Sie sind auf Seite 1von 10

OTC 6430

m
An Integrated Towed Flowline Bundle Production System for
Subsea Developments
A.S. den Boer and E.J. Rooduyn, Rockwater Offshore Contractors, and W.A. Barber,
Brown & Root Vickers Ltd.

Copyright 1990, Offshore Technology Conference

This paper was presented at the 22nd Annual OTC in Houston, Texas, May 7-10, 1990.

This paper was selected for presentation by the OTC Program Committee following review of Information contained In an abstract submitted by the author(s). Contents of the paper,
as presented, have not been reviewed by the Offshore Technology Conference and are subject to correction by the author(s). The material, as presented, does not necessarily reflect
any position of the Offshore Technology Conference or Its officers. Permission to copy Is restricted to an abstract of not more than 300 words. Illustrations may not be copied. The
abstract should contain conspicuous acknowledgment of where and by whom the paper is presented.

ABSTRACT aubsea intervention.

The concept of the INTEGRATED TOWED FLOWLINE A subsea satellite development typically involves
BUNDLE PRODUCTION SYSTEM (ITFPS) is based on a cluster of wells or a template structure and
onshore construction and testing of a complete the connecting flowlines and control lines to the
subsea system that consists of flowlines and parent facility. This paper introduces the
control lines, as well as facilities for concept of the INTEGRATED TOWED FLOWLINE BUNDLE
manifolding and, if so appropriate, for drilling PRODUCTION SYSTEM. This system combines all
and processing. The installation of such a required flow and control lines within a bundled
system can be done by a pull or towing technique. configuration, together with integrated
facilities for manifolding and processing. It is
The ITFPS is a concept designed for the based on onshore construction and testing of a
development of subsea fields such as: satellites total system that can be installed offshore by
to existing offshore production facilities; a using a towing technique, thereby minimising
floating production development whereby the ITFPS underwater activity during construction and
can include the riserbase on one end, as well as operation.
the production manifold on the other end; or for
a 'near shore' subsea development that can be Installation of submarine pipelines by towing
remotely operated from an onshore base. techniques are now an established and accepted
method of installation. Pipelines can be
installed by bottom tow (with or without added
INTRODUCTION buoyancy), off bottom tow, near surface or
surface tow, or towed at a controlled depth (see
Subsea production dates from the mid sixties, Figure 1 ) . The CONTROLLED DEPTH TOW METHOD
when simple subsea trees were Installed in (CDTM) is particularly suitable for the
shallow water depths, and possibly operated by transportation of onshore fabricated and tested
divers. Ever since the subsea rrrultlwell integrated systems (ITFPS). This relatively new
manifolding and floating production technologies technique for bundle transportation is outlined
have been developed to provide total subsea in the following section.
concepts that now operate satisfactorily,
however, generally in diver accessible depths. GENERAL DESCRIPTION OF CDTM
The present research and development efforts of
the oil majors aim for total remote production The principle of the Controlled Depth Tow Method
systems for developments in water depths beyond (CDTM) involves the transportation of a
diver access by the mid 1990's. Major objectives pre-fabricated and fully tested flowline bundle
in the design of such complex remote systems are suspended between two tugs (see Figure 2 ) . To
to achieve the highest possible system maintain control during the tow, the bundle has
reliability and to develop efficient procedures been designed and constructed within specific
for installation, commissioning, operation and tolerances with respect to its submerged weight.

Table and figures at end of paper

85
2 AN INTEGRATED TOWED FLOWLINE BUNDLE PRODUCTION SYSTEM FOR SUBSEA DEVELOPMENTS OTC 643C
In order to achieve sufficient buoyancy for the have demonstrated the feasibility of towing a
bundle, the flowlines, control lines etc are bundle with larger structures than the size of a
placed within a carrier pipe (see Figure 3 ) . "conventional" towhead and resulted in the
Chains are attached to provide additional weight following alternatives.
in order to obtain a system which has a limited
submerged weight. At rest the bundle floats at
several metres above the seabed. ITFPS CONCEPTS

