Beruflich Dokumente
Kultur Dokumente
ABSTRACT
This project report documents the analysis and designing of water supply and
underground sewerage systems with sewage treatment plant. It gives an overview of
the steps which can be used for obtaining the optimal design for water supply and
underground drainage systems. Analysis and designing of water supply and
sewerage systems with STP begins with site visit and estimation of projected area
population. The database preparation with the help of base map is used in LOOP,
BRANCH, SEWER and AutoCAD software for the network designs and to work out
the optimal design of an efficient, sustainable and cost effective system. This report
also provides details about network design software used for the design of water
supply system and underground drainage system. The design of water distribution
network, sewer network and STP strictly follows CPHEEO manual and as per client
guidelines. The detailed cost estimation of the project undertaken involves BOQ
preparation of each component of the proposed water supply and drainage systems
with STP. The rates were taken from the SOR of GWSSB. Firstly the conceptual
project report is submitted to the client and after their suggestions and comment,
detailed project report is submitted. This report is based on the work of four months
on live projects involving preparation of conceptual report and DPR of
Underground drainage project and DPR of water supply scheme.
INTRODUCTION
After complete treatment of water taken from source i.e. surface water like
reservoir, river, canal or ground water or both, must be distributed to a number of
houses, estates, Industries and public places with the help of water distribution
network. The water supply system consists of water treatment plant, storage
structures like ESR and Sump, water distribution network, pumping stations and
house connections.
The 80% of water supplied in the town will ultimately contribute to the sanitary
wastewater generation which is to be collected through sewer line and treated to the
required degree before it will be discharged to river or land without causing any
health or environmental problems. The underground sewerage system essentially
consists of house connections, sewer lines, intermediate and main pumping stations.
3
This work involved detailed analysis and designing of water supply system and
underground sewerage system with STP for the given project areas. The preparation
of Bill of Quantity for each project was done for water supply and underground
drainage system. During the project work preparation of conceptual and draft
detailed project report of water supply and underground sewerage system with STP
of given project areas were carried out in depth.
The analysis of existing infrastructure like existing water supply, existing drainage
system in the project area were carried out through site visit and relevant data
collection from urban local body of that town.
The system were analyzed in depth and new water supply and UG drainage system
were proposed based on the design considerations of CPHEEO and as per client
requirement. Designed sewage treatment plant and provide efficient and cost
effective technological options. The proposed system must meet optimal design
criteria for the given area both in terms of low cost and reliability of the system.
4
LITERATURE REVIEW
To design the optimal water distribution and sewerage system, the basic step is the
accurate estimation of future population for the design period of 30 year. The time
lag between design and completion of the project year should not exceed 2 to 5
years depending on the size of project. The project component may be designed to
meet the periods mentioned below in Table 1.
Table 1
1. Storages by dams 50
2. Infiltration works 30
3. Pumping:
6. Sewer Network 30
8. Pumping Machinery 15
POPULATION FORCAST
Graphical method
o In this method, the population as well as its log value is plotted on the
graph. An equation based on the available census data helps to
project the population up to the design period.
Logistic Method
o The S shaped logistic curve for any city gives complete trend of
growth of the city right from beginning to saturation limit of
population of the city. This method is applicable for very large cities
with sufficient demographic data.
Method of Density
o In this approach the trend in rate of density increases of population
for each sector of the city is found out and population forecast is done
for each sector based on the above approach. Addition of sector wise
population gives the population of the city.
When a Master Plan containing land use pattern and zoning regulation is available
for the town, the anticipated population can be based on the ultimate densities and
permitted floor space index (FSI) provided in the Master Plan. FSI is the ratio of
total floor area to the plot area.
Note:
The source identification is an important step, reliable and protected source of water
is required for uninterrupted supply of water to the town. The water from source is
taken to the storage structures like ESR, Underground Sump and internal storage
tanks. The water is lifted to the elevated storage structures through the help of
pumps from underground sumps.
9
The next important step is survey of the project area and preparation of base map
having elevation, length of each road, ward boundary, central line of the road and
important utilities will be shown on the base map. The detailed study of project
areas topography suggests which type of water distribution network i.e. gravity
type, pumping type and dual type is suitable and sustainable for 30 years period. The
description of each type is described below:
Gravity type
The gravity distribution system is used in cases where ESR is positioned at high
elevation so that water can flow in mains due to gravitational force. The water head
at the last node is minimum required and remaining head is consumed in frictional
and other losses.
Pumping type
In this kind of distribution system the water is pumped in the mains. The biggest
disadvantage of such system is that if power supply is cut, then entire system will
suffer, thus standby diesel pumps are required.
Dual type
In this type of distribution system when demand is small the water is stored in ESR
but when demand increases, the water needs to be pumped into the mains for which
pumps need to be installed.
There are four different types of distribution system based upon their layout and
direction of supply namely dead end, grid iron, ring and radial system. Dead end
type distribution design will be through BRANCH Software and other types will be
through LOOP Software.
The LOOP and Branch software uses Hazen Williams Formula for the design of
water distribution network through pressure pipelines of various pipe materials. The
Hazen Williams Equation is used to calculate head loss in the pressure pipeline
which is due to friction in pipes at entrance, due to valves, bends, water meters, till it
reaches the consumers tap. The net head available at the consumers tap is head at
10
entrance minus all the losses in the way is known as effective head. The effective
head at the service connection to a building is very important since it will decide the
height up to which water can rise in the building. Thus, greater the head, the more
will be the height up to which water will rise.
