Sie sind auf Seite 1von 5

c- 0

-. .- . . .. . . . . .

,.

The Fry In Situ Combustion Test-l?ield Operations


.
MhRAWON OIL CO,
G. A, CLARK
FtNDLAV, OHIO
R, G. JONES TULSA, OKIA.
W. 1, KINNEY , TERRE HAUTE.. IND,
R: E. SCHILSON 117TLETON, COLO, , ,
.
MEMBERS AIME
H. SURKALO 7ERRE HAUTE, lt4D, ,
JUNIOR MEMSER AIME
1 R. S. WILSON TERRE jiAUTE, IND.

ABSTRACT years. As the dissolved-gas energy was dissipated, early


attempts to retard the decline consisted of vacuum, air,
This paper, ~escribe~ the field operations at the Fry in and gas represstiring, and recently, most of the nrea has
situ combustion project in Crawford County, III. Field op- been subjected_to water flooding. .:
eratlcms may be divided into three phasespreliminary Following early air repressuring., th~ Fry waterflood
cngineerhig siudies of 1960 arid 196t, igtdtlon, and, finally, unit was formed and water flooding i:.itiated in July, 1952. :
operation of the test. In the area in which the Fry combustion test was c9n-
The ~ ry combustion project was a pilot test of cocur- ducted, a peripheral water flood of a 160-acre area was ..
retu % situ co)nbus(ion on a 3.3-acre inverted five-spot. developed as shown in Fig. 1, Between 1956 and 1960,
In the summer of 1960, air injection tests were conducted it became apparent that the water flood was unsuccessful.
using old wells in the area and a new air inject[on well in looking for a suitable site for an in situ combustion te%t,
drilled especially for the (cst, In the sunoiter of 1961, the Marathon Oil Co, selected the Fry tinit as possessing
jour new oil wells were drilled on a 3,3-acre pattern for those features most dcsirttble for such a research project.
the pilot [est. A 11old wel[s in the near vicinity of the pilot Field operations associated with the Fry combustion test
\est were abandoned to preclude any possibility of gas began in the spring of 1960.
escaping to adjacent fornl.ations.
A compressor plant was al.ro insttdled al the t@st site in
1961. Air injection tests and other engineering studies

y-ere made; At the conclusion of these tests, ignition was


a;compli.vhed with a 40 k w electrical igniter,
~ Operation of the Fry cmnbustion test was We di&r-

ent from the usualoilfield operation with the excepdon O!



the idgh rate of .ai[ injection. No dificulty was found, with

the openhole completion. There were no unusual corrosion


or ettllil,qion problems until bottom-hole tetilperatures ex-
-.
;5
ceeded 150F. Four cores were drilled into the burned-out
portion of the reservoir with no mechanical diflicnhies.

INTRODUCTION
A cocurrent or conventional in situ combustion test was
conducted on the Fry unit of the Marathon Oil Co., in
Crawford County, Ill.
Besides testing combustion in the Fry type of reservoir, .
the test was intended to evaluate various operating proce-
dures. This paper presents a discussion of the Fry conl-
bustion test field operations, The geology of the reservoir
and the test performance are discussed irr other papers. i

HISTORY OF THE FRY UNIT

The Fry unit consists of 1I leases totaling 337 acres in Zce 4W Wo


o
an area in which oil was origirmlly discovered in 1906. SCALE- FT
Production fromthis reservoir, as from all Robinson sand [
reservoirs iii the are%=was very high duiing the first-few N - , OILWELL ~ oB5ERvAT,0~
WELL .:-
J1/. .4 WATER INJECTIONWELL

+
ASANDONEP OIL WELL @
,
DRY HOLE 5 AIR INJECTION WELL
Orkhud manuscript received in SOdety of Petroleum Enfrineers ottlcc +

I JUIY 20, 19S4. Revised manuscript Feceived Feb. 1, 19S6. Paper rmaented
at SPSI S9th Annual Fall ?@ettng held in Houston, Oct. 11-14, 1!)64.
1RMerence9 given at end of nnuer.
1
f%, IMAP OF FRY AREA SiiOWUYGI.,OCATIOS OF TEST.

1-
1.
MARG1[, 14)63

,.. . ..
34s

(..
*

---- .. . . ..
..

