Sie sind auf Seite 1von 86

PROJECT: BANGALORE METRO RAIL PROJECT

DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDIT
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 1 Standards
1.1 Bureau Indian Standards (IS)
1.2 Indian Railway standards (IRS)
1.3 Indian Road Congress (IRC)
1.4 ASTM Standards
1.5 AASHTO standards
1.6 British Standards (BS)
1.7 UIC 772/R The international Union of railways Publication
Section 2 Earthworks
Sl No Name
2.1 Excavation
2.1.1 Site Clearence
2.1.2 Top soil stripping
2.1.3 Removal unsuitable material
2.1.4 Excuvation

2.1.5 Excavation beyond True lines & Levels


2.1.6 Approval of excavation
2.1.7 Excavations for structure
2.1.8 Trench excavation
2.1.9 Trenches
2.1.10 Road crossings
2.1.11 Channels
2.1.12 Approval
2.2 Fill
2.2.1 Fill-general
2.2.2 Fill material

2.2.3 Backfill - general


2.2.4 Backfill to structures
2.2.5 Preparation of foundation for embankment
2.2.6 Placing embankment
2.2.7 Compaction of embankment

2.2.8 Inverted Filter


2.3 Tests
2.3.1 Testing of fill - general
2.3.2 Materials for top layer of fill
2.3.3 Testing of top iayer
2.4 Landscaping
Top soiling
Grassing
Section 3 Road works
Sl No Name
3.1 Control of Traffic
3.2 Granular Sub-base(Non Bituminous)
3.2.1 Material

3.2.2 Physical requirements

3.2.3 Strength of sub - base


3.2.4 Construction Operations
3.2.5 Control of Traffic

3.3 Water-bound Macadam Sub-base/ Ease


(Non-Bituminous)
3.3.1 Description
3.3.2 Materials
3.3.3 Construction Method

3.4 Bituminous Materials

3.4.1 Materials
3.4.2 Methods of Storage and Handling
3.5 Prime Coat
3.5.1 Description
3.5.2 Materials
3.5.3 Construction methods
3.6 Tack Coat
3.6.1 Description
3.6.2 Materials
3.6.3 Construction Operations
3.7 Bituminous Macadam
3.7.1 Description
3.7.2 Materials
3.7.3 Construction Methods
3.7.4 Surface Control
3.7.5 Control of Traffic
3.8 Open-graded Pre-mix Carpet
3.8.1 Description
3.8.2 Materials
3.8.3 Construction Methods
3.8.4 Control of Traffic
3.9 Bituminous Concrete
3.9.1 Description
3.9.2 Materials
3.9.3 Mix-design
3.9.4 Construction operations
3.10 Seat Coat
3.10.1 Description
3.10.2 Materials
3.10.3 Construction Methods
3.10.4 Control of traffic
3.11 Cement Concrete Pavements
3.11.1 General
3.11.2 Materials
3.11.3 Equipment and Tools
3.11.4 Construction Methods
3.11.5 Control of Traffic
D STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING

Scope

Removing vegetation,debris,trees,along with their roots buildings etc

Bolders , stones
Excavations free from water,Dispose of all excavated material to
approved site,

Dead man, Additional excuvation


Recompaction,

Notice of No Objection
Not Use of unsuitable materials like Clay,Peat,Loam etc
Initial Tests on proposed material:one test for each 2000cum of fill
1)Wet seive analysis
2)Dry density/Moisture content relationship
Approved materials
Embankment : Dry density at least equal to 95% of max dry density
Sub-base/Shoulder : Dry density at least equal to 90% of max dry density
Stone boulders,CA to accepted grading

As per relavent standards


As per relavent standards

Grass Sprigs shall be planted @ 0.3m x 0.3m spacing

Scope
Section - 9 - Employers requirments,Cl,9.1,9.2,9.3
As per Requirment/IRC Standards
Natural Sand,Moorum,Gravel,Crushed stone and
As per MOST specification for Roads and Bridges
Water absorption as per : IS:2386(Part 3) BS:812(Part III)
Soundness as per : IS:383
As per MOST specification for Roads and Bridges
As per methodology
Approval of traffic management plans
Diversion of traffic
Adequate signs, Signals,Barriers ,Lamps and as per IRC standards

WMM thk shall not < than 75mm and not > 200mm
Relavent all tests for Aggregates
Preparation of Base
Preparation of Mix
Spreading of Mix
Compaction

As per relavent IS codes


Cut Back Bitumen :IS:217
Cationic Emulsion :IS:8887
Paving Bitumen : IS:73
PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDIT
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 4 Piling and Diaphragm Walling
Sl No Name
4.1 General
4.1.1 Piling plant and Methods

4.1.2 Records
4.1.3 Programme and Progress Report
4.1.4 Setting Out
Tolerances

4.1.5
4.1.6 Disturbances and Noise
4.1.7 Obstructions
4.2 Concrete Piles
4.2.1 Materials - General

4.2.2 Reinforcement
4.3 Precast Concrete Piles
4.3.1 Form work
4.3.2 Casting Tolerances
4.3.3 Protection of Finished Piles

4.3.4 Lengthening Concrete Piles


4.4 Cast-in-Place Piles
4.4.1 Bored Piles
4.4.2 Concreting
4.4.3 Drilling Fiuid
4.4.4 Extracting Temporary Casings
4.5 Pile Testing
4.5.1 General
4.5.2 Safety Precautions
4.5.3 Presentation of Results
4.5.4 Completion of a Test
4.5.5 High Strain Dynamic Testing of Piles
4.5.6 Lateral Load Tests
4.5.7 Pile Integrity Tests
4.6 Diaphragm Waliing
4.6.1 General

4.6.2 Method Statement


4.6.3 Levels of Work
4.6.4 Length of Panels
4.6.5 Tolerances

4.6.6 Access
4.6.7 Adjacent Properties
4.6.8 Reinforcement
4.6.9 Concrete
4.6.10 Test Cubes
4.6.11 Bentonite
4.6.12 Storage of Bentonite
4.6.13 Alternative Materials
4.6.14 Placing Concrete by Tremie

4.6.15 Stop Ends


4.6.16 Inserts
4.6.17 Checking and Monitoring
4.6.18 Safety and Emergency Procedures
4.6.19 Site Cleanliness
4.6.20 Obstructions
4.6.21 Disposal of Spoil
4.6.22 Joints
4.6.23 Records
4.6.24 Disposal of Slurry
D STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING

Scope

Piling Plant details and method statements shall be submittedn not less than
2 weeks before any piling work comencement
Each pile data and two signed copies of each pile

Establish and maintain permanant datum level points


Driven/Bored
C/s dimension - +50mm and -10mm
Levels - +/- 25mm
Minimise Noise and Disturbance

Pre-cast/Cast-in-situ
Min Grade M25 unless otherwise specified
Min Cement Content : 400kg/cum

As required
C/s dimensions Not >6mm
Using sulphate resistant cement:(ASTM or TIS Type 5) (Equivalent IS:12330-1988)
Increase concrete cover for reinforcement

Temporary Casing/Bentonite slurry


Monolithic
Bentonite slurry
Precautions&

IS:2911(Part -IV)-1985
Kentledge/Tension Piles and ground anchors
Graph

Dynamic Pile Testing


1.5 times

BS:8004
IS:9556,IS:4651,IS:456

Min Cover to Main reinforcement :70mm


Clear distance b/w reinforcement : 100mm
Longitudinal tolerance: 75mm
Vertical tolerance: 50mm

