Beruflich Dokumente
Kultur Dokumente
improve the policy and institutional framework. Some d. The treatment of projects in
basic flaws in the EIA of a mega project namely Zero environmentally critical areas
Point Interchange Project ( ZPIP) have been is less than satisfactory.
highlighted at the end.
v. Public participation is an effective tool for the
1.2 Constraints in implementation of EIA involvement of the basic stakeholders in the
procedure in developing Countries: [6] EIA process and particularly the affected
community. But unfortunately this process is
i. EIA implementation unit is often the often neglected in developing countries. In
subsidiary of the project management units in some countries the government is unwilling to
developing countries and hence placed at very have any form of public debate or scrutiny of
priority. The relatively low status of these its development policy. In other countries,
agencies in the bureaucracy makes it difficult while there are no formal prohibitions, there
for them to have sufficient influence to ensure are no mandatory requirements for public
effective implementation of the EIA process. participation. In most countries, affected
groups do not have sufficient resources to
ii. The EIA monitoring and Management units participate in the process.
are lacking the qualified and trained human
resource. There is a shortage of qualified vi. The Environmental Impact Statement (EIS) or
environmental engineers, ecologists and Environmental Impact Report is not well
socio- economists in many parts of the standardized in the developing countries of
developing countries. Asia. The variety of formats used by these
countries makes the analysis and assessment
iii. The project managers are often expert in of the developmental projects towards
monitoring and execution of construction environmental impact more difficult. The lack
projects, with very little or no knowledge of baseline data and shortage of requisite
about the Environmental monitoring and information makes the prediction of the
management. There is a need to place the EIA potential developments on environment more
as core subject in Civil Engineering and difficult. Asian Development Banks (ADB)
Project Management curriculum. has reported the following weaknesses in the
EIA reports of the developing countries: 1)
iv. In many developing countries a time limit is assessment of ecological impacts; 2) analysis
imposed on approval of the EIA to avoid of alternatives; 3) economic analysis of
project delays in public and private sectors. environmental impacts; and 4) public
But due to limited human resource in the participation. [8]
relevant departments and subsequent pressure
on the agencies involved, the quality of the vii. Finally, the environmental management plans
review of EIA is not of the desired standards. proposed for implementation of the
While examining the EIA process in many recommendations of the EIA report were
developing countries, Ross [7] stated pointed usually inadequate both in terms of the
out the following major problems in the EIA institutional arrangements proposed and the
review: funding allocated.
a. The EIA process is seen as a
bureaucratic requirement needed to
obtain project approval in
developing countries; II. EIA PROCESS IN PAKISTAN:
In Pakistan EIA started with the promulgation of
b. Political interference determines Pakistan Environmental Protection Ordinance
the outcomes of some (PEPO) of 1983 (repealed in 1997).The National
environmental reviews; Environmental Protection Act was enacted in 1997,
which was followed by National Environmental
c. Questionable practices by public Policy in 2005. The ECNEC (Executive Committee
servants serve to discredit the of the National Economic Council) decided in 2004,
process; and that in case of development projects having
environmental implication, an environmental impact
assessment (EIA) report should be submitted along
2010 ENVIRONMENT IMPACT ASSESSMENT 49
with the project document at the time of getting parameters is collected. In developing
approval. countries like Pakistan, the non availability
The Pakistan Environmental Protection Agency is the of sufficient baseline data makes the scoping
main organization to evaluate and monitor EIA. both time consuming and expensive process.
The generic EIA process followed in Pakistan in For developmental projects, the baseline
shown in Fig.1. data about Air quality, Noise levels, water
quality, landscape and visual quality etc. are
more important considerations.
preparation. The process helps in obtaining review. The existing Environment Cells in
the local knowledge at one hand and the Planning and Development Departments
reducing conflicts during in project at provincial levels are not having the
implementation. The process must be desired human and non human resources for
inclusive, transparent, fair and credible. A the implementation of the EMP. It is
good public consultation process must required to clearly define the roles and
provide essential information, time for responsibilities of these organs and one hand
feedback of the stakeholders. and provide them the necessary equipment
and infrastructure on the other hand.
