proceed
revamped, and the customs area, together centres to accept the loading from the aircraft to the next stage (phase I I ) , the building
w i t h the bulk of baggage reclaim, will be access bridges on an approximately 2.1 m complex, etc., w o u l d be ready by m i d - 1 9 7 4 ,
resited in the extension. T h e extension is (7 ft.) module. This will be provided for by the by w h i c h time the building w o u l d be required
approximately 1 6 5 m ( 5 4 0 ft.) long and the use of structural steel bents tied to the c o n - to cope w i t h w e l l over 2 / 2 m . passengers per
1
appearance and construction will be generally crete floor slabs at the requisite centres in a n n u m . W e c a n only hope that these estimates
as the major part of the existing building. The order to carry the loads directly to ground are not as far out as the original, w h i c h w a s
foundation problem is as before, but w i t h the level. three years, or w e may have to consider the
added problem of larger and deeper base- development of the development by the time
The ancillary w o r k in connection w i t h the
ments. This will entail taking precautions, both the development is complete.
satellite will consist of the high-level link to
Fig. 5
Bridge to nose-loaders to provide direct covered access from aircraft to the building
12
I I .
mi
J
Fig. 7
External stair to
public v i e w i n g gallery
( P h o t o : Henk S n o e k )
r
Id
Fig. 6 Fig. 8
T h e semi-circular staircase from the concourse to the restaurant and lounge bar C h e c k - i n hall
(Photo : Henk S n o e k ) (Photo : Henk S n o e k )
i I
7
:
-: [TXrJDLLlJ
1
13
Sonic booms ground will be. and hence the pressure ( 5 0 lb./ft. ) range. It is quite clear that super-
2
and ancient T h e shock w a v e s are reflected from the overpressures between 5 0 - 1 5 0 N / m (1 and 2
ground and from any hard surfaces they hit 3 l b . / f t . ) cannot, by any stretch of the
2
(Q I
0 ambient vibration and to 'snifter' bangs in
those positions w h e r e these bangs w o u l d not
be complicated by reflections from nearby
buildings so as to make them too unrepresen-
tative of simple sonic booms. The 'snifter'
responses w e r e measured at five cathedrals.
T h e results of this investigation revealed a
number of factors. Not surprisingly, w a l l s in
and near bell towers had by far their w o r s t
vibrations imposed by bell ringing. Organ play-
ing generally produced oscillations of these
w a l l s a hundred times less intense and the
effect of the 'snifters' varied considerably from
being about ' A of the w o r s t of the bell v i b r a -
tions to less than 7 , o thereof. T o put this
0 0
to the damping effect of the internal friction in not enough, the damping characteristics ( 2 . 5 l b . / f t . ) 'N w a v e ' such as w o u l d result
2
the material and of the aerodynamic resist- of most building materials and assemblies are from a scheduled supersonic overflight.
ance to the oscillations. imperfectly k n o w n , to put it mildly, so that an Generally speaking, taking the average of the
analytical approach to the problem is measurements made on the various cathedrals,
W h e n the damping is substantial, the effect of
generally impractical, and one is therefore the calculations s h o w that the effect of a s o n i c
the forced vibration becomes dependent on
thrown back on to the experimental approach. boom of this magnitude on w a l l s , roofs and
the energy input, as w e l l as the degree of
resonance. If it were possible to produce a 'synthetic sonic vaults, will generally be comparable to. or
boom' producing the same shape of pressure less, than that produced by bell ringing, organ
If elements are built together they interfere playing, etc., and, incidentally, the measure-
with e a c h other's resonance frequencies and w a v e but at reduced intensity, it might be
possible to measure the effect of this and ments also s h o w that traffic vibration
as a result, any element found in a real generally has an insignificant effect.
building will have a large number of frequen- arrive at the effect of real sonic booms by
means of multiplying in proportion to the ratio T h e situation is, however, not nearly so clear
cies at w h i c h it will respond to outside w h e n w e turn to stained glass w i n d o w s . It w a s
excitation. between the pressures.
