Beruflich Dokumente
Kultur Dokumente
SCOPE OF WORKS 1 1 Complete supply and installation of control system including all necessary wirings,
conduits, accessories, actuators, control relays and termination from equipment to all
control devices, sensors and dry terminals and those installed shall be compatible with
equipment, panel and unit specified in Division 16 Electrical Works. OK
SCOPE OF WORKS 1 2 Electrical works associated with the fire service installations including fuse-switches,
switch fuses, busbar chambers and starters, conduits and wiring to the pump motors,
float switches for pump control and high / low level alarms for all fire service water tanks
and the like. Those installed shall be compatible with equipment, panel and unit OK
specified.
SCOPE OF WORKS 1 3 Liaison with local fire department company and government departments to obtain all WITCO's scope shall limit only
necessary certificates and approvals for Building Permit including the completion of all to provide engineering
forms, preparation of all shop drawings and other documents for necessary submission /technical documents
purpose and the payment of any fees or charge for the submission. All the costs for the required to have building
checking and endorsement of documents by qualified persons required and tests permit.Liaison with LGU by
required by various statutory authorities shall be included in the tender price. others
SCOPE OF WORKS 1 4 Complete supply and installation of Fuel Oil System including but not limited to fuel oil
storage tank, fuel day-tank, fuel oil pump, fuel oil piping and accessories and fuel oil OK
system controls.
SCOPE OF WORKS 1 5 Preparation and submission of calculations to demonstrate the offered systems and/or By Others
equipment fully comply with statutory requirement, design requirement and technical
specification.
SCOPE OF WORKS 1 6 Complete supply and installation of painting and labelling for all pipework, fittings, and
all equipment. Colours for painting shall be selected by Owners Representative and
different colours will be selected for different items and locations. The type of paint shall OK
be approved by the Owners Representative before application
SCOPE OF WORKS 1 7 The Sub-Contractor shall be responsible for the shop drawing preparation and
submission based on the latest architectural layout, structural framing plan, and interior
design layout. Would there be any adjustment requested in order to comply with the
specification, statutory requirement, and design intent, the Sub-Contractor shall revise OK
the drawing accordingly.
SCOPE OF WORKS 1 8 The Sub-Contractor shall supply and install all sleeves for pipe works and ductworks
passing thru walls or slabs and backfill the space between the sleeves and the pipes and
ducts with approved material. OK
SCOPE OF WORKS 1 9 The Sub-Contractor shall supply and install all approved fire resistant material (i.e. By others - These items are
sealant, fire wrap, and fire damper) for pipe works and ductworks passing thru fire for structures
compartment walls or slabs to be complied with local government regulations,
guidelines and ordinances.
1 12 Testing and commissioning (from Factory Acceptance Test to Functional Acceptance Add cost of For
Test). Particular testing, commissioning and balancing works shall be done. equipment provide WITCO to
provide
1 13 Provision of 24 months Defects Liability Period or as required by GMCAC. One (1) year assistance only
1 14 Provision of 24 hours emergency call services and within 2 hours site attendance Include cost for 2 persons for 1
once received emergency call from GMCAC during the Defect Liability period. year
1 15 Training of the Building Engineering staff in operating and maintaining the Mechanical Include Cost
system.
1 16 Submission of As-Built drawings, Operation and Maintenance Manuals in 3 sets both in Include Cost
hardcopy and electronic copy to the Owner and 1 set both in hard copy and electronic
copy to the Engineer.
1 17 Provision of spare parts Not yet Included
1 18 Product submission for mechanical equipment, materials and accessories. OK
1 19 Submission of all mechanical system installation drawings and relevant document to OK
local power company and government authorities for approval and application for
Building Permit. The Sub-Contractor shall arrange and pay all costs relating to statutory
submissions, inspections and certificates for the works and also renewal of same up to
end of the Defect Liability period.
1.1 Contractor to complete and submit the following equipment suppliers schedule below in Review cited sections
accordance with the submittal requirements outlined in sections 15010, 15016 and
15050.
