Sie sind auf Seite 1von 14

Applied Energy 87 (2010) 21282141

Contents lists available at ScienceDirect

Applied Energy
journal homepage: www.elsevier.com/locate/apenergy

Cost-effective CO2 emission reduction through heat, power and biofuel


production from woody biomass: A spatially explicit comparison
of conversion technologies
Johannes Schmidt a,*, Sylvain Leduc b, Erik Dotzauer c, Georg Kindermann b, Erwin Schmid d
a
Doctoral School Sustainable Development, University of Natural Resources and Applied Life Sciences, Peter Jordan Strae 82, A-1190 Vienna, Austria
b
International Institute for Applied Systems Analysis, Schlossplatz 1, A-2361 Laxenburg, Austria
c
Mlardalen University, P.O. Box 883, SE-72123 Vsters, Sweden
d
Institute for Sustainable Economic Development, University of Natural Resources and Applied Life Sciences, Feistmantelstrae 4, A-1180 Vienna, Austria

a r t i c l e i n f o a b s t r a c t

Article history: Bioenergy is regarded as cost-effective option to reduce CO2 emissions from fossil fuel combustion.
Received 4 August 2009 Among newly developed biomass conversion technologies are biomass integrated gas combined cycle
Received in revised form 2 November 2009 plants (BIGCC) as well as ethanol and methanol production based on woody biomass feedstock. Further-
Accepted 4 November 2009
more, bioenergy systems with carbon capture and storage (BECS) may allow negative CO2 emissions in
Available online 2 December 2009
the future. It is still not clear which woody biomass conversion technology reduces fossil CO2 emissions
at least costs. This article presents a spatial explicit optimization model that assesses new biomass con-
Keywords:
version technologies for fuel, heat and power production and compares them with woody pellets for heat
Bioenergy
CO2 mitigation
production in Austria. The spatial distributions of biomass supply and energy demand have signicant
Pellets impact on the total supply costs of alternative bioenergy systems and are therefore included in the mod-
Biofuels eling process. Many model parameters that describe new bioenergy technologies are uncertain, because
Combined heat and power some of the technologies are not commercially developed yet. Monte-Carlo simulations are used to ana-
Bioenergy system with carbon capture and lyze model parameter uncertainty. Model results show that heat production with pellets is to be pre-
storage ferred over BIGCC at low carbon prices while BECS is cost-effective to reduce CO2 emissions at higher
Mixed integer program carbon prices. Fuel production methanol as well as ethanol reduces less CO2 emissions and is there-
Monte-Carlo simulation
fore less cost-effective in reducing CO2 emissions.
2009 Elsevier Ltd. All rights reserved.

1. Introduction place fossil fuels in several sectors. CO2 reduction potentials are
therefore varying between conversion technologies. It is still not
The Austrian government has committed to reduce greenhouse obvious which conversion chain saves most CO2 emissions. In addi-
gas (GHG) emissions by 13% below the level of 1990 in the period tion, the systems costs of a conversion chain inuence the compet-
20082012 [1]. The private heating sector, the transport sector and itiveness with respect to fossil commodities.
the power and heat production sector contributed to 56% of total This article assesses the use of forest biomass to reduce CO2
anthropogenic GHG emissions in Austria in 2006 [2]. In 2006, Aus- emissions in three sectors including heat, power and transporta-
tria was far away from reaching emission reduction targets. Bioen- tion fuels. In each sector, at least one conversion technology is cho-
ergy is seen as an economic viable and politically favorable option sen for the assessment. The selection of technologies for the
to reduce CO2 emissions in Austria. Particularly wood is an impor- modeling process depends on their techno-economic performance
tant feedstock for biomass based energy production. Over the last 5 in comparison to other bioenergy technologies in the sector. In the
years, substantial subsidies have stimulated the installation of heating sector, pellets heating systems are chosen. Burning pellets
additional heat and power plants red by biomass in Austria in single stoves to heat dwellings is highly efcient [6]. Pellets are
[3,4]. Further increases are possible because the annual growth also convenient to handle for the user due to their high energy den-
in wood stocks is currently not fully exploited [5]. There are several sity and low storage space requirements in comparison to other
technologies available to produce bioenergy from woody biomass wood fuels [7]. We model pellets production in a bioenergy com-
(Fig. 1). The commodities produced by plants of different type re- bine that integrates pellets production with combined heat and
power production [8] and burning of the pellets in single dwelling
* Corresponding author. Tel.: +43 6502151579; fax: +43 1476543692. heaters. A biomass integrated combined cycle (BIGCC) production
E-mail address: johannes.schmidt@boku.ac.at (J. Schmidt). technology with optional combination with carbon capture and

0306-2619/$ - see front matter 2009 Elsevier Ltd. All rights reserved.
doi:10.1016/j.apenergy.2009.11.007
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2129

Nomenclature

Variables ctransb
i;j;l costs of biomass transportation from i to j (
1
bi;j;l biomass transported to plants (MW hbiomass) MW hbiomass )
esav total emission reductions (tCO2) ctransc
j;k;c costs of transporting commodity from j to k ( MW h1)
qbio
j heat production in the plant (MW h) cplantl
ref
reference plant investment costs ()
qdh
j;h;ps;t heat transportation from plant to district heating net- dk;d energy demand (MW h y1)
work (MW h) e error term ()
qlocal
h;t local heat production (MW h) eccs
1
carbon capture rate in plant (tCO2 MW hbiomass )
l
qpeak
h;t
peak heat production (MW h) efossil
c CO2 emission factor of fossil fuels (tCO2 MW h1)
totem total CO2 emissions (tCO2) elocal CO2 emission factor of local heat production (tCO2
h
udnet
h;ns binary variable for investment in district heating net- MW h1)
work () epeak
h;t
CO2 emission factor of peak heat production (tCO2
upipe
j;h;ps
binary variable for investment in transportation pipe- MW h1)
line () etrans CO2 emission factor of biomass transportation from i to j
i;j
uplant
j;l
binary variable for plant investment () 1
(tCO2 MW hbiomass )
zbio
j;c amount of energy commodity produced in a plant etrans CO2 emission factor of commodity transportation (tCO2
j;k;c
(MW h) MW h1)
zbio
j;k;c amount of energy commodity transported to consumers lom lower bound of plausible range of parameters (depend-
(MW h) ing on parameter)
zfossil
k;c
amount of fossil fuel used to satisfy demand (MW h) n number of runs in Monte-Carlo simulation ()
OM operation and management costs (% of investment
Parameters costs)
b0 ; bm regression coefcients () parm input parameter vector (depending on parameter)
gbio
c;d efciency of converting a bioenergy commodity to use- qDh;t heat demand in settlement (MW h season1)
ful energy () qDh;ns;t heat demand in district heating network (MW h sea-
gcon v conversion efciency in bioenergy plants ()
j;l;c son1)
gdh
h;t efciency of distributing heat in district heating net- qpipe
ps;t capacity of heat transportation pipeline (MW h sea-
work () son1)
gfossil
c;d
efciency of converting fossil fuel to useful energy () s annuity factor ()
gheat heat efciency in bioenergy plants () sf scaling factor ()
j;l
sizej;l plant size (MWbiomass)
glocal local heat conversion efciency ()
h;t
sizeref
l reference plant size (MWbiomass)
gtrans
j;h;ps;t transportation efciency of heat pipeline () Dtt relative length of a season ()
sup
b biomass supply capacity (MW h y1) upm upper bound of plausible range of parameters (depend-
i

b production capacity of plant (MW h y1) ing on parameter)
j;l

cccs
costs of carbon capture and storage ( tCO1
2 ) Subscripts
cdnet annualized costs of investment in district heating net-
h;ns c energy commodity ()
work ( y1)
d energy demand for useful energy ()
cem CO2 price ( tCO12 ) h settlement ()
cfossil
c price of fossil fuel ( MW h1)
i biomass supply site ()
cin v investment cost necessary at consumer ( MW h1)
c j plant location ()
clocal
t costs of local heat production ( MW h1) k demand region ()
csup
1
i
costs of biomass supply ( MW hbiomass ) l technology ()
cpipe
j;h;ps
annualized costs of investment in transportation pipe- m input parameter ()
line ( y1) ns district heating network size ()
cpeak
t costs of peak heat production ( MW h1) ps pipeline size ()
cplant annualized costs of plant investment ( y1) t season ()
j;l
cprod
1
j;l
variable costs of bioenergy production ( MW hbiomass )

storage (CCS) is chosen for the power production sector. Such [15]. However, from those conversion technologies, the methanol
plants produce power more efciently than steam engines [9,10]. process is identied as the least cost option for CO2 reductions
Carbon capture and storage is an emerging low carbon technology [16,17]. We selected therefore ethanol production through hydro-
and one of the view options that allows achieving negative CO2 lysis and methanol production through gasication as CO2 reduc-
emissions [11] which may be necessary to manage climate risk tion options in the transportation sector. Biomass transportation
appropriately [12]. It is therefore also included in our analysis. For- costs as well as energy distribution costs have signicant impact
est wood is currently not used as feedstock for fuel production in on the nal cost of a bioenergy supply chain [18,19]. Particularly,
the transportation sector. However, so called second generation district heating (DH) may induce high infrastructure costs depend-
technology allows converting woody biomass into fuels. Biofuels ing on the spatial densities of heat demand. The spatial variability
as ethanol, Fischer Tropsch (FT) diesel, DME or methanol can be of energy demand is high in Austria [20], which signicantly im-
produced by such technologies [13]. Hydrolysis and subsequent pacts distribution costs. The different technologies and plants con-
fermentation is identied to be the best available ethanol process sidered in the analysis produce a wide set of commodities which
technology according to the techno-economic efciency [14]. Gas- have to be transported by various means (e.g. pipelines, truck
ication of biomass allows producing FT diesel, DME and methanol transportation) to consumers. The relative competitiveness of a
2130 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Forest wood

