Activities Unit

Excavation by hand 6.00 MH / cu.m. 0.7500 day / cu.m. 1.3333 cu.m. / day
Excavation by machine 0.50 MH / cu.m. 0.0625 day / cu.m. 16.0000 cu.m. / day
Backfilling by hand 5.00 MH / cu.m. 0.6250 day / cu.m. 1.6000 cu.m. / day
Backfilling by machine 2.00 MH / cu.m. 0.2500 day / cu.m. 4.0000 cu.m. / day
Formwork
Fabrication 2.00 MH / sq.m. 0.2500 day / sq.m. 4.0000 sq.m. / day
Installation 1.00 MH / sq.m. 0.1250 day / sq.m. 8.0000 sq.m. / day 2.6666 sq. / day
Rebars
Fabrication 70.00 MH / M.T. 8.7500 day / M.T. 0.1143 M.T. / day 114.2857 kg / day
Installation 80.00 MH / M.T. 10.0000 day / M.T. 0.1000 M.T. / day 100 kg / day
Concreting 9.00 MH / cu.m. 1.1250 day / cu.m. 0.8889 cu.m. / day
Roofing 9.00 MH / sq.m. 1.1250 day / sq.m. 0.8889 sq.m. / day
Siding 12.00 MH / sq.m. 1.5000 day / sq.m. 0.6667 sq.m. / day
Ordinary Doors 2.00 MH / sq.m. 0.2500 day / sq.m. 4.0000 sq.m. / day
Sliding Doors 8.00 MH / sq.m. 1.0000 day / sq.m. 1.0000 sq.m. / day
Rollup Doors 73.00 MH / sq.m. 9.1250 day / sq.m. 0.1096 sq.m. / day
Plain Cement Finish 1.50 MH / sq.m. 0.1875 day / sq.m. 5.3333 sq.m. / day
Colored Cement Finish 1.70 MH / sq.m. 0.2125 day / sq.m. 4.7059 sq.m. / day
Peeble Washout Finish 3.00 MH / sq.m. 0.3750 day / sq.m. 2.6667 sq.m. / day
Marble Finish 4.00 MH / sq.m. 0.5000 day / sq.m. 2.0000 sq.m. / day
1/4" 24K Plywood Ceiling 18.00 MH / sq.m. 2.2500 day / sq.m. 0.4444 sq.m. / day
Acoustic Tile Ceiling 27.00 MH / sq.m. 3.3750 day / sq.m. 0.2963 sq.m. / day
Painting on Wall 1.50 MH / sq.m. 0.1875 day / sq.m. 5.3333 sq.m. / day
Painting on Ceiling 2.00 MH / sq.m. 0.2500 day / sq.m. 4.0000 sq.m. / day
Paint Removal 2.00 MH / sq.m. 0.2500 day / sq.m. 4.0000 sq.m. / day
Bricks Installation 6.50 MH / sq.m. 0.8125 day / sq.m. 1.2308 sq.m. / day