Beruflich Dokumente
Kultur Dokumente
DOCUMENT TITLE:
REVISION RECORD
CONTENTS Pag
DEFINITIONS.......................................................................................................................4
ABBREVIATION...................................................................................................................5
1 INTRODUCTION.....................................................................................................6
2 OBJECTIVE.............................................................................................................6
3 SCOPE DEFINITION...............................................................................................6
3.1 BACKGROUND......................................................................................................6
3.2 SCOPE....................................................................................................................7
4 BASIC DATA...........................................................................................................7
4.1 ENVIRONMENTAL CONDITIONS..........................................................................7
4.2 TAGGING SYSTEM................................................................................................8
6 DEFINATIONS.........................................................................................................9
6.1 CONSUMED LOAD (in KW)...................................................................................9
6.2 RATED POWER (in KW)........................................................................................9
6.3 CONTINUOUS LOADS.........................................................................................10
6.4 INTERMITTENT LOADS.......................................................................................10
6.5 STANDBY LOADS................................................................................................10
7 METHODOLOGY OF CALCULATION.................................................................10
9 SUMMARY.............................................................................................................11
DEFINITIONS
For the purposes of this report, the following definitions of terms and interpretations shall
apply regardless of and other meaning the words may have in other respects:
ABBREVIATION
AC - Alternating Current
ACB - Air Circuit breaker
AWA - Aluminum Wire Armour
BP RP - British Petroleum Recommended Practices
BS - British Standard
CT - Current Transformer
CU - Copper
DEPM - Diesel Engine Prime Mover
DG - Diesel Generator
ES - Engineering Standard
EPIC - Engineering Procurement Installation and Commissioning
ESD - Emergency Shutdown System
FAT - Factory Acceptance Test
GCP - Generator Control Panel
IEC - International Electro-technical Commission
IET - Institute of Environmental Technology
IEEE - International Electrical Electronics Engineers
ISO - International Organization for Standardization
kVA - kilo Volt Ampere
LV - Low Voltage
OEM - Original Equipment Manufacturer
PLC - Programmable Logic Controller
PVC - Poly Vinyl Chloride
QDC - Qatar Design Consortium
QP - Qatar Petroleum
RMS - Root Mean Square
SB - Switchboard
TEFC - Totally Enclosed Fan Cooled
XLPE - Cross Linked Poly Ethylene
1 INTRODUCTION
QATAR PETROLEUM (QP) has awarded contract to Petroserv Controls &
Communication for the project (Engineering Consultancy Services for Upgrading of
500kVA Emergency DG set at GD station S) under the contract no. LC16104300. Qatar
Design Consortium (QDC) is engineering design consultant to perform the detailed
design and engineering services for the contract.
2 OBJECTIVE
The main objective of this document is to check adequacy of LV Breaker Sizing for
DG Incomer Breaker.
3 SCOPE DEFINITION
3.1 BACKGROUND
The Emergency switch board SSB-104 is now in excess of load, it would be more than
500kVA. Therefore, the existing 500kVA DG set needs to be upgraded to higher range of
DG capacity. Power supply to the existing switch board (S-SB-104) is fed from 500KVA
DG set in case of emergency power required. The existing DG set is skid mounting type;
Make: FG Wilson (Engineering) Ltd, the rating of the DG set is 500KVA or rated standby
power capacity of DG is 548 kVA (438kW).
Controller ACESS 4000 is provided for the protection of DG set. ACCESS 4000 controller
has a facility to operate the DG set in both Auto & Manual mode. The existing batteries:
2nos of 12V of capacity 200AH (Make: CAT; model: 1400 CCA) maintenance free with
auxiliary charger used for charging of batteries during DG off condition.
The power cables laid in existing cable trench from generator power panel to switch
board SWB-104. Adequacy of existing power cable needs to be checked for new
proposed DG set and the higher range of cable shall be replaced suitably, if the existing
cables are found inadequate.
The existing cable shall be 2Rx1Cx 630 Sq.mm per phase; Cu/XLPE/AWA/PVC cables
per phase & 1Rx1Cx 630Sq.mm for neutral; Cu/XLPE/AWA/PVC laid and these are
connected from DG power panel to the DG incomer ACB in the existing emergency
switch board SB-104.
3.2 SCOPE
This document specification detailed about requirements for industrial type self-excited
power generators driven by diesel engine abbreviated DEPM (Diesel engine prime mover)
along with brushless excitation system, automatic voltage regulator, generator control panel,
generator breaker and associated accessories.
4 BASIC DATA
4.1 ENVIRONMENTAL CONDITIONS
The highest average humidity occurs during the months of December and January. At the
time of maximum temperature the maximum relative humidity is 46%. Humidity in the
range of 100% at 27C is recorded previously. Moisture in the atmosphere occasionally
holds salts.
4.1.3 Rainfall
Average annual rainfall 80 mm
4.1.4 Winds
Prevailing wind direction is from the North-West to North-North-West
4.1.5 Lightning
Thunderstorms and lighting occur at infrequent periods
4.1.6 Sandstorm
Severe sandstorms are common.
4.1.7 Earthquakes
Earthquakes do not occur and an earthquake zone rating is not applicable.
Dummy tags shall be used for the proposed equipment. A request for actual tags shall be
generated by EPIC contractor to QP during detail design phase as per QP
Engineering Standard QPR-DKN-05_Rev.02 (2012).
5.1 QP STANDARDS/SPECIFICATIONS
QP STANDARDS
E.S.2.14.0015 Low Voltage Switchgear and Control gear for use indoor
INTERNATIONAL STANDARDS
6 DEFINATIONS
The following items defined below are for general information and better understanding of Load
Schedule
This is the design power requirement of the driven equipment at design point, in kilowatt. The
design power requirement is the power drawn by the equipment when the plant is operating at the
design capacity under normal operating condition.
The rated power is the rated kilowatt indicated on the name plate of the equipment.
All the loads, which may be running continuously in normal operating conditions like motors,
lighting loads, UPS and battery charger loads etc.
All the loads which are required for intermediate operations like Hoist, Motor operated Valves etc.
All loads which are required to be operated only in the event of failure of normal operating loads
and during shutdown of plant like spare motors, receptacle outlets, welding outlets etc.
7 METHODOLOGY OF CALCULATION
Conclusion:
Looking into the above, the existing DG incomer ACB (1600A) is adequate to carry
the rated full load current of 1000KVA DG set.
Load details:
= 711 A
= 888A
9 SUMMARY
Referring to the above sizing calculation result, selection of breaker size (1600A) is
adequate for 1000kVA DG set.