During tow the drag on the chains creates a "lift The INTEGRATED TOWED FLOWLINE BUNDLE PRODUCTION
force", and so reduces the bundle submerged SYSTEM can accept hydrocarbon production from a
weight and thus the bundle deflections. By number of subsea wells and transport same to a
controlling the towing speed in combination with production facility (see Figure 4 ) .
the tension maintained by the trailing tug at the
rear, the bundle configuration and its To illustrate the flexibility in design of the
deflections are kept under control during ITFPS and its adaptability to meet specific field
transport to location. development requirements, several concepts are
described below (also see Figure 5 ) .
Prior to the tow, a detailed analysis of the
bundle behaviour is made. The relation between 1) FLOWLINE BUNDLE TO SINGLE OR CLUSTER OF
essential parameters such as pull force, tow WELLS
speed, tension and bundle deflection are
calculated, and presented in "towing The CDTM application involves bundles to
characteristics" graphs. The essential connect a fixed production platform to a
parameters are continuously monitored during the single satellite well. The bundle
tow, and adjusted if necessary to maintain the comprises two (TFL) flowlines and a number
desired bundle configuration, well clear of the of hydraulic lines.
seabed and safely under the sea surface wave
actions. The tow takes place along a presurveyed Similarly the bundle configuration can be
route, obstacle-free and with dedicated safe designed to envelop all flowlineB to
"parking areas". When the tow approaches its connect a multi-well template (or a cluster
final location the towspeed is reduced and the of wells) to the production facility. In
bundle is lowered to the seabed within a this case all flowline connections are
pre-selected landing area. situated within the bundle towhead
structure.
At a distance of some metres above the seabed,
the bundle can now easily be manoeuvred into its 2) FLOWLINE BUNDLE WITH LATERAL ENTRIES
final position. Any configuration can be
achieved by UBing temporary anchor blocks to If the reservoir development requires
secure the bundle position. By flooding of the 'spaced-out' tree locations, a series of
carrier pipe annulus the bundle settles to a lateral entries can be provided along the
stable position on the seabed. Tie-ins can be length of the bundle. Each such lateral
made using either direct pull-in type connectors entry will require a small manifold and
or spool pieces of either flexible or rigid pipe. control interface that can be retrofitted
to the side of the bundle. This manifold
Both the bundle installation and the connection will provide entry to an individual or to a
of towheads to gathering and production manifolds bulk flowline and chemical injection as
have been performed diverless in the past, using required. The control interface will
direct pull-in and deflect-to-connect-pull-in connect with the control/data acquisition
type methods. umbillcals.

DEVELOPMENT HISTORY 3) INTEGRATED MANIFOLDING

The first commercial application of CDTM was in The bundle towhead structure is designed tc
1980 in the North Sea on the CONOCO "MURCHISON" accommodate a manifold, to which the subsea
field. Those first bundles were 12 inch in trees can be tied in. Similar to a
diameter, up to 2,000 metres long and 250 tons in separate template manifold this can
mass. Since then CDTM has been further developed provide, for example, dedicated or
and bundles installed are now up to 4,400 metres comingled flowlines systems, full pigging
long. In 1990 the 'largest ever' bundles, loops, pig launch/receipt facilities etc,
diameter 38 inches and 2,700 tons mass, will be and controls and monitoring systems.
installed in the North Sea SHELL "OSPREY" field,
and this will be the first application of If the flowline bundle routing can be
integrated manifolding facilities. Table 1 lists worked out such to also pass an
all completed CDTM projects. intermediate cluster of wells (between
production facility and towhead/manifold),
A natural step in further development of the these can also be tied into the system by
bundle concept is to allow for integration of any using a manifold structure integrated in
component of the subsea system. Recent studies the bundle at such intermediate location.

86
OTC 6430 DEN BOER, ROODUYN & BARBER
Detailed static and dynamic engineering towed out with the bundle.
analyses show that the characteristics of
the bundle are not influenced TYPICAL CASE: BUNDLE TOWHEAD WITH INTEGRATED
significantly (during CDTM tow and MANIFOLD
installation) by the integration of a
manifold on each end. The results show A typical example of a towhead with integrated
that manifolds with a dry weight of up to manifold is presented to highlight the principles
300 ton in combination with a bundle of the system. A four bay production/WI manifold
length of 5km and a bundle diameter up to has been considered since this could handle
40" can be transported and installed in production of 15,000 - 20,000 BOPD and
the field using existing CDTM techniques. associated water injection. This is typical of a
number of marginal fields being considered for
4) ITFPS PULLED INTO PRE-INSTALLED DRILLING development.
TEMPLATE
It has been assumed that the depth of water would
For a major subsea development involving facilitate diver assisted operations for
a cluster of wells, a purposely designed installation and maintenance.
pre-drilling template may be preferred.
This unit is kept deliberately simple and Should a different development scenario be
serves as a receiving module into which a required, such as a diverless system, a
bundle towhead manifold assembly is configuration could be developed to satisfy the
docked. A rapid connection of the requirements. Figure 6 shows typical layouts of
pre-drilled wells can be then the main equipment which governs the overall
accomplished with minimum diver size.
intervention. Again, all required
manifolding functions can be integrated
in the pull-in towhead. 1) FLOWLINE BUNDLE CONFIGURATION