Hazen-Williams Formula
Empirical formulae are sometimes used to calculate the approximate head loss in a
pipe when water is flowing and the flow is turbulent. Unfortunately the results
depend upon the value of the friction factor C which must be used with the formula
and this can vary from around 80 up to 130 and higher, depending on the pipe type,
pipe size and the water velocity.
The Hazen-Williams formula is expressed as:
V = 4.567 X 10^3 C d^0.63 S^0.54
Q = 1.292 X 10^3 C d^2.63 S^0.54
11
Where:
Q = discharge in cubic meter per hour
V = velocity in meter per second
S = slope of hydraulic grade line
C = friction coefficient, depends upon roughness of internal pipe surface
d = inside diameter of the pipe in mm
These factors include some allowance to provide for the effects of changes to the
internal pipe surface due to the buildup of deposits or pitting of the pipe wall during
long periods of use.
The node number and elevation, pipe length, pipe number, range of commercial
diameter of pipe is entered in the LOOP & BRANCH software for the optimal
design.
The results from the above software include pipe details, node details, longitudinal
section, pipe wise cost, excavation cost and entire cost summary.
12
After population estimation sanitary wastewater quantity for each zone, ward and
for entire area is estimated. Stage wise i.e. present, intermediate and ultimate
sanitary wastewater quantity is also estimated. The 80 % of water supplied to any
area contribute to municipal wastewater generation. Ground water infiltration is
also considered; usually 10 % is taken if no data is available. Domestic sewage
includes typical wastes from the kitchen, bathroom, and laundry, as well as any
other wastes that people may accidentally or intentionally pour down the drain.
Sanitary wastewater consists of domestic wastewater as well as those discharged
from commercial, institutional, and similar facilities. Technically wastewater can be
defined as any water or liquid that contains impurities or pollutants in the form of
solid, liquid or gases or their combinations in such a concentration that is harmful if
disposed into the environment.
To design the sewer network with the use of SEWER Software, the input data
required can be obtained through the detailed study of base map having information
about elevation, length of each road, ward boundary, central line of the road and
important utilities. The detailed Node to Node analysis has to be carried out on the
13
base map as sewer network is designed as a gravity type system in which liquid
wastewater flows from high elevation to low elevation. The intermediate pumping
may be required because of increase in the excavation depth beyond its feasible and
economical excavation for pipeline trenches.
The SEWER Software uses Mannings Formula for the design of circular sewers.
The available head in the channel is utilized in overcoming surface resistance and, in
small part, in attaining kinetic energy for flow.
The value of Mannings coefficient recommended for various pipe materials are
given below in the tabular form:
Table - 4
Material Manning's
(n)
Metals
Brass 0.011
Cast Iron 0.013
Smooth Steel 0.012
Corrugated Metal 0.022
14
Non-Metals
Glass 0.010
Clay Tile 0.014
Brickwork 0.015
Asphalt 0.016
Masonry 0.025
Finished Concrete 0.012
Unfinished Concrete 0.014
Gravel 0.029
Earth 0.025
Planed Wood 0.012
Unplaned Wood 0.013
Corrugated Polyethylene (PE) with smooth inner walls 0.009-0.015
Corrugated Polyethylene (PE) with corrugated inner walls 0.018-0.025
Polyvinyl Chloride (PVC) with smooth inner walls 0.009-0.011
It is necessary to size the sewer so as to have adequate capacity for the peak flow to
be achieved at the end of design period and also to avoid steep gradient and deep
excavations. It is desirable to design sewers for higher velocities at peak flow
wherever possible so that the silt deposited during the low flow would be flushed
during the peak flow. It is therefore, recommended to have minimum velocity as
0.6 m/s which is also self cleansing velocity at the average or at least at the
maximum flow.
The node number and elevation, pipe length, pipe number, range of commercial
diameter of pipe is entered in the SEWER software for the optimal design of sewer
network.
The results from the above software include pipe details, node details, longitudinal
section, pipe wise cost, excavation cost and entire cost summary.
15
The collected sanitary wastewater from the sewer network is pumped to the inlet
chamber of the Sewage treatment Plant (STP). A treatment system is combination
of unit processes and unit operations required for treatment of wastewater. A
wastewater treatment plant is designed for either of the following treatment
systems:
The primary treatment plant consists of screen chamber to remove floating solids,
grit chamber to remove heavy suspended solids and primary clarifier also known as
the primary sedimentation tank. . Any colloidal or dissolved solids cannot be
removed with only primary treatment scheme. The primary treatment scheme is
essential for removal of floating solids which can cause maintenance and
operational problems during further treatment.
16
a. Waste stabilization ponds: in case of such ponds, screen chamber is the only
required primary treatment unit. The grit chamber and primary settling tank
are not required as the settling has already taken place. It is comprises of a
single or several series of anaerobic, facultative or maturation ponds. It is
the most cost effective wastewater treatment technology but land
requirement is huge.
During the project work, involved in the design of STP comprises of screen
chamber, grit chamber with proportional flow weir, aerated lagoon as biological
unit, chlorine contact tank, and chlorine storage house and inlet-outlet arrangement.
The STP designed for the average flow of 27 MLD which is briefly explained in the
methodology part of the report.
The hydraulic design of pumping station, manhole cum lifting station, pumping &
rising main consider peak flow of the average sewage generation from the ultimate
stage population.