HYSD bars ,IS:1786-1985


Min cement content:400kg/cum,BS:8004 or IS:456,Min slum:150mm
As per relavent codes
IS:9556-1980
Dry cool conditions.IS:4082-1996

Min Pipe dia 250mm and Min embedment of 2.0minto concrete to prevent reentry of
slurry into pile

As per drawing details


PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR COND
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 5 Concrete
5.1 Concrete Materials
5.1.1 General

5.1.2 Aggregate

5.1.3
Reinforcement
5.1.4 Water
5.1.5 Admixtures
5.1.6 Min the risk of Alkali Silica Reaction(ASR)
5.2 Concrete Workmanship
5.2.1 Grade
5.2.2 Trial Mixes
5.2.3 Quality Control
5.2.4 Batching
5.2.5 Control of Chlorides and Sulphates
5.2.6 Placing
5.2.7 Formwork
5.2.8 Reinforcement
5.2.9 Joints
5.2.10 Curing and Protection
5.2.11 Finishes
5.2.12 Special Concrete
5.2.13 Protective Coatings
5.2.14 Tolerances
5.3 Precast Concrete
5.3.1 Manufacture Off the Site
5.3.2 Forms
5.3.3 Curing
5.3.4 Storage
5.3.5 Handling and Transport
5.3.6 Assembly and Erection
5.3.7 Arming Structural Connections
5.3.8 Epoxy Grout for Structural Connections
(if required)
5.3.9 Protection
D STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING

Cement
Testing
Delevary & Storage
Source,CA,FA,water absorptionshould be less than 3% by weight
alkali silica reactivity Cloridee content:IS:383 or BS:882,Sulphate content,
Storage
HYSD bars ,IS:1786-1985 Round Bars if applicabrl as per IS:432
Tying wire:MS1.25mm dia
Fresh portable as per IS:3025,IS:456
IS:9103 or BS:1014
Precautions

IS:456,BS:5328

Steel/Plywood(min thk.19mm)
PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR COND
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 6 Prestressed Members
6.1 Prestressing Tendons
6.1.1 Materials
6.1.2 Handling and storage
6.1.3 Surface condition
6.1.4 Straightness
6.2 Precast Construction
6.3 Stressing Tendons
6.3.1 General
6.3.2 Tensioning Apparatus
6.4 Testing by Contractor
6.5 Pretensioning
6.6 Post-tensioning
6.7 Prestressing Tendons - Protection and Bond
6.8 Ducts for Bonded Tendons
6.8.1 Ducts
6.8.2 Grouting of Prestressing Tendons
6.9 Ducts for Unbonded Tendons

6.10 Prestressing Tendons - Trial Construction-Unbonded Tendons


6.11 Prestressing Tendons - Temporary Tendons
6.12 Preparation for Casting
Section 7 Structural Steel work
7.1 General
7.2 Material Properties
7.3 Testing
7.4 Fabrication
7.5 Detailing of Connections
7.6 Submissions
7.7 Welding
7.8 Electrodes
7.9 Welders
7.10 Testing
7.11 Site Welding
7.12 Erection of Steelwork
7.13 Tolerances
7.14 Bolted Connections
7.15 Transportation and Storage
7.16 Damaged Material
7.17 Galvanising
7.18 Preparation of Steelwork for Protective
Treatment
7.19 Painting Generally
7.20 Application of Protective Layers
7.21 Protection of Bolts etc/
7.22 High Strength Friction Grip Connections
7.23 Protective Treatment
7.24 Paintwork Executed on Site
IONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING

12.7mm,as per TIS 420 Grade 1860

Not > 80% specified min Ultimate tensile strength


Blast Cleaned
PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR COND
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 8 Architectural and Building Works
8.1 General Requirements
8.1.1 Permeable to outline Construction specification
8.1.2 Technical

8.1.3 General Requirements Materials


8.1.4 Compliance with Specification
8.2 Brick Layer
8.2.1 Materials
8.2.2 Mortar
8.2.3 Blockwork Generally
8.2.4 Blockwork Reinforcement
8.2.5 Movement Joints
8.2.6 Precast Concrete Units
8.3 Pavior
8.3.1 Materials
8.3.2 Samples
8.3.3 Preparation of Surfaces
8.3.4 levels
8.3.5 Mortar
8.3.6 Workmanship Generally
8.3.7 Granite Paving
8.3.8 Clay Floor Paving
8.3.9 PVC Floor Covering
8.3.10 Division Strips and Matwell frames
8.3.11 Curing
8.3.12 protection
8.4 Roofer
8.4.1 General
8.4.2 Materials
8.4.3 Sample
8.4.4 Preparation of Surfaces
8.4.5 Roof screeds
8.4.6 Installation of Liquid-Apllied Modified Polyurethane
Elastomeric Roofing
8.4.7 Installation od Insulation
8.4.8 Ponding Test
8.4.9. Completion
8.4.10 Guarantee
8.4.11 Profiled Metal Roof Decking

8.4.12 Profiled Metal Roof Coverings


8.4.13 Roofmesh
8.4.14 Aluminium Foil Insulation
8.4.15 Metal Roofing Finish
8.5 Carpenter and Joiner
8.5.1 Reference to Other Traders
8.5.2 Timber
8.5.3 Plywood
8.5.4 Laminated plastic sheeting
8.5.5 Adhesives
8.5.6 Workmanship
8.5.7 Raised Access Floors
8.5.8 Sound Absorbing Material
8.5.9 Acoustic Non-Combustible Board Suspended Ceilings
8.5.10 CEM Board Ceilings
8.5.11 Fibrous Gypsum plaster Boad Ceilings
8.5.12 Metal Suspension System
8.5.13 Modifications Generally
8.5.14 Workmanship Generally
8.5.15 Protection
8.5.16 Ironmongery
8.6 Steel and Metal Worker
8.6.1 Shop Drawings
8.6.2 materials
8.6.3 Galvanizing
8.6.4 Stainless Steel
8.6.5 Chromium Plating
8.6.6 Shop Priming
8.6.7 protective Coatings
8.6.8 Polyster Powder Coating
8.6.9 Fluorocarbon Coating
8.6.10 Workmanship Generally
8.6.11 Installation Generally
8.6.12 Site Measurements
8.6.13 Roller Shutters and Roller Grilles
8.6.14 Fire-rated Metal Doors, Hollow Metal Doors and Door Frames
8.6.15 Perforated Metal Ceilings
8.6.16 Granite trim to Metal Metal Ceiling
8.6.17 Aluminium Strip Ceilings
8.6.18 Metal Wall Cladding
8.6.19 Aluminium Windowss, Panels, Louvers and Grilles
8.6.20 Entrances and Storefronts
8.7 Plasters and Tiler
8.7.1 Materials
8.7.2 Samples
8.7.3 Preparation of Surfaces
8.7.4 Workmanship Generally
8.7.5 Internal Plain Face plaster
8.7.6 backing Screeds
8.7.7 Curing
8.7.8 Tiling generally
8.7.9 Glazed wall Tiling
8.7.10 Protection
8.8 Plumber
8.8.1 rferece to other Trades
8.8.2 Soil, Waste and ventilating Pipework
8.8.3 Hot and cold water Supply Pipework
8.8.4 Sanitary Fittings
8.9 Glazier
8.9.1 Glass
8.9.2 Glazing compounds snd Accessories
8.9.3 Glazing Generally
8.9.4 Compound Glazing
8.9.5 Bead Glazing
8.9.6 Gasket Glazing
8.9.7 Mirror Fixing
8.9.8 Cleaning and Protection
8.10. Painter
8.10.1 Materials