PRE-IGNITION OPERATIONS tions prior to ignition, It was determined from bottom-hole


pressure measurements on oii welis within the 160-acre
Pre-ignition operations at the Fry combustion project peripheral waterflood area that fhe project site had not
were designed to determine the reseryoir characteristics been penetrated by the injected water.
from engineering tests and to obtain corm for geological
study, During Aug., 1961, after the installation of. the com-
pressor, an air injection test was run to determine the dis-
In the summer of 1950, the preliminary selection of sr tribution of the injected air, At this time, the old oii wells
test site was made and an ~ir injection well, L, B, Wampler had been abandoned and the new pattern oii weiis had
1,

No. AI-1, was drilled especially for air injection tests. been completed. The results of this test are presented in
Conipletion of this injection well was acco~plished with Table 1. Shown are the short-term air injection test at
cementing a string of 8%-in, casing at 880 ft. with the rates of 255,000, 499,000 and 1,020,000 scf/D, as well as
bottom 30-ft joint being stainless steei, This well was later the areai distribution of the produced gases,
cietuted out with cabie toois. and eventually shot with one The injection rate of 1,020,000 scf/D was. continued
quart of ]iqu]d nitroglycerine from 885 to 934 f!, the gross for five weeks. During this time, the ,nir injection pressure
sand intervai occurring from 880 to 936 ft. increased, reflecting the ~.onfined nature of the reservoir
A preliminary air-injection test was conducted in i 960 due to geologic boundaries and the effect of the peripheral
to determine the ahiii}y of the reservoir to accept air and water flood. .
the areal distribution of the produced gases, These data
were used for a preliminary design of the compressor
piant, IGNiTION
The resuitk .of the air-injection test demonstrated that Ignition of the Robinson sand was accomplished by
the areai distribution of air was not uniform in all direc- a 40 kw electrical. igniter instaiicd at the nir !njection
tions, but at the same time, there ~ere no highiy pernle- weil, as shown in Fig, 2, The 1()-ft active eiemcnt was
ahle streaks evident, The gas production rate compared to iocated between 880 iitd X90 ft. Ignition operations
the air injection rrrte indicated the reieryoir was confined, began on Oct. o, 1961, by injecting air at a rate of I(#),000
and that most of the injected air in an In situ combustion scf/ D. On Oct. 9, 1961, the electrical igniter wus dnergized
test couid be accounted for. tit 10 per cent loud. The he~t output of this unit was reg-
: Oil production measurements were made during the test uiated by an on-off controller which controlled the frac-
on the four wells nearest the air injection .weil. Combined tion of time the heater was on each minute. During igni-
oii production for these fmlr weils increased ftom 5 to tion, the on-time was increased from 10 to 90 per cent
30,1 B/D by the end of the test, and water production of continuous operation, The progress of ignition was fol-
increased from 42,1 to 91 B/D, The combined gas-oii ratio iowed by temperature surveys of the air injection weii ttnd
for these wells was 9,7oo scf/bbi, and the air-oii, ratio was analysis of gas sarnpies from the observation weil, L, B,
i 4,300 scf/bbi, The two welis to the southwest and north- Wamplcr. No. O-1, 100 ft west of the air injection wcii.
west, L, B. Warnpler No. 5 and L. B. Warnplei No. 12, Initial ignition occurred at 4 a.m. Ott, 13, 1961, as indi-
respect iveiy, showed considerable stimulation by the air cated by a temperature survey. At that time, 2,571 kw-
drive. Littie oii stimuiatirm was noted to the northeast and hours of electrical energy had been introduced into the
southeast, hut water production increased considqrabiy in reservoir (8.77 X 10 Btu).
these two directions. Fig. 3 shows th}ee temperature profiics tukcn during ,
Utiiizing data from the J960 field test and from labora- ignition. Ignition was confirmed four days Iatcr on Oct. 17,
ttiry siudies; the tlnai engineering studies were completed when a marked increme in carbon dioxide content wa,,
in the spring of. 1961, As a result of these studies, five noted in the gas samples taken at the observation wei], L. B.
new weiis were drilied on a 3.3-,acre pattern. These were Wampler No. O-i. Even though ignition had been con-.
oii, weiis, L, B. Wampler No. 14; L, B. Wampier No. 15, firmed, operation of the igniter was continued until Oct.
Emma Fry a/c 1 No. 15, Emma Fry a/c I No. 16, and
Okiervation Weli L. B, Wampier O-1, Concurrently, old
wcils in the vicinity of the project were abandoned, In addi-
tion, five old weiis previously abandoned were iocrited
and re-abandoned. These abandonment steps were under-
taken to en~ure no loss of gases to formations above the
Robinson sand.
Du@tg the rest of the summer of 1961, surface and
production well fiumping equipment was instailed, and
tests were run to evaluate further the restirvoir condi-
..
TASLE 1-AIR INJECTION TEST, 196t
F!Lmr
Air
Back Pressure