BILL OF QUANTITY
The detailed cost estimation of each component of water works like water supply
scheme, underground drainage scheme having STP design is the preparation of Bill
of Quantity (BOQ). It is prepared with the help of Schedule of Rates (SOR) of
Gujarat Water Supply & Sewerage Board (GWSSB). The important components
18
The materials and data required to carry out detail designing of water supply
scheme are following:
For Water Supply Network Designing, two softwares LOOP and BRANCH are
used, which are developed and distributed under the joint efforts of two UNDP and
World Bank.
19
LOOP Software: It is used for the optimal design of new or partially existing,
gravity branched water distribution system. It allows for reservoirs (both with fixed
head and variable head viz. pumps), valves (pressure reducing as well as check
valves) and on-line booster pumps. It has been programmed in Microsoft
QuickBasic 4.5. The code developed by Prasad Modak/Juzer Dhoondia is
structured and optimized. Memory utilization is dynamic. The program is
hierarchical and structured.
The input section is divided into thirteen screens. Input data required by LOOP for
network designing includes number of pipes, number of nodes, type of pipe
materials used, number of commercial diameters of each material, peak design
factor, type of formula, pipe diameter and its unit, pipe length and its unit, flow and
its unit, head (HGL) and its unit, elevation and its unit, pressure (minimum and
maximum( and its unit, velocity and its unit, pipe details node number wise,
roughness coefficient, number of res. Nodes with fixed and variable HGL, number
of booster pumps, number of PRV, number of CV, pipe internal diameters, Darcys
constant, cost, Newton Raphson stopping criteria.
Loop network design for a small portion of a hypothetical project area. The data
input for a small portion of the project area in the LOOP software is given below:
Pipe Data
============================================================
Pipe From To Length Diameter Hazen's Pipe Status
No. Node Node m mm Const Material (E/P)
----------------------------------------------------------------
1 300 1 800.00 200.0 110.00000 CI
2 1 3 350.00 100.0 110.00000 CI
3 1 2 500.00 150.0 110.00000 CI
4 2 7 600.00 75.0 110.00000 CI
5 3 4 720.00 75.0 110.00000 CI
6 1 5 700.00 100.0 110.00000 CI
7 2 6 750.00 50.0 110.00000 CI
8 7 8 700.00 50.0 110.00000 CI
9 5 4 350.00 100.0 110.00000 CI
10 6 5 500.00 100.0 110.00000 CI
11 6 8 600.00 150.0 110.00000 CI
12 4 11 800.00 75.0 110.00000 CI
13 11 13 900.00 150.0 110.00000 CI
14 12 13 550.00 50.0 110.00000 CI
15 8 12 800.00 100.0 110.00000 CI
16 8 9 500.00 150.0 110.00000 CI
17 9 10 650.00 100.0 110.00000 CI
18 9 17 800.00 75.0 110.00000 CI
19 12 17 500.00 75.0 110.00000 CI
20 13 14 350.00 150.0 110.00000 CI
21 14 15 900.00 100.0 110.00000 CI
22 14 16 1200.00 100.0 110.00000 CI
50 100 11 500.00 150.0 110.00000 CI
60 200 6 350.00 200.0 110.00000 CI
============================================================
22
Node Data
============================================================
Node Peak Flow Elevation Min Press Max Press
No. lps m m m
-------------------------------------------------------------
1 2.00 -2.600 15.00 7.00 30.00
2 2.00 -3.400 15.00 7.00 30.00
3 2.00 -1.500 15.00 7.00 30.00
4 2.00 -1.300 15.00 7.00 30.00
5 2.00 -1.200 15.00 7.00 30.00
6 2.00 -1.500 15.00 7.00 30.00
7 2.00 -1.200 15.00 7.00 30.00
8 2.00 -1.300 15.00 7.00 30.00
9 2.00 -1.200 10.00 7.00 30.00
10 2.00 -2.600 10.00 7.00 30.00
11 2.00 -1.300 10.00 7.00 30.00
12 2.00 -1.400 10.00 7.00 30.00
13 2.00 -1.500 10.00 7.00 30.00
14 2.00 -1.800 10.00 7.00 30.00
15 2.00 -1.600 10.00 7.00 30.00
16 2.00 -2.100 10.00 7.00 30.00
17 2.00 -1.300 10.00 7.00 30.00
300 2.00 0.000 10.00 7.00 30.00
100 2.00 15.000 10.00 7.00 30.00
200 2.00 20.000 10.00 7.00 30.00
============================================================
Fixed Head Reservoir Data
=============================
Source Head Ref Res?
Node m (R)
-----------------------------
300 40.00 R
=============================
23
The results from the LOOP software for a hypothetical project area are given in
result section of the report.
BRANCH Software: BRANCH is used for the optimal design of new or partially
existing, gravity branched water distribution system. It has been programmed in
Microsoft QuickBasic 4.5. The code developed by Prasad Modak/Juzer Dhoondia is
structured and optimized. Memory utilization is dynamic. The program is
hierarchical and structured.