8.10.2 Samples
8.10.3 Preparation of surfaces
8.10.4 Workmanship Generally
8.10.5 Protection
8.10.6 Textured Acrylic Sprayed Paint
8.10.7 Solvent Type Acrylic Coating

Section 9 Tunnelling
9.1 Introduction
9.2 General

9.3 Survey
9.4 Excavation
9.4.1 General
9.4.2 Soft Rock Excavation
9.4.3 Tunnel and Shaft Blasting
9.4.4 Hard Rock Excavation

9.4.5 Exploration of Tunnel Face

9.4.6 Over Break


9.4.7 Cleaning and scaling

9.4.8 Dental Excavation

9.4.9 Disposal of Excavated material


9.4.10 Excavation of Contractor's convenience

9.5 Support Systems


9.5.1 Tunnel Lining
9.5.2 Alternative Tunnel Lining

9.5.3 Tunnel Support (NATM)

9.5.4 Tunnel Permanenr Lining

9.5.5 Grounting

9.5.6 Water tightness of Tunnel


9.6 Invert Concrete

9.7 Field Control and Monitoring Equipment


9.7.1 Setting out of line, level and profile
9.7.2 Chainage markers and bench marks

9.7.3 Monitoring Equipment


9.8 Backfillign of shafts

9.9 Geological Record


9.10 Daily Records
9.10.1 Daily Records

9.10.2 Other records

9.11 Safety and underground Facilities


9.11.1 Safety general

9.11.2 Underground Facilities


Section 10 Cut And Cover Construction
10.1 General

10.2 Waterproofing
10.2.1 General

10.2.2 Structural Concrete works

10.2.3 Cleaning & preparation of Surfaces


10.2.4 Waterproofing Underground Structures

10.2.5 Roof

10.2.6 Water Proofing to Surface and Particularly Underground Structures

10.2.7 Warranty

10.3 Hard Rock Excavation


IONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING

The final Specification document shall be structured to clearly address both


material and workmanship including protection aspects of the work

Section 5
General, References, submittals, Manufacturer's Literature, Samples,
Certificates, Material:- general, decking, Accessories,Fasteners. Fabrication
Installation. Cleaning
Concrete, Palstering or brick work
Asbestos cement and asbestos based insulating board
Wood work

All works shall be caried out according to the requirements detailed in


appendix 20 Employers requirement manual

Comply with section 2, 2.10

Excavation Method, Rock stabilization, Blasting etc should be stictly


followed accordign to the specifications
At least one exploratory hole shall be drilled a head of each tunnel face to
probe th e ground conditions ahead of the advancing tunnel.
All excavation outside the theoritical line is clasiified as over break.
Scaling, after excavation the immediate removal of loose rock from
excavated walls and roofs to prevent further accidents.
Includes the removal of soil, rock fragments, decomposed rock etc. from
seams, cavities, depression or limited areas which requires hand tools.

This type of excavation shall conform in every respect with the


specifications, will not qualify for payment.

Precast concrete lining Design, Trial Assembly, Marking of Segments,


transporting and Storing segments, loints, Rolled Rings, Bolts, Plane,
Sealing strips and gaskets, caukling Grooves, Grout Valves, As-built
tolerances, non- Compliance with Tolerences, Damaged Segments,
Grade of concreter least M40, Tolerences.
The contractor can propose his design to use as alternative contains details
of amterials, method statements, specifications and design sufficient to
demostrate and compliance with design requirements
New Australian Tunneling Method, materials used are spray concrete with
wire mesh or fibre, steel arch rib and rock bolts.
Spilling, tension rock bolts, grout and mortar for rock bolts, anchors and
spilling, testing of rock bolts, steel sets,spray concrete.
Concrete lining, preparation od surfaces,Placing of concete and testing of
Concrete.
Groutings used, cavity grouting, primary grouting, secondary grouting.
Method, Mix, Injection, Grout Plugs,Performance and Verification.
Cavity grouting.
The contractor shall prepare the upper suface of the first stage concret to
meet the requirements of track bed design specification

shall be provided at every 10m interval


The contractor shall provide bsic equipment for measuremnt of deformation.

Temporary shafts and adits shall be completely backfilled on completion of


works, backfill material shall be of grade M10 concret covering 2m over the
tunnel crown which may be placed either wet or dry.shafts shall be filled
inlayers not hicker than 250mm

Cycle time of each round of Excavation, Rock stabilisation, Drainage


arrangement, Spray concrete compressive strength records, pull out tests
on rock bolts, details of structural concrete, linings erected, shortcrete and
grouting done.
The Contractor shall , on daily basis provide Engineer with documentation
of the progress of the work, which includes adherence to line, level an
profile over break or under break.

The contractor shall employe a team and train them for under ground
rescue tea. All precautions shall be taken to avoid Accidents
General installationns like, telephonic communications, Electric cables,
Temporary vebtilation system, Lighting and dewatering
Shall comply with relevant Outline Design Specification as temporary
ground support section 2,4,5, Support by bracing, Sections 4 and 7,
Excavation and Backfilling Section 2, RCC section 2.

Submission, requirements, Method statements and Working Drawings,


Water proofing Appliation
Concrete Joints, Water stops,Piles and Pile caps, Filler and Sealant to
Expansion joints.

(1)Base slab with Bonded membranes,


(2)External Walls to Structures built in Open Excavation,
(3)External walls built against diaphram walls
(4)External Walls Built Against Pile Walls or Rock or Soil Faces.

Water proofing shall be provided by a fully bonded membrane system apllied


to th eupper suface of the Roof slab and also should be in accordence with
Clause 10.2.4(1)
Clause 10.2.4(1) for base slabs for under ground structures,
Clauses 10.2.4 (2),(3) and (4) shall apply to all external walls at depths
greater than 500mm below finished groung level.
minimum warranty period of 10 years from the date of completion of the
whole works against all defects
PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR COND
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 11 Building Management Systen And AS-SCADA
11.1 Mechanical and Electrical Works
11.1.1 General
11.1.2 Design Coordiantion Requirements- General
11.1.3 Design Procress
11.1.4 Software Requiremnts
11.1.5 Environmental
11.1.6 Power Supplies
11.1.7 Design Documentation
11.2 BMS Central Hardware
11.2.1 Central Processing Equipment (Work Station)
11.2.2 Personal Computers
11.2.3 Colour Monitor
11.2.4 Notebook Persoanl computers
11.2.5 Printers and Printing
11.2.6 DOT-Matrix Printer
11.2.7 Network Switches, Modems, Hubs, Gateways
11.2.8 Consoles, Furnihings etc
11.3 ECS PLC Design - Control and Monitoring
11.3.1 General