SECTION 15010 1.1 SUMMARY
SECTION 15010 A This Section describes general requirements that apply to all parts of the work described Review cited sections
in Division 15. Where this Section conflicts with another section of Division 15 the most
stringent requirement shall apply
SECTION 15010 B The Sub-Contractor shall be familiar with the scope of Division 16. Where the division of Review cited sections
responsibility between Division 15 and 16 for a system, piece of equipment, component
or material is ambiguous the Division 15 Sub-Contractor shall provide the item in
question and inform the Architect/Engineer of the conflict
SECTION 15010 C The drawings are diagrammatic and are a graphic representation of the Contract Review cited sections
Requirements showing the general arrangement of all piping, ductwork, conduit and
equipment
SECTION 15010 D No measurements shall be scaled from the Documents and used as a definite dimension OK
for layout or fitting work in place. All dimensions should be measured from the Architects
drawings and verified in the field. The Sub-Contractor shall verify all dimensions and
sizes prior to installation and confirm that equipment fits dimensionally in locations
shown in the Documents and existing as-built drawings. The Sub- Contractor shall take
into consideration the space & access clearances required by the mechanical
equipments.
SECTION 15010 The Sub-Contractor shall provide a complete mechanical system in full working order. ???? MBV to draft comment
The Sub-Contractor shall examine the Documents at the time of the bid and notify the
Architect/Engineer in writing of any and all discrepancies. Unless a discrepancy is
notified during the bid period the Sub-Contractor shall provide a system in fully working
order including all equipment, accessories and attachments necessary for the complete
operation of the mechanical system whether shown in the documents or not.
1.6 SUBMITTALS
A This section describes general requirements for product submittals, and shop drawings.
For additional specific requirements refer to the individual sections of Division 15.
B Submittal Schedule OK
1. Within one month of the award of the contract, the Sub-Contractor shall prepare a
schedule of submittals to be made. All submittals shall be identified by description,
specification section and drawing number. The schedule shall indicate the manufacturer
to be proposed for each product and shall clearly indicate where a substitution will be
requested. The schedule shall indicate dates on which the submittals will be forwarded
to the Architect/Engineer.
2. The submittal schedule shall include a minimum of ten days for each
Architect/Engineer review and shall allow for a minimum of one re-submittal of each
item.
3. Failure to submit shop drawings in ample time for review shall not entitle the Sub-
Contractor to an extension on contract time.
4. The Sub-Contractor shall be responsible for equipment ordered and/or installed prior
to receipt of submittals returned bearing the Architect/Engineers stamp of "No
Exceptions Taken". Corrections or modifications to equipment as noted on returned
submittals shall be at the Sub-Contractor's sole expense without additional
compensation.
C 1. Provide submittals for all products and materials specified in Division 15. OK
2. Product submittals shall contain the following data as a minimum:
a. Manufacturer's drawings and performance data on all equipment.
b. Dimensioned drawings showing all required openings, supports and suspension
systems.
c. Equipment wiring diagrams.
d. Field installation diagrams.
e. Controls diagrams including diagrams and layout, software packages and control
wiring diagrams.
f. Compliance with all listings (UL, ETL, etc).
g. Acceptance certificates from inspecting agencies.
h. Manufacturers performance tests on equipment.
3. Submittals shall conform to the following:
a. Submit complete sets of product data only.
b. Submit pertinent catalog and performance data sheets only. Do not submit entire
catalogs.
c. Mark the exact equipment item and data on each sheet.
d. Each group of material shall be submitted in tabulated form with separate index
divider for each product/equipment by mechanical section designation.
e. Incomplete submittals and submittals not in compliance with the above requirements
shall be returned without action, and re-submittal shall be required.
f. Where current limiting devices are specified, submit technical data to substantiate
adequate protection of equipment downstream. Submittals shall not be reviewed
without supporting calculations and data.
D Shop Drawings
The following shop drawings shall be submitted:
a. Dimensioned drawings of all equipment rooms at 1:20 scale. Drawings shall include
exact equipment locations, bases, pads and inertia bases.
b. Color coordination drawings showing all Division 15 trades on the same drawing at
1:50 scale. Each trade should be in a separate color.
c. Sketches as requested by the Architect/Engineer during the submittal process to
demonstrate specific installation and coordination details.
d. All shop drawings shall be drawn in the latest version of AutoCAD or Revit 2014; or an
approved software of similar quality.