5) STEP-OUT WELL EXTENSIONS Typical flowline sizes with associated


service lines, umbilical and electrical power
Once an XTFPS has been installed, the cables for this example are listed below:
towhead (or any intermediate integrated
manifold structure) can be extended with i) 2 x 8 " insulated product lines
guide posts for drilling of "step-out" ii) 8" water injection line
wells. The preset spacing enables the iii) 2" bulk chemical service line
time (and thus cost) efficient hook-up of iv) 1" hydraulic fluid supply
such step out well extensions. v) 2" umbilical for electric power,
control and data acquisition
6) ITFPS WITH INTEGRATED DRILLING SLOTS vi) 5" umbilical for hydraulic power and
chemical injection.
Drilling slots can also be integrated in
a towhead structure. Where permanent All of these can be pre-installed within a 32
guide bases are utilised all subsea inch diameter carrier pipe and attached to a
hook-ups and tie-ins (from base of towhead manifold for installation by the
platform through manifold to trees) may Controlled Depth Tow Method (CDTM).
be avoided thereby resulting in an
integrated remote drilling and Fabrication of these flowlines and inclusion
manifolding system that is totally of service lines within a bundle affords
pre-connected and tested onshore with the insulation, restrains the hot lines against
required control/data acquisition systems upheaval buckling and thermal expansion, and
and flowlines. provides protection against mechanical
damage, thus eliminating the need for
7) INTEGRATED PROCESSING FACILITIES trenching.

Similar to the features previously


described, a towhead assembly or 2) TOWHEAD
intermediate structure can be designed to
accommodate processing facilities. These The towhead and its associated structure
can be subsea pumping (booster station) serves the following design functions:
or separation systems.
i) Connections for launch and tow-out.
Various subsea production concepts are
being developed for deepwater ii) Buoyancy and protection to the complete
application, based on modular template manifold assembly during tow out and
designs, so enabling remote surface installation.
recovery and replacement of components.
These designs can easily be adapted for iii) Some protection to the complete
incorporation as modules within a towed manifold equipment during the
bundle configuration. production phase, although
supplementary housings may be required
A further application is for near shore according to project needs.
developments where the manifold can be
87
AN INTEGRATED TOWED FLOWLINE BUNDLE PRODUCTION SYSTEM FOR SUBSEA DEVELOPMENTS OTC 6431
iv) 30V docking points for valve The choke valves in this system are
uverride. considered part of the tree package
although it is possible to include these ir.
v) Receptacles for piles to provide the manifold.
additional stability and lateral
rigidity. Connections between wells and the manifold
will be made up by short jumpers and
vi) The towhead may be extended to umbilicals installed by divers.
accommodate additional manifolding
and potential well slot Where diverless systems are required an
developments. overall increase in size of the pull-in
head will result. The manifold will
vii) Within the overall strength require modularisation to allow
requirements for launch and tow-out maintenance/replacement and space
operations, the towhead structural allowances for pull-in and connection
tubular diameter and wall thickness tooling.
will be designed to provide the
required balance between weight and 4) WELLS
displacement parameters.
The production or injection wells utilised
In addition to the above features the in this concept are standard satellite or
integrated towhead incorporates the cluster completions. This allows completed
features of the manifold as discussed in appraisal or development wells to be
the next section. This has the advantage connected into the system immediately after
of eliminating all offshore connectors at installation, providing early revenue.
this interface.
5) CONTROLS AND MONITORING