11.3.2 TVS Control and Monitoring Facilities on ECS work Station


11.3.3 Control Modes
11.3.4 Equipment for BMS Interface
11.3.5 System Components
Technical Requirements of Programmable Logic Controllers(PLCs)-
11.3.6 General
11.3.7 Functionality
11.3.8 PLC Proccessor
11.3.9 PLC Interface Modules
11.3.10 Plc Hardware Requirements
11.3.11 PLC Programming
11.3.12 PLC Additional Features
11.3.13 PLC Power Supply backup
11.3.14 Environmental Conditions
11.3.15 PLC communiations
11.3.16 PLC Total Failure
11.3.17 PLC Panel Internal Wiring
11.3.18 ECS Control and Monitoring
11.3.19 Station Air Conditioning System Operation
11.3.20 Environmental Plant control
11.3.21 Indications
11.3.22 Trackway Exhaust Systems
11.3.23 Smake Extract System
11.3.24 Peration mode Tables
11.3.25 Station air conditioning system in an Emergency
11.3.26 Time table control
11.3.27 Enthalpy Control
11.3.28 Chilled water Palnt
11.3.29 Chilled water System
11.3.30 Chiller Control
11.3.31 Cooling Tower System
11.3.32 Track way Exhaust fan
11.4 Syatem Interfaces- Mechanical

11.4.1 AS-SCADA System Interface with Mechanical System,General


11.4.2 Monitoring and Control
11.4.3 Environmental Controll Interface
11.5 Syatem Interfaces- Fire Detction System
11.5.1 Initial basis for Design
11.5.2 Design Principles
11.5.3 Interface with Fire Protection system

11.5.4 Techincal Requiremnts fro Interfacing with Fire Protection System


11.5.5 Technical Requirements by BMS
11.5.6 BACNet/ LAN Option
11.6 System Interfaces - Electrical
11.6.1 AS-SCADA interfacing
11.6.2 Control
11.6.3 Equipment to be monitored - General Clarifications
11.6.4 Power and Lighing Interface
Seepage Pumps, sump Pumps, Filter Feed Pumps and Soft Water
11.6.5 Pumps
11.7 OCC/BCC Control and Monitoring points
11.7.1 OCC/BCC AS-SCADA Point
11.7.2 Change of State (COS) Signals
11.8 Auxillary System (AS) SCADA
11.8.1 Overview of the AS_SCADA

11.8.1.1 The Equipment to be monitored and/or controlled from the field


11.8.2 Operation control centre/ Backup Control Centre
11.8.3 Trainign Facility
11.8.4 Scope of the Work
11.8.4.1 Genreal
11.8.4.2 Scope of Supply
11.8.4.3 Works Excluded From this Contract
11.8.5 Functional Requirements
11.8.5.1 General
11.8.5.2 Loation
11.8.6 Equipment
11.8.6.1 Remote terminal units

11.8.6.2 Operations Control Centre/Backup Control Centre Theatre


11.8.6.3 OCC/BCC Equipment Rooms
11.8.6.4 System Functional requirements
11.8.7 Performance Requirements
11.8.7.1 General
11.8.7.2 Reliability
11.8.7.3 Availability requiremnts
11.8.7.4 Quantified Requirements
11.8.7.5 Redundant design
11.8.8 Remote Terminal Unit Requirements
11.8.8.1 RTU Functions
11.8.8.2 RTU Hrdware
11.8.8.3 RTU Softwares
11.8.9 OCC and BCC control facilities
11.8.9.1 Central AS_SCADA Services
11.8.10 Work Station facilities
11.8.11 Printers and Printing
11.8.12 Historic data Storage and Software backup
11.8.13 Un-interruptible power Supplies
11.8.14 Software Development
11.8.16 Software Development
11.8.16 HMI Requirements
11.8.16.1 database Facilities
11.8.16.2 Workstation display
11.8.16.3 Graphic Display
11.8.16.4 Other Displays
11.8.16.5 Display construction
11.8.16.6 Alarms
11.8.16.7 Event Logging Reports
11.8.16.8 Calculated and derived Value
11.8.16.9 Access Security
11.8.17 Speed of Operation
11.8.17.1 The two state definitions
11.8.17.2 Change Responses
11.8.17.3 System Loading
11.8.18 Time synchronisation
11.8.19 Accuracy
11.8.20 Historical Data Management
11.8.21 Communiation System
11.8.21.1 OCC/BCC to Field Communication
11.8.21.2 Local Station Communications
11.8.21.3 Communicatios with in OCC/BCC
11.8.22 Design Requirements
11.8.22.1 Ergonomic Study
11.8.22.2 Scree Graphic displays
11.8.22.3 OCC?BCC Status and Control Interfaces
11.8.22.4 Field Equipment to be monitored
11.8.22.4.1 Tunnel Ventilation System Control and Monitoring
11.8.22.4.2 Control and Monitoring at OCC/BCC
11.8.23 Construction and Installation
11.8.24 Verification, Testing and Commissioning
11.8.24.1 General
11.8.24.2 Factory Acceptance Test
11.9 Performance Requirements
11.9.1 General
11.9.2 Electro-Magnetic Compatibility
11.9.3 Equipment Mounting
11.9.4 Maintainability
11.9.5 Equipment Identification
11.9.6 General safety Requirements
11.10 Installation

11.10.1 Installation Paln and Program


11.10.2 Method Statement
11.10.3 Not Used
11.10.4 Drawings and Records
11.10.5 Genral
11.10.6 Circuit Wiring Book
11.10.7 Cable records
11.10.8 Earthing
11.10.9 Asset Identification
11.11 Electrical Works
11.11.1 General
11.11.2 Condition and Intefaces
11.11.3 to 11.11.34 Not used
11.12 Verification, Testing and Commissioning
11.12.1 General
11.12.2 Fire Alarms and Detectors
11.12.3 Electrical Works
11.12.4 Mechanical Works
11.12.5 Compressed Air System
11.12.6 Earthing and Lighting Protection
11.12.7 Tests on Completion - General
11.12.8 Test Logs
11.12.9 Pre-Revenue Operations
11.13 Operation & Maintenance Support
11.13.1 Gneral
11.13.2 Maintenance during Defects liability period
11.13.3 Defects Liability and Management plan

11.13.4 Discrepencies between Installation and Documentation


11.13.5 Support Documentation
11.14 Spare parts, Special Tools & Test Equipment
11.14.1 General
11.14.2 Spare List
11.14.3 Second Sourcing
11.14.4 Long Lead Times
11.14.5 Routine Change
11.14.6 Shelf Life
11.14.7 Identification and Configuration Control
11.14.8 Testing of Spares
11.14.9 Tools and Test Equipment
11.15 Training
11.15.1 General
11.15.2 Scope of Training
11.15.3 System Design and Cofiguration
11.15.4 Maintenance Training
11.15.5 Training Format
11.16 Contract Documentation
11.16.1 General requirements
11.16.2 Submission Control
11.16.3 Contractor's Responsibilities
11.16.4 Material Contract Deliverables
11.16.5 Supplemental Modification Deliverables
11.17 Mode Tables and Other BMS documents
11.17.1 Mode table, Interlock schedule, Mode fail conditions, Tine Table
control, Chiller logic and enthalpy control, vcp operating procedure,
Interface with Fire Alarm System

Section 12 Environmental Control System

12.1 General Specification for Environmental Control System


12.1.1 General
12.1.2 Qulaity Control
12.1.3 Not used
12.1.4 Tools
12.1.5 Training of Operating and Maintennce Personnel
12.1.6 Submission of Drawings
12.1.7 Maintenance
12.1.7.1 Maintenance Plan