1:~~
. Behavior, Alr

Rate
Infection Wel I

I niectl;:~i:)eoure
- .
$zis 1.
.
255,000
499,000 , 1;;
1,020,000 !74

Ili$tribufim of Effluent Goses al __


Produckn Wells
,.. .
Well Lamtlm -- Per cent of Go; Pratfu&d
.: - -
40.7
28.2
11.6
4.2
5.9
8.0
12 2,4

JO I! RAAL OF PET~OI.EUM TECI{XOLOGY

.
.!,,
.-
,
.
)

. . .
. ..

19. ~ottd energy rclcascd was 22.5 ~ 10 Mu. Temperature spot pat k?rn, {he ~wigina}observation WCII,and the project
data indicated that, eventually, i the entire sand face was husk battery.
ignited, the deepest portion after the igniter was turned THE COhlPRESSORPLANT
off (Fig. 3). The compressor plant incorporated a high-speed 500 hp
packaged unit with. a three-stage compressor and a diesel:
OPERATION engine driver, The maximum discharge pressure rating for ~
Once ignition was assured, tmention turned to the opera- this assembly wa~ 340 psia.
tion of the combustion pilot. Fig. 4 shows a layout of the WELL CONPLETIONS ~~ ;
pilot site at the time of ignition including the compressor Allof the new wells ccmpleted in the Fry projecr were ,
plant, the five ngw wells which constituted the inverted five- drilled and cored with rotary tools, Eventually, four oil
wells and four observation wells were drilled and com-
pleted withi,n the confines of the 3.3-acre project, -1
,,!~.-
070 -
1
The ojl producers (Fig. ~5) were completed witkt ii ;:
string Of T-in. OD ~asing set on top of the Robinson
880 sand With a 30-ft shqe joint in each string consisting of ,
$ 6%-in. OD, Type 304, stain!ess steel, The oil wells were
al[ tailed in with cabje teds, shot with nhroglycerirre, turd
s 890 completed with dual tubing strings, a 2-in. pumping string.
r- -1
a and ~ V+-in. thermowell string. All tubular goods exposed
I , to the Robinson sand were stainless steel.
~ 900 ,
I Various methods of well completion were utilized in
, the observation wells, as shown by Fig, 6,, :
z-
I& 910 Within the first two months after ignition, the tempera-
I&l ture in the Robinson sand at L. B, Warnpler No, O-1,
;0 khcated 100 ft west of No, AI-1, begtm:to rise rapidly. By
Dec. 24, 1961, the temperature had climbed to over
2,000F. The extremely high temperature was the result
930 of an oil fire in the open hole, Later, the fire was exting-
uished by injecting water, but the heat had damaged the
down-hole tubing and therrnowell, rendering the well use-
94 0 less as an observation well. Subsequently, a second obser-
0 200 400 600 800 000 vation well, L. B, Wampler No, O-2, wiis drilled in Jan..
, .... ~ TEMP., F 1962.
],ffol)u(:~l~N wf~fJ,$j

Al R RATE = 150,000 to 900,000 scf/~ t3peration of producing wells wos very satisfactory dur-
10-12-61, 4;00 p.m.
Igniter on
b--.----o 10-13-61; 4:00 an 1-
N---,-x 10-22-61, [0:00 p.m. Igniter off
FJC,3TmPmATmE PROIVLESN AIR .ISJ KTIOX WFM.
I)unINc ICXITION$ -

. .. .. ..
..
..
.
.
1. k. WAMPLER

T f
EMMA FRY. O/C 1

. . .
.i.,,
.A

scar,
0, w w

-. I
w
f,,;.
N
j., , ; FL041 COLLAR
14
. 0-1
.
~,.,

,6

I
.
>~
,-,
l-we lN9ERr PUMP

.! /4. WERMOWELL
Sho ,wm? i
., STAINLESS STEEL
CAW9 SCAT-J ;,. Snoe 401NT
$+ 1
- Troller

