STOD PROJECT
STOD-OTP-PMT-0808-PM-PRO-0003
Page 1 of 15
OMV (Tunesien) Production GmbH
TABLE OF CONTENTS
1 SCOPE 3
2 REFERENCE DOCUMENTS
4 RESPONSIBILITIES 3
5 CALENDAR 4
5.1 PROJECT CALENDAR 4
6 ROUTINE REPORTS 4
6.1 MONTHLY PROGRESS REPORT 4
6.2 WEEKLY PROGRESS REPORT 5
6.3 DAILY PROGRESS REPORT 5
8 PROGRESS MEETINGS 5
APPENDICES
Page 2 of 15
OMV (Tunesien) Production GmbH
1 SCOPE
The scope of this procedure is to establish guidelines and parameters for the Progress
Reporting System to be implemented by CONTRACTOR for STOD Project in order to
highlight and report to COMPANY how the Project is progressing at each month ending
during the execution of the Project.
Furthermore the procedure is aimed to define type, contents, layouts and timing for each type
of reports to be prepared and issued on routine basis as a part of the Reporting System.
This procedure is issued and revised by the Project Services Team and approved by the
Project Manager.
3 CONTRACTORS RESPONSIBILITIES
Under the leadership of the Project Control Manager, the CONTRACTORs Project Reporting
Engineer, or equivalent figure, is responsible for liaising with the CONTRACTORs Discipline
Team Leaders in order to receive all data and information as necessary to prepare the
Reports as described hereinafter.
Each CONTRACTORs Project Manager, Discipline Team Leader, the Engineering Manager,
the Procurement Manager; Construction Manager and Commissioning Manager are
responsible for providing accurate and timely data as input to the Reporting Engineer.
Page 3 of 15
OMV (Tunesien) Production GmbH
4 CALENDAR
5 ROUTINE REPORTS
Page 4 of 15
OMV (Tunesien) Production GmbH
The layout and contents of the Monthly Progress Report, as sample, are illustrated in the
Appendix 2.
Brief narratives of the activities performed by each discipline during the week
(Engineering, Procurement, Construction etc.) with highlights on specific
achievements
Areas of concern and proposed corrective actions
Activities planned for next week
List of documents and correspondence transmitted during the week
List of outstanding responses to documents and correspondence requiring response
by either COMPANY or CONTRACTOR.
The layout and contents of the Weekly Progress Report, as sample, are illustrated in the
Appendix 3.
Highlights of the day (expended man-hours, direct and indirect manpower, discipline
breakdown and brief activity description by discipline)
Major Construction Equipment employed
Materials received
Key milestones achieved
Lost time accidents
Major activities of the day
CONTRACTOR shall prepare a final Closeout report for the works, which shall be submitted
to COMPANY no later than one month after PROVISIONAL ACCEPTANCE. COMPANY will
agree format and content of this report during the later stages of the Project.
7 PROGRESS MEETINGS
CONTRACTOR shall report to and discuss with COMPANY the status of the Contract at
Weekly Progress Meetings and Monthly Progress Meetings.
Page 5 of 15
OMV (Tunesien) Production GmbH
Page 6 of 15
OMV (Tunesien) Production GmbH
Holidays
Page 7 of 15
OMV (Tunesien) Production GmbH
N.
MONTH ENDING:
Page 8 of 15
OMV (Tunesien) Production GmbH
Executive summary
1.1 HSE
1.2 Interface
1.8 Commissioning
1.12 Attachments
1.12.1 Overall progress tabulation
1.12.2 Overall project S curve
1.12.3 Overall project manpower histogram
1.12.4 Overall cost trend projection
1.12.5 Major milestones status
1.12.6 Level 2 contract master schedule
1.12.7 Key progress indicators
Page 9 of 15
OMV (Tunesien) Production GmbH
2 DETAILED REPORT
Each Detailed Report section shall contain a narrative of the major activities undertaken during the
month, planned activities for the next month and deviation from plan.
2.1 Interface
2.2 Engineering
2.2.1 Process design
2.2.2 Safety
2.2.3 Static equipment
2.2.4 Rotating equipment & Packages
2.2.5 Piping design
2.2.6 Civil engineering
2.2.7 Structural steel
2.2.8 Electrical
2.2.9 Instrumentation
2.2.10 Automation & Control
2.2.11 Attachments
2.2.11.1 Engineering document status
2.2.11.2 Engineering progress S curve
2.2.11.3 Engineering progress by discipline
Page 10 of 15
OMV (Tunesien) Production GmbH
2.7 Quality
2.7.1 Attachment
2.7.1.1Non-compliance report (NCR) status
2.8 Construction
2.8.1 Attachment
2.9 Pre-Commissioning
2.10 Commissioning
3 APPENDICES
Page 11 of 15
OMV (Tunesien) Production GmbH
Page 12 of 15
OMV (Tunesien) Production GmbH
Example of Histogram
Page 13 of 15
OMV (Tunesien) Production GmbH
N.
WEEK ENDING:
Page 14 of 15
OMV (Tunesien) Production GmbH
1. EXECUTIVE SUMMARY
This section shall contain a HSE summary (first aides, accidents, lost time incidents etc.), brief
narratives by discipline highlighting major achievements of the week, areas of attention, areas of
concern and proposed corrective action.
2. DETAILED REPORT
Each Detailed Report section shall contain as a minimum a narrative of the major activities
undertaken during the week, planned activities for the next week, deviation from plan and corrective
actions.
2.1. INTERFACE
2.6. QUALITY
2.8. COMMISSIONING