Contribution to Local Authority ( Majlis Perbandaran Klang )

1. Planning Department

Element Amount Total Amount


Application fees RM50.00 RM50.00
Fee application for RM500 x (1800m/100) RM9,000.00
planning permission
Billboard RM200.00 RM200.00

2. Building Department
Application of Building Plan
The distribution park consist of 2 toilet which is located on the ground floor and first floor
of the office building. The application of building plan for drainage is calculated based on
gross floor area according to the ground floor area and first floor area. As for the
hoarding board, the estimated length is based on the perimeter of the site which is 410
meter.
Element Amount Total Amount
Sanitary Appliances
WC RM5.00 x 2 RM10.00

Sink RM5.00 x 2 RM10.00


Drainage
Ground floor RM2.59 x 1400m RM3,626.00

First floor RM2.59 x 400m x 10% RM3,988.60


Hoarding Board RM3.00 x 410m x 6 months RM7,380.00
3. Engineering Department
Street lights
The payment for the distribution cost of installation of street lights that have been made
and prepared by the Klang Local Authority should be referred. For industrial areas, the
street light should be of LED type with the power of 150 watt (HPSV). The distance from
one lamppost to another should be within 30 to 40 meter. The perimeter of the proposed
site is 410 m and since the areas have existing lamppost nearby, the suitable distance
between lampposts within proposed site would be 35m. This makes the number of
lamppost that should be positioned on site is estimated as 12 in number.
Element Amount Total Amount
Street lights RM3,000.00 x 12 RM36,000.00

4. Landscape Department
Landscape
For landscape plan approval, the distribution park to be constructed at Kampung
Nelayan Teluk Gong on lot PT 11883 is categorized under Category A which involves an
application approval of less than 10 acres of land.

Element Amount Total Amount


Landscape plan approval RM200.00 RM200

5. Department of Services Management


Security
The Security fees will cover for cleanliness on site, safety and also the equipment on
site from trespassers.

Element Amount Total Amount


Cleanliness on site RM100.00
Safety on site RM100.00
RM300.00
Site Equipment RM100.00

6. Licensing Department
Temporary advertisement permit
Since the distribution park is constructed to be sold, it will required the building to be
advertised before construction works occur until it is completed. Since the demand for a
distribution park and warehouse are high in Klang areas, the time range for the building
to be sold is within 18 months.

Element Amount Total Amount


License : Large Banners > 8m RM60.00 x 18 months x 1 unit RM1,080.00

Summary of contribution to Local Authority


NO Element Amount
.
1. Planning Department RM 9,250.00
2. Building Department RM 15,014.00
3. Engineering Department RM 36,000.00
4. Landscape Department RM 200.00
5. Department of Services Management RM 300.00
6. Licensing Department RM 1,080.00
TOTAL RM 61,844.00
Soil Investigation ( SI )

In construction industry, Soil Investigation is the most crucial thing that should be
conducted in construction projects before any further works being carried out. The
purpose is to collect information regarding the physical properties of soil and rock
underneath the ground on site in order to determine the suitable design of foundation for
the proposed structure and also for earthworks process. Besides, soil investigation
method is also appropriate to make good any distress on structures and earthwork
caused by subsurface conditions.

Subsurface exploration is required to collect information regarding the conditions


of soil below the ground. In this process, there are a few test that should be conducted
to obtain samples and obtaining the physical properties of soil and rocks which are, test
pits, boring and in-situ tests.

Test pits is conducted to obtain soil sample collection and also to observe soil
condition by excavating the soil up to 4.5m deep manually either by using hand shovel
or machine. Usually, this technique is applied for low rise developments where deep
foundations are not involved.

As for deep soil boring method, the most commonly used technique is Rotary
Wash Boring where the drilling rig can bore up to 100m into the soil depth depending on
the site conditions. There are many alternatives available to collect Disturbed and
Undisturbed soil samples such as Split Spoon (SPT Sampler), Piston Sampler, Thin wall
tube, Mazier, etc. Once the rock layer is reached, Coring method is used to core
through the layer and collect rock samples.

During soil testing, in-situ test which were commonly carried out includes
Standard Penetration Test (SPT), Dynamic Cone Penetration (DCP) and Cone
Penetration Test (CPT).

As for the site on lot PT 11883 in Kampung Nelayan Teluk Gong where the
proposed development is a Distribution Park, the soil investigation will include all the
three methods which are trial pits, boring and in-situ test. To obtain a satisfying result,
the proposed number of soil investigation for the 2.335 acres of land are 6 trial pits, 2
bore holes and 2 in-situ test.

Elements Amount Total


1.0 Trial Pit
1.1. Mobilization of personnel and
equipment to site and demolish upon
completion for distance up to 50Km. RM517.00
1.2. Carry out trial pit excavation and
backfilling of pit size 2m x 2m x 2m
inclusive of small disturbed sample RM259.00
1.3. Mapping ad logging of pit faces. RM104.00
1.4. Provision of shoring and dewatering. RM1,000.00

1.5. Obtain bulk sample not exceeding


50kg. RM65.00
1.6. Obtain 300mm x 300mm block smple. RM124.00
Total cost for Trial pit RM2069 x 6 RM 12,414.00
2.0 Boring in soil test
.1 Carry out boring in soil weather cased
or uncased using Rotary Wash Boring
(NW size) depth from existing ground
level not exceeding 10m but not
exceeding 20m. RM34.00
.1 Drilling in rock by carry out diamond
core drilling of 52mm diameter into
rock including storing of core samples
in standard boxes :
.1 Drilling in soft rock from existing
ground level exceeding 10m but not
exceeding 20m.
RM150.00
.1 Reaming through rock when
encountering cavities/boulders (NW
Casing) RM98.00
Total cost for bore holes RM282.00 x 2 RM564.00
3.0 In-situ Test (SPT)
.1 Carry out Standard Penetration Test RM38.00
including provision of disturbed
samples depth from existing ground
level exceeding 10m but not
exceeding 20m.
.1 Carry out Acker Vane Shear Test RM45.00
depth from existing ground level
exceeding 10m but not exceeding
20m.
Total cost of In-situ Test (SPT) RM83.00 x 2 RM166.00
Total Soil Investigation Cost RM 13,144.00