O -D!wd Tmk V,, O-PUMP


O- Cmio Tank
cm,,,, ..p-cmp ,
01190. Catch B.wn pi!
Hcale{ o @3

,- . .. . . . .COMPR&SOR PLANT .. -. :.:


q -.j:~:,

TANK BATTERY
. LU CINDA SMIIH s/c 2

FIS. 4-LOCA IOrJOF SURFACE f@rrPNFNT AND ?JFxJ.5. l%: 5-TYPICAL PRODUCING
WRLL INSTALLATION.
.!
MA RCST, 196S

... .. .. . . .. . ._ , -:. ,

. . . .
.- ,..
.

ing the project. Corrosion tm~ emulsion problems had been The back pressuring apparently permitted fluid entry
anticipated but never developed, except in the terminal into the wellbore from portions of the reservoir not imme-
stage of operation when the wellbore temperature in- diately ht front of the combustion zone, and resulttxl in
creased above 150F. Liquids and gases were collected in reducing the emulsion and corrosion difllculties, In fact,
separate gathering lines and transported to the project the pH and chloride ion content of the produced water
tank battery. At the tank battery, provisions were, made increased, indicating the recovery of water from areas
at the headers for isolating production from an individual away from the combustion front. Production from both
well for test purposes. of these wells was finally terminated when the gas-oil
Only when the combustion front approached a produc- ratios became excessive; .,
tion well did conditions change from routine production
operati~ns, As the wellbore temperature increased due to EXPERIMENTAL MEASUREMENTS
the approach of the combustion front, the gas and fluid
production rates increased also, The approach of the com- Since the Fry combustion project was a research project,
bustion front was telegraphed many weeks in advance by a c~nsiderable amount of data were taken to follow the
progress of the test. 4
changes in the character of the produced water. we water
became yellow in color, the pH dropped to 4,2 and the A continuous record of air injection ~as made by an
chloride ion content decreased. orifice flow meter in the air injection line, The gas pro- .
When the we!lbore.tempemtures approached 150F, both duction rates of all wells producing gas were monitored
emulsion and corrosion problems became quite sxwere. throughout the test. Those wells ,connected to the project
As an example, the normal treatment for emulsion re- tank battery were monitored with twg orifice flow meters
quired about 1 quart of chemical/100 bbl of crude in installed at the tank battery, In the case of those wells not
conjunction with a heater treater. The emulsion produced connected to the Fry project tank battery but which pro-
at thehigher reservoir temperatures required about 60 duced gases as a result of the test, gds flow rhtes were ~
quarts of chemicall 100 bbl of crude. Thus, chemical costs monitored periodically by a portable orifice flow meter.
became u major factor in setting the economic limit of To facilitate monitoring the progress of combustion, gas
ope~ations. In the case of oorrcsdon, no unusuaf difllculties analyses were made periodically of all produced gas
were experienced until the well was produced at the higher streams by both Ors@ and mass spectrographic equipment,
wellbore temperatures with the 1OW-PHwater. In one case, The results of thesetwo methods were then used to deter-
astainless-steel pump required complete replacement of all mine the composition of tbe gas for ctwbcm dioxide, oxy-
major paI cs after only 10 days operation. gen, carbon monoxide, nitrogen and hydrocarbon gas
The first well to be invaded by the combustion front content.
wus the west pattern well, L. B. Wampler No: 1+~-This- Oil and water production rates for individual wells were
weil was produced until the emulsion and corrosion diffi- determined periodically by diverting the production from
culties dictated suspensions of operations. The next two the well in question into the test tank at the project. tank
wells approached by the front were the north and east pat- batlery. Water and oil sam~les were collected periodically
tern wells, Fry 15 and Fry 16, respectively, When ernul- from the producing wells and these were analyzed to deter-
sion. difficulties became severe at these wells, the tubing nline changes in characteristics as the front approached,
was raised about 240 f( and production con[inued with
[he fluid-column hack-pressure on the reservoir. Since. gas analyses indicated th: presence of hydrocar-
hons irr the gas stream throughout the test, tests were run
to determine the quality of these hydrocarbons and if they
were recoverable. Using cold traps and activated charcoal
1;. traps, it was found that most of these. hydrocarbons were
~ - THERMOCOUPLE LEAR WIRE
highly volatile and little would cpndense fit temperatures
above 15F~ The indicated hydrocarbon loss to the tmrlos-
7HERM0COUPLE
LEAO WIRE
pher~ was 6 to 8 B/D,
I .