quite clear that the effects of the 'snifters' w e r e
Whilst the sustained vibration can therefore Whilst measuring the effect of such a synthetic s u c h as to produce accelerations between 5
produce a large amplification of the effect boom, one w o u l d naturally also measure the and 10 times as large as those produced by
w h i c h w o u l d normally result from a simple response of such imposed vibrations as c o n - organ playing. A s the predicted response for
applied force of the same intensity, a sonic stitute part of the normal environment of the the 1 2 0 N / m 2
( 2 . 5 l b . / f t . ) 'N w a v e ' w a s
2
boom represents a mixture of t w o c a s e s ; it is building, i.e.. in the instance of cathedrals, the generally w e l l above that measured from the
not a single force nor a sustained oscillation, ringing of bells and the playing of the organ ; 'snifters', it w o u l d appear that sonic booms
but something in between the t w o . and, whilst and for any historical building in a built-up w o u l d subject stained glass w i n d o w s to s u b -
the oscillations considered in the previous area, the effect of traffic, and. in the case of old stantially greater vibration than anything
paragraphs are generally thought of in terms of slender pinnacles, the effect of w i n d , to see normally occurring as part of cathedral
sine w a v e s ' , the sonic boom has a sharp ' N ' whether the sonic booms w o u l d produce environment. Whilst generally speaking, this
outline. T h i s shape c a n , however, be broken effects of similar or bigger magnitude than w o u l d still not result in w h o l e s a l e shattering,
d o w n into a number of sine w a v e s of different those w h i c h the building appears to sustain there remains the u n k n o w n effect of repeated
frequencies but. the net result is that w e are successfully at present. vibrations and the brittleness w h i c h seems to
considering a system subjected to a short-term T h e perfect simulation of a sonic boom has attack lead w i t h age.
imposition of vibrations at a number of fre- unfortunately not been invented yet. at least
organs have failed and thus start deterioration
w h e r e there w a s none before. Some experi-
mental work on this w o u l d seem to be indica-
ted, as cumulative damage of this nature
NORMAL CONDITIONS INVERSION might be significant.
Further problems
Whilst some progress has undoubtedly been
Stratosphere
made towards better assessment of the effect
(cold air, constant
of sonic booms on ancient buildings there are
temperature)
still many u n a n s w e r e d questions such a s :
'What manoeuvres are possible at supersonic
speeds for Concorde-type aircraft?' T h o s e
w h i c h are possible will be done at some time
or other, even if they are against the regula-
tions and. in that case. 'What will be the
focusing e f f e c t ? ' ' H o w frequently will c l i m a -
tic conditions w i t h cold air on top of w a r m
Troposphere lead to "atmospheric f o c u s i n g " and w h a t
(warmer air, variable pressure magnification is likely to result ?' A n d .
temperature) to look at it another w a y , 'Is it practical to fly
supersonic transport planes at s u c h high alti-
tudes that the M a c h - C o n e will a l w a y s flare
out to vertical above ground level and there-
fore the shock w a v e will not hit the ground ?'
These problems should be fully investigated
before overland supersonic flight is permitted.
After all, the old buildings w e r e here first, and
they give pleasure to many, so the onus must
No Half boom "Atmospherical be on the advocates of speed for the f e w . to
boom carpet width focusing" prove that no damage will be caused.
This summer will see the beginning of a seriesJ
of 5 0 test flights planned to extend over three
years to try the Concorde under normal and
Fig. 3 slightly abnormal operating conditions. These
Normal dispersion of shock w a v e s as opposed to atmospherical focusing flights will take place over the Irish Channel in
the main, but will pass over O b a n . St. D a v i d ' s
and Truro Cathedrals. It is planned to make
measurements, at these cathedrals, of res-
ponses of various elements to sonic booms.