viii. Final Approval of the project:
iv. Poor implementation and enforcement of
On the basis of the public consultation and EIA
feedback process, the EIS may be revised
and resubmitted for review. In case the One can see some good EIA work at the
relevant concerns have been attended, the planning stage, but its implementation has
project may be approved for been always an uphill task due to potential
implementation. However in many case the pressure from the politicians and other
project is redesigned resubmitted for influential groups. The lack of political will
approval. and poor infrastructure at low levels makes
2.1 Problems and issues in EIA of developmental the implementation of EIA, very difficult.
Projects in Pakistan. The involvement of core stakeholders at the
Like many other countries of the South Asia, serious lowest level is essential and It has been
efforts have been made at policy and institutional proposed that the EIA may be involved
levels to develop EIA studies for developmental through the Tehsil Municipal Authority (
projects in Pakistan, however the following issues as TMA), monitored and controlled by
identified by Pak EPA (2000)[10] through Provincial EPA and evaluated by the Federal
consultation with the stakeholder, needs to be EPA for the involvement of stakeholders.
addressed:
i. Availability and reliability of baseline data: v. Weak public participation practices:
The accuracy of the anticipated impacts depends The public Participation is considered as an
on the available base line data and selection of important part of EIA process, for creating
appropriate methods and techniques for awareness and ownership amongst the
prediction of the impacts owning to the proposed community and basic stakeholders. In
developmental activities. The lack of baselines Pakistan, the public participation process is
data about the existing environment is one of the most of the time a formality and the affected
major impediments to the quality of EIA studies. populations and communities are not
To solve this problem more research is required mobilized for their participation. The media
to develop and enhance the existing database and persons, though appear in the process, but
linking of the available data for easy access to their knowledge is often is limited and they
researchers, through National Database System. cannot guide the masses about the
ii. Lack of standardization and dissemination detrimental aspects of the projects. There
of EIA procedures must be training and awareness opportunities
for these basic stakeholders and media
The procedures and methods adopted for people.
EIA are not standardized at Federal and
provincial levels and again these are not well vi. Lack of standards consultancy services for
disseminated. There is a need to use all print Environmental Assessment.
and electronic media besides internet and
other sources for data sharing. The quality of services provided by the
iii. Lack of institutional capacity, trained consultants for Environmental Assessment
human resources and shortage of non of developmental projects is usually of low
human resources: quality and lacks the desired depth. Most of
the consultancy firms in the Environmental
The exiting institutional framework of the Assessment at Pakistan are predominantly
nation building departments is not sufficient engineering and design firms registered with
to deal with the volume of EIA work and its Pakistan Engineering Council (PEC). Their
2010 ENVIRONMENT IMPACT ASSESSMENT 51
decade, as no serious efforts have ix. The quality of EIA report later
been made to solve the problem on submitted to EPA, was regarded up
rational grounds. The money to the desired by the concerned
collected from the sales of plots in authorities, however the actual
housing projects has been spent on success of the EIA would depend
relatively insignificant projects, on the compliance to various
which shows the non serious commitments exhibited in the
attitudes of the planners and CDA report and Environmental
executive management towards Management Plan (EMP) of the
solving the long standing housing EIA studies, which seems a remote
problem in the capital city of possibility for ZPIP.
Pakistan.
Some of the damages inflected to the environment by ZPIP has been shown in Fig.3.
d. Unnecessary use of concrete in pedestrian crossing. e. Visual quality of many building damaged f. Huge earth &
concrete work.
Fig 3 : The various environmental issues observed during execution of the ZPIP.
IV.CONCLUSION
resources and equipment for better compliance towards the
Sustainable built environment requires equitable use of natural commitments in the EIA for developmental projects.
resources to provide modern facilities to the people for their
socio-economic development. The developing countries
require more physical development for their economic uplift
and alleviation of poverty, but the principles of sustainable
development need to be religiously followed. Despite of
visible changes in the attitudes of legislature, policy makers,
media people and general public towards environmental
improvement, there is a need for more funding and support for
the concerned organization for the improvement in the human
54 OIDA INTERNATIONAL JOURNAL OF SUSTAINABLE DEVELOPMENT VOL. 01:04
Author Biography:
Dr.Attaullah Shah is with Allama Iqbal Open University Islamabad
440000 Pakistan (corresponding author to provide phone: +92-333-5729809 ;
fax: +92-51-9250100; e-mail: pdaiou@yahoo.com).
Dr. SAlimullah K is at Hazara University Mansehra Pakistan (e-mail:
salim41us@yahoo.com).
Dr. Manzoor Hussian Shah is at Allama Iqbal Open University Islamabad
440000 Pakistan ( e-mial: epm_3aiouedupk@yahoo.com