Pelletising Gasification Hydrolisis Pyrolisis

Synthesis Fermentation

FT Diesel DME Methanol Ethanol Biodiesel

Combustion Biomass integrated Combustion Combustion


furnace combined cycle gas turbine IC engine

Automotive
Heat Power power

Fig. 1. Energy conversion routes for forest wood [15,63].

conversion technology also depends on the spatial distribution of nological input parameters are highly uncertain, because some of
consumers and costs arising from distribution of nal products. the technologies are currently not available on the market. Addi-
Consequently, spatially explicit modeling is necessary in assessing tionally, prices of fossils fuels are highly volatile. They, however,
the competiveness and CO2 reduction potentials of alternative con- determine mainly the competitiveness of the bioenergy technolo-
version technologies. gies. Monte-Carlo simulations are used to account for model
There are several studies that have assessed the techno-eco- parameter uncertainties. An extended sensitivity analysis allows
nomic performance of emerging bioenergy technologies based on identifying the model parameters which have the highest impact
woody biomass [14,15,17,2031]. Table 1 lists which technologies on results and contribute most to uncertainty.
were assessed by which methodologies and if spatial explicit mod- The article is structured as follows: system boundaries, technol-
eling has been used in the studies. Only a few models consider spa- ogies and other model parameters are briey discussed in Sections
tial factors in their analysis. Most of them are limited to assessing a 2.12.6. The optimization model and the use of Monte-Carlo simu-
single technology. For instance, [30] has applied a GIS analysis to lations to deal with model parameter uncertainty are presented in
compare BIGCC and pellets production. A large set of technologies Sections 2.72.9. Section 3 reports on results including optimal
has been assessed by the two models presented in [28]. Both are locations, scenario and sensitivity outcomes. Section 4 closes the
global energy models and do not consider specic details of the article with a discussion of results and conclusions. The appendix
technologies as well as spatial factors therefore. Bioenergy systems contains details on the model, determination of optimal plant
with carbon capture and storage (BECS) are not included in their sizes, sensitivity analysis and model validation.
analysis. A detailed technical study on new bioenergy technologies
can be found in [17]. A wide range of technologies, including DME,
methanol and ethanol production as well as pellets production in 2. Methods and materials
stand alone plants and in energy combines and BIGCC are assessed
within that study. Demand restrictions are only discussed but for- 2.1. System boundaries, assumptions and limitations
mally not considered in modeling CO2 emission reductions and
costs of technologies. Spatial factors of any kind are not explicitly We apply a static, spatially explicit MIP model to assess the rel-
included in the assessment and BECS is not considered. However, ative competitiveness of bioenergy conversion technologies in
spatial factors are fundamental in analyzing and comparing differ- Austria. The model includes the full supply chain of bioenergy pro-
ent conversion technologies. We apply a spatially explicit mixed duction from wood harvests to nal energy distribution. Bioenergy
integer programming (MIP) model to assess different conversion conversion technologies in the transportation, heating and electric-
technologies by optimizing the supply chains as well as the loca- ity sectors are modeled explicitly. Forest wood serves as feedstock.
tion of bioenergy facilities at least cost. It is therefore possible to Biomass supply and energy demand are limited to domestic Aus-
assess the relative competitiveness of alternative technologies tria only, therefore, imports and exports of biomass and bioenergy
and to seek least cost plant locations in Austria. Many of the tech- products are not accounted for. It is assumed that newly built bio-
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2131

Table 1
List of publications on new bioenergy technologies for woody biomass.

Paper Technologies considered Methodology Spatially


explicit
[20] BIGCC MIP Yes
[21,22] Methanol MIP Yes
[23] Methanol Calculation of production potentials and CO2 emission reductions (no No
economic assessment)
[31] Ethanol MIP Yes
[24,25,26] CCS with pulp and paper mills Calculation of total costs and emission reductions No
[27] CCS with ethanol Calculation of total costs and emission reductions No
[15] Co-combustion, BIGCC, fuel wood, Fischer Tropsch biodiesel, ethanol System perburtation analysis (no economic analysis) No
[28] BIGCC, methanol, ethanol Linear program No
[29] Ethanol, bio-oil, BIGCC Comparative cost calculations No
[30] BIGCC, pellets GIS Yes
[14] Ethanol through hydrolysis, ethanol through gasication Comparative cost calculations No
[17] Ethanol, methanol, DME, pellets, BIGCC Comparative cost and emission reduction calculations No

energy plants replace fossil fuels in each of the sectors. The CO2 either decrease the utility of CCS or even pose a risk to life. In
emission baseline for each sector consists of the technologies and the case of CO2 storage in deep oceans, marine eco-systems may
fuels currently in use in Austria. The model does not consider ef- be affected negatively [36]. This article assesses BECS in combina-
fects of wood harvests on the forest CO2 cycle but assumes that tion with BIGCC.
wood production is organized CO2 neutral, i.e. forests sequestrate
amounts of the CO2 released by burning of previously harvested 2.2.3. Transportation fuel production
biomass. However, CO2 emissions from biomass transportation Second generation transportation fuel production from woody
are considered in the model. A stochastic approach is used to mod- biomass increases per hectare yields of fuel in comparison to rst
el varying prices and demand levels. The next sections report de- generation fuels which are mainly produced from agricultural crop
tails on bioenergy technologies, model input parameters, CO2 grains [37]. However, second generations biofuels are not yet fully
emission baseline assumptions, the optimization model and how available on a commercial level. Two conversion technologies are
we assess uncertainty. The model input parameters including tech- considered in this article: (i) enzymatic hydrolysis of biomass with
nical plant characteristics are reported in Table 2. Details on the subsequent fermentation to ethanol and (ii) gasication of biomass
validation of the model can be found in Appendix A. with subsequent reforming to methanol.

2.2. Technologies 2.2.3.1. Ethanol from ligno cellulose. The fuel characteristics of etha-
nol are very similar to fossil gasoline. Up to 10% of ethanol can be
2.2.1. Biofuel integrated gasication combined cycle (BIGCC) blended with fossil gasoline without the need to modify car en-
In biomass combined heat and power (CHP) plants, a steam en- gines [37]. In the production process, biomass is rst pre-treated
gine is operated with evaporated water that is produced by burn- for the hydrolysis of (hemi)cellulose. The sugars from hydrolysis
ing biomass. The technology is well known and plants of varying are fermented to ethanol. Lignin is a residual of the process and
sizes are installed in Austria [4]. However, the power to heat ratio is burnt in a CHP plant to produce heat and power for the ethanol
is low: the total conversion efciency for power reaches about 30% production process. Depending on the quantity of lignin contained
[10]. Gasication of biomass in an integrated combined cycle plant in the biomass, surplus production of power is possible. A detailed
allows reaching efciencies that are signicantly higher than in description of the process can be found in Piccolo [14] and Hame-
plants with steam engines. The power efciency goes up to 43%. linck [38]. The theoretical conversion efciency for ethanol is lim-
However, no commercial plants have been installed yet [9]. Instal- ited to about 52%, current pre-commercial installations are
lation costs are high and plants have to be sized bigger than steam however far from reaching these fuel yields. Costs for raw materi-
engines to be economically competitive [9]. In this article, a pres- als and plant investments are high and depend on the processing
surized BIGCC plant is assessed as it is expected to have the best technology [14,38].
power to heat ratio of all gasication technologies [9,10].
2.2.3.2. Methanol through gasication. Methanol can be used as
2.2.2. Bioenergy system with carbon capture and storage (BECS) transportation fuel by blending it with gasoline. Mixtures of up
CCS allows decreasing the release rate of CO2 of fossil fuelled to 85% methanol and 15% gasoline are possible, requiring minor
power plants. CO2 is captured either before or after combustion modications of car engines [22]. In the production process, the
and then transported to permanent storages. BECS combines this biomass is rst gasied. Subsequently, the gas is cleaned and high-
technology with biomass red CHP plants. This way, CO2 is re- er hydrocarbons are created through gas reformation. Shift reac-
moved from the atmosphere: CO2 is sequestrated in tree growth tions and gas separation then produce the methanol. Production
and released in the energy production process where it is captured in very large facilities is necessary to make the production process
and permanently stored. A transfer of atmospheric CO2 to the per- competitive [21]. Theoretical conversion efciencies reach up to
manent storage is therefore possible [11,32,33]. 70%, which are, however, not reached in current pre-commercial
The captured CO2 is transported by pipelines or ships to the - installations [39]. District heating networks can be fed with sur-
nal deposits which may be oil, gas or coal elds, deep saline aqui- plus heat from the production process [21].
fers or oceans. Costs for CCS arise mainly from transportation and
compression of the CO2. Gas and oil elds are low cost storages be- 2.2.4. Pellets
cause the injected CO2 can be used to increase the total depletion Wood pellets are made of dry wood stock and are small, cylin-
of the elds. Risks are associated with all possible deposits: CO2 drical objects [7]. They have an average higher heating value (HHV)
may leak slowly or suddenly from the deposits [34,35] and thus of 18.5 GJ t1 [40]. Transport as well as storage of pellets is cheaper
2132 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Table 2
List and ranges of model parameters as well as method of data generation.