12.1.7.1.1 Documentation of various Operation and Maintenance Manuals


12.1.7.3 Asset Identification
12.1.8 General Requiremnets for Products
12.1.9 Acoustic Criteria
12.1.10 Vibration Isalation
12.1.11 Equipment Mounting
12.1.12 Maintainability
12.1.13 Equipment Identification
12.1.14 General safety Requirements
12.1.15 Voltage Levels
12.1.16 Panel Enclosures
12.1.17 Location and Space
12.1.18 Service Life
12.1.19 Space spare Capacity
12.1.20 Execution
12.1.21 Site Preparation
12.1.22 Insallation
12.1.23 Testing and Commissioning
12.1.23.1 General
12.1.23.2 Site Tests
12.1.23.3 Cleaning
12.1.23.4 Hydraulic Tests
12.1.23.5 Air Flow Blalancing
12.1.23.6 Distribution System-ductwork
12.1.23.7 Fluid Circuit balancing
12.1.23.8 Refrigerant circuits
12.1.23.9 Chill tests
12.1.23.10 Condenser/Evaporator/Tank/Receiver vessel tests
12.1.23.11 Equipment output tests
12.1.23.12 Sound level measurement
12.1.23.13 ECS performance Testing
12.2 Air Handling Units
12.2.1 General
12.2.2 Qulaity Control
12.2.3 Submittals
12.2.3.4 Drain Pan
12.2.3.5 Coil and Filter housing
12.2.3.6 AHU enclosure/housing
12.2.3.7 Fan motor&starter
12.2.3.8 Accessories
12.2.3.9 Unit Pan
12.2.3.10 Limitations
12.2.3.11 Execution
12.2.3.12 Filters testing
12.2.3.13 Inspection during assembly of components

12.2.3.14 Cooling capacity measurements, Flow measurements.

12.2.3.15 UVC Emitters


12.3 Fan Coil
12.3.1 General
12.3.2 Quality Control
12.3.2.1 Reference Standards
12.3.2.2 Manufacturer's Qualification
12.3.2.3 Submittals
12.3.3 Technical and Installation requirements
12.3.3.1 General
12.3.3.2 Cooling coil
12.3.3.3 Fan and Motor
12.3.3.4 Drain pan
12.3.3.5 Air Filter
12.3.3.6 water Connections
12.3.3.7 Noise Control
12.3.3.8 Valves
12.3.3.9 Installation
12.3.3.10 Field tests
12.4 Chilling Water Units-Screw Compressors
12.4.1 General
12.4.2 Quality Control
12.4.2.1 Reference Standards
12.4.2.2 Manufacturer's Qualifications and experience
12.4.3 Technical and Installation requirements
12.4.3.1 Description
12.4.3.2 compressor
12.4.3.3 Compressor motor
12.4.3.4 Condenser
12.4.3.5 Chiller
12.4.3.6 Oil recovery Unit
12.4.3.7 Control Pannel
12.4.3.8 Refrigerant Piping
12.4.3.9 Lubrication System
12.4.3.10 Accessories
12.4.3.11 Soft Starter for Compressor Motor
12.4.3.12 Typr of Refrigerant
12.4.3.13 Limitation
12.4.3.14 Execution
12.5 Not used
12.6 Water Circulatng Pumps
12.6.1 General
12.6.2 Quality control
12.6.3 Technical and Installaiton requirements

12.6.4 Variable Speed Secondary Chilled Pumping System


12.6.4.1 General
12.6.4.2 Secondary Pumps
12.6.4.3 Pump Logic Controller
12.6.4.4 Adjustable Frequency Drive
12.6.4.5 Sensor/Transmitters
12.6.4.6 Sequence of operation
12.6.4.7 Quality Assurance
12.6.4.8 Painting

12.7 Ductworks, dampers, diffusers and accessories


12.7.1 General
12.7.2 Quality Control
12.7.3 Technical and Installation requirements
12.7.3.1 Sheet Metal Duct Work
12.7.3.2 Flexible ducts
12.7.3.3 Fire Dampers
12.7.3.4 Fire Rated Ductwork
12.7.3.5 Motor Operated Dampers (MOD)
12.7.3.6 Motorised Smoke and Fire Dampers (MSFD/MFD)
12.7.3.7 Guide Vanes
12.7.3.8 Ductwork Installation
12.7.3.9 Diffusers, Registers and Grilles installation
12.7.3.10 MOD and MSFD/MFD Installation
12.7.3.11 Air Duct Cleaning Points
12.7.3.12 Grills and Diffusers
12.8 Insulation
12.8.1 General
12.8.2 Quality Control
12.8.3 Technical and Installation requirements
12.8.3.1 The materals, finishes fro insulation specification
12.8.3.2 Finisheas for Insulation
12.8.3.3 Execution
12.8.3.4 Insulation on Sheet Metal Ducts
12.8.3.5 Insulation of Pumps
12.8.3.6 Piping

12.8.3.7 Insulation and Protection at Pipe and Duct Supports


12.9 Cooling Towers
12.9.1 General
12.9.2 Quality Control

Codes, Regulations, Reference Standards and Specifications apply


12.9.2.1 to this section of Quality control
12.9.2.2 Submittals
12.9.3 Technical and Insullation requirements
12.9.3.1 General
12.9.3.2 Water Distribution System
12.9.3.3 Fan Assembly
12.9.3.4 Ladder
12.9.3.5 Noise level
12.9.3.6 Installation
12.9.3.7 Field Tests
12.10 Pipe Work
12.10.1 General
12.10.2 Quality Control
12.10.3 Technical and Installation requirements
12.10.3.1 Pipe Material
12.10.3.2 Pipe Fitting - Materials
12.10.3.3 Flanges
12.10.3.4 Gaskets
12.10.3.5 Jointing
12.10.3.6 Supports and Hangers
12.10.3.7 Protective Coating
12.10.3.8 Installation
12.10.3.9 Supports
12.10.3.10 Hangers
12.10.3.11 Welding
12.10.3.12 Jointing
12.10.3.13 Protective Coating
12.10.3.14 Cleaning
12.10.3.15 Testing
12.11 Pipe Line Fittings
12.11.1 General
12.11.2 Quality Control
12.11.3 Technical and Installation Requirements
12.11.3.1 Globe Values
12.11.3.2 Gate Values
12.11.3.3 Balancing Values
12.11.3.4 Flow Measurement avlues

12.11.3.5 Flow Measurement variable Orifice Double Regulating values


Flow Measurement Fixed Orifice Double Regulating values (FODR
12.11.3.6 values)
12.11.3.7 Check valuse
12.11.3.8 Butterfly Values
12.11.3.9 Ball Float Values
12.11.3.10 Ball Values
12.11.3.11 Foot Values
12.11.3.12 Three-way Escape Value
12.11.3.13 Strainers
12.11.3.14 Thermoplastic Values
12.11.3.15 Stopcocks
12.11.3.16 Drain Valves
12.11.3.17 Drain cocks
12.11.3.18 Guage/Test Cocks
12.11.3.19 Automatic Air Eliminator Valves
12.11.3.20 Vortex inhibitors
12.11.3.21 Expansion tank
12.12 Packaged Split air-Conditioning Units/VRV Units
12.12.1 General
12.12.2 Quality Control
12.12.3 Technical and Installation Requirements

12.12.3.1 Unit shall be of minimum vibrationand Noise level During Operation


Provide Units completely piped , wired, charged and factory tested
12.12.3.2 as a package.
All Components shall be dehydrated, sealed and shipped with
12.12.3.3 holding charge/refrigerant
12.12.3.4 Split Type Evaporator unit
12.12.3.5 Split-type Condensing Unit
12.12.3.6 Compressor
12.12.3.7 Refrigerant Circuit
12.12.3.8 Evaporator Coil
12.12.3.9 Condenser Coil
12.12.3.10 Evaporator Fan Motor
12.12.3.11 Condenser fan motor
12.12.3.12 Drain Pan
12.12.3.13 Controls
12.12.3.14 Installation
12.12.4 Split Type AC units with VRV/VRF System
12.12.4.1 General
12.12.4.2 Compressor
12.12.4.3 Heat Exchanger
12.12.4.4 Refrigerant Circuit
12.12.4.5 Safety Devices
12.12.4.6 Indoor Unit
12.12.4.7 General