The input data for a small hypothetical area in the BRANCH software is provided is
provided below:
Title of the Project : Branch Network
Name of the User : Anand
Number of Pipes : 13
Number of Nodes : 14
Number of Commercial Diameters : 5
Peak Design Factor : 3
Minimum Headloss in m/km : .005
Maximum Headloss in m/km : 20
Minimum Residual Pressure m : 5
Type of Formula : Hazen's
Pipe Data
===========================================================
Pipe From To Length Diameter Hazen's Status
No. Node Node m mm Const (E/P)
-----------------------------------------------------------
1 1 2 500.00
2 2 3 500.00 100.0 110.00000 E
3 2 4 500.00
4 2 6 500.00 100.0 110.00000 P
5 6 5 500.00
6 6 7 500.00
7 6 9 500.00
8 9 8 500.00
9 10 9 500.00
10 9 12 500.00
11 12 11 500.00
12 12 13 500.00
13 14 10 500.00
===========================================================
25
Node Data
============================================================
Node Peak Flow Elevation Res. Press Meet Res.
No. Factor lps m m Pres (Y/N)?
------------------------------------------------------------
1 3.00 0.000 20.00 5.00
2 3.00 -3.000 0.00 5.00
3 3.00 -3.000 0.00 5.00
4 3.00 -3.000 0.00 5.00
5 3.00 -3.000 0.00 5.00
6 3.00 -3.000 0.00 5.00
7 3.00 -3.000 0.00 5.00
8 3.00 -3.000 0.00 5.00
9 3.00 -3.000 0.00 5.00
10 3.00 -3.000 0.00 5.00
11 3.00 -3.000 0.00 5.00
12 3.00 -3.000 0.00 5.00
13 3.00 -3.000 0.00 5.00
14 1.00 10.000 0.00 5.00
============================================================
Reference Node Data
===================
Node Grade Line
No. m
-------------------
1 25.00
===================
26
The output of the BRANCH software for the same area is included in the result
section of the report.
The materials and data required to carry out detail designing of sewerage system
are following:
SEWER Software: For the optimal design of Sewer Networks, SEWER software is
used which is developed and distributed under the joint efforts of UNDP/World
Bank. It is used for the design and simulation of new or partially and/or fully
existing gravity as well as pumped sanitary sewer. It has been programmed in
Microsoft QuickBasic 4.5. The code developed by Prasad Modak/Juzer Dhoondia is
structured and optimized. Memory utilization is dynamic. The program is
hierarchical and structured. It has Help provision which is chosen while choosing
menu options. It is online context specific. It has command line option and
installation routine provision.
Input section is divided into seven screens. Input data required by SEWER for
network designing includes number of pipes, minimum and maximum velocity,
minimum and maximum allowable cover, number of existing pipes, number of
commercial diameters, number of excavation layers, infiltration rate (%), pipe
length and its unit, pipe diameter and its unit, pipe flow and its unit, elevation and
its unit, pipe velocity and its unit, mannings coefficient, node number wise pipe
details, peak factor, pumping requirement, pipe internal diameters, maximum d/D
28
(d = actual depth of flow in pipe, D = full depth of flow in pipe i.e. pipe internal
diameter), pipe thickness, trench width, pipe cost details, pipe strength details,
excavation layer wise rate, maximum and minimum allowable slope, type of
backfill.
The input data for a small hypothetical area in the SEWER software is provided is
provided below:
Title of the Project : SEWER NETWORK
Name of the User : ANAND
Number of Pipes : 10
Number of Nodes : 11
Minimum Velocity m/sec : .6
Maximum Velocity m/sec : 2.5
Minimum Allowable Cover m : 1.2
Maximum Allowable Cover m :6
Number of Existing Pipes :0
Number of Commercial Diameters : 10
Number of Excavation Layers :4
Maximum Allowable Slope as X (1:X) : 30
Minimum Allowable Slope as X (1:X) : 1000
Diameter Progression Considered? (Y/N) :Y
Manning 'n' to be kept constant? (Y/N) :Y
Lay Pipe Parallel to Ground? (Y/N) :Y
Provide Drop if Min Cov Violates? (Y/N) :Y
Lowest/Mean/Highest/Auto Dia? (L/M/H/A) : L
Type of Backfill : Damp Clay
Unit Weight of BackFill Soil kg/sq m : 1920
29
Pipe Data
============================================================
Pipe From To Length Manning Diameter Min. Vel.
No. Node Node m 'n' mm m/sec
----------------------------------------------------------------
1 1 2 30.00 0.0110 169.0 0.60
2 2 3 30.00 0.0110 169.0 0.60
3 3 4 30.00 0.0110 300.0 0.60
4 4 5 30.00 0.0110 300.0 0.60
5 5 6 30.00 0.0110 300.0 0.60
6 6 7 30.00 0.0110 300.0 0.60
7 7 8 30.00 0.0110 300.0 0.60
8 8 9 30.00 0.0110 300.0 0.60
9 9 10 30.00 0.0110 300.0 0.60
10 10 11 30.00 0.0110 300.0 0.60
============================================================
Node Data
=========================================================
Node Flow Elevation Peak Pumping Minimum
No. lps m Factor (Y/N/F) Cover (m )
----------------------------------------------------------
1 1.320 54.00 3.00 1.20
2 0.132 53.84 3.00 1.20
3 0.132 53.68 3.00 1.20
4 0.057 53.48 3.00 1.20
5 0.057 53.36 3.00 1.20
6 0.416 53.20 3.00 1.20
7 0.057 53.40 3.00 1.20
8 0.057 53.20 3.00 1.20
9 0.057 52.76 3.00 1.20
10 0.057 52.11 3.00 1.20
11 0.057 52.00 3.00 1.20
==========================================================
30
The output data provided by the program SEWER for a hypothetical project area is
included in result section. The output file contains detailed sewer network design
information.
