Beruflich Dokumente
Kultur Dokumente
Introduction - Potential
Energy calculation
Efficiency parameters
Hydrology
Data sources
Professor .Killingtveit
Energy calculation
Screening studies
Pre-Feasibility study
Detailed planning
Operation
1
Potential for Renewable energy
- Theoretical potential
- Technical potential
- Economical potential
- Head (H, m)
- Flow (q, m3/s)
- Efficiency
P = 9.81 q H (kW)
EEKV = P/(q*3600) (kWh/m3)
EEKV = 9.81* *H/3600 (kWh/m3)
E = P t (kWh)
Net head HN is always < H
q
due to friction loss in
the water conveying system
This is called Head loss
HN = H kf q2 (m)
3
P = 9.81 q (H - kf q2 ) (kW)
Hydropower potential - Different methods (GEA, IIASA)
TWh)
Technical potential at < 57.4 EJ Portion of technical potential
20 c/kWh (15 940 TWh) with cost low enough to justify a
site assessment
4 1 EJ = 277.5 TWh
Hydropower Potential A Global overview
Professor .Killingtveit
Efficiency
Hydraulic efficiency in the turbine in p.u (typically >0.9 for hydropower)
Total (station) efficiancy also include efficiency in Generator and
Transformer: tot = turb* gen* trafo
Typical values: tot = 0.93 * 0.98 * 0.99 = 0.90
Capacity factor Cf
How much is the installed capacity utilized?
1. Reconnesance (Screening)
3. Feasibility study
Professor .Killingtveit
4. Detailed design
Hydrological
5. Operation information
requirement
7
Exercise Part 1 Case Inga Falls in Congo
1 kW = 1000 W
1 MW = 1000 kW
1 GW = 1000 MW
1 kWh = 1 kW in 1 hour
Professor .Killingtveit
8
Capacity factor, Cf
Capacity factor or Load factor
The (net) capacity factor or load factor of a power plant is the ratio of the
actual output of a power plant over a period of time and its potential output if it
had operated at full nameplate capacity the entire time
To calculate the capacity factor, take the total amount of energy the plant
produced during a period of time T (EA) and divide by the amount of energy
the plant would have produced at full capacity EP = N (kW) T (h)
As of 2010, Three Gorges Dam is the largest power generating station in the
world by nameplate capacity. In 2009, not yet fully complete, it had 26 main
Professor .Killingtveit
Typical Cf
Thermal power (coal, oil, gas, ..) 0.8 0.9
Head 210 m
Head loss 10 m
Flow 1 m3/s
Efficiency 0.90
E = 1765.8 24 (kWh/day)
E = 42379 kWh/day
E = 15.47 GWh/year
Head 278 m
Head loss 5m
Flow 2 18 m3/s
Efficiency 0.92
E = 88700 24 (kWh/day)
E = 2 128 792 kWh/day
E = 777 GWh/year
Cu = EA/EP
Example:
QA = 100 Mill. m3/year
EEKV = 0.90 KWh/m3
EP = 100 * 0.90 = 90 GWh/year
If EA = 65 GWh/year
14
Hydrology Data sources
Information about hydrology can be found from various sources
and with varying degree of accuracy and cost
- Runoff maps giving average runoff per unit area (specific runoff)
- Global
- National
- Project based
- Runoff measurement
- Principles for runoff gauging
- Setting up a new station
- Rating curve calibration
- Data collection and preparation
1) Catchment boundary
16
Runoff maps (1) Example from Norway
Specific runoff 20
in l/s*km2
Professor .Killingtveit:
30
B
40
Some examples:
19 Rule of thumb: 1000 mm runoff equals 1 Mill.m3 pr km2 or 32 l/s*km average flow
A head of 400m and runoff 1000 mm/year gives a potential of 1 GWh/km2
Catchment Runoff Different measurement units:
River runoff can be measured directly, units are m3/s or l/s (small rivers)
Specific runoff is runoff pr km2, usually given as l/(s*km2) or in mm
Example:
If average annual runoff from a 10 km2 catchment is 1 m3/s then,
20
15
Average runoff, m3/s
Professor .Killingtveit
10
60 62 64 66 68 70 72 74 76 78 80 82 84 86 88 90 92 94 96 98 00 02 04
19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 19 20 20 20
22
Rough estimate of hydropower potential
If topographic maps and runoff map exist for the project area
the following steps can be taken to estimate energy potential EP:
1) Locate places for power plant intake and outlet at the topographic map
23 NB: This is the theoretical, upper limit, not considering flood spill due to variable flow!!
Production calculation in Screening studies
In a screening study a large number of possible project sites are investigated
At each site a project (power plant) is identified and the following main
parameters are investigated and computed:
700
River flow nearly always varies with time:
- During a day
600 - From day to day
- Seasonally (summer/winter)
- From year to year (Dry/Wet year)
500
As a consequence hydropower output
will be variable and only operate fully part
of the time (Assuming no regulation)
400
m3/s
Professor .Killingtveit
100
2
0 1
25 Jan-02 Feb-02 Mar-02 Apr-02 May-02 Jun-02 Jul-02 Aug-02 Sep-02 Oct-02 Nov-02 Dec-02
Selecting best project alternative (Screening)
For all identified project alternatives do:
26
Production calculation in Pre-Feasibility studies
The result of the screening process is that one or more projects
that will be taken to a Pre-feasibility study
27
The Flow Duration Curve
250
Professor .Killingtveit:
200
Discharge, m3/s
150
100
50
0
0 10 20 30 40 50 60 70 80 90 100
25 25
20 1 20
3
Vannfring m3/s
Flow
15
15
10
10
5
5
0
0 20 40 60 80 100
Professor .Killingtveit:
0
% of time exceeded
01.01.1973 01.01.1978 01.01.1983 01.01.1988 01.01.1993 01.01.1998 01.01.2003
250
100.00
Professor .Killingtveit:
200
Discharge, m3/s
Discharge, m3/s
10.00
150
1.00
100 0 10 20 30 40 50 60 70 80 90 100
500.10
0
0
0.01 10 20 30 40 50 60 70 80 90 100
31 Duration
Durationofof
exceedance (%)(%)
exceedance
Flow Duration Curve - Krinsvatn
The duration curve may be difficult to read at very low and very high flows
More detailed plots of Upper and Lower 10% duration may be very useful
200
150
100
50
0
0 1 2 3 4 5 6 7 8 9 10
Professor .Killingtveit:
Duration of exceedance (% )
2.0
1.5
1.0
0.5
0.0
32 90 91 92 93 94 95 96 97 98 99 100
Duration of exceedance (% )
Duration curve for a small hydropower plant
Duration curve for two different gauging stations
Plotted up to maximum flow in the turbine
Bjrnar - Vannfring i kraftverk ved makskapasitet 3.2 m3/s
3.500
2.180
2.907
3.000
2.500
Professor .Killingtveit:
2.000
1.500
1.000
0.500
0.000
0 10 20 30 40 50 60 70 80 90 100
33
Production calculation using duration curves
Some problems:
Professor .Killingtveit:
- Bypass/minimum flow
- Turbine minimum flow (cutoff)
- Variable efficiency in turbine/generator
- Head loss (variable, depending on flow)
5.000
Qflom
4.500 1
Qgjenn
4.000
Qforbi
3.500
Professor .Killingtveit:
3.000
2.500
2.000
3
1.500
1.000
0.500
2
0.000
0
35 0 10 20 30 40 50 60 70 80 90 100
A warning about time resolution in runoff data
Even daily (average) flow data may overestimate the real production in a small hydropower
plant. This is illustrated by the example below taken from another NVE station at Kjelstad.
18
Hourly data
Daily average
16
Weekly average
14
12
Discharge, m3/s
10
Professor .Killingtveit:
0
0
0
10
10
01
01
01
20
20
20
20
20
.2
.2
.
p.
ug
ug
ug
ul
ul
ep
ep
se
.j
.j
.a
.a
.a
.s
.s
21
31
9.
19
29
10
20
30
36
In complex systems flow data are required many places
37
Correlation with other gauging stations
Sometimes river discharge data may be available in a neighbouring
catchment (A) but not in the river where our project is located (B)
B
Professor .Killingtveit:
38
Correlation with other (nearby) gauging stations
Assuming that hydrological conditions are similar in the two catchments,
River flow in B can be computed by scaling data from A. The scaling can be
based on ratios between either:
B
Recommended method:
qB = qA QB/ QA
It is also possible to do this type of scaling using 2 or more runoff gauging stations
Can be useful if project catchment (B) is hydrologically complex (different flow
regimes within the catchment)
39
Correlation with other (nearby) gauging stations
WG2 6
40
Illustrative example
3
Date Observed flows (m /s) Computed flows (m3/s)
01-Jan 120 460 50.0 70.0 38.3 80.0 172.5 57.5
02-Jan 180 550 75.0 105.0 45.8 120.0 206.3 68.8
03-Jan 160 720 66.7 93.3 60.0 106.7 270.0 90.0
04-Jan 140 600 58.3 81.7 50.0 93.3 225.0 75.0
41 05-Jan 120 480 50.0 70.0 40.0 80.0 180.0 60.0
Summary and recommendations
Hydropower planning depends heavily on correct hydrological information
If possible use daily runoff data (weekly or mothly data less good)
42