E Format of Submittals
1 The Sub-Contractor shall submit one hardcopy and one electronic copy in pdf format to OK
the Architect/Engineer for review.
2 The Architect/Engineer shall return one copy to the Contractor. The Contractor shall OK
make additional copies as needed for Sub-Contractors.
3 Each submittal shall include a 4x8 space for the Architect/Engineers review stamp and OK
general remarks.
Each submission shall be made under the Specifications Section Number it has been OK
specified under or drawing and detail number and reference number appearing on
Equipment Schedules.
F Architect/Engineers Electronic Files
1 Electronic files of the documents shall be available to the Sub-Contractor to assist in OK
preparing submittals subject to the following caveats:
a. Provision of electronic files does not release the Sub-Contractor from the requirements
of the Contract Documents regarding coordination, submittals or any other issues
outlined in the Contract Documents.
b. The official Contract Documents are the hard copy versions, not the electronic files.
c. The Sub-Contractor is responsible for all information extracted or inferred from the
electronic files.
d. Submission of the electronic file unchanged as a shop drawing will be rejected without
review.
e. These documents are provided only as a convenience to the Sub- Contractor. The
Architect/Engineer is under no obligation to provide updated drawings during the
Construction Phase.
2 The Architect/Engineer will make electronic files available at the time of the Construction OK
Set. Electronic files may be made available to the Sub-Contractor at other times by
mutual agreement.
G Architect/Engineers Review:
1 The Architect/Engineer shall review submittals for overall conformance with the design OK
intent described in the Documents. The Architect/Engineer shall not review the
documents for coordination.
2 The Architect/Engineers No Exception Taken stamp does not relieve the Sub- OK
Contractor of their responsibility to comply with all aspects of the Contract Documents
or prohibit the Architect/Engineer from making further comments at a later time.
1.8 SUBSTITUTIONS
A For any piece of equipment or material the specified product is that shown on the OK
equipment schedules or the first named manufacturer in the applicable specification
section. All other manufacturers including others listed in the Specifications are
considered substitutions and must meet the requirements of this Section.
C Only one substitution proposal shall be made for each product or material unless OK
otherwise permitted by the Architect/Engineer. If the first proposed substitution is
rejected submit the specified product.
E Any additional work required by other trades as a result of a substitution shall be the OK
Sub-Contractor responsibility.
F When a substitution is proposed, the Sub-Contractor shall be responsible to ensure that OK
the performance and quality of the scheduled or specified equipment is met whether it
requires additional accessories or not.
B Identification OK
1. Identify materials and equipment delivered to Site to permit checking against
approved materials list and reviewed Shop Drawings.
C Loss or Damage OK
1. The Sub-Contractor shall replace lost or damaged materials and equipment with new
at no increase in Contract Sum.
D Storage OK
1. All stock piled piping shall be placed on dunnage, and protected from weather and
from entry of foreign material.
2. All stored materials and equipment shall be carefully inspected prior to installation
and replaced with new material or equipment if found to be damaged or corroded.
3. Completely cover motors and other moving machinery to protect from dirt and water
during construction.
4. Cap all openings in pipe daily to protect against entry by foreign matter.
B The fact that the defects may have previously been overlooked by the OK
Architect/Engineer shall not constitute total or partial acceptance or grounds for
additional payment for corrective work.
1.11 COOPERATION BETWEEN TRADES
A General OK
1. Cooperate with all other Divisions performing work on this project as necessary to
achieve a complete neatly fitted installation for each condition. Consult the Drawings
and Specifications to determine nature and extent of work specified in other Divisions
which adjoins or attaches to the work of this Division. Confer with other Divisions at the
site to coordinate this work with theirs in view of job conditions to the end that
interferences may be eliminated and that maximum head room and clearance may be
obtained. In the event that interferences develop, the Architect/Engineer's decision will
be final as to which Division shall relocate its work and no additional compensation will
be allowed for the moving of piping, ductwork, conduit or equipment to clear such
interferences.