12.12.4.8 Ceiling Mounted Cassette Type unit (multi Flow Type)


12.12.4.9 Ceiling Mounted Ductable Type Unit
12.12.4.10 High Wall Mounted Units
12.13 Fans
12.13.1 General
12.13.2 Quality Control
12.13.3 Technical and Installation requirements
12.13.3.1 Desciption
12.13.3.2 Propeller Fans
12.13.3.3 Axial Flow Fans
12.13.3.4 Centrifugal Fans
12.13.3.5 Smake Extraction and Pressurization fans
12.13.3.6 Installation
12.14 ECS Equipment control
12.14.1 General
12.14.2 Quality Control
12.14.3 Technical and Installation requipments
12.14.3.1 Control Valves
12.14.3.2 Different Pressure Control Valves
12.14.3.3 Temperature Sensors/Transducers
12.14.3.4 Motorized Valve Operators
12.14.3.5 Motorized Damper Operators
12.14.3.6 Differentisl Pressure Transmitters
12.14.3.7 Limit Switches
12.14.3.8 Automatic Flow Control Valves
12.14.3.9 Electromagnetic Flowmeters
12.14.3.10 Static Pressure Sensors
12.14.3.11 Water Flow Switches
12.14.3.12 Humidity Sensors
12.14.3.13 Level Controllers
12.14.3.14 Water Level Controllers
12.14.3.15 Modulating Damper Actuators
12.14.3.16 Installation
12.15 Acoustic Treatment and Vibration Control
12.5.1 Genral
12.5.2 Quality Control
12.5.2.1 Reference Standards
12.5.3 Technical and Installation Requirements
12.5.3.1 Equipment Bases
12.5.3.2 Concrete Inertis Bases
12.5.3.3 Horizontal Pipe Isolation

12.5.3.4 Selection Guide for Equipment base and Vibration Isolator


12.5.3.5 Method of Installation
12.5.3.6 Pipe work Vibration Isolation
12.15.3.7 Ductwork Vibration Isolation
12.15.3.8 Ductwork Acoustic Insulation
12.15.3.9 Acoustic Duct lag
12.15.3.10 Duct Silencers
12.15.3.11 Acoustic Enclosure
12.16 Not Used
12.17 Not used
12.18 Cable Containment System
12.19 Local ElectricalPanels
12.20 Motors

12.21 Sub-Mains Electrical Switch Boards and Equipment


12.22 Water Treatment Systems
12.22.1 General requirements
12.22.2 Water Treatment for Chilled Water Systems
12.22.3 Water Treatment for Condenser water Systems
12.22.4 Water Testing Equipment
12.22.5 Training Operation and Maintenance Facilities
IONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING
General Requirements, Design Requirements,Equipment, Installation of UVC emitters, copper-Silver
Ionizing system
PROJECT: BANGALORE METRO RAIL PROJECT
DESIGN AND CONSTRUCT CONTRACT OF UNDERGROUND STATIONS AND TUNNELS INCLUDING VENTILATION AND AIR COND
CONTRACT NO: BMR/UG-1(NORTH SOUTH CORRIDOR)
Section 13 Building Sevices
13.1 Mechanical and Electrical Works
13.1.1 General
13.1.2 Standards
13.1.3 Technical and Installation Rerquirements
13.1.3.1 General Requirements
13.1.3.2 Quality Control
13.1.3.2.1 Workmanship
13.1.3.2.2 Tropicalisation
13.1.3.3 Low Voltage Swithboards Cubicle Construction
13.1.3.4 Low Voltage Main Switch Boards earthing
13.1.3.5 LVSBs Electrical Safety Arrangements
13.1.3.6 Busbars
13.1.3.7 Polarity
13.1.3.8 Not used
13.1.3.9 Terminal Blocks
13.1.3.10 Intrnal and Control Wiring
13.1.3.11 Instrumentation
13.1.3.12 Relays
13.1.3.13 Interlocking and Padlocking Facilities
13.1.3.14 Emergency Push Button (EPB)
13.1.3.15 Equipment for BMS Interface
13.1.3.16 Wiring Diagrams
13.1.3.17 Indicating Lamps
13.1.3.18 Control Switches
13.1.3.19 Operating Coils
13.1.3.20 Auxillary Switches and Contacts
13.1.3.21 Control Supply
13.1.3.22 Air Circuit Breakers
13.1.3.22.1 General
13.1.3.22.2 Operating Mechanisms
13.1.3.22.3 Shunt Trip Coils
13.1.3.22.4 Interlocks and Test Operation Facilities
13.1.3.22.5 Safety Shutters
13.1.3.22.6 Control Switch For Air Circuit Breakers

13.1.3.23 Not used


13.1.3.24 Moulded case Circuit Breakers
13.1.3.25 Remote Monitoring
13.1.3.26 Current Transformers (CTs) and Voltage Trasformers (VTs)

13.1.3.27 BMS/SCADA/RS485/Mod BUS connectivity of communicable


ACB/MCCB
13.1.3.28 Contractors
13.1.3.29 Power factor Correction Equipment
13.1.3.30 Finishes
13.1.3.31 Nameplates and Lables
13.1.3.32 Installations
13.1.3.33 Relay & Current Transformer (CT) Requirements fro Transformer
LV standby Earth Fault & LV Restricted Earth Fault Protection

13.1.3.34 Other Provisions


13.1.3.35 Annunciation
13.2 LV Power and Control Cables
13.2.1 General
13.2.2 Standards
13.2.3 Technical and Installation Requirements
13.2.3.2 Construction Requirement for cables required fro underground
station
13.2.3.2.2 Insulation
13.2.3.2.3 Cable and Wire Colours
13.2.3.2.4 Fillers and Binders
13.2.3.2.5 Bedding
13.2.3.2.6 Armour
13.2.3.2.7 Over-Sheath
13.2.3.2.8 Properties of cable Sheathing
13.2.3.3 Fire Performace Requirements
13.2.3.4 Flame Propagation/Integrity under Fire Conditions

13.2.3.5 Corrosive and acid gas Emission


13.2.3.6 Smoke Emission
13.2.3.7 Toxic as emission
13.2.3.8 Cable Current Carrying Capacity and design Parameters

13.2.3.9 Testing of cables and Accessories


13.2.3.10 cable Construction Identification
13.2.3.11 Cable Drums
13.2.3.12 Cable Installation
13.2.3.13 Not Used
13.2.3.14 Installation of Insulated Power Cables
13.2.3.15 Installation of Cable Supports fro Insulated Cables

13.2.3.16 Termination
13.2.3.17 Cable Glands and Accessories
13.2.3.18 Cable joints
13.2.3.19 Cable Identification
13.2.3.20 Screened Signals and control cables
13.3 Cable Containment System
13.3.1 General
13.3.2 Standards
13.3.3 Technical and Installation Requirements
13.3.3.1 General
13.3.3.2 Installation of cable containment system, supports and hangers