Nmb Parameter name Variable name Unit Minimum lom Maximum upm Methoda Sources

Prices
1 Power cfossil
c
MW h1 29.09 73.80 B [56]
2 Heating oil cfossil
c
MW h1 22.18 66.74 B [55]
3 Gasoline cfossil
c
MW h1 27.34 44.70 B [55]
CO2 price cfossil
c tCO1 Scenarios: 0, 25, 50, 75, 100 tCO1
2 2

Investment costs for plants (100 MW size)


4 BIGCC cplant Million 62.61 70.22 ND [9,10,33]
j;l
5 BECSb cplant Million 4.48 11.15 ND [32,33,64]
j;l
6 Ethanol cplant Million 83.75 107.56 ND [14,38]
j;l
7 Methanol cplant Million 82.73 111.93 ND [39]
j;l
8 Pelletsc cplant Million 9.22 10.77 ND [41,65]
j;l
Variable production costsd
9 BIGCC cprod
1
MW hbiomass 1.85 6.43 ND [9,10,33]
j;l
10 BECSe cprod MW
1
hbiomass 1.85 6.43 ND [9,10,33]
j;l
11 Ethanol cprod MW
1
hbiomass 6.16 10.00 ND [14,38]
j;l
12 Methanol cprod MW
1
hbiomass 1.77 2.40 ND [39]
j;l
13 Pellets cprod MW
1
hbiomass 0.94 2.60 ND [41,65]
j;l

Efciency
Commodity Plant type gcon v
j;l;c
14 Power BIGCC gcon v 0.34 0.43 ND [9,10,33]
j;l;c
conv
15 BECS gj;l;c 0.25 0.33 ND [32,33,64]
16 Ethanol gcon v 0.01 0.04 ND [14,38]
j;l;c
17 Pellets gcon v 0.04 0.06 ND [41,65]
j;l;c
18 Heat BIGCC gcon v 0.43 0.47 ND [9,10,33]
j;l;c
19 BECS gcon v 0.33 0.55 ND [32,33,64]
j;l;c
20 Methanol gcon v 0.05 0.10 ND [21,51]
j;l;c
21 Pellets gcon v 0.02 0.02 ND [41,65]
j;l;c
22 Ethanol Ethanol gcon v 0.35 0.39 ND [14,38]
j;l;c
23 Methanol Methanol gcon v 0.54 0.60 ND [39]
j;l;c
24 Pellets Pellets 0.79 0.84 ND [41,65]
Other parameters
25 Costs carbon capture and storage cccs tCO1 13.06 41.62 ND [32,33,64]
2
26 Connection rate district heating Factor 0.61 0.74 ND Estimate
27 Transportation costs ctransb
i;j;l
1
MW hbiomass km1 0.03 0.04 ND [21,66]
28 Local heating costs clocal
t MW hheat
1 72.00 88.00 ND [20,67]
29 Emission savings BECS eccs
l
1
tMW hbiomass 0.19 0.40 ND [32,33,64]
30 Biomass supply costs csup
i
MW h1 20.08 26.79 B [47]
31 Amount of biomass supply Factor 0.95 1.05 ND Estimate
32 DH infrastructure costs cdnet
h;ns
Factor 0.50 1.50 ND [68,69]
33 Efciency of distributing heat in DH network gdh Factor 0.94 0.99 ND Estimate
h;t
34 CO2 emissions fossil power efc;ff tCO2 MW hpower
1 0.54 0.58 ND [70]

a
(B)oostrapping, (N)ormal (D)istribution.
b
Additional to standard CHP costs.
c
Without CHP unit.
d
Not including biomass costs.
e
Without carbon capture and storage costs.

compared to sawdust or traditional fuel wood because of the better separate CHP unit. A part of the feedstock is burnt in the CHP. Sur-
HHV. Pellets can be manipulated with compressed air which facil- plus power (heat) can be sent to the power grid (a district heating
itates the handling of pellets in comparison to other wood based network) [8]. Such a combined power, heat and pellets production
energy products [7]. Pellets can be used either in power or heating is assessed in the model, assuming that a BIGCC is used for power
plants or in small local boilers to directly heat buildings. Boilers and heat production.
with condensing heating technology allow increasing the energy
efciency signicantly above that of traditional fuel wood fur-
naces. In this study, the use of pellets in heating boilers for single 2.3. Plant investment costs
dwellings is assessed.
The production process of pellets starts with the drying of the As the optimization model considers one year of operation,
wood which requires large amounts of heat. The wood is ground plant investment costs are annualized. Investment costs
and then pressed through a die resulting in the nal pellets. This depend on the plant size. A standard scaling function with a
process consumes signicant amounts of electricity [41]. The elec- scaling factor sf of 0.7 [9,39,42] is used to model economies of scale.
tricity as well as the heat necessary for drying can be produced in a The annual plant costs cplant
j;l for a plant of technology l at location j
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2133

include annualized investment costs and operation and manage- Table 3


1
ment costs. The costs are given by CO2 emission reductions in tCO2 MW hbiomass relative to heating oil (pellets), to the
Austrian fossil fuel mix in power production (BIGCC and BECS) and fossil gasoline
!sf (ethanol and methanol). Lower (upper) bounds assume the lower (upper) bound of
sizej;l ref
cplant
j;l s OM ref
cplant l ; 1 conversion efciencies given in Table 1 and 0% (100%) usage rate of surplus heat for
sizel district heating. Sources: Table 1, [2], own calculations.

Pellets BIGCC BECS Ethanol Methanol


where s is the annuity factor assuming a lifetime of 25 years and an
interest rate of 10%. Parameter OM denotes annual operating and Lower bound 0.26 0.23 0.33 0.10 0.14
Upper bound 0.28 0.37 0.76 0.12 0.19
management costs in percent of investment costs. In the scaling
function, parameter sizej,l is used to model the size of the plant.
The reference size for a plant of type l at location j is denoted by
ref ref CO2 emission factors of fuels with the amount of the respective fuel
sizel . Parameter cplant l are reference costs of a plant with tech-
nology l. There is an upper limit on the size of plants because the that is used in the settlement.
equipment cannot be scaled innitely. Maximum plant sizes are Estimations of CO2 emission reductions per TWhbiomass for the
250 MW for all plant types [9,38]. All economical and technological different technologies regarding the chosen reference technolo-
parameters which are listed in Table 2 are chosen to reect ex- gies are listed in Table 3. Those values are given for illustration
pected technological developments within the next 10 years. only and show theoretical lower and upper bounds of CO2 emission
reductions. The gures in row Upper bound represent conversion
2.4. Forest wood supply efciencies (and rates of carbon storage for BECS) that are equal to
the upper bound of the parameters in Table 2. The use of surplus
In this analysis domestic forest wood is regarded as feedstock to heat for district heating is assumed to reach 100%. The gures in
bioenergy production. Forests cover about 47% of land in Austria. row Lower bound represent the lowest possible conversion ef-
On average, wood harvests are currently lower than the amount ciency assuming a surplus heat utilization of 0%. The table shows
that can be sustainably harvested [5]. If forests are managed at that ethanol production reduces fewer CO2 emissions than any
the maximum sustainable yield, additional fuel wood is available other technology, regardless if upper or lower bounds are
to supply new bioenergy projects. The spatial distribution of for- considered.
estry yields is estimated with increment curves from Assmans
yield table [43], assuming sustainable forest management, and a 2.6. Energy demand
net primary production (NPP) map from Running [44]. It is cali-
brated with the observations from the national forest inventory Heating demand is estimated spatially explicit with a bottom
of Austria [5]. The forest land cover is taken from the Corine Land up model that combines average consumption values with private
Cover dataset [45]. An equation system describes the forest incre- dwelling areas and with the number of employees for commercial
ment and mortality per hectare and year depending on yield level, buildings and industrial applications. Heating demand is differen-
age, and stand density. An NPP map was used to estimate the yield tiated by fuels. The bottom up model is validated with national
level. The observed increment data from the Austrian national consumption values for heating fuels. Heating demand is esti-
inventory was used to calibrate the transformation from NPP to mated in cells of 1 km2 size for whole Austria. The costs of the dis-
yield level. The diameter of the harvested wood, which is used in trict heating infrastructure are determined by applying an
the CHP plants, is below 15 cm. Wood that is additionally available exponential cost function that depends on heat demand density.
for new bioenergy plants is determined by reducing the total har- Cells where the costs for district heating infrastructure of con-
vest potential by current wood harvests as stated in ofcial statis- sumed heat are higher than the costs of the competing fossil heat-
tics [46]. Wood prices have been determined from the energy ing technology are not included in the optimization model.
wood index [47] that reports prices of fuel wood every quarter of Therefore, the model complexity can be reduced without loosing
a year. accuracy of results, because cells where the district heating infra-
structure alone is more costly than total heat generation costs of
2.5. CO2 emissions competing technologies will not be selected in the optimization
model. The demand for heat in non-district heating areas is deter-
The model tracks CO2 emissions from bioenergy production as mined by dwellings that are currently heated by oil boilers. Pellets
well as CO2 emissions from fossil fuel combustions. CO2 emissions use is restricted to single-dwellings buildings [7]. The detailed
from biomass transportation are also included into the model description of the heating demand model can be found in [20].
while it is assumed that CO2 emissions created from burning bio- Transportation fuel consumption is estimated based on the spatial
mass are offset by tree growth. This assumption is consistent with distribution of the population, which is combined with the average
the current version of the UNFCC reporting guidelines for the Kyoto gasoline consumption per capita in the year 2006 [49].
protocol that assumes that woody biomass use in energy applica-
tions is CO2 emission neutral [48]. The optimal mix of biomass 2.7. The optimization model
technologies depends on technologies and products that are cho-
sen as competitors to bioenergy production. We assume that bio- A MIP model, that builds on previous work published in [20
energy power production competes with the current fossil fuel 22,31,5052] is used to minimize the costs for supplying demand
based power production i.e. with the mix of fossil fuels currently regions (index k) with different forms of energy products (index
used for power production in Austria. This assumption is made be- d) from either biomass plants or fossil fuels. Biomass is transported
cause biomass based power production is able to produce base and from supply regions (index i) to possible plant locations (index j)
peak load power similar to fossil fuels. Ethanol and methanol are where different conversion technologies (index l) may be em-
competing with gasoline as a direct substitute. Pellets replace fossil ployed to produce different commodities (index c). Ethanol, meth-
heating oil in single dwelling buildings because oil boilers are most anol and pellets are transported to the demand regions by truck.
appropriate to be substituted by wood pellets boilers [7]. District Power is directly distributed to the power grid, while heat is deliv-
heating substitutes fuels currently used in the settlements. The ered to the settlements (index h) using pipelines of different sizes
CO2 emission factor for a settlement is determined by weighting (index ps). District heating networks of different sizes (index ns)
2134 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Power Demand
BIGCC Fossil Power