At St. David's, measurements will be taken of
responses to w i n d excitations w h i c h will be
correlated w i t h gust speeds measured at the
same time. In addition to measurements of
dynamic response, a certain amount of instru-
mentation will be provided to try and detect
any permanent deformation caused by these
flights. The small number of flights, coupled
with the fact that in very f e w instances have
measurements been taken of behaviour before
the test flights, make it unlikely that anything
substantial will emerge from these tests, the
more so as they will all be confined to as near
as possible fair weather conditions
A far more promising approach w o u l d seem to
be the ' B l u n d e r b u s s . ' T h i s is a large conical
tube in w h i c h a sudden release of air p r e s s u r e j
by transmission through a long conical funnel,
w i l l , at the w i d e end, produce a very good
As sin f i , yti decreases with increasing speed imitation of the ' N - w a v e ' to any desired
intensity. T h i s w a s w h a t w a s used for the
Fig. 4 stained glass experiments at Farnborough. A
Acceleration focusing larger version is currently being built at the old
R 1 0 1 Hangar at the R A F Station at Cardington
and it may be possible there to carry out
experiments to establish whether or not
At the Royal Aircraft Establishment at Farn- adhere too w e l l , it should be classified as cumulative damage in masonry is going to be a
borough. experiments are currently being vulnerable, together with slender monuments problem !
carried out. in w h i c h panels of mediaeval of friable stone.
M e a n w h i l e guardians of old buildings may
stained glass are being subjected to a s u c c e s -
One last question to w h i c h at present there is find it prudent to measure the responses to
sion of 'synthetic organ music' and ' N - w a v e s '
no clear a n s w e r is due to the fact that, irt the general vibration of the more delicate treasures
produced by a laboratory device. T h e ob|ect of
core of many mediaeval w a l l s , the mortar has in their care and to provide protective stiffen-
these experiments is to compare the behaviour
deteriorated to s u c h an extent that by n o w it is ing to cope w i t h the odd 2 4 0 N / m ( 5 l b . / f t . )
2 2
Fig. 1 Fig. 2
Site plan Ground floor plan (library) and first floor plan (public hall)
G
L
CtMITft*
OHM tMLl
(.Ml
R
_ 5
-
e CITtlKF
f
EITIilCE TO
muc MIL
a n
- I
lig-3
section through
adult library
Fig. 4
Library main entrance ( P h o t o : Ernie Hills)
have, this area, like the w h o l e library, has been entrance and w a l k straight ahead, passing
furnished with subdued luxury by providing the main staircase w h i c h leads up to the
coffee tables and Mines & West chairs (see public hall. T h e area below this main stair will
Fig. 5 ) . A w i n d o w w a s built in the outer w a l l be used as an exhibition area (see Fig. 6 ) .
so that passers-by w o u l d be able to look into The public hall is an octagonal building
the young adult library; it is hoped that this behind the library, the hall proper being at first
v i e w will attract the younger people. T w o floor level and designed to seat 2 5 0 people.
further sides of the courtyard are formed by At ground level there are a restaurant, kitchen,
the adult library and. in the summer, sliding bar and a small room available for hire to
w i n d o w s will be opened so that the borrowers clubs, etc., and below this is the basement
will be able to sit out and browse al fresco. T h e boiler room. For evening functions an alter-
main control area is located between the native main entrance will be used, so that the Fig. 5
administration block and the adult library. main section of the library c a n be closed to the The young adult library
People visiting the latter enter by the main general public (see Fig. 2 ) . ( P h o t o : Ernie Hills)
m
r i
Foundations
A soil survey of the site had s h o w n that there
w a s a small amount of made ground over
8.2 m ( 2 7 ft.) of shrinkable brown clay,
followed by blue London Clay. T h e high
perimeter to floor ratio of the building resulted
in fairly light foundation loads and this fact,
coupled w i t h the presence of shrinkable clay,
ruled out continuous strip foundations. W e
were left w i t h the choice of pad footings or
short bored piles. T w o s c h e m e s were pre-
pared s h o w i n g the alternatives and the
difference in cost between the t w o w a s found
to be negligible. W e decided that piled founda-
tions should be adopted due to the presence of
some Black Poplar trees on the site boundary.
These trees have a rather notorious reputation
and there have been several recorded in-
stances of settlement w h e n they have been
near shallow foundations and shrinkable clay.
The administration building and the public
hall were designed to be supported on pad
footings, as w e felt that the greater weight and
deeper foundations of these blocks w o u l d
make them less susceptible to the movements
of shrinkable clay.