13.3.3.3 Cable Trays and Ladders


13.3.3.4 Cable Trunking
13.3.3.5 Ducts
13.3.3.6 Conduit and Accessories
13.3.3.7 Penetration in Walls
13.4 Wiring Accessories and Miscellaneous Electrical Equipment

13.4.1 General
13.4.2 Standards
13.4.2.1 Relevant Codes and standards
13.4.3 Technical Installation Requirements
13.4.3.1 Quality Control
13.4.3.2 Lighting and Appliance Switches
13.4.3.3 Socket Outlets
13.4.3.4 Industrial Socket Outlets
13.4.3.5 Outdoor Bell push Buttons
13.4.3.6 Terminal Blocks
13.5 Sub-Mains Electrical Switch Boards and Equipment

13.5.1 General
13.5.2 Standards
13.5.3 Technical and Installation requirements
13.5.3.1 Quality Control
13.5.3.2 General
13.5.3.3 Moulded Case Circuit Breakers (MCCB)
13.5.3.4 Miniature Circuit Breakers(MCB)
13.5.3.5 Residual Current Circuit Breaker
13.5.3.6 Busbar Chambers
13.5.3.7 Automatic Load Transfer Switches
13.5.3.8 Air Circuit Breakers Specifications
13.5.3.9 Nameplates and Lables
13.5.3.10 Other Elements
13.6 Local Electrical Panels
13.6.1 General
13.6.2 Standards
13.6.2.1 Relevant Codes and standards
13.6.3 Technical and Installation Requirements
13.6.3.1 Quality Control
13.6.3.2 Local Motor Control Panel (LMCP)
13.6.3.3 Distribution Boards
13.6.3.4 Moulded Case Circuit Breakers Boards (MCCB Boards)

13.7 Not Used


13.8 Lighting
13.8.1 General
13.8.2 Standards
13.8.3 Technical and Installation Requirements
13.8.3.1 General Requirements
13.8.3.2 Light Control System
13.8.3.3 Electro-Magnetic Compatibility
13.8.3.4 Fluorescent Luminaries (Linear & Compact Fluorescent)

13.8.3.5 High Intensity Discharge (HID) Luminaries


13.8.3.6 Installation of Interior Luminaries
13.8.3.7 Exterior Luminaries
13.8.3.8 Emergency Lighting
13.8.3.8.1 shall comply with NFPA 101, NFPA 130, BS 5266

13.8.3.8.2 Exit signs shall comply woth 415/240V UPS


13.8.3.8.3 Emergency Luminaries
13.8.3.8.4 Illuminated Emergency Exit Signs
13.8.3.8.5 Installation
13.8.3.9 Parameters for Lamps
13.8.3.10 Parameters for Control Gear
13.8.3.11 Electronic Ballast fro Fluroscent lamps
13.8.3.12 Electronic Ballast for ceramic Arc Tube Metal Halide Lamps

13.8.3.13 Low Loss Magnetic Ballasts


13.8.3.14 Not Used
13.9 Earthing System
13.9.1 General
13.9.2 Standards
13.9.3 Technical and Installation Requirements-Earthing and Bonding

13.9.3.1 General requirements


13.9.3.2 Main Earthing terminal
13.9.3.3 Main Equi-Potential Bonding Conductor
13.9.3.4 Earthing and Protective Conductor
13.9.3.5 Protective Conductors for Electrical Apparatus
13.9.3.6 Spplementary Bonding Conductor
13.9.3.7 Circuit Protective Conductor
13.9.3.8 Earthing Mats
13.9.3.9 Earth Pits and Earth Electrodes
13.9.3.10 Plate Earthing Station
13.9.3.11 Not Used
13.9.3.12 Not Used
13.9.3.13 Not Used
13.9.3.14 Platform Design
13.9.3.15 Earthing of Eletrical Services
13.9.3.16 Earthing of Fences
13.9.3.17 Earthing Cable Colour Identification
13.9.3.18 Lables for Earthing and Bonding
13.9.3.19 Testing
13.9.3.20 Additional Earthing Requirements for Signalling and
Telecommunication Systems
13.9.3.21 Tunnel wire Earth shall be 240 sqmm annealed or hard drawn multi
standed bare copper condutor

13.10 Not Used


13.10.1 Not Used
13.10.2 Not Used
13.10.3 Not Used
13.10.3.4 Test Joint
13.10.3.5 Earth Termination
13.10.3.6 Spacer Saddle
13.10.3.7 Joints in Conductors
13.10.3.8 Testing
13.11 Uninterruptable Power Supply
13.11.1 General
13.11.2 Standards
13.11.2.1 Relevant Codes and standards
13.11.3 Technical and installtion Requirement of Three Phase UPS

13.11.3.1 General Requirements


13.11.3.2 System Description
13.11.3.3 Modes of Operation
13.11.3.4 Electrical Characteristics and UPS Performance
13.11.3.5 Automatic Supply Changeover System
13.11.3.6 Rectifier/Changer
13.11.3.7 Battery System
13.11.3.8 battery Circuit Breaker
13.11.3.9 Inverter
13.11.3.10 Automatic Static Bypass Switch
13.11.3.11 External manual By-Pass Switch
13.11.3.12 Control and Indication Panels
13.11.3.12.1 Controls
13.11.3.12.2 Instrumentation
13.11.3.12.3 Indications and alarms
13.11.3.13 Diagnostics
13.11.3.14 Mouting Enclosure
13.11.3.15 Electronic components and sub-Assemblies
13.11.3.16 Electrical owrks and accessories
13.11.3.17 System Equipment and Equipment Earthing
13.11.3.18 Testing & Commissioning
13.12 Motora
13.12.1 General
13.12.2 Standards
13.12.3 technical and Installation Requirements
13.13 Diesel Generator
13.13.1 General Requirements
13.13.2 Codes and Standards
13.13.3 Rating
13.3.4 Data Missing
13.13.5 Data Missing
13.13.6 Basic Engine.
13.13.7 Air Intake System
13.13.8 Turbocharger and after-cooler system
13.13.9 Exhaust System
13.13.10 Engine Cooling System
13.13.11 Lubricating System
13.13.12 Fuel System
13.13.13 Governer
13.13.14 Starting System and Battery Charging
13.13.15 Crankcase System
13.13.16 Engine Instrumentation, alam and safety System
13.13.17 Engine drive End
13.13.18 Alternator
13.13.19 Mountins and Package Generator Set
13.13.20 Power Command Centre (PCC)
13.13.20.1.1 Metering
13.13.20.1.2 Protection
13.13.20.1.3 Operations
13.13.20.1.4 Power
13.13.20.1.5 Connections
13.13.21 Generator Control Unit (GCU)
13.13.21.1 Two units of Generators shall be provided
13.13.21.2 Major functions of the GCU
13.13.21.3 Start/Stop
13.13.21.4 Paralleling
13.13.21.5 Load Sharing
13.13.21.6 Load management
13.13.21.7 Protection
13.13.21.8 Metering
13.13.21.9 Alarms
13.13.21.10 Circuit Breakers
13.13.21.11 Neutral Controls
13.13.21.12 Data Management
13.13.22 Automatic amins Failure Operation
13.13.23 Failure to Start
13.13.24 Run-Down Sequence
13.13.25 Minimum Stopped Period
13.13.26 Protection Operations
13.13.27 Automatic Testing
13.13.28 Manual Mode
13.13.29 Acoustic Damping
13.13.30 Not used
13.13.31 Fuel Tanks
13.13.32 Fuel Filters
13.13.33 Fuel pipe work and valves
13.13.34 Fire Protection and Suppression
13.13.35 Cabling
13.13.36 Generator LV Switchboard
13.13.37 Generator Aux. Switchboard
13.14-13.21 Not Used
13.22 Pipe Work for Hydraulics and Fire Suppression System