31
The data and material required for the design of STP is tabulated below:
Table - 5
Waste Water ( Sewage ) 26.65 MLD
A flow
Say 27.00 MLD
Overall Substrate Removal 0.8
B Rate Constant (K/d)
Dispersion Number 0.1 to 4.0
C
Minimum Ambient 15 C
D Temperature
Waste Water Temperature 25 C
E
Oxygen Required in Ultimate BOD removal in kg/d
F Aeration (kg/d)
Aerator Capacity in field 1.6 kg O2 / KWh
G
Slugde Depth (m) Consideration of 5 yrs sludge
H accumulation
Detention Time 5 days
I
Liquid Depth (m) 6 m maximum including sludge
J deposition
1. Site visit of the project area and data collection from the urban local body
which include development plan of the town, last five decade census data,
SBC report & information about previous water works in the town. Source
identification is also done at the time of site visit.
2. Site survey and the preparation of base map of the project area showing
road networks, their lengths, elevations at fixed intervals and important
locations.
3. Estimation of population by various population forecast method for the
32
design period of 30 years. The population is also forecasted for stage wise,
zone wise and ward wise.
4. Water requirement and capacity of reservoir is estimated for the
intermediate and ultimate stage.
5. Database preparation from the node to node analysis of the base map for the
entry in the LOOP & BRANCH Software.
6. Water Distribution Network design and simulation using the software.
7. Hydraulic design of pumping station, pumping machinery, rising main,
sump and ESR is separately done.
8. Bill of Quantity preparation of each component of the water supply scheme.
9. Relevant drawings are also prepared with the help of AutoCAD software.
1. Site visit of the project area and data collection from the urban local body
which include development plan of the town, last five decade census data,
SBC report & information about previous water works in the town. Site
identification for STP is also done at the time of site visit.
2. Site survey and the preparation of base map of the project area showing
road networks, their lengths, elevations at fixed intervals of 30 m and
important locations.
3. Estimation of population by various population forecast method for the
design period of 30 years. The population is also forecasted for stage wise,
zone wise and ward wise.
4. Sanitary wastewater is estimated for the intermediate and ultimate stage and
for each zone which is distributed on each node.
5. Database preparation from the node to node analysis of the base map for the
entry in the SEWER Software.
6. Sewer Network design and simulation using the software.
7. Hydraulic design of pumping station, pumping machinery, manhole cum
lifting station, rising & pumping main, collection well and effluent disposal
pipe.
33
8. STP and its inlet outlet arrangement is designed as per guideline of the
CPHEEO Manual on Sewerage and Sewage Treatment.
9. Bill of Quantity preparation of each component of the underground drainage
scheme.
10. Relevant drawings are also prepared with the help of AutoCAD software.
The key achievements during project work were learning of hydraulic design of
water distribution network pipelines through the use of LOOP and BRANCH
software which uses Hazen William formulae and sewer network pipelines design
through the use of SEWER software which uses Mannings formulae. I involved in
designing of STP having aerated lagoon as biological treatment unit. I also prepared
Bill of Quantity for the water supply and UG drainage projects which estimate the
component wise cost of project in detail.
The results of the water distribution network design for a hypothetical project area
are comprises of two sections:
1. Using LOOP Software The results include pipe details, node details
excavation depth & cost summary. Detailed Looped Water Distribution
Network Design Output is given below:
Bandwidth = 3
Number of Loops = 5
Newton Raphson Iterations = 6
34
Pipe Details
====================================================
Pipe From To Flow Dia HL HL/1000m Length Velocity
No. Node Node (lps) (mm) (m ) (m ) (m ) (m/s )
-------------------------------------------------------------------------
1 300 1 22.600 200.0 3.22 4.02 800.00 0.72
2 1 3 4.245 100.0 1.86 5.32 350.00 0.54
3 1 2 9.621 150.0 1.68 3.36 500.00 0.54
4 2 7 2.586 75.0 5.17 8.62 600.00 0.59
5 3 4 1.245 75.0 1.60 2.23 720.00 0.28
6 1 5 3.534 100.0 2.65 3.79 700.00 0.45
7 2 6 0.234 50.0 0.55 0.73 750.00 0.12
8 7 8 0.186 50.0 0.33 0.48 700.00 0.09
9 5 4 2.715 100.0 0.81 2.32 350.00 0.35
10 6 5 1.580 100.0 0.43 0.85 500.00 0.20
11 6 8 15.654 150.0 4.96 8.27 600.00 0.89
12 4 11 1.360 75.0 2.10 2.62 800.00 0.31