Waterproof construction
Fig. 6 The basement of the public hall is made up of a
T h e entrance staircase boiler room, electrical intake room, trans-
( P h o t o : Ernie Hills) former, oil storage area, ventilation equip-
ment, kitchen, toilets and welfare room. All of
these rooms had floor ducts and as these A l t e r n a t i v e d e s i g n s f o r p u b l i c hall r o o f gated. W e feel that the w a y in w h i c h the
w o u l d have led to complicated tanking We arrived at the final design for the hall roof design developed is of interest and the stages
details, w e decided that waterproof concrete after a series of solutions had been investi- through w h i c h it passed are set out below
should be used for the slabs and retaining
walls.
The soil report had not revealed any evidence
D e v e l o p m e n t of t h e r o o f d e s i g n
of a water table, although slight traces of
water had been encountered during boring. Design criteria Solution
Due to the l o w permeability of the brown
London Clay, w e felt that any surface water 1 T h e plan shape w a s to be octagonal and the Triangulated timber trusses w e r e used ( F i g , 7 ) .
finding its w a y into the backfill around the roof pitched. T h e roof w a s to be visually
retaining w a l l s w o u l d be trapped. Therefore, interesting internally and structural timber
although no ground water w a s k n o w n to be w a s suggested.
present, w e felt it desirable to form a water-
proof basement.
Having once decided that there is water and a
need for waterproofing, the next problem is to
decide the standard of protection that is -
Fig. 11
6 Concealed lighting w a s required on the The ring beam sizes and roof geometry at the
ring beam. Additional electrical services support were modified. Provision w a s made for
were required for the main hall roof services to be fed through rectangular hollow
sections and then into a c h a n n e l section
w h i c h supported the light fittings. Fig. 12
s h o w s the completed s c h e m e and details of
one of the trusses.
F i g . 13
Library seen from the cemetery
( P h o t o : Ernie Hills)
II
iJL.iL
F i g . 14
The projection room
(Photo : Ernie Hills)
~ *^' "HIW .
3 w , l k
F i g . 15
The courtyard
(Photo : Ernie Hills)
"T"
\ 21
Surface Finishes
Turlogh O'Brien
This paper was originally commissioned by compare, at least in a qualitative w a y . The the problems of the environment are receiving
the Institute of Building and was published trouble is that, w i t h surface finishes, it is often considerable attention, at least at a political
in their journal Building T e c h n o l o g y and difficult to describe precisely the standards level. However, freedom from atmospheric
Management April 1970. It is reprinted required. In some cases it is possible to have a pollution w i l l not come quickly and buildings
here with the Institute's permission. mock-up made w h i c h is then used as the must be designed with this in mind.
standard for comparing performance on the
The q u e s t for variety The main visual objection to effects of
lob. In most cases, specifications must rely on
Modern buildings are often said to be dull and weathering is non-uniform staining. F e w
rather general descriptions of uniformity,
repetitive, but more careful observation people mind about a general uniform darken-
flatness, freedom from defects, etc. These
reveals that, at least as far as surface finishes ing of buildings, provided that large sums of
problems may often lead to assumptions being
are concerned, variety is highly valued. T h e money have not been spent on light coloured
made about 'currently accepted good prac-
finishes used within one scheme may be dull finishes (e.g. w h i t e c o n c r e t e ) . The formation
tice'. T h e designer assumes that the contractor
of unplanned dirty streaks is generally c o n -
and repetitive, but variety may be seen by will have the same standards of quality as
sidered to be undesirable.
comparing one with another. Certain fashions himself.
may be found at any one time, ribbed concrete The trouble is that it is extremely difficult to
Under relatively static conditions this w o u l d
being an example at present, but. in general, design external surfaces in s u c h a w a y that
not be expected to cause trouble, but the
the approach may be s u m m e d up by the this does not happen. T h e quest for variety of
quest for variety brings the problem of lack of
cliche 'variety is the spice of life'. colour, texture and profile in finishes means
experience, bothof operativesand supervisors.