District Heating
BECS Fossil Fuel Mix
Demand
(Gas, Oil)

Forest Ethanol
Wood Plant Transportation
Fuel Demand Fossil Gasoline
Methanol
Plant

Pellets Single Dwellings Heating Oil


Plant Heating Demand

Fig. 2. Diagram of the mixed integer programming model.

have to be built in the settlements to allow heat distribution. Bio- 4. Costs for fossil fuels (parameter cfossil c ) times the amount of fossil
energy competes with fossil fuels. Fig. 2 shows the overall scheme fuels used in a demand region (variable zfossil k;c ).
of the model. It is static and models 1 year of operation. All invest- 5. Annualized costs of building a pipeline from the plant to the
ment costs are annualized assuming an interest rate of 10% and settlement (parameter cpipe j;h;ps ) times the binary variable for pipe-
25 years of economical lifetime. Heating seasons (index t) are used line selection (upipe j;h;ps ).
to differentiate between seasonal heating demands. 6. Annualized costs for installing a district heating network in the
The total costs in the objective function f(b, z, q, u) are settlement (parameter cdnet h;ns ) times the binary variable for dis-
minimized: trict heating network selection (udnet h;ns ).
X  sup  7. Costs for producing peak heat (parameter cpeak t ) for district heat-
f b; z; q; u ci ctransb cprod eccs
l c
ccs
bi;j;l ing times the amount of peak heat (variable qpeak h;t ) produced.
i;j;l j;l
i;j;l
8. Costs for producing local heat including investment and fuel
X X 
inv costs (parameter clocal
cplant
j;l uplant
j;l ctransc
j;k;c c c zbio
j;k;c t ) times the amount of local heat (variable
j;l j;k;c qlocal
h;t ) produced.
X X X 9. Total CO2 emissions (totem) which consist of: (i) CO2 emissions
cfossil
c zfossil
k;c cpipe pipe
j;h;ps uj;h;ps cdnet dnet
h;ns uh;ns
k;c j;h;ps h;ns
of biomass transportation (CO2 emission factor etrans i;j ), (ii) CO2
X X emissions of commodity transportation (CO2 emission factor
cpeak qpeak
h;t clocal qlocal em
h;t c totem 2 etrans
j;k;c ), (iii) CO2 emissions of fossil energy production (CO2 emis-
t t
h;t h;t
sion factor efossilc ), (iv) CO2 emissions of local heating systems
where (CO2 emission factor elocal h ), (v) CO2 emissions of peak heat pro-
X X X duction (CO2 emission factor epeak h;t ), and (vi) CO2 emission sav-
totem etrans
i;j bi;j;l etrans
j;k;c zj;k;c efossil
c zfossil
k;c ings by BECS in bioenergy production (CO2 emission factor
i;j;l j;k;c k;c
X X X eccs
l ). Total CO2 emissions (totem) are multiplied by the CO2 price
elocal
h qlocal
h;t epeak peak
h;t qh;t  eccs
l bi;j;l 3 (parameter cem).
h;t h;t i;j;l

The objective function in Eq. (2) is minimized subject to the fol-


The different summands in the objective function represent:
lowing constraints. Biomass utilization (variable bi,j,l) in the plants
is restricted by
1. Biomass supply costs (parameter csup i ), biomass transportation
X
costs (parameter ctransb
i;j;l ), bioenergy production costs (parameter sup ;
bi;j;l 6 b 4
i
cprod
j;l ) and carbon capture and storage costs (parameter c
ccs
times j;l
the amount of CO2 emissions captured by unit of biomass eccs l )
where parameter b sup denotes the total amount of biomass available
times the amount of biomass (variable bi,j,l). i
2. Annualized costs of plant investments (parameter cplant ) times in supply region i.
j;l
the binary variable for plant selection (uplant ). The plant size constraints the production by
j;l
3. Costs for transporting energy commodities to demand regions X
 uplant ;
bi;j;l 6 b 5
inv j;l j;l
(parameter ctransc
j;k;c ) plus investment costs (parameter c c ) times i
the amount of commodities (variable zbio j;k;c ). Costs for power
transportation and investment are zero as it is assumed that where parameter b is the production capacity of plant j using tech-
j;l
the power can be sold directly to the power grid. For ethanol, nology l. The commodity production (variable zbio
j;c ) is determined by
the biomass input and conversion efciency (parameter gcon v
methanol and pellets, transportation costs from plants to j;l;c )
demand regions by truck are considered. Investment costs cin v shown in the following equation:
c
are zero for biofuels, because no additional investments are X
gcon v bio
necessary to operate cars with ethanol or methanol. For pellets, j;l;c bi;j;l zj;c : 6
i;l
the investment costs represent the average difference between
a pellets boiler and an oil boiler per unit of useful energy District heat production is modeled with variable qbio
j because it is
produced. distributed differently than the other commodities:
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2135

X
gheat bio
j;l bi;j;l qj ; 7 ity distributions (i.e. normal) are assumed for uncertain input
i;l parameters (index m). Then, n different input parameter sets are
built and the simulation is run n times, thus providing n different
where gheat
j;l is the conversion efciency for heat. Distribution of
results. The results are statistically analyzed to test the inuence
commodities to demand regions k is restricted by
X of model parameters on output (sensitivity) and determine which
zbio bio
j;k;c 6 zj;c ; 8 parameters contribute most to model uncertainty (uncertainty
k analysis).
A literature review provides upper (upm ) and lower (lom ) bounds
where variable zbioj;k;c denotes the amount of a commodity c trans-
for investment and production costs as well as for technological
ported from plant location j to demand region k.
parameters of bioenergy plants, transportation costs, district heat-
Energy demands (parameter dk,d) are satised by different com-
ing infrastructure costs, biomass availability, biomass costs, and
modities from bioenergy production (variable zbio j;k;c ) and by fossil
CO2 emission factors. It is assumed that the parameters are ran-
fuels (variable zfossil
k;c ):
X X domly distributed, following a normal distribution with parame-
gbio bio
c;d zj;k;c gfossil fossil
c;d zk;c dk;d : 9 ters l = (upm + lom)/2 and r = (l  lom)/1.96. Input parameters are
j;c c randomly drawn from the distribution, values lower than lom or
fossil higher than upm are removed. A different method is used to capture
In the equation, parameter gbio
c;d (gc;d ) describes the efciency of
volatile energy prices because these are generally correlated [54].
converting bioenergy commodities (a fossil fuel) to forms of useful
Energy prices are determined by using a database of prices for
energy.
heating oil, gasoline [55], power prices [56] and re wood [47] be-
The part of the model handling the usage of surplus heat for dis-
tween January 2003 and December 2008. A bootstrapping process
trict heating and the district heating infrastructure can be found in
[57] is applied to determine the values of the different parameters
Appendix B.
for the Monte-Carlo simulation. Prices are determined by ran-
The MIP is nally dened as:
domly choosing one of the 24 quarters in the statistical database.
minf b; z; q; u 10 The prices of fossil fuels, biomass and power are set to the value
s:t: of that quarter. Table 2 shows all stochastically modeled parame-
ters and the corresponding range of values. All prices and costs
29; B:1B:5
are given in 2008.
fossil peak
0 6 bi;j;l ; zbio bio bio dh local
j;c ; zj;k;c ; zk;c ; qj ; qh;t ; qj;h;ps;t ; qh;t
pipe plant
udnet
h;ns ; uj;h;ps ; uj;l 2 f0; 1g: 3. Results