3) MANIFOLD PIPEWORK AND EQUIPMENT Control pods for the manifold have been
included into the towhead structure. The
The manifold layout has been developed using control pod(s) stab in to a dedicated base
standard equipment with a proven track record mounted on the structure. Pod installatior.
meeting API 5000 psi max WP requirements. and removal is facilitated by a guidance
This offers flexibility of design without system utilising guide wires.
sacrificing reliability and the utilisation
of standard components also minimses lead The hydraulic valve actuators would be
times. controlled by an electro-hydraulic
multiplex system or by means of a direct
The design of the manifold is based upon the supply depending upon line size and
requirement to Incorporate all the equipment response time requirements. Data
in the,;-Bmallest practicable space whilst transmission from the manifold would be vie
affording adequate diver and ROV accesB for communication lines within the control
local override operations and maintenance. umbilical, using the multiplex system if
The arrangement of valves and actuators is available.
such as to provide horizontal access for ROV
intervention. The manifold provides In order to minimise the connections
protection against damage from dropped between the wellheads and the manifold the
objects by means of hinged covers which can well control pods are mounted within the
be folded back to provide vertical access for xmas tree guide frames.
divers.
6) INSTALLATION
The manifold includes arrangements for
commingling, testing and pigging. The bundle, integrated towhead and manifold
are fabricated, connected, hydrotested,
Injection points are provided in the manifold function tested and pre-commissioned on
or at individual wells for bulk chemicals and shore to the maximum extent prior to
Inhibitors as required. launch/tow-out. This ensures that the
control system-is working correctly and
The manifold connections enable a production that adjustments can be made prior to
tree, together with associated jumper spools installation.
and pipework, to be flushed prior to
disconnection. The bundle and manifold are launched and
towed to the offshore site by conventional
The manifold layout shown is for four wells, bundle installation methodB. The manifold
but additional wells could be accommodated by is like a large towhead, and provided it is
increasing the length to provide additional designed for towage, does not affect the
bays as required. This is a relatively low towing operation. The manifold is thus
cost addition as the well slots involve only installed with the bundle, obviating the
simple steel fabrication. requirements for heavy craneage or tie-in
spools to the bundle.
OTC 6430 DEN BOER, ROODUYN & BARBER 5

"pon qrri'.'^l at the offshore location the available dependent on circumstances,


manifold is positioned, flooded, levelled such as neoprene, polyurethane elastomer
and piled. Any vibration sensitive control (PUR), or filling the annulus with an
pods (removed from the manifold after insulating gel.
testing onshore) are then refitted offshore
upon completion of these piling operations.
* The exotic materials like Duplex
Pre-drilled wells are tied in to the stainless steels or composites can be
manifold, the control system hooked up and used with a high degree of reliability,
tested in readiness for start up when due to optimum fabrication conditions
required, and quality control facilities, inherent
to onshore fabrication.

7) DIVERIiESS SYSTEMS * Onshore fabrication offers further


benefits such as working in a
Diverless systems and equipment have been climate-controlled environment, rigorous
developed and successfully used in a number inspection and full onshore testing and
of field developments, although a number commissioning, which avoids expensive
of these have been prototype systems within offshore hold-ups. All these together
diver depths. All of these components can, provide a high level of confidence.
with consideration, be incorporated within
the bundle towhead. The advantages of a * Further benefits may include a far less
system of this type are obvious, i.e. a complicated umbilical design by laying
minimum number of equipment interface the individual hoses and cables in the
connections, which results in less tooling carrier without armouring.
and vessel time, ultimately saving money.
This arrangement has benefits in deep water * Bundles reduce the pipeline corridor
applications where the minimising of width to a minimum and avoid unnecessary
tooling is a major cost Baving. congestion, allowing for future
developments and minimising potential
risk with anchor handling.
TECHNICAI, ADVANTAGES
* Integrity monitoring of the bundle can
The integration of a flowline bundle with be provided by measuring the annulus
manifolds or riserbases on the ends offers pressure.
important technical and economic benefits, which
make the concept ideally suitable for satellite * The carrier pipe provides an initial
developments both in shallow and very deep barrier against any leaking product and
water. When comparing the integrated towed thus minimising environmental pollution.
flowline bundle with reel or laybarge/vessel
installation techniques, the following additional * Present carrier designs can be made
advantages emerge: suitable for very deep waters (over
1000m).
1) The Bundle Concept
2) The Integrated Manifold
The carrier pipe together with two end
bulkheads provides a closed container, When the manifold, the riserbase, or both
which when filled with inhibited can be integrated into the bundle concept,
seawater after installation gives a this will offer further benefits.
corrosion free environment. This
reduces or avoids individual corrosion * Free transportation and installation of
coating of flowlines. the manifolds, since they are an
integral part of the bundle.
The submerged weight of the flooded
bundle is sufficient to provide * Full testing and commissioning onshore
on-bottom stability and resistance to of the total system, from the riserbase
upheaval buckling without trenching or on one end to the manifold on the other
burial. end, giving a maximum level of
confidence and avoiding expensive
The carrier pipe provides protection hold-ups offshore.
against external hazards, such as trawl
board impacts. * The number of subsea tie-ins and spool
installations reduced, thus minimising
Thermal insulation of the flowlines, subsea work and increasing reliability.
when required, can easily be provided
and accommodated for in the carrier * Easy accommodation of ESD systems and
design. Various insulation systems are controls.