13 11 13 13.760 150.0 5.86 6.51 900.00 0.78
14 12 13 0.240 50.0 0.42 0.76 550.00 0.12
15 8 12 4.004 100.0 3.82 4.77 800.00 0.51
16 8 9 9.236 150.0 1.56 3.11 500.00 0.52
17 9 10 5.200 100.0 5.03 7.74 650.00 0.66
18 9 17 1.636 75.0 2.95 3.69 800.00 0.37
19 12 17 0.964 75.0 0.69 1.39 500.00 0.22
20 13 14 11.000 150.0 1.51 4.30 350.00 0.62
21 14 15 3.200 100.0 2.84 3.15 900.00 0.41
22 14 16 4.200 100.0 6.26 5.21 1200.00 0.53
50 100 11 15.000 150.0 3.82 7.64 500.00 0.85
60 200 6 20.000 200.0 1.12 3.21 350.00 0.64
35
Node Details
=======================================================
Node Flow Elev. HGL Pressure
No. (lps) (m ) (m ) (m )
-------------------------------------------------------
1 -5.200 15.00 36.78 21.78
2 -6.800 15.00 35.10 20.10
3 -3.000 15.00 34.92 19.92
4 -2.600 15.00 33.32 18.32
5 -2.400 15.00 34.13 19.13
6 -3.000 15.00 34.56 19.56
7 -2.400 15.00 29.93 14.93
8 -2.600 15.00 29.60 14.60
9 -2.400 10.00 28.04 18.04
10 -5.200 10.00 23.01 13.01
11 -2.600 10.00 31.22 21.22
12 -2.800 10.00 25.78 15.78
13 -3.000 10.00 25.36 15.36
14 -3.600 10.00 23.85 13.85
15 -3.200 10.00 21.02 11.02
16 -4.200 10.00 17.60 7.60
17 -2.600 10.00 25.09 15.09
300 S 22.600 10.00 40.00 30.00
100 15.000 10.00 35.04 25.04
200 20.000 10.00 35.68 25.68
=======================================================
37
2. Using BRANCH Software The results include pipe details, Pipe pressure
details, node details excavation depth & cost summary. Branched Water
Distribution Network Design Output are given below:
Pipe Details
============================================================
Pipe From To Peak Flow Diam Hazen's HL HL/1000 Length Status
No. Node Node (lps) (mm) Const (m ) (m ) (m ) (E/P)
----------------------------------------------------------------------------
1 1 2 98.000 250.0 120.00000 8.82 17.64 500.00
2 2 3 9.000 100.0 110.00000 10.84 21.68 500.00 E
3 2 4 9.000 150.0 110.00000 1.50 3.00 500.00
4 2 6 71.000 100.0 110.00000 4.26 8.52 500.00
250.0 120.00000 4.26 8.52 500.00 P
5 6 5 9.000 150.0 110.00000 1.50 3.00 500.00
6 6 7 9.000 150.0 110.00000 1.50 3.00 500.00
7 6 9 44.000 200.0 110.00000 0.81 13.92 58.21
250.0 120.00000 1.77 4.01 441.79
8 9 8 9.000 150.0 110.00000 1.50 3.00 500.00
9 10 9 1.000 75.0 100.00000 0.90 1.80 500.00
10 9 12 27.000 200.0 110.00000 2.83 5.66 500.00
11 12 11 9.000 150.0 110.00000 1.50 3.00 500.00
38
The results of the sewer network design using SEWER Software for a hypothetical
project area. The results include node details, pipe details, pipe level details, node
details, excavation details, pipe cost summary and other miscellaneous details. The
detail results are given below:
Pipe Details
Pipe From To Peak Flow Length Dia. Pipe Ground Existing
No. (lps) (m ) (mm) Slope Slope Pipe
------------------------------------------------------------------------
1 1 2 3.960 30.00 169.0 170 187.5
2 2 3 4.356 30.00 169.0 178 187.5
3 3 4 4.752 30.00 300.0 137 150.0
4 4 5 4.923 30.00 300.0 213 250.0
5 5 6 5.094 30.00 300.0 155 187.5
6 6 7 6.342 30.00 300.0 249 -150.0
7 7 8 6.513 30.00 300.0 122 150.0
8 8 9 6.684 30.00 300.0 52 68.2
9 9 10 6.855 30.00 300.0 36 46.2
10 10 11 7.026 30.00 300.0 247 272.7
Node Details
Node Node Peak Peak Ground Excav. Pumping
No. Type Factor Flow in Elev. Depth Provided
(lps) (m ) (m ) (Y/N)
---------------------------------------------------------
1 REF 3.00 3.960 54.00 1.4
2 3.00 0.396 53.84 1.4
3 3.00 0.396 53.68 1.5
4 3.00 0.171 53.48 1.6
5 3.00 0.171 53.36 1.6
6 3.00 1.248 53.20 1.6
7 3.00 0.171 53.40 1.9
8 3.00 0.171 53.20 2.0
9 3.00 0.171 52.76 2.1
41
Excavation Details
Pipe Avg. Exc. Exc. Vol. Exc. Cost Cumulative
No. Depth Exc. Cost
(m ) (m 3) (1000 Rs ) (1000 Rs )
--------------------------------------------------------
1 1.4 33.58 2.02 2.02
2 1.4 33.88 2.03 4.05
3 1.5 41.70 2.50 6.55
4 1.6 42.25 2.54 9.09
5 1.6 42.98 2.58 11.67
6 1.8 47.75 2.88 14.55
7 2.0 52.71 3.19 17.74
8 2.0 55.19 3.34 21.08
9 2.2 59.44 3.60 24.69
10 2.3 61.97 3.76 28.45
The design of STP and hydraulic design of other components of water supply and
underground drainage system are appended in annexure section of the report.
42
The results of the network design of water supply and underground sewerage
system gives detailed engineering design as well other miscellaneous data required
to carry out any water works for a town. The works involved to carry out the
project work involves rigorous site visits, detailed analysis of the existing systems,
and topography study of the project area. The project gives opportunity to learn
some key concepts of hydraulic design of water supply and sewerage system, hands
on experience of the software like LOOP, BRANCH, SEWER and AutoCAD.