3.1. Optimal plant sizes and optimal locations


2.8. A pre-selection of plant size and plant locations

The optimal sizes of BIGCC, methanol and ethanol plants are


As the model size grows exponentially with the number of pos-
found to be 250 MW which is the maximum allowed in the model.
sible plant locations (index j), the model is limited with respect to
The impact of economies of scale is therefore more important to
its spatial resolution. The plant size has also signicant effect on
total production costs than biomass transportation costs. A size
total costs [21]. Therefore, a three-step approach is performed to
of 180 MW is found to be optimal for pellets plants. Regarding
pre-select likely plant locations and plant sizes in Austria:
the optimal plant locations, the model results (Fig. 3) show clearly
that BIGCC plants are clustered around bigger cities while fuel and
(1) A set of likely locations is identied which is suitable for bio-
pellets plants are more evenly distributed over the country. Cities
energy production using results of previous studies [20,21].
like Vienna and Graz are main locations for BIGCC and BECS plants.
The model is solved separately for each technology with
A reason is that heat production of BIGCC is ten times higher than
alternative plant sizes ranging from 50 MWbiomass to
of pellets and fuel plants. Proximity to main heat consumers such
250 MWbiomass, varying plant investment costs according to
as big cities is therefore important for BIGCC and BECS plants. Con-
the scaling function in Section 2.3. As some of the parame-
sequently, biomass needs to be transported over longer distances.
ters are uncertain, the model is run 1000 times with varying
The transportation of fuels and pellets by truck does not inuence
parameter values (see Section 2.9). Then a surface response
the choice of locations much. Therefore, pellets and fuel plants are
function is estimated and the rst derivate of that function
positioned closer to biomass resources.
is taken to determine the optimal plant size (see Appendix
C for details).
(2) The model is again run 1000 times separately for each tech- 3.2. Technological mixes and CO2 emission reductions
nology, using the previously determined plant size. If a loca-
tion has been selected it is used for the subsequent analysis. CO2 emission reductions and technological mixes depend
This reduces the total number of possible locations from 60 mainly on the CO2 price. This section presents least cost technolog-
to around 15, depending on the technology. ical mixes and CO2 emissions for ve different CO2 prices (0, 25, 50,
(3) The pre-selected locations are used in the complete model 75, 100 tCO1 1
2 ). The upper limit of 100 tCO2 is chosen because
with all technologies. the European Emission Trading Scheme introduces a penalty of
that amount for participants that have not bought sufcient num-
ber of allowances on the market. This penalty can therefore be con-
2.9. Sensitivity and uncertainty analysis sidered as upper limit on the CO2 price. Fig. 4 presents the
technological mix under the inuence of alternative CO2 prices. Ta-
We assess technologies which are currently not available on the ble 4 reports the share of biomass utilization of the technologies
market. Uncertainties related to investment and operation costs with condence intervals. Pellets production is the predominant
are therefore high. Additionally, energy prices are also volatile. technology in each scenario while fuel production is not selected
Uncertainties in model parameters are considered by applying in any of the CO2 price scenarios. Fuel conversion technologies
Monte-Carlo simulations, following the approach in [53]. Probabil- are inferior with regard to cost-efcient CO2 emission reductions
2136 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Fig. 3. Optimal locations of bioenergy plants.

Pellets from Pellets Plant


Power from Pellets Plant
Power from BECS
Power from BIGCC
15.0

Unused Heat
Substituted Heat
12.5
Energy Production (TWh)

10.0
7.5
5.0
2.5
0.0

0 25 50 75 100
-1
CO2Price ( tCO2 )

Fig. 4. Energy production and technology mixes for alternative CO2 prices.

because conversion efciencies and CO2 emissions savings are low rably high. BIGCC is economically viable for lower CO2 prices. Loca-
relative to the other technologies and investment costs are compa- tions with large and concentrated amounts of heat demand make
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2137

Table 4
Mean and condence intervals of biomass utilization per technology at different CO2 prices in percent. Note: L and U denote the lower and upper bound of the 99% condence
interval of the mean.

CO2 price ( tCO1 BIGCC biomass use (% of total biomass) BECS biomass use (% of total biomass) Pellets biomass use (% of total biomass)
2 )

Mean L U Mean L U Mean L U


0 10 5 14 0 0 0 90 81 99
25 21 14 28 1 0 2 77 70 85
50 12 8 15 6 3 9 82 78 86
75 5 2 7 23 19 28 72 67 76
100 1 0 2 38 32 44 61 55 67

Fossil Fuel Substitution (TWh)


BIGCC competitive to pellets production. BECS utilization starts at CO2 Emission Reductions(MtCO2)
around 50 tCO12 and is increasing with the CO2 price. At 100

15
tCO1
2 , about 38% of biomass is used for BECS. At low CO2 prices,
only part of the available biomass (64% for 0 tCO12 and 81% for
25 tCO1 1
2 ) is utilized for bioenergy production. At 50 tCO2 , al-
most all available forest biomass (96.30%) is used to produce
bioenergy.

TWh, MtCO2
10
CO2 emission reductions (esav ) in each of the scenarios are
determined by the following equation:
!
X 1 X 1
esav efossil
c zfossil
k;c dk;d elocal
h qDh;t  totem 11
gfossil glocal
h;t
5
k;c;d d h;t

Fig. 5 shows the CO2 emission reductions and the amount of fos-
sil fuels that are substituted in the ve scenarios. At a CO2 price of 0
tCO12 , annual CO2 emission reductions of 2.71 MtCO2 y
1
are
achieved. This amounts to around 3% of total Austrian CO2 emis-
0

sions. At a price of 100 tCO1


2 , this sum goes up to 5.64 MtCO2 y
1
0 25 50 75 100
(6.27% of total CO2 emissions in Austria). A signicant contribution -1
CO2 Price ( tCO2 )
to Austrian climate targets can thus be achieved through using bio-
energy. However, there is a tradeoff between fossil fuel substitu- Fig. 5. Mean of CO2 emission reductions (grey bars, in MtCO2) and fossil fuel
tion and CO2 emission savings: at high CO2 prices when BECS substitution (white bars, in TWh) at alternative CO2 prices. Note: the intervals
utilization is increased less fossil fuels are substituted due to indicate the 99% condence interval of the mean.
the lower conversion efciencies of BECS (Fig. 5).
analysis on the 90% level are shown. The numbers in the gure are
3.3. Sensitivity and uncertainty analysis a reference to column 1 in Table 2 where all stochastically modeled
parameters are listed. At 25 tCO1 2 , the efciency of converting
The sensitivity of model results to changes in input parameters wood to pellets (24) is elastic and positively related to CO2 emis-
and the contribution of single parameters to model uncertainty are sion reductions. The availability of biomass (31), biomass costs
discussed in this section. Each of the ve CO2 price scenarios is ana- (30), the oil price (2), the efciency of BIGCC plants (14) and the
lyzed separately. Elasticities are estimated to measure the percent- power price (1) are inelastic and positively related with CO2 emis-
age change of model outputs on percentage change of model input sion reductions. A negative, inelastic relationship exists between
parameters. The estimation process involves determining a re- the costs of district heating infrastructure (32) and variable costs
sponse surface by means of linear regression and subsequent for BIGCC plants (9). While most of the results are as expected, it
numerical calculation of the elasticities. The procedure is outlined is not immediately intuitively clear that biomass costs are posi-
in Appendix D. If the uncertainty of the distribution of a parameter tively correlated with CO2 emission reductions, i.e. that an increase
is low, a high elasticity does not necessarily imply that the param- in biomass costs causes an increase in bioenergy production. This is
eter contributes a lot to the uncertainty of the model. To estimate a result of the bootstrapping mechanism. Increases in biomass
the contribution of a parameter to model uncertainty, an error costs are positively correlated with increases in power and fossil
measure is calculated from the response surface following [53]. fuel costs in the price data. However, relative biomass cost in-
The mean absolute percentage error (MAPE) was calculated in creases are lower than increases in energy prices. This allows for
[53] as error measure. MAPE was criticized as it puts high penalties additional production of bioenergy because higher energy prices
on errors if the actual value is very low [58]. The median absolute more than compensate the increase in feedstock prices. The oil
percentage error (MdAPE) protects against such outliers [59] and is price (2) and biomass costs (30) contribute most to model
therefore used in this study. uncertainty.
The results of the sensitivity and uncertainty analysis of two BECS parameters, i.e. efciency of power and heat production in
scenarios are discussed in detail as they are of special interest: BECS plants (15 and 19), the costs (25) and the efciency (29) of
the rst one, 25 tCO12 represents a price that is close to the mean
carbon capture and storage are relevant parameters in the 75
market price at the European Energy Exchange. The second one, 75 tCO1
2 scenario. There are also minor changes regarding pellets
tCO1
2 , is the lowest CO2 price that allows BECS production. The
parameters. The efciency of pellets production (24) is not signi-
means of elasticities from Monte-Carlo simulations are plotted cant in this scenario while the variable costs (13) and the efciency
against the uncertainty of the parameter measured as MdAPE in of power production (17) in pellets plants are signicant. However,
Fig. 6. Only model parameters that are signicant in the regression the elasticity as well as uncertainty of the parameters is very low. It
2138 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Elasticity and Uncertainty of CO2 Emission Reductions Elasticity and Uncertainty of CO 2 Emission Reductions