In response to this demand, building mater- that each n e w proposal has to be considered
Surface finishes applied in a factory can be
ials' producers have expended considerable on its merits, w i t h o u t recourse to years of past
practiced and a high standard of uniformity
effort in providing a w i d e range of surface experience. A f e w general principles may be
may be obtained. On site, the situation is
finishes on their products. Even humble used for this, but a look at many recent build-
different Even w i t h skilled tradesmen, the
products like bricks have received their share ings suggests that if these have been used at
conditions under w h i c h they w o r k may limit
of surface improvement. Concrete provides the all. they have not been fully understood.
the quality that can be achieved. W h e n n e w
most spectacular example of a material that finishes are required, site staff do not often In addition to weathering defects, failures and
has suffered all manner of ingenious treat- have the c h a n c e to carry out a sufficient loss of youth may arise through i n c o r r e ^
ments in the cause of variety. T h e s h o w r o o m s number of trial samples to get the technique selection of materials and poor detailing of th
of c o m p a n i e s specializing in precast concrete right. They must learn on the job. junctions between them.
cladding are filled with examples of s u c c e s s f u l In addition there is the necessity of ensuring Green staining from copper flashings, streaks
and u n s u c c e s s f u l attempts to enliven the often that expensive surface finishes are not of bitumen at parapets, rust from partly c o n -
dull surface of concrete. T h e results of this damaged during subsequent building opera- cealed steel components w h i c h cannot be
experimentation as seen on recent buildings, tions. Too often, stains or mechanical damage maintained, bleeding of oils or other c o n -
in some cases called sculpture, may not please occur w h i c h must be made good. With n e w stituents from mastics, migration of salts from
everybody, but it should not be long before the materials it is sometimes difficult to remove brickwork to stone and leaching of lime from
'real' surface appearance of concrete can no the traces of the defects and the overall quality concrete to form stalactites may all be seen on
longer be positively identified. of the job is lowered. Some of these problems recent buildings. Many defects are attributable
In the last decade, plastics have finally estab- stem from a lack of understanding on the part to a combination of design and w o r k m a n s h i p
lished a position for themselves in the reper- of the operatives of the amount of money that faults. E x a m p l e s are the loss of adhesion of
toire of external surface finishes. They are may have been invested in achieving particu- mosaic and tiling and of slip bricks on boot
often, however, made to take on the appear- lar finishes. It also arises from the experience lintels, or the inadequate provision of c o m -
ance of something else, usually w o o d , that in traditional building, most of the usual pression joints in cladding, particularly stone,
because many people consider that the 'true' damage may be cleared up or made good in order to prevent load being transferred from
appearance of plastics is unattractive. Plastics relatively easily by time-honoured methods. the concrete frame.
weatherboarding and w o o d - g r a i n e d effects Today, materials that find increasing use on
sites are very difficult to remove (crane oil and Defects of this type call attention to the fact
are c o m m o n . In other cases the surface is
epoxy resins, for example) and traditional that the cladding must be seen as a part of
masked by using stone chippings to provide a
stains (e.g. rust) are difficult to remove from the overall building. The surface finishes may
texture. Plastics are sometimes offered as
n e w surface finishes. be affected by a number of components w h i c h
'maintenance-free' paints, but discussions
in themselves do not necessarily contribute to
w i t h the paint industry w o u l d s h o w that, even
Clay bricks have proved themselves to be the initial appearance. The difficulties of the
if this claim could be substantiated, a w i d e
durable materials for external finishes, and f e w designer have been emphasized already. He j i
range of colours w o u l d be required. Also,
defects usually appear after the building is the man responsible for the performance of t h f l
changing the colour after some years can be a w h o l e s y s t e m , but his detailed knowledge o r
completed. With other materials, and particu-
positive advantage. Paints exemplify one larly w i t h concrete, some defects may not the behaviour of the parts will not be as
extreme of the quest for variety. become apparent for some years after comple- complete as that of the materials' producers.
