0 Bewertungen0% fanden dieses Dokument nützlich (0 Abstimmungen)
165 Ansichten20 Seiten
This document discusses the challenges of designing and constructing a large heap leach pad in northern China. It summarizes the project location and conditions, including extreme weather. It describes the pad layout optimization process and general design, focusing on challenges like thin soils, freezing temperatures, and material sourcing/quality. Construction challenges involved managing weather impacts, ensuring earthworks and liner quality control, and overseeing an inexperienced local contractor and suppliers. Careful planning, an on-site lab, and bilingual engineers helped address issues and complete the project successfully.
This document discusses the challenges of designing and constructing a large heap leach pad in northern China. It summarizes the project location and conditions, including extreme weather. It describes the pad layout optimization process and general design, focusing on challenges like thin soils, freezing temperatures, and material sourcing/quality. Construction challenges involved managing weather impacts, ensuring earthworks and liner quality control, and overseeing an inexperienced local contractor and suppliers. Careful planning, an on-site lab, and bilingual engineers helped address issues and complete the project successfully.
This document discusses the challenges of designing and constructing a large heap leach pad in northern China. It summarizes the project location and conditions, including extreme weather. It describes the pad layout optimization process and general design, focusing on challenges like thin soils, freezing temperatures, and material sourcing/quality. Construction challenges involved managing weather impacts, ensuring earthworks and liner quality control, and overseeing an inexperienced local contractor and suppliers. Careful planning, an on-site lab, and bilingual engineers helped address issues and complete the project successfully.
Bruno Borntraeger, Knight Pisold Ltd., Canada Daniel Yang, Knight Pisold Ltd., Canada XD Jiang, China Gold International Resources Corp. Ltd., Canada Table of Contents Project Location Pad Layout Optimization General Area / Section Design Challenges Construction Challenges Conclusion Project: CSH Gold Mine Located in Inner Mongolia, China (650 km northwest of Beijing)
Commenced production in 2007
Currently processing 30,000 tonnes of CSH Gold Mine
Beijing ore per day Bautou
Producing 133,000 ounces of gold per
year
Expansion underway to double annual
production of gold
Involves construction of new heap
leach facility with capacity of 100 million tonnes of ore General Site Conditions Inner Mongolia Plateau (1,550 to 1,750 MASL)
Gentle Sloping Rolling Hills and
Undulating Topography
Thin Fine Grained Overburden
(0 to 2.8 m)
Clastic Sedimentary Formation
Bedrock Intercalated with Carbonate Rich Rocks (Quartz Sandstone, Greywacke, Siltstone and Shale with Dolomite and Limestone)
Earthquake Magnitude : 7 (Peak Ground Acceleration : 0.1g) Weather Conditions Extreme Temperatures (-38 C to 37 C)
High Ambient UV Radiation
Strong and Persistent Winds
Long Dry Periods and Extreme
Evaporation Rates
Severe Summer Rain Storms
Sand storm on site
Layout Optimization Phase 1 Pad Existing Heap Leach Pad Phase 2 Pad (Original Proposal) Covers Flat Area of 133 ha Pile Capacity of 75 million m 3 Utilized the Best (Gentlest) Topography Phase 2 Pad (Optimized Layout) Phase 2 Maximizes Land Use and Minimizes Heap Slope (original) Area Phase 1 Reduces Footprint Area of Original Phase 2 Design By 20% Requires Construction of Only One Pregnant Pond Phase 2 Preserves Land for Future Heap Leach Pad (revised) (Phase 3) General Layout Revised Phase 2 leach pad: Surface Area 120 ha Ultimate Heap 90 m Phase 1 Heap Leach Pad Storage Capacity 105 million tonnes El. 1695 Phase 2 Heap (65.2 million m 3 ) Leach Pad El. 1700 Typical Cross Section Design Challenges: Liner bedding Site Is In Semi-desert Region with Very Thin Overburden Cover (3 m)
Challenge: Find Suitable Low