(25 tCO2-1) (75 tCO2-1)

2 2
0.10
0.12

0.10 0.08

Uncertainty (%)
29
Uncertainty (%)

0.08 0.06
19
0.06
0.04 25 15
30 31

0.04 1
1 0.02 32
14 30 28
9 24
0.02 32 31 17 33
14 913

0.0 0.5 1.0 1.5 0.0 0.5 1.0 1.5


Elasticity Elasticity

Fig. 6. Plots of parameter elasticities against parameter uncertainties corresponding to CO2 emission reductions. Left: CO2 price of 25 tCO1 1
2 , Right: 75 tCO2 . Note: The
numbers indicate the number of the parameter in Table 2.

24 4. Discussion and conclusions


31

1.5 34
30 24 The model results show clearly that ethanol and methanol from
forest wood is not an economically and technically sound option to
31

1.0
reduce CO2 emissions in Austria. For countries similar to Austria
31
2 33 this result may be valid, if heat demand is high and considerable
Elasticity

31 15
29
amounts of fossil fuels can be replaced by either pellets or district
0.5 30
2
15
29
19
15
heating. Pellets production is preferred to BECS production at low
1
19 28
19
CO2 prices. National statistics conrm the trend of biomass based
28
1 29 17
1
1 power and heat production: the number of dwellings heated by
1
0.0 9
13 9
32
25 32 32
25
biomass increased by 13% from 2003/2004 to 2007/2008, which
2 25
30 30
14
has resulted in an estimated increase of around 2 TWhbiomass
2 4
-0.5 2 [60]. Furthermore, biomass based power production has increased
by about 1 TWh in the same period [4]. It should be noticed that
0 25 50 75 100 both, biomass based power production and pellets boilers, are cur-
CO2Price ( tCO2-1) rently subsidized. The model results are very much in line with
ndings of other research. Fuel production is rated worst with re-
Fig. 7. Elasticities between input parameters and CO2 emission reductions for ve
spect to costs and CO2 emission reductions [15,17,28]. The model
CO2 prices. Note: the numbers indicate the number of the parameter in Table 2.
results clearly show that spatial restrictions in heat demand have
signicant impact on the competiveness of BIGCC. The results also
is of interest that the sign of the elasticity of the efciency of power show that BECS is an economically viable option to reduce CO2
production in BIGCC plants (14) changes. While it is positive in the emissions. However, there is a tradeoff between fossil fuel substi-
rst scenario, it is negative in the second one. High power efcien- tution and CO2 emission savings. Less fossil fuels are replaced by
cies in BIGCC plants decrease the utilization of BECS, which saves BECS due to the lower efciency. Additionally, serious concerns
more CO2 emissions than the former. The costs of biomass (30) also are related to carbon capture and storage: it is not clear by now
change the sign and are negative in the 75 tCO1 2 price scenario.
if CO2 storages are environmentally safe. All results on potentials
While the relative difference between biomass costs and energy of the technologies to reduce CO2 emissions depend on the as-
prices is relevant in the low CO2 emission-price scenario, the rela- sumed CO2 emission baseline. Outside of the bioenergy sector, var-
tive difference between biomass costs and the CO2 price is more ious new CO2 emission reduction technologies like photovoltaic
relevant in the high emission-price scenario. CO2 price and bio- and wind for the power sector, insulation and solar heating for
mass costs are not correlated, therefore the sign of the elasticity the heating sector and electric vehicles in the transportation sector
of biomass costs (30) changes. Uncertainty of model results is are either already used or emerging. Assuming different baseline
mainly inuenced by the oil price (2) and BECS plant parameters, CO2 emissions in the bioenergy scenarios e.g. a fossil fuel free
i.e. the efciency (29) and costs of carbon capture and storage power sector changes the relative techno-economic efciency
(25), and the efciency of power (15) and of heat production of bioenergy technologies for climate change mitigation. Interpre-
(19). The elasticities of all ve CO2 price scenarios are shown in tations of the results of this paper have to regard this model
Fig. 7. The gure shows that elasticities decrease with increasing boundary.
CO2 price, because the higher CO2 price stabilizes results. However, The spatial distribution of biomass supply and energy demand
when BECS becomes selected at 75 tCO1 2 , the elasticities increase
is important for total costs and CO2 emission savings. The locations
because the introduction of the technology adds uncertainty to the of pellets plants are scattered over Austria while BIGCC plants
model. are located closely to big cities due to the high heating demand
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2139

Fig. 8. Results of model validation for CHP plants (left) and for pellets plants (right).

densities and amounts. Biomass transportation costs are therefore tions applying our model on methanol [21,22,51], ethanol [31],
higher for BIGCC plants. The total production costs can signicantly biodiesel [52] and BIGCC [20] production are available. Regarding
decrease with respect to economies of scale of bioenergy plants. the validation of the model with respect to the selection of optimal
Plants of smaller size do not show the same competitiveness like plant locations, we opted for validating the model with existing
plants of the size discussed in our analysis. Both elasticities and pellets facilities and additionally CHP steam engine plants.
uncertainties related to energy prices are high. Energy prices are Although CHP steam engine plants have different technical and
the main factor in determining the competiveness of bioenergy economical properties than BIGCC, it is expected that the choice
plants, particularly at low CO2 prices. However, technical plant of the location is similar to BIGCC because feedstock supply and
parameters, i.e. conversion efciencies and carbon capture and heat demand are important for both types of plants. Facilities in-
storage rates inuence model results signicantly. stalled since 2002 (for CHP) and since 1998 (for pellets) serve as
Model results indicate that pellets production and subsequent basis for model validation [61]. The year 2002 is chosen because
combustion for heating dwellings is a low cost technology to re- the green electricity law was implemented in Austria in that year
duce CO2 emissions. The technology is available on the markets while rst large scale pellets plants started operations in 1998.
and substitution of existing heating oil fuelled boilers would be The green electricity law guarantees feed-in tariffs to power pro-
favorable. There is also some potential for big scale BIGCC plants. duced from biomass and triggered a substantial increase in the
However, there are little suitable locations for such plants. BECS number of CHP plants installed. Large scale pellets production
is a high cost option for reducing CO2 emission and risks associated started earlier in Austria but also experienced a boost due to sub-
with the permanent storage of the CO2 have to be considered as sidies given by state governments for the installation of pellets
well. Total CO2 emission reduction potentials are, however, higher heating systems. For the validation process, only facilities that
than for any of the other technologies. are larger than 20 MWbiomass are considered. We do not assume
that the model performs well for plants of lower capacity due to
the limited spatial resolution of the model. Investment costs and
Acknowledgements
plant characteristics size and efciencies were taken from data
provided publically by the operating companies on their websites.
The article has been prepared in the framework of the doctoral
Eleven CHP and 17 pellets plants of a capacity above 20 MWbiomass
school Sustainable Development (DOKNE) at BOKU University of
were built in the period. Model parameters were set to values cor-
Natural Resources and Applied Life Sciences, Vienna, Austria. The
responding to the year of 2004. Additional to the 28 existing loca-
doctoral school is funded by the Austrian Research Program on
tions, 36 additional locations were added to the model to test if the
Sustainability provision as well as by the Federal Ministry of
model selects the right locations. The model was forced to choose
Agriculture, Forestry, Environment and Water Management
11 locations for CHP plants and 17 locations for pellets plants
(BMLFUW) and the states Lower Austria, Styria, and Vienna. This
among the 64 possible locations. The results of the validation pro-
article has been also supported by the FP7 Project: Climate Change
cess are shown in Fig. 8. For the CHP case, the model selected 9 of
Terrestrial Adaptation & Mitigation in Europe (ccTAME) funded
11 positions correctly. Only two locations are chosen differently,
by the European Commission. Comments received from two anon-
and both are plants of lower capacity (27 MWbiomass and 31 MWbio-
ymous referees are gratefully acknowledged.
mass). In the pellets case, the model selected 11 out of 17 locations
correctly. An explanation is that the optimal position of pellets
Appendix A. Model validation plants depends less on the proximity to the consumers than in
the CHP case. Distribution of pellets is inexpensive in comparison
The validation of models that assess emerging technologies is a to district heating and therefore the proximity to wood resources
difcult task because there is no real world data available which is of more importance. Wood resources are, however, not as con-
can be used for comparison with model results. No commercial centrated as heating demand. Locations differ therefore less in
installations of BIGCC, BECS, methanol and ethanol production their suitability for pellets production than for CHP production
are currently operating. Regarding parameters and costs of future which explains why the model does select only a subset of the
technologies, we relied therefore on expert opinion, on peer re- locations found in reality. Considering this, the model performs
views and on existing publications to validate the model. Publica- well in the selection of plant locations.
2140 J. Schmidt et al. / Applied Energy 87 (2010) 21282141