2. Provide templates, information and instructions to other divisions to properly locate
holes and openings to be cut or provide.
3. For Testing and Balancing of the system, ensure full co-ordination between the Sub-
Contractor and all other Trades to achieve access to all system components including
leaving wall/ceiling sections down for access.
4. Full co-ordination to ensure the system is commissioned in accordance with the
requirements of the contract documents.
B The Sub-Contractor shall be responsible for the coordination of the mechanical ducting OK
and piping distribution with the lighting, conduit, cable tray and structural members.
B The Sub-Contractor shall be responsible for being aware of the nature and arrangement OK
of the materials and construction to which the work attaches or passes through.
C Manufacturer's representative shall review the overall system design relative to the OK
proper application of his equipment in the particular system. He shall note conduit,
wiring, control, location, and other relevant relationships, and furnish appurtenances
necessary for satisfactory operation.
D Before final payment is issued, the manufacturer's representative shall submit to the OK
Owner's Representative, a signed statement certifying to their inspection and the
equipment is properly installed and ready for operation
B Underground utility services, both inside and outside of buildings, shall be dimensioned OK
from permanent structures or bench marks. Utility services outside buildings shall show
the depth of burial with reference to the finished ground floor elevation.
C Immediately upon commencing work on the project, obtain a set of blue line prints of OK
the contract drawings pertaining to this branch of work. This set of drawings shall be
kept on the project site at all times for use in recording "record" conditions.
D At the completion of the project obtain from the Architect/Engineer an electronic copy of OK
the Contract Drawings relating to the work. Amend the drawing files to record conditions
as outlined above to reflect the as built condition. Reference to RFIs or Change Orders
in lieu of drawing the exact change will not be acceptable.
E Submit one copy of the record drawings to the Architect/Engineer for approval. The OK
accuracy of record drawings shall be certified by the signature of the Sub-Contractor and
shall be stamped or otherwise identified as record drawings.
F Each trade shall submit record copies of their respective shop drawings as part of the OK
project closeout. These record copies shall indicate as-built conditions and shall show all
work installed by that trade. All elements shall be dimensioned from grid lines or bench
marks and all elevations shall be noted. Construction notes such as component number
or conflict notes shall be removed and the drawings shall clearly be noted in the title
block as being as-built drawings.
C Training: Furnish the Owner with five 8-hour days of training/and instruction to the OK provide cost
Owner's designated personnel. The training and instruction sessions shall be conducted
at the Owner's convenience and shall be video recorded.
PART 2 - PRODUCTS
2.1 MATERIALS
A All materials shall be new, clean, undamaged and free of corrosion at the time of OK
handover to the Owner. Any damaged materials or equipment shall be replaced with
new.
B All materials shall be approved for use by local authorities. OK
C Material specified to meet local approved listing agency or trade standards shall include OK
manufacturer's or vendor's certification of conformance.
D No materials or products shall be provided which are not approved for use in the City OK
where the project is located.
2.2 FLAME SPREAD & SMOKE DEVELOPED PROPERTIES OF MATERIALS
A Materials and adhesives used throughout the mechanical systems shall have a flame OK -take note
spread rating not over 25 without evidence of continued combustion and with a smoke
developed rating not higher than 50.
B Flame Spread Rating and "Smoke Developed Rating" shall be as determined by the OK -take note
"method of test of surface burning characteristics of building materials, NFPA no. 244,
ASTM E84, Underwriters' Laboratories, Inc., Standard." Such materials are listed in the
Underwriters' Laboratories, Inc., "Building Materials List" under the heading "Hazard
Classification (Fire)."
B Galvanized pipework shall not be used for fuel oil distribution. OK - take note
1.2 RELATED SECTIONS
A Consult all other Sections, determine the extent and character of related work and OK - take note
properly coordinated work specified herein with that specified elsewhere to produce a
complete installation.
1.3 DEFINITIONS
A. AST: Aboveground storage tank OK
B. Exposed, Interior Installations: Exposed to view indoors. Examples include finished
occupied spaces and mechanical equipment rooms.
C. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor
ambient temperatures and weather conditions. Examples include rooftop locations.