To conclude this report the importance of the basic infrastructure of water supply
and underground sewerage system for a town cant be ignored as it provide the base
for the development of the town. The efficient, reliable and cost effective design of
water supply and underground sewerage system could be one step to achieve the
sustainable development and to achieve their goals.
43
REFERENCES
Arceivala J. S., 2000, Wastewater Treatment for Pollution Control, 2nd Edition,
Tata McGraw-Hill Publishing Company Limited, New Delhi.
Christian R. A., Karia G. L., Wastewater Treatment-Concepts and Design,
3rd Edition, Prentice Hall of India Pvt. Ltd.
Desai A. G., 2001, Hydraulic Design Tables for Pipelines and Circular Sewers
and Drains, Deep Publishers.
Eddy & MetCalf, 2003, Wastewater engineering-treatment and reuse, 4th
Edition, TATA McGraw-Hill Publishing Company Ltd., New Delhi.
Arceivala J. S., Asolekar R. S., 2001, Waste water Treatment for Pollution
Control and Reuse, 3rd Edition, Tata McGraw Hill Education Pvt. Ltd., New
Delhi.
Chawathe D. S., 2004, Manual on Water Demand Assessment-for urban water
supply projects, Indian Water Works Association, Goa.
1993, Manual on Sewerage and Sewage Treatment, 2nd Edition, Central Public
Health Environmental Engineering Organization, New Delhi.
1999, Manual on Water Supply and Treatment, 3rd Edition, Central Public
Health Environmental Engineering Organization, New Delhi.
44
A N N E X U R E N O . 1 : E S T IM A T IO N O F F U T U R E P O P U L A T IO N F O R D E E S A T O W N
ANNEXURE(S)
T h e p o p u l a t i o n o f t h e D E E S A a s p e r t h e c e n s u s re c o rd s a re g i v e n b e l o w f o r t h e
y e a rs 1 9 6 1 - 2 0 0 1 . T h e g e s t a t i o n p e ri o d o f o n e y e a r m a x i m u m i s c o n s i d e re d f o r t h i s
p ro j e c t a n d t h e re b y t h e b a s e y e a r o f t h e p ro j e c t s t a n d s t o 2 0 1 1 , h e n c e i t i s re q u ri e d
t o e s t i m a t e t h e p o p u l a t i o n 3 0 y e a rs h e n c e i . e . 2 0 4 1 a n d a l s o t h e i n t e rm e d i a t e
p o p u l a t i o n 1 5 y e a rs a f t e r 2 0 1 1 i . e . 2 0 2 6 .
1. Population projection by various methods for a project area is given below:
C e n su s R e co rd
DEESA
Y ear P o p u la t io n I n c re m e n t
(P e rs o n s )
n p x
1961 18891
1971 28324 9433
1981 41730 13406
1991 62435 20705
2001 83340 20905
64449
Ave ra ge 1 6 1 1 2 .2 5
Say 16120
1 . A r ith m e tic a l P r o g r e s s io n M e th o d :
2001 83340
2010 83340 0 .9 0 16120 97848
2011 83340 1 .0 0 16120 99460
2016 83340 1 .5 0 16120 107520
2021 83340 2 .0 0 16120 115580
2026 83340 2 .5 0 16120 123640
2031 83340 3 .0 0 16120 131700
2036 83340 3 .5 0 16120 139760
2041 83340 4 .0 0 16120 147820
A BGeom
2. S T Retrical
A C T Progression Method
Solution
ABSTRACT
Solution :
Projected
Population
Projected
Decade Population Incremental with 10%
Year Last Census Increment Population
(n) (Persons) Increase Floating
(Persons)
Population
(Persons)
2001 83340
2010 83340 0.9 16120 97848 3270 101118 112000
2011 83340 1.00 16120 99460 3824 103284 114000
2016 83340 1.50 16120 107520 7170 114690 127000
2021 83340 2.00 16120 115580 11472 127052 140000
2026 83340 2.50 16120 123640 16730 140370 155000
2031 83340 3.00 16120 131700 22944 154644 171000
2036 83340 3.50 16120 139760 30114 169874 187000
2041 83340 4.00 16120 147820 38240 186060 205000
ABSTRACT
1000000 6.00
100000 5.00
10000 4.00
1000 3.00
POPULATION
Series2
100 2.00
10 1.00
1 0.00
1961
1971
1981
1991
2001
2010
2011
2016
2021
2026
2031
2036
2041
Design Considerations
NODE 1
Ground Level 124.15
Invert Level 118.2
Diameter of Incoming Pipe (mm) 350
Diameter of Outfall Pipe (mm) 900
Leading Manhole (LM)/Point Collection Well
Ground Level of LM 124
Invert Level of LM 122.5
Distance 1500
Min. Invert of Connecting Pipe 1
Population 127700
Design Flow (lps) 576.42
Design
Identification 1
Design Flow (lps) 576.42
Design Flow (cum/min) 34.5854
Detention Period (min) 30
Volume (cum) 1037.56
Sewage Depth (m) 3
Area (Sq m) 345.85
Diameter (m) 20.99
Say 21.00
GLRL 124.15
ILRL 118.20
Free Board (m) 0.30
FSLRL (m) 117.90
Sewage Depth (m) 3.00
Bottom RL 114.90
Depth of Lifting Station (m) 9.25
Distance (m) 1500.00
Leading Manhole ( LM) Collection Well
GLRL of LM 124.00
ILRL of LM 122.50
ILRL of Connecting Pipe 123.10
Depth of Leading Manhole (m) 1.50
Static Head (m) 8.20
48
PROCESS
1 Primary treatment
2 Secondary treatment
1 PRIMARYTREATMENT
a. Barscreenchamber To remove suspendedmatter
b. Grit removal chamber To remove grit / hardmatter
Proportional flowweiris provdedto control flowvelocity at different flows.