Appendix B. District heating model Appendix D. Sensitivity analysis

Heat production limits the amount of heat available for district Elasticities can be estimated for all combinations of input
heating. The commodity production is modeled on an annual time parameters and output variables. Variable esav is used for further
period. However, variations in heat demand in winter and summer descriptions of elasticity estimations. The elasticity is dened as:
are considered in the model. Seasonal supply of heat in the plant is
@esav parm
restricted by esav parm ; D:1
@parm esav
X
qdh bio
j;h;ps;t 6 Dt t qj ; B:1 where esav parm is the elasticity between esav and parameter parm.
h;ps @esav
The derivative @par m
cannot be derived analytically from the optimi-
zation model. However, it is possible to estimate a response surface
where parameter Dtt denotes the relative length of a season.
by applying a linear regression model of the output on the input
The production of heat has to meet the demand (parameter qDh;t )
parameters and thereby approximating a continuous function [62],
in each period, which is guaranteed by
X
! ! esav b0 bm parm e; D:2
X m
gdh
h;t gtrans dh
j;h;ps;t qj;h;ps;t qpeak
h;t glocal local D
h;t qh;t qh;t ; B:2
j;ps where coefcient b0 is the intercept, coefcients bm are the regres-
trans
sion coefcients and e is an error term. The size of the plant is xed
where parameter g denotes the heat losses in the pipe system
j;h;ps;t and is therefore not included in this estimation. The parameter vec-
from the plant to the settlement. Losses in the heat distribution net- tors parm, which represent the input to the Monte-Carlo simulation,
work within the settlement are modeled by parameter gdh h;t . Param- and the corresponding result vectors esav are used in the regression
eter glocal
h;t is introduced to describe conversion efciencies of local analysis. The regression is not able to capture the whole dynamics
heating systems. of the non-continuous relationship between the variables which re-
The sum of heat produced by the bioenergy plant and by the sult from the MIP. However, the ordinary least square estimators
peak demand boiler has to match the district heating demand exhibit ts of R2 > 0.5 for all combinations of input parameters
(parameter qDh;ns;t ) in settlement h. This is modeled by and outputs. The signs of the coefcients have the expected direc-
! ! tion for all parameters. The response surface is used to numerically
X X
gdh
h;t gtrans dh
j;h;ps;t qj;h;ps;t qpeak
h;t qDh;ns;t udnet
h;ns : B:3 compute the elasticities:
j;ps ns
@esav parm parm
esav parm bm D:3
The existence of a transportation pipeline, in case a settlement @parm esav esav
is supplied by a bioenergy plant, is ensured by When no bioenergy is produced at all, the elasticity is not de-
ned as the denominator of the fraction in Eq. (D.3) is zero. Unde-
qdh pipe pipe
j;h;ps;t 6 qps;t uj;h;ps ; B:4 ned elasticities are excluded from further calculations. The
procedure is applied separately to the ve CO2 price scenarios.
where parameter qpipe
ps;t denotes the capacity of the pipeline.
Only one district heating network can be built in every settle-
References
ment, which is ensured by
X [1] European Council. Council decision of 25 April 2002 concerning the approval,
udnet
h;ns 6 1: B:5 on behalf of the European Community, of the Kyoto protocol to the United
ns Nations framework convention on climate change and the joint fullment of
commitments thereunder, vol. L 130; Ofcial Journal 2002.
[2] Umweltbundesamt. Austrias national inventory report. Umweltbundesamt
sterreich; 2008.
Appendix C. Determination of optimal plant size [3] Madlener R. Innovation diffusion, public policy, and local initiative: the case of
wood-fuelled district heating systems in Austria. Energy Policy 2007;35:
The optimal plant size with regard to the biggest CO2 emissions 19922008.
[4] E-Control. Development of approved green power plants according to
savings is determined by rst running the model with 1000 sto-
decisions of provincial governments (Entwicklung der anerkannten
chastically determined input parameters for each technology sep- kostromanlagen laut Bescheiden der Landesregierungen). Vienna: E-
arately. The plant size is varied between 50 MWbiomass and Control; 2009. <http://www.e-control.at/portal/page/portal/ECONTROL_ HOME/
250 MWbiomass. From the results, a response surface is estimated OKO/ZAHLEN_DATEN_FAKTEN/Anlagenstatistik/ANERKANNTEOEKOANLAGEN>.
[5] Schadauer K. The Austrian forest inventory 2000/02 main results (Die
by regressing the total CO2 emission savings on all input parameter sterreichische Waldinventur 2000/02 Hauptergebnisse). Vienna:
variations parm, assuming that the plant size has a quadratic effect Bundesamt fr Wald; 2004. <http://bfw.ac.at/040/pdf/1818_pi3.pdf>.
on model output as biomass transportation distance and econo- [6] Ammann H, Brecht I, Albisser Vgeli G. Comparison of wood-red heating
systems. Agrarforschung 2009;16:649.
mies of scale in bioenergy production have opposite effects: [7] Gustavsson L, Mahapatra K, Madlener R. Energy systems in transition:
X perspectives for the diffusion of small-scale wood pellet heating technology.
2
esav b0 bm parm bm1 size e C:1 Int J Technol Manage 2005;29:32747.
m [8] Wahlund B, Yan J, Westermark M. A total energy system of fuel upgrading by
drying biomass feedstock for cogeneration: a case study of Skelleftea
bioenergy combine. Biomass Bioenergy 2002;23:27181.
The b0 is the intercept, bm are the regression coefcients, bm+1 is
[9] Marbe G, Harvey S, Berntsson T. Biofuel gasication combined heat and
the regression coefcient of the quadratic term of the plant size, powernew implementation opportunities resulting from combined supply of
and e is an error term. The optimal size of the plants with regard process steam and district heating. Energy 2004;29:111737.
[10] Dornburg V, Faaij APC. Efciency and economy of wood-red biomass energy
to CO2 emission savings is determined by calculating the root of
systems in relation to scale regarding heat and power generation using
the rst derivate (@esav =@size). However, for biofuel plants and combustion and gasication technologies. Biomass Bioenergy 2001;21:
CHP plants, the root of the derivate is bigger than the maximally 91108.
allowed plant size (250 MWbiomass). Therefore, the plant size is [11] Kraxner F, Nilsson S, Obersteiner M. Negative emissions from bioenergy use,
carbon capture and sequestration (BECS) the case of biomass production by
set to 250 MWbiomass. The optimal size for pellets plants is sustainable forest management from semi-natural temperate forests. Biomass
180 MWbiomass. Bioenergy 2003;24:28596.
J. Schmidt et al. / Applied Energy 87 (2010) 21282141 2141