RJw#4, fj~ .=
FROMWATER ~~;
LINE
In &dditiorr to the above techniques, the progress of the
combustion front was monitored by temperature surveyi
I > at $
; ,of the pattern producing wells and observation wells, Once
. . - .- .. . . . . . .. K
the combustion zone passed an observation well. which was
1
!:
coinpleted with tubing or casing cemented through the
.3/4 v THERMOWELL
formation, it was pbssible to monitor progress of conlbus-
.:
~~ ~ ,@ oocA~,mG
tion, with neutron logs in conjunction with temperature
.!
> 5-!/S O 0 CASING Sllrvcys.
,,
~~ :
? 1 r -
HAZARDS

Potential hazards do exist with the in situ combustion


process. Toxic gases, explosive gases, and high-pressure air
,syslems are potential dangers; how,~{er, awsrreness of these
problems can eliminate accidents.. .rhe presence of toxic
gases was not a hazwd as long m proper venting to the
atmos~here
. . was assured. and at no time was an extiosive
miXtureof hVdro&rbons and oxygen bresi?nt at a~y: of the
L. B. WA MPIEi No. 0.1 l, B: WAMPLER No.04
producing w~lls. A periodic che~~ wti~smade for &e pres-
and
ence of explosive mixtures throughout the life of the
EMMA FRY A/Cl No, O+
project,
FIc. &-OBSSXWATION WELLS, ~onwLETIoN ~ETAIL. To minimize explosion hazards in the air injection sys-

a46
.

tem; a synthetic lubricant with a high flash point was used expiosive and toxic gases were vented to the atmosphere.
in the compressor. once combustion. was under way, 4, The approach of the combustion front to a weil was
proper precautions were taken when driiiing into the pres- si@taled by changes in the characteristics of the produced
surized reservoir; that is, surface casing was set and ce- water.
mented; blow-out preventer equipment was used, driiling 5. Advance of the combustion front could be followed
mud quality ,vas carefuiiy controlled, and proper super- by temperature surveys and neutron logs obtained at ob.
vision was maintained, servation Wells.
j 6, The use of stainless ~teel for down-hoie equipment
CORING THE BURNED-OUT RESERVOIR I was not necessary for the Fry combustion test.
7, NO completdy reliable quantitative determjriation, of j
Four welis were cored into the burned-out portion of
combustion front temperatures, was accomplished, .
the Robinson reservoir during the summer of 1963, No
difficulty was encountered in these drilling and coring OPF 8, Coring and drilling behind the combustion front were
emtions after proper precautions Were taken. accomplished with very little difilculty.
After coring was completed on the L. B. Wample~.A
ACKNOWLtiDtiME.NTS
and B wells (S0 and 145 ft west of L. B. Wampler No.
AI-1,, respectively], the core holes were iogged and the The authors wish to express iippreciation to the manage-
holes plugged with cement from total depth to the surface. ment of the Marathon Oil Co. for permission to publish
After coring L. B. Wampler No.O-3 and Em,rna Fry a/c 1 ~~is paper, .Thanks are due to those people in the Produc-
No. O-1, these wells were completed as observation wells tion Dept. and the Denver Research Center who contri-
by cementing 4%-in. OD casing through the reservoir. buted to the success of this test. Particular recogrtition is
due W. W. Smith, fieid engineer, and V. L. Bush, mechania.
CONCLUSIONS
RMIiREN(:lM
1. Data from air injectivityy t~sts are helpful in compres- i, Ilmrit[, (1, l+, umi .: ..~un, J, T.: -TIw. Fry In Sit41 Goml)us.
sor sizing, tirm ~esi-Rw[,rwi I [ .hrurt(vht i rs~,, Jwrr, Pet. Td, I Mwd)
2. Ignition was uchieved without difficulty. 1%5 ) :+37.
2, (lark, G..&, Jonw, R, (;,, fiinnry, \V. L., SrAilwu, K, ii..
j. Gcneraliy, the combustion process involved only lit- Surkulo, [i, and Wilson, IL S.: T IV Fry [n Shu (Mnlmtiun
tle more hazard than normal field operations as long as Tt,stl>t,rf[)rl]] ult(,,>. /,)//r. Pc(, 7ew )i. ( .lIti,ch. lYb!i I M. ***

:,

-. ,- .

3.1 i

.,.. . ..
,

Das könnte Ihnen auch gefallen