13.22.1 General
13.22.2 Standards
13.22.3 Technical and Installation requirements
13.22.3.1 Installation general
13.22.3.2 Cleaning Procedures
13.22.3.3 Installation
13.22.3.4 Jointing-General
13.22.3.5 Gaskets
13.22.3.6 Jointing-Particular
13.22.3.7 Supprts General
13.22.3.8 Hanger Rods
13.22.3.9 Protective Coatings and Linings-General
13.22.3.10 Protective Coatings and Linings-Particular
13.22.3.11 Welding
13.22.3.12 Testing
13.22.3.12.1 At manufacturer's Premises or Testing Stations
13.22.3.12.2 At site after installation
13.22.3.13 CI, Soil, Waste, Vent Pipes
13.22.3.14 Pipe materials for Plumbing and drainage Systems

13.23 Piping Ancillaries


13.23.1 General
13.23.2 Standards
13.23.3 Technical Specifications
13.23.3.1 Globe Values
13.23.3.2 Gate Valves
13.23.3.3 Check Valves
13.23.3.4 Butterfly valve
13.23.3.5 Guage cocks
13.23.3.6 Automatic Air Vents
13.23.3.7 Strainers
13.23.3.8 Stopcocks
13.23.3.9 Sluice Valve
13.23.3.10 Pressure Reducing Valves
13.23.3.11 Saferty and Pressure Relief valves
13.23.3.12 Pressure Guages
13.23.3.13 Pipe Sleeves
13.23.3.14 Expansion Joints
13.23.3.15 Pipe anchors
13.23.3.16 Pump test Assembly
13.23.3.17 Vortex Inhibitors
13.23.3.18 Pressure Switch
13.23.3.19 Flow Switches
13.23.3.20 Drain cocks
13.24 Not used
13.25 Not used
13.26 Pumps For Water Supply/Water treatment
13.26.1 General
13.26.2 Standards
13.26.3 Technical and Installation requirements
13.26.3.1 Quality Control
13.26.3.2 Cold water supply pump sets
13.26.3.3 Drainage Sump pumps and sewage Ejector Pumps

13.26.3.4 Water Supply Pump Sets Control


13.26.3.5 Sum Pumps Control
13.26.3.6 Float Switches
13.26.3.7 Spee of Pump
13.26.3.8 Pump/Motor Couplings
13.26.3.9 maintenance Facilities
13.26.3.10 Installation
13.26.3.11 Site Testing
13.26.3.12 testing at Manufacturer's Work
13.27 Water Treatment
13.27.1 General
13.27.2 Standards
13.27.3 Quality Control
13.27.4 Technical and Installation Requirements
13.27.4.1.1 R.O Plant
13.27.4.1.2 Under drain System
13.27.4.1.3 Face Piping
13.27.4.1.4 Accessories
13.27.4.1.5 Face Piping
13.27.4.1.6 Filter Media
13.27.4.1.7 Test Kits
13.27.5 Painting and Finishes
13.27.5.1 General
13.27.5.2 Paint Finish Schedule
13.27.5.3 Materials
13.27.5.3.2 Undercoat Paint
13.27.5.3.3 Finish Paint
13.27.5.3.4 Identification Colours
13.27.5.3.5 Valves
13.27.5.3.6 Colours bands/Materials and Workmanship
13.27.5.3.7 Colours Schedule
13.28 Pumps For Fire Protection System
13.28.1 General
13.28.2 Standards
13.28.3 Technical and Installation Requirements
13.28.3.14 Pumps/Motor coupling
13.28.3.15 Pump Set Auxillary Equipment
13.28.3.16 Installation
13.28.3.17 Controls
13.28.3.17.1 FireHydrants/Hosereel System
13.28.3.17.2 Automatic Sprinkler System
13.29 Not Used
13.30 Not Used
13.31 Fire Hydrant and Hosereel System
13.31.1 General
13.31.2 Standards
13.31.3 Technical and Installation Requirements
13.31.3.1 Quality Control
13.31.3.2 Fire Hydrants
13.31.3.3 Hosereels
13.31.3.3.7 Fire Brigade Connections
13.32 Automatic Spinkler System and Water Spray System

13.32.1 General
13.32.2 Standards
13.32.3 Technical and Installation Requirements
13.32.3.1 Quality Control
13.32.3.2 Sprinkler control valve Set
13.32.3.2.4 Deluge valve
13.32.3.3.5 Sprinkler Heads
13.32.3.4 Commissioning and Testing
13.33 Miscellaneous Fire Services Equipment
13.33.1 General
13.33.2 Standards
13.32.2.1 Relevant Codes and standards
13.33.3 Technical and Installation Requirements
13.34 Automatic Inertgas Flooding System
13.34.1 General
13.34.2 Standards
13.34.3 Technical and Installation Requirements
13.34.4 Quality Control
13.34.3.2 Design Requirement
13.34.3.3 Design Calculation
13.34.3.4 System Operation and Equipment
13.34.3.5 Safety Features
13.34.3.6 Control Panel
13.34.3.7 Battery Charger and Batteries
13.34.3.8 Smoke Detectors/Heat detectors
13.34.3.9 Not used
13.34.3.10 Discharge time
13.34.3.11 Discharge Nozzle
13.34.3.12 Manual and Automatic Operational Mechanism
13.34.3.13 Gas Storage Bottle
13.34.3.14 System Of Wiring
13.34.3.15 Pipe work
13.34.3.16 Pressure trip Unit
13.34.3.17 Quality of Extinguishing Agent
13.34.4 Firetrace Liner Tube "Diect" Gas Flooring System For Electric
Panels Including AMF Panels

13.34.4.1 Scope
13.35 Fire Alam And Detection
13.35.1 General
13.35.2 Standards
13.35.3 Technical and Installation Requirements
13.35.3.1 Quality Control
13.35.3.2 Control Panel
13.35.3.3 Battery Charger and Batteries
13.35.3.4 Breakglass Units
13.35.3.5 Detectors
13.35.3.5.1 General
13.35.3.5.2 Muti Sensor Detectors
13.35.3.5.3 heat Detectors
13.35.3.5.4 Probe Type Smoke Detectors
13.35.3.5.5 Alam Bells and Circuits
13.35.3.5.6 Flashing Lights
13.35.3.7 Communiation cables
13.35.3.8 Interfacing Relay
13.35.3.9 Printers
13.35.3.10 Monitor Modules
13.35.3.11 Control modules
13.35.3.12 Fault Islator Modules
13.35.3.13 Repeater Panels
13.35.3.14 Fire Xone Mimic Panel
13.36 Voice Evacuation and Public Address System
13.36.1 Scope of Work
13.36.2 Design Concept
IONS AND TUNNELS INCLUDING VENTILATION AND AIR CONDITIONING
Air Circuit Breakers shall have panel space and equipped with Transformer Incomers,Outgoing Feede
Circuit Breakers, Remote Indication and alarm facilities, Essential/Non-Essential Bus-Section Circuit
Breaker
a) Fixed fire pumps, b) Jockey Pumps
a) Sprinkler Pumps, b) Jockey Pumps

Das könnte Ihnen auch gefallen