D. Finished Spaces: Spaces other than mechanical and electrical equipment rooms,
furred spaces, pipe and duct shafts, unheated spaces immediately below roof, spaces
above ceilings, unexcavated spaces, crawlspaces, and tunnels.
E. FPM: Vinylidene fluoride-hexafluoropropylene copolymer rubber.
F. FRP: Glass-fiber-reinforced plastic.
G. UST: Underground storage tank.
1.5 SUBMITTALS
A Product Data: For each type of product indicated. Include construction details, material OK
descriptions, and dimensions of individual components and profiles. Also include, where
applicable, rated capacities, operating characteristics, electrical characteristics, and
furnished specialties and accessories.
1. Piping specialties.
2. Valves: Include pressure rating, capacity, settings, and electrical connection data of
selected models.
3. Each type and size of fuel-oil storage tank. Indicate dimensions, weights, loads,
components, and location and size of each field connection.
4. Fuel-oil storage tank accessories.
5. Fuel-oil storage tank piping specialties.
6. Fuel-oil storage tank pumps.
7. Fuel-oil transfer pumps.
8. Fuel maintenance system.
9. Liquid-level gage system.
10. Leak-detection and monitoring system.
B Shop Drawings: For facility fuel-oil piping layout. Include plans, piping layout and OK
elevations, sections, and details for fabrication of pipe anchors, hangers, supports for
multiple pipes, alignment guides, expansion joints and loops, and attachments of the
same to building structure. Detail location of anchors, alignment guides, and expansion
joints and loops.
1. Shop Drawing Scale: 1:50.
2. For fuel-oil storage tanks and pumps, include details of supports and anchors.
C Delegated-Design Submittal: For fuel-oil piping and equipment indicated to comply with Item 1 & 2 not our scope
performance requirements and design criteria, including analysis data signed and sealed
by the qualified professional engineer responsible for their preparation.
1. Detail fabrication and assembly of anchors and seismic restraints.
2. Design Calculations: Calculate requirements for selecting seismic restraints.
3. Detail fabrication and assembly of pipe anchors, hangers, supports for multiple pipes,
and attachments of the same to building structure.
4. Qualification Data: For qualified professional engineer.
5. Brazing certificates.
6. Welding certificates.
7. Field quality-control reports.
8. Warranty
D Comply with ASME B31.9, "Building Services Piping," for fuel-oil piping materials, OK
installation, testing, and inspecting.
E Comply with requirements of the local authorities. Include recording of fuel-oil storage OK
tanks and monitoring of tanks and piping.
PART 2 - PRODUCTS
2.1 PIPES, TUBES AND FITTINGS
A See Part 3 piping schedule articles for where pipes, tubes, fittings, and joining materials OK
are applied in various services.
B Steel Pipe: ASTM A 53/A 53M, black steel, Schedule 40, Type E or S, Grade B. OK
1. Malleable-Iron Threaded Fittings: ASME B16.3, Class 150, standard pattern.
2. Unions: ASME B16.39, Class 150, malleable iron with brass-to-iron seat, ground joint,
and threaded ends.
3. Forged-Steel Flanges and Flanged Fittings: ASME B16.5, minimum Class 150, including
bolts, nuts, and gaskets of the following material group, end connections, and facings:
a. End Connections: Threaded or butt welding to match pipe.
b. Lapped Face: Not permitted underground.
c. Gasket Materials: Asbestos free, ASME B16.20 metallic, or ASME B16.21 nonmetallic,
gaskets compatible with fuel oil.
d. Bolts and Nuts: ASME B18.2.1, cadmium-plated steel.
4. Protective Coating for Underground Piping: Factory-applied, three-layer coating of
epoxy, adhesive, and PE.
a. Joint Cover Kits: Epoxy paint, adhesive, and heat-shrink PE sleeves.
B Nonmetallic Connectors OK
1. Listed and labeled for underground applications acceptable to local authorities.
2. PFTE bellows with woven, flexible, bronze or stainless-steel, wire-reinforcing
protective jacket.