89
6 AN INTEGRATED TOWED FLOWLINE BUNDLE PRODUCTION SYSTEM FOR SUBSEA DEVELOPMENTS OTC 643
T>-=i manifoVl structure can be designed to savings:
provide permanent in situ protection and - the onshore fabrication of a total
it can be used to support any additional integrated system gives a considerable
protection structures required to cost saving.
protect the jumpers to satellite wells - manifolds and, in the case of a floater
or future xmas trees. development also the riserbase, do not
require separate installation.
* The concept allows for maximum - cables/umbilicals do not require
flexibility in the development, both in separate installation.
place and in time, thus minimising - trenching of flowlines/control lines is
capital expenditure. not required.
- reduced scope of tie-in work.
Engineering analysis shows that integration - reduced scope for installation of
of manifolds up to 300 Te dryweight is protective covers.
feasible.
* TESTING and COMMISSIONING - up to 50%
savings:
3) The Transportation and Installation Method - the offshore scope for testing can be
considerably reduced as the fully
The controlled depth tow method provides a integrated ITFPS is tested onshore.
number of advantages in comparison to other
tow methods or pipeline installation For the typical case as described in Section 5
techniques. the total costs of a subsea satellite
development, however excluding drilling, subsea
* Bundle and manifolds are towed clear of trees and excluding the provision and
the seabed, thus allowing a free passage installation of risers, would, at today's (early
above existing subsea pipelines, and 1990) price levels, amount to approximately U.S.
well below the surface thus minimising dollars 14 million for a conventional
wave influence. installation approach, whereas application of an
ITFPS will give some 10-15 percent savings on
* Due to its flexibility the bundle can be overall costs. For developments involving more
installed in any desired configuration, than just one system, and for developments with
thereby minimising field occupance. more complex specifications, the total CAPEX
savings may prove to be 20 percent or more.
* Installation vessels do not require
anchoring, thus allowing deepwater In the case where the ITFPS is designed to take
applications. into account potential future extensions
(additional wells), considerable savings on the
* Diverless installation has been done in costs of such later developments can be achieved.
the past, these techniques can be
readily extended to deepwater (> 1000m). From an operational point of view the reduced
number of subsea components, i.e. fewer tie-ins,
* Low stress levels in the flowlines may give OPEX savings up to 5-10 percent.
during launch, tow and installation.

ACKNOWLEDGEMENTS
ECONOMICAL ADVANTAGES
Authors herewith thank all colleagues of
If compared with conventional installation, i.e. Rockwater, Brown & Root Vickers, Kestrel Subsea
separate lay of lines and placement of manifolds Systems Ltd and staff of Smit Engineering b.v.
and a riserbase, the total system approach based who have been involved in the development of
on a pull or tow installation can result in ITFPS concept for their contribution to this
development cost savings. paper.

Reviewing the major cost elements and potential


differences: BIBLIOGRAPHY

* DESIGN - costs will be about equal. 1) T.C. Vergouw and A.J. Odone : "The
Integrated Manifold/Flowline Bundle : A
* PROCUREMENT - up to 10% savings: cost effective solution for marginal field
- the carrier pipe and accessories will be development", paper presented at Subsea
extra. 1989 Conference, London.
- cables/umbilical armouring can be
simplified. 2) E.J. Rooduyn and H. Boonstra: "Design
- the number of tie-in spools/connections Aspects of the Controlled Depth Tow Method
will be reduced. for Pipeline Bundles", paper presented at
Deep Oil Technology Conference, Sorrento,
* FABRICATION and INSTALLATION - up to 25% 1985.

go
OTC 6430 DEN BOER, ROODUYN & BARBER 7

" Costello, F.A. Brink and D. Henery 4) E.J. Rooduyn : "Submarine Flowlines :
"Insulated Pipelines between the UMC and Transportation of Pre-fabricated Pipelines
Cormorant 'A.' Platform in the Northern with the Controlled Depth Tow Method",
North Sea", paper 4611 presented at paper presented at Offshore Petroleum
Offshore Technology Conference, Houston, Technology Conference, Birmingham, 1984 and
1983. at Subsea 1985 Conference, London, 1985.