Boththe process protect abnormal wear&tearof mechanical equipments, helps insatisfactory operationof treatment units, reduce the cleaning frequency of aerated
lagoons andavoiddepositioninpipelines, etc.
2 SECONDARYTREATMENT.
a. AeratedLagoon: Stage I Boththe stages canbe termedas Biological Process as inorganic matteris
b. AeratedLagoon: Satge II removedinprimary treatment. Thus, mainly biodegradable organic matteris
removedinsecondary treatment.
AeratedLagoons are providedto remove the soluble andinsoluble organic matterinwaste wateri.e. sewage by virtue of aerobic microbes. The oxygenrequiredby
microbes is providedby surface aerators.
3 SEWAGECHLORINATION
DESIGNPARAMETERS
1 Screencham ber
a. Velocity 1.2m
/s
b. ScreenBarSpacing 25mm
c.Barsize-10x50m mflats
d. ScreenSlope 45m anualoperation
e. HfthroughScreens 0.15to0.30mm anualoperation
2 GritCham ber
a. SpecificGravityofParticles 2.65
b. ParticalSize 0.15
c. Minim umTem perature 15C
d. Kinem aticViscosity 1.14X10^-6 sqm/sat15degree
e. FrictionFactor 0.03
f. SettlingVelocity AsperStoke'sLawandTransitionLaw
g.DetentionTim e 60s
h.FlowthroughVelocity 0.3m/s
ProportionalW eirisprovidedtocontrolthe
3 Q=CbxSqrt(2agx(h-(a/3))
horizontalvelocity
4 AeratedLagoon(Facultativetype)
a.RawBOD(m g/l)
b.SuspendedSolids(m g/l)
c.Overallsubstraterem ovalrateconstant(K/d) 0.8
d.DispersionNum ber 0.1to4.0
e.W asteW aterTem perature 25C
f. OxygenRequiredinAeration(kg/d) Ultim
ateBODrem ovalinkg/d
g.AeratorCapacityinfield 1.6kgO2/Kwh
h.SlugdeDepth(m ) Considerationof5yrssludgeaccum ulation
i. DetentionTime 5days
j.LiquidDepth(m ) 6mm aximumincludingsludgedepostion
k.BafflesProvidedineachAeratedLagoon 2No.ofBaffles
5 Chlorination
a. ChlorineDose 15m g/l
b. DetentionTimeofMixingCham ber 30to60sec
c. DetentionTimeinChlorineContactCham
ber 30to60m in
50
PROCESSDESIGNCALCULATIONS
1 SCREENCHAMBER
ScreenBarSpacing 25 mm
BarSize-10x50mmflats
NumberofSpacings 50 Nos
NumberofBars 49 Nos
ActualWidthofScreen 1.74 m
Say 1.75 m
Inclinationofthebar 45 Degree
Inclinedlengthofbars 1.31 m
horizontalprojectedlength 1 m
LengthofPerforatedplate 1.75 m
DepthofScreeningpocket(Assumed) 0.15 m
Widthofscreen(Assumed) 1.40 m
Lengthofoutletzone 2.0 m
AssumeLengthofinletzone 1.0 m
Toatallengthofscreenchannel 4 m
Netarearequiredforthescreenchamber 14 sqm
Grossarearequiredforthescreenchamber 21 sqm
Thus, providetwoscreenchambersofdimension1.75mx4mx0.9meach.
Checkforheadloss
VelocitythroughScreen 1.2 m/sec
VelocityafterScreen 0.89 m/sec
NowheadlossthroughscreenatQmax 0.05 m
Quantityofscreening
ScreenProductionfor25mmopeninganda
maximumflowof81MLD 0.0015 cum/MLofflow
QuantityofScreening
0.1215 cum/day
Cleaningcanbedonemanuallyevery3daysforanapproximatequantityof0.3645cumsay(0.1215*3)whichis
equivalentto365litresevery3days.
51
2 GRIT CHAMBER
4 AERATED LAGOON
The facultative type aerated lagoon system is divided into two parallel equal streams. Each stream is divided into
two stages, I and II.
Flow Per Stream 13500 cum/d
Let Detention Time for Stage I 2.5 days
Volume of each Ist Stage Lagoon 33750 cum
For D/UL=Dt/L*L
where, L 675 m
W 10 m
D=33 x W 330
Thus, D/UL 0.04
Now, Lagoon Temperature in Winter t/h = Ti - Tw / f(Yw - Ta)
K L 22.29 0.87
K L 22.29 x t 2.2
For D/UL = 0.04 and K Lt =2.2, BOD removal (from 85 %
figure 3.6 of Arceivala)
Total BOD at outlet of 2nd stage Aerated Lagoon 19 mg/l (which is less than 30 mg/l)
5 SLUDGE ACCUMULATION
6 POWER REQUIREMENT
7 CHLORINATION SYSTEM
Chlorine Requirement