Even metals have been made to conform to tion. These failures result in expensive repairs, The integration of a w i d e range of increasingly
the n e w ethic of variety. The range of coatings usually involving alterations to the appear- specialized technical factors is a task of great
for steel has increased considerably, partic- ance, and in unpleasant arguments. Their complexity, and this is often notfully apprecia-
ularly w i t h the addition of plastic coatings. avoidance through better quality control is ted by the suppliers on the one hand and the
A l u m i n i u m and stainless steels have been easier to specify than to achieve. Quality contractors on the other. At the same time, the
'improved' ( y o u can n o w get aluminium clad c h e c k s generally take the form of inspections designer often expects the component
w i t h stainless steel) and copper can n o w be of materials arriving on site, but by this stage manufacturer to have a range of understanding
prevented from weathering to its normal green the ability to reject defective components is of building problems that close examination
by the use of clear lacquers. severely restricted by the problems of c o n - w o u l d reveal to be unreasonable.
The search for attractive finishes can take sequent delays to the construction programme.
W h e n put in this w a y , it is clear that the
some surprising turns. W h o w o u l d have Whereas the responsibility for the cost of
problems of avoiding obvious defects in
thought 10 years ago that rusty steel could be replacing defective components is quite clear,
design of surface finishes are formidable. S o
an acceptable decorative material ? Yet the it is usually much more difficult to recover
much effort must go into this that little is left
s l o w rusting 'weathering' steels have been consequential costs, w h i c h may be much
for solving the other weathering problems.
used on some impressive buildings in the U S A larger.
W h e n an attempt is made, it is often too late to
and are slowly catching on here.
Under present conditions, good quality, alter major details because these have been
It seems curious that, alongside the require- durable surface finishes can only be achieved settled at an earlier stage.
ments for standardization for economical mass if everyone concerned is really interested in
production of building components, there It is small wonder, therefore, that, instead of
the result.
should be this trend towards diversity. Per- controlling the weathering of buildings,
haps the latter trend is a direct result of the attempts are often made to prevent it. A s this
The quest for eternal youth fits in w i t h the quest for eternal youth, c o n -
former. T h e a n s w e r is standardized variety, but
it is not clear w h a t this means. The cleaning and restoration of the external siderable effort is being expended to achieve
surfaces of many important buildings seems to it. B u t some building materials just are not
The q u e s t for quality be part of a general fashion for a clean, fresh weather resistant in the right w a y . Invisible
Quality is a difficult attribute to specify. In the look. Whilst this is generally w e l c o m e , it is surface treatments are needed to enable the
context of most building w o r k there is no such necessary to examine the implications if this appearance to remain u n c h a n g e d . Experi-
thing as 'absolute' quality. There are relative approach is carried too far. T h e results of the ence has s h o w n that these are difficult to
22 levels of quality and these are usually easy to Clean Air A c t are n o w being observed, and develop, and those available n o w have limited
durability. T h e most familiar example is that of Fig. 1
clear varnishes for timber. T h e s e require T h e detailing of surface finishes
maintenance at 2 - 3 year intervals. Lacquers occasionally overlooks some
have been developed for preventing the important aspects of the structural
weathering of copper, but they must be system of the building
renewed after a period of 5 - 8 years. T h e poor ( P h o t o by courtesy of the Institute
weathering of concrete has boosted the use of of Building)
silicone water-repellent treatments, but as
w i t h the controversial rejuvenation drug
procaine, silicones only alleviate the s y m p -
toms of ageing, they do not prevent. Regular
courses of treatment are required and these
can be costly.
These thoughts on surface finishes may be
summed up by the following statements:
1 Variety is achieved at the expense of quality.
2 Quality c o m e s w i t h repetition, or at least
with the ability to discard the first attempts.
3 Eternal youth requires costly medication,
and may, in the end, be illusory.
Fig. 2
Non-uniformity of weathering
can produce interesting and
unexpected results.
Unfortunately this is the exception
rather than the rule
ft (Photo by courtesy of the Institute
of Building)
? it
Fig. 3
Variety of surface finishes is
apparent in all types of building.
T h i s modern house has t w o colours
of brick (dark b r o w n , g r e y - b r o w n ) ,
a panel of dark blue mosaic,
light blue painted panels below
first floor w i n d o w s , dark blue
painted garage door, drab-green
painted timber cladding to
water tank, and white paint
elsewhere
( P h o t o by courtesy of the Institute
of Building)