PROJECT TITLE : CONSTRUCTION AND COMPLETION OF 1 UNIT OF WATCH TOWER AT K3D2, SIBU
CLIENT : BINTULU LUMBER DEVELOPMENT SDN BHD
CONTRACTOR : HY GENERAL CONTRACTOR
CONTRACT PERIOD : 16.02.2017 - 15.07.2017
WEEKLY REPORT
% Complete
NO SCOPE OF WORKS
Last Week 13/03-17/03/17
1 PILING 100% 100%
2 PILE CAP/FOOTING 100% 100%
3 GROUND BEAM 100% 100%
4 GROUND SLAB 100% 100%
5 FENCING + GATE 0% 0%
6 TRUSSES/BRACING 30% 40%
7 LADDER 0% 0%
8 ROOFING WORK 0% 0%
9 BOLT & NUT/PAINTING/WELDING WORK 0% 10%
10 LIGHTNING ARRESTER 0% 0%
OVERALL COMPLETION 43.0% 45.0%
PREPARED BY,
(WILLIAM TING)
PROJECT ENGINEER, KTS PD3
Page 1 of 3
REF: SB012/BLDK3D2/HYGC/WR04
Page 2 of 3
REF: SB012/BLDK3D2/HYGC/WR04
Site Diary
1. Trusses welding still in progress.
2. Length of the welding at the side end must be 300mm or more.
3. Distance between 2 welding must be 100mm or less.
4. Mr. Ling instructed workers on the welding methodology.