[12] Obersteiner M, Azar Ch C, Kauppi P, Mllersten K, Moreira J, Nilsson S, Read P, [41] Polagye BL, Hodgson KT, Malte PC. An economic analysis of bio-energy options
Riahi K, Schlamadinger B, Yamagata Y, Yan J, van Ypersele J-P. Managing using thinnings from overstocked forests. Biomass Bioenergy 2007;31:10525.
climate risk. Science 2001;294:7867. [42] Andersson E, Harvey S, Berntsson T. Energy efcient upgrading of biofuel
[13] Fatih Demirbas M. Bioreneries for biofuel upgrading: a critical review. Appl integrated with a pulp mill. Energy 2006;31:138494.
Energy 2009;86:S15161. [43] Assmann E. The principles of forest yield study. Oxford: Pergamon; 1970.
[14] Piccolo C, Bezzo F. A techno-economic comparison between two technologies [44] Running SW. Terrestrial remote sensing science and algorithms planned for
for bioethanol production from lignocellulose. Biomass Bioenergy EOS/MODIS. Int J Remote Sens 1994;15:3587620.
2009;33:47891. [45] European Environment Agency. Corine land cover. European Environment
[15] Bram S, De Ruyck J, Lavric D. Using biomass: a system perturbation analysis. Agency; 2008. <http://www.eea.europa.eu/publications/COR0-landcover>.
Appl Energy 2009;86:194201. [46] Federal Ministry of Agriculture Forestry Environment and Water Management.
[16] Faaij A. Modern biomass conversion technologies. Mitigat Adaptat Strategies Logging report 2001 2007 (Holzeinschlagsmeldung 20012007). Vienna:
Global Change 2006;11:33567. Federal Ministry of Agriculture, Forestry, Environment and Water
[17] Wahlund B, Yan J, Westermark M. Increasing biomass utilization in energy Management; 2008. <http://duz.lebensministerium.at/duz/duz/category/
systems: a comparative study of CO2 reduction and cost for different bioenergy 1025>.
processing options. Biomass Bioenergy 2004;26:53144. [47] Landwirtschaftskammer Niedersterreich. Energy wood index Austria
[18] Eriksson LO, Bjrheden RW. Optimal storing, transport and processing for a (Energieholzindex sterreich). St. Plten: Landwirtschaftskammer
forest-fuel supplier. Eur J Operat Res 1989;43:2633. Niedersterreich; 2008.
[19] Grohnheit PE, Mortensen BOG. Competition in the market for space heating. [48] UNFCCC. Updated UNFCCC reporting guidelines on annual inventories
District heating as the infrastructure for competition among fuels and following incorporation of the provisions of decision 14/CP.11. In: Advice
technologies. Energy Policy 2003;31:81726. Sbfsat, editor, vol. FCCC/SBSTA/2006/9: United Nations; 2006.
[20] Schmidt J, Leduc S, Dotzauer E, Kindermann G, Schmid E. Potential of biomass- [49] Statistik Austria. Energy bilances 19702006 (Energiebilanzen 19702006).
red combined heat and power plants considering the spatial distribution of Statistik Austria; 2007.
biomass supply and heat demand. Int. J. Energy Res.; in press. doi:10.1002/ [50] Leduc S. Development of an optimization model for the location of biofuel
er.1623. production plants. Phd Thesis, Lule University; 2009.
[21] Leduc S, Schwab D, Dotzauer E, Schmid E, Obersteiner M. Optimal location of [51] Leduc S, Lundgren J, Franklin O, Schmid E, Dotzauer E. Location of a biomass
wood gasication plants for methanol production with heat recovery. Int J based methanol production plant: a dynamic problem in Northern Sweden.
Energy Res 2008;32:108091. Appl Energy 2009;87:6875.
[22] Leduc S, Schmid E, Obersteiner M, Riahi K. Methanol production by gasication [52] Leduc S, Natarajan K, Dotzauer E, McCallum I, Obersteiner M. Optimizing
using a geographically explicit model. Biomass Bioenergy 2009;33:74551. biodiesel production in India. Appl Energy 2009;86:S12531.
[23] Suntana AS, Vogt KA, Turnblom EC, Upadhye R. Bio-methanol potential in [53] Salhofer K, Schmid E, Streicher G. Testing for the efciency of a policy intended
Indonesia: forest biomass as a source of bio-energy that reduces carbon to meet objectives: general model and application. J Agri Resour Econom
emissions. Appl Energy 2009;86:S21521. 2006;31:15172.
[24] Mllersten K, Gao L, Yan J. CO2 capture in pulp and paper mills: CO2 balances [54] Batlle C, Barqun J. Fuel prices scenario generation based on a multivariate
and preliminary cost assessment. Mitigat Adaptat Strategies Global Change GARCH model for risk analysis in a wholesale electricity market. Int J Electr
2006;11:112950. Power Energy Syst 2003;26:27380.
[25] Mllersten K, Gao L, Yan J, Obersteiner M. Efcient energy systems with CO2 [55] Energy Information Administration. Ofcial energy statistics from the US
capture and storage from renewable biomass in pulp and paper mills. Renew government. Washington: Energy Information Administration; 2009. <http://
Energy 2004;29:158398. www.eia.doe.gov/>.
[26] Mllersten K, Yan J, Westermark M. Potential and cost-effectiveness of CO2 [56] European Energy Exchange. Market data. European energy exchange; 2009.
reductions through energy measures in Swedish pulp and paper mills. Energy <http://www.eex.com/en/Download/Market%20Data>.
2003;28:691710. [57] Efron B. Bootstrap methods: another look at the jackknife. Ann Statist
[27] Mllersten K, Yan J, Moreira JR. Potential market niches for biomass energy 1979;7:126.
with CO2 capture and storage opportunities for energy supply with negative [58] Makridakis S. Accuracy measures: theoretical and practical concerns. Int J
CO2 emissions. Biomass Bioenergy 2003;25:27385. Forecast 1993;9:5279.
[28] Grahn M, Azar C, Lindgren K, Berndes G, Gielen D. Biomass for heat or as [59] Armstrong JS, Collopy F. Error measures for generalizing about forecasting
transportation fuel? A comparison between two model-based studies. Biomass methods: empirical comparisons. Int J Forecast 1992;8:6980.
Bioenergy 2007;31:74758. [60] Statistik Austria. Total use of energy sources (Gesamteinsatz aller
[29] Kumar A. A conceptual comparison of bioenergy options for using mountain Energietrger 2003/20042007/2008). Statistik Austria; 2009.
pine beetle infested wood in Western Canada. Bioresour Technol [61] Kopetz H, Scheiber E. Basis data bioenergy Austria (Basisdaten Bioenergie
2009;100:38799. sterreich). sterreichischer Biomasse-Verband; 2006.
[30] Alfonso D, Perpi C, Prez-Navarro A, Pealvo E, Vargas C, Crdenas R. [62] Saltelli A, Ratto M, Andres T, Campolongo F, Cariboni J, Gatelli D, et al. Global
Methodology for optimization of distributed biomass resources evaluation, sensitivity analysis: the primer. Chichester: John Wiley & Sons Ltd.; 2008.
management and nal energy use. Biomass Bioenergy 2009;33:10709. [63] Sims REH. Bioenergy a renewable carbon sink. Renew Energy 2001;22:317.
[31] Leduc S, Starfelt F, Dotzauer E, Kindermann G, McCallum I, Obersteiner MJL. [64] Azar C, Lindgren K, Larson E, Mllersten K. Carbon capture and storage from
Optimal location of ethanol ligno-cellulosic bioreneries with polygeneration fossil fuels and biomass costs and potential role in stabilizing the
in Sweden. Energy; in press. doi:10.1016/j.energy.2009.07.018. atmosphere. Climate Change 2006;74:4779.
[32] Rhodes JS, Ketih DW. Engineering economic analysis of biomass IGCC with [65] Thek G, Obernberger I. Wood pellet production costs under Austrian and in
carbon capture and storage. Biomass Bioenergy 2005;29:44050. comparison to Swedish framework conditions. Biomass Bioenergy
[33] Uddin NS, Barreto L. Biomass-red cogeneration systems with CO2 capture and 2004;27:67193.
storage. Biomass Bioenergy 2007;32:100619. [66] Gronalt M, Rauch P. Designing a regional forest fuel supply network. Biomass
[34] van der Zwaan B, Gerlagh R. Economics of geological CO2 storage and leakage. Bioenergy 2007;31:393402.
Climate Change 2009;93:285309. [67] Styles D, Jones MB. Current and future nancial competitiveness of electricity
[35] Holloway S. Safety of the underground disposal of carbon dioxide. Energy and heat from energy crops: a case study from Ireland. Energy Policy
Convers Manage 1997;38:2415. 2007;35:435567.
[36] Thistle D, Sedlacek L, Carman KR, Fleeger JW, Bewer PG, Barry JP. Simulated [68] Konstantin P. Handbook energy industry (Praxisbuch
sequestration of industrial carbon dioxide at a deep-sea site: effects on species Energiewirtschaft). Berlin: Springer Berlin Heidelberg; 2007.
of harpacticoid copepods. J Exp Mar Biol Ecol 2006:330. [69] Arbeitsgemeinschaft Fernwrme e.V. Strategies and technologies of a
[37] Demirbas A. Present and future transportation fuels. Energy Sources Part A pluralistic district heating supply in a liberalized energy market considering
2006;30:147383. combined heat and power and renewable energies (Strategien und
[38] Hamelinck CN, Hooijdonk GV, Faaij AP. Ethanol from lignocellulosic biomass: Technologien einer pluralistischen Fern- und Nahwrmeversorgung in einem
techno-economic performance in short-, middle- and long-term. Biomass liberalisierten Energiemarkt unter besonderer Bercksichtigung der Kraft-
Bioenergy 2005;28:384410. Wrme-Kopplung und erneuerbarer Energien). Frankfurt: Arbeitsgemenschaft
[39] Hamelinck CN, Faaij APC. Future prospects for production of methanol and Fernwrme e.V.; 2000. <http://www.isi.fhg.de/e/publikation/waerme/band1-
hydrogen from biomass. J Power Sour 2001;111:122. lang.pdf>.
[40] Magelli F, Boucher K, Bi HT, Melin S, Bonoli A. An environmental impact [70] E-Control. Production of electric energy in Austria, time series until 2006
assessment of exported wood pellets from Canada to Europe. Biomass (Aufbringung elektrischer Energie in sterreich, Jahresreihen bis 2006). E-
Bioenergy 2009;33:43441. control; 2008.

Das könnte Ihnen auch gefallen