TABLE-1 COMPLETED CDTM PROJECTS

OPERATOR FIELD BUNDLE BUNDLE CARRIER FLOW & C0NTR0LLINE8


LENGTH MAS8 PIPE DIA. CONFIGURATION
YEAR OF
(m) Item) dm)
INSTALL.

8HELL EXPRO OSPREY 3,500 2,680 38 2 OFF 8" INSULATED


(1990) 10"
(UNDER CONSTR.) MID FIELD TIE-IN
3,100 2,370 38 A8 ABOVE
INTERMEDIATE MANIFOLD
31.5 10' PLUS UMBILICAL

ELF AQUTAINE EAST 1,600 565 24 10"


NORGE A/S FRIGQ 4" UMBILICAL
(1988)
1,600 565 24 A8 ABOVE

OCCIDENTAL SCAPA 4,394 1,810 28.25 10" INSULATED


PETROLEUM 6" INSULATED
(CALEDONIA) 3 OFF 3"
(1986)
4,390 1,810 28.25 AS AIOVE

SHELL EXPRO CENTRAL 3,343 1,250 26 8* INSULATED


(1984) CORMORANT
3,343 1,250 26 8* INSULATED

SHELL EXPRO CENTRAL 3,345 1,258 26 S" INSULATED


(1982) CORMORANT
MID FIELD TIE IN
3,343 1,256 26 8" INSULATED

3,310 1,865 24 2 OFF 4" W8ULATED


MID FIELD TIE-IN
3,310 1,865 24 2 OFF 4" INSULATED

OCCIDENTAL CLAYMORE 2,053 591 14 6* INSULATED


PETROLEUM 5 HYDRAULIC LINES
(CALEDONIA)
(1981)
3,206 1,152 26.25 10" INSULATED
2 O f 8"
10 HYDRAULIC LINES

CONOCO-UK MURCHI80N 2,005 255 12.75 2 OFF 3"


(1980) 4 HYDRAULIC LINES

1,242 149 12.75 AS ABOVE

8D0 102 12,75

91
HOLD-BACK VESSEL TOW VESSEL

CABLE fJ-^-TT^ PIPELINE PULL HEAD

NEAR-SURFACE TOW.

MONITORING VESSEL TOW VESSEL


-4,

CHAINS
//A\S /4W- 77ZSS
CONTROLLED DEPTH TOW.

HOLO-BACK VESSEL MONITORING VESSEL TOW VESSEL

7ZZZT >/<<\\
OFF-BOTTOM TOW.
MONITORING VESSEL TOW VESSEL

PIPE
//x<N\ /AS\ ~^s^r
BOTTOM TOW.

Fig 1-PIPELINE/BUNDLE TOW METHODS.

FIs. 2 : CDTM ARTISTS IMPRESSION


Rg. 3Typical bundle cross section.

Fig. 4Model of integrated towhead/manlfold, Including drill slots.

93
BUNDLE W11TH LATERAL ENTRIES

TO
PLATFORM
OR FPF

INTEGRATED MANIFOLDING

ITFPS WITH DRILLING SLOTS AND MANIFOLD

ITFPS PULLED INTO A PRE-INSTALLED


DRILLING TEMPLATE

TOTAL INTEGRATED TOWED FLOWLINE


BUNDLE PRODUCTION SYSTEM
OFFSHORE OR ONSHORE
PRODUCTION FACILITY 4(iLys=jM&4^:i-PBMlMQ

Fig. 5 : ITFPS ALTERNATIVE CONCEPTS

11500mm APPROX. I4-WELL) VALVES SERVICABLE


MAIN TOWHEAD FROM ABOVE Is REMOVE
MEMBER AT BREAK FLANGES.

BASED ON 5000 psl

ROUND TRIP INTELLIGENT


PIGGABLE HEADER

REMOVABLE PILING GUIDE

CONTROL PODS

WELL TIE-IN (SINGLE LINE FLOWLINE BUNDLE


ASSUMES ANNULUS X-OVER
AT TREE) ELEVATION

Fig. 6 : INTEGRATED TOWHEAD/MANIFOLD ASSEMBLY


94

Das könnte Ihnen auch gefallen