5(3)ABAD/P&D/2007
Government of the Punjab
Planning & Development
Department

Dated Lahore the 28th February,


2009

To,

The Director General,


Agency of Barani Area Development (ABAD),
Murree Road, Rawalpindi.

Subject:- REVISED PC-I OF ADDITION/ALTERNATION OF ABAD


COLONY

Kindly refer to your letter No.ABAD/949/Dev dated


20.02.2009 on the subject noted.

It is submitted that this document is not in accordance with


decision of the meeting and same is hereby returned.

Please advise to use proper format of revised PC-I and


clearly indicate on map work already done and to be done to process
this case further.

(Ch. Iftikhar Ahmad)


Assistant Chief (RP)
URGENT No. 5(3)/ABAD/P&D/2007
GOVERNMENT OF THE PUNJAB
PLANNING & DEVELOPMENT DEPARTMENT

Dated Lahore, the 25th March 2009

To

The Section Officer (I&P),


Government of the Punjab,
Finance Department,
Lahore.

Subject:- PROVISION OF ADDITIONAL FUNDS DURING 2008-09

Reference your U.O. No. FD.SO(I&P)2-9/08-09-Vol-I dated


16.03.2009 on the subject noted above.
It is stated that execution of the work was delayed by the
contractor and funds to the tune of Rs. 4.055 million were utilized
against allocation and releases of Rs. 10.00 million up to 30 June 2008.
Thus the demand of additional funds of Rs. 3.00 million is genuine and
endorsed. The same may be released at the earliest. Non-release of
the same may cause further delay and escalation in the cost of the
scheme.
Scheme was also discussed in DDSC meeting dated
14.02.2009 and its approval was deferred due to some observations of
Finance Department. Scheme is being placed in DDSC meeting within a
week for approval proposing extension in gestation period up to June
2010 and some additional works.

(MUHAMMAD ASLAM CH.)


CHIEF (RP)

C.C.

Director General, ABAD, Murree Road, Rawalpindi with reference


to your letter No. ABAD/AAOL/650/Dev dated 19.03.2009.
MEETING NOTICE No. 5(3)/ABAD/P&D/2007
URGENT GOVERNMENT OF THE PUNJAB
PLANNING & DEVELOPMENT DEPARTMENT

Dated Lahore, the 27th March 2009

To
1. The Director General,
Agency for Barani Areas Development (ABAD),
Government of the Punjab,
Murree Road,
Rawalpindi.
2. The Deputy Secretary (Infrastructure/Technical Advisor),
Government of the Punjab,
Finance Department,
Lahore.
3. The Chief (Technical),
Government of the Punjab,
P&D Department,
Lahore.

Subject:- ADDITION / ALTERATION OF ABAD COLONY

I am directed to state that a meeting of Department


Development Sub Committee (DDSC) is scheduled under the
chairmanship of Secretary, P&D Department in his office chamber on
31.03.2009 at 1:00 p.m. to discuss the subject scheme. Working paper
is enclosed and D.G. ABAD is also requested to please provide the copy of
requisite map to Deputy Secretary, Finance Department and also depute
technical person to discuss this map with him before this meeting.
All concerned are requested to please make it convenient to
attend the meeting on the above mentioned date and time.

(KAHLID MEHMOOD GILLANI)


Assistant Chief (RP)
C.C.
1. PS to Secretary, P&D Department, Lahore.
2. Section Officer (General), P&D Department for making
necessary arrangements.
3. P.A. to Chief (RP), P&D Department, Lahore.
Government of the Punjab
Planning and Development Department

ORDER

No.5(3)ABAB/P&D/2008. Governor of the Punjab is pleased to accord sanction and


release a sum of Rs.9.314 (Rupees Nine Million Three Hundred Fourteen
Thousand Only) for the year 2009-10 for the scheme titled “Addition / Alteration of
Old ABAD Colony” at general Sr.No.2234 MTDF 2009-10 under grant
No.PC22036-Development Regional Planning.

2. The expenditure would be incurred after completion of all the codal


legal procedural formalities.

3. The expenditure shall be debitable to Grant No.PC-22036-


Development 06-Housing & Community Amenities, 062-Community Development,
0621-Urban Development, 062103-Urban Planning-A-052-Grant-Domestic A05270
to Others LE-4317- Project code No.-RI01000252 “Addition / Alteration of old ABAD
Colony” Rawalpindi during the year 2009-10

SECRETARY
P&D DEPARTMENT
Dated Lahore the July, 2009
NO. & DATE EVEN
A copy is forwarded for information and necessary action to the:-
i. The Accountant General (Punjab), Lahore (Sanction for Grant
No.PC22036-Development).s
ii. The District Accounts Officer, Rawalpindi.

Section Officer (P&D)


Finance Department
NO. & DATE EVEN
A copy is forwarded for information and necessary action to the:-
i. The Secretary, Government of the Punjab, HUD & PHED
Department, Lahore.
ii. The Director General, ABAD, Murree Road, Rawalpindi.
iii. The Executive Engineer Public Health Engineering Department,
Rawalpindi.
iv. The Budget Officer (I), (III) & (V), Government of the Punjab,
Finance Department, Lahore with reference to this letter No.BV-
21(86-18)2009-10, dated 01.07.2009.
v. The Section Officer (P&D) Government of the Punjab, Finance
Department, Lahore.

(Ch. Iftikhar Ahmad)


Admin Officer (RP)