Permeable Material (Clayey Silts) and Sufficient Water Resources for Moisture Conditioning of Liner Bedding Layer
Suitable Bedding Material Was Found
Along Ancient River Beds 5 km East of The Mine
Identify Suitable Water Source
Shape Sharp Bedrock Outcrops to
Minimize Consumption of Liner Bedding Material Design Challenges: Geomembrane Challenge: Freezing Temperatures and High Winds Required Special Consideration of Geomembrane Type and Thickness High Density Polyethylene (HDPE) Was Selected 80 mil (2 mm thick) HDPE Geomembrane, Smooth and Textured Were Selected Manufacture and Quality of Product Was a Concern Design Challenges: Liner Manufacture Challenge: In-plant Quality Control Is Limited Amongst Chinese Manufactures Despite Significant Cost Advantages Foreign, ISO 9000 Certified Manufacturer Was Chosen Laboratory Certified By GAI/LAP Provides Third-party, In-plant Quality Assurance Program Owner and Engineer Visited Sites to Review Plant Set Up and Quality of Manufacturing Process Design Challenges: Solution Collection Piping Challenge: 610 mm HDPE Pipes, Whilst Reliable, Were Found To Be Heavy, Less Flexible, Expensive, and Difficult To Install In Phase 1 North America and South America Leach Pad Designers Commonly Use Smooth Wall CPT Chinese Manufacturers Very Innovative And Entrepreneurial With Respect To Fitting Options Proposed Design Challenges: Solution Collection Piping The Flexibility Of CPT Pipes Make Them Easier To Install Within The Topography Of The Pad 600 mm Smooth Interior Corrugated Polyethylene Tubing (CPT) Was Selected For The Main Solution Header Pipes 300 mm and 100 mm Pipe Diameters Were Selected For Collection Piping System Construction Challenges: Weather Challenge: Weather Incurred Damage To Subgrade And Liner Installation Causes Delays To Schedule And Costs Liner Installation Crew Deploys Liner In The Early Morning and Ballasts Edges Before Winds Pick Up Careful Planning For Surface Water Control Off Geomembrane and Subgrade to Minimize Erosion and Re-Work Construction Challenges: Site Materials Challenge: Confirm That Specified Earthworks Materials Meet Technical Requirements Soil Laboratory Established On Site To Rapidly Evaluate Material Quality Earthworks Contractors In China Had To Be Convinced That QA/QC Added Value To the Construction Process Construction Challenges: Earthworks QA/QC Challenge: Contractors Had to Be Encouraged to Conduct Quality Control Testing On Overliner Manufacture to Ensure Compliance Material Local Earthworks Contractor Had Limited Experience In Quality Control and Construction Management Field Soil Laboratory Was Established Water Was In Short Supply During Moisture Conditioning Process (Dry Season) Eroded liner bedding due to heavy rainfall and poor surface water runoff planning Construction Challenges: Earthworks QA/QC Compaction Had to Be Performed Quickly Strong Winds and Sand Storms Often Blew Away Fine Grain Material, Requiring Re-work Sudden, Intense Rainfall Removed Fines And Caused Excessive Erosion.
Destroyed liner bedding due to heavy rainfall
Construction Challenges: Geomembrane QA/QC Local Installer Had Limited Experience With Heap Leach Projects But Was Skilled and Reputable in Liner Installations The QA/QC Field Program Focused On Industry Standard Visual Inspection and Field Installation Testing Program Strong Winds Were Main Challenges to Installation Numerous Sandbags and Temporary Ballasting Were Required Throughout Installation Process Construction Challenges: Pipeworks QA/QC Likely The First Time CPT Used as Solution Collection System For a Heap Leach Operation In China Maintaining Good Quality Pipework and Fittings Was a Big Challenge Chinese Testing Standards (and Product Quality) Do Not Yet Meet International Standards Suppliers Were Forced to Modify Manufacturing Processes and Re- manufacture Returned Products Conclusions Weather, Design And Construction Challenges Were Overcome By Experienced Engineers KP Was Very Fortunate To Have Chinese Speaking Engineers In-House To Complete Design and Field Work Activities. Drawings and Engineering Documentation was prepared in English and Chinese Languages.