3. Minimum Operating Pressure: 150 psig (1035 kPa).
4. End Connections: Socket, flanged, or threaded end to match connected piping.
5. Maximum Length: 750 mm
C Y-Pattern Strainers OK
1. Body: ASTM A 126, Class B, cast iron with bolted cover and bottom drain connection.
2. End Connections: Threaded ends for NPS 2 (DN 50) and smaller; flanged ends for NPS
2-1/2 (DN 65) and larger.
3. Strainer Screen: [60] [80]-mesh startup strainer, and perforated stainless-steel basket
with 50 percent free area.
4. CWP Rating: 125 psig (860 kPa).
E Joining Materials OK
1. Joint Compound and Tape: Suitable for fuel oil.
2. Welding Filler Metals: Comply with AWS D10.12/D10.12M for welding materials
appropriate for wall thickness and chemical analysis of steel pipe being welded.
3. Brazing Filler Metals: Alloy with melting point greater than 1000 deg F (540 deg C)
complying with AWS A5.8/A5.8M. Brazing alloys containing more than
0.05 percent phosphorus are prohibited.
B General Requirements for Metallic Valves, NPS 2 (DN 50) and Smaller for Liquid Service: OK
Comply with approved listing agency requirement.
1. CWP Rating: 125 psig (860 kPa).
2. Threaded Ends: Comply with ASME B1.20.1.
3. Dryseal Threads on Flare Ends: Comply with ASME B1.20.3.
4. Tamperproof Feature: Locking feature for valves indicated in the valve schedule.
5. Service Mark: Initials "WOG" shall be permanently marked on valve body.
C General Requirements for Metallic Valves, NPS 2-1/2 (DN 65) and Larger: Comply with OK
approved listing agency requirement.
1. CWP Rating: 125 psig (860 kPa).
2. Flanged Ends: Comply with ASME B16.5 for steel flanges.
3. Tamperproof Feature: Locking feature for valves indicated in the valve schedule.
4. Service Mark: Initials "WOG" shall be permanently marked on valve body.
D Two-Piece, Full-Port, Bronze Ball Valves with Bronze Trim: MSS SP-110. OK
1. Body: Bronze, complying with ASTM B 584.
2. Ball: Chrome-plated bronze.
3. Stem: Bronze; blowout proof.
4. Seats: Reinforced TFE; blowout proof.
5. Packing: Threaded-body packnut design with adjustable-stem packing.
6. Ends: Threaded, flared, or socket as indicated in the valve schedule.
7. CWP Rating: 600 psig (4140 kPa).
8. Service Mark: Initials "WOG" shall be permanently marked on valve body.
Mechanical Leak Detector: Comply with approved listing agency requirement. Exclude
1. Listed and labeled for fuel-oil service by an NRTL acceptable to authorities having
jurisdiction.
2. Body: ASTM A 126, cast iron.
3. O-Rings: Elastomeric compatible with fuel oil.
4. Piston and Stem Seals: PTFE.
5. Stem and Spring: Stainless steel.
6. Piston Cylinder: Burnished brass.
7. Indicated Leak Rate: Maximum 3 gph (3 mL/s) at 10 psig (69 kPa).
8. Leak Indication: Reduced flow.
D Motor: Comply with NEMA designation, temperature rating, service factor, enclosure Exclude
type, and efficiency requirements for motors in section 15158 Motor and Drives.
1. Motor Sizes: Minimum size as indicated. If not indicated, large enough so driven load
will not require motor to operate in service factor range above 1.0.
2. Controllers, Electrical Devices, and Wiring: Comply with requirements for electrical
devices and connections specified in electrical Sections.
E Piping Furnished with Pumps: Steel with ferrous fittings and threaded or welded joints.
F Strainers Furnished with Pumps: Duplex, basket type with corrosion-resistant-metal- Exclude
screen baskets.
1. Capacities and Characteristics:
2. Number of Stages: 1.
3. Capacity (Each Pump): 1 L/s.
4. Inlet Vacuum: 65 kPa.
5. Discharge Pressure: 90 kPa.
6. Electrical Characteristics (Pump Set):
a. Volts: 220 V.
b. Phase: Single.
c. Hertz: 60.
B Annunciator Panel: With visual and audible, high-tank-level and low-tank-level alarms, Accuracy to be defined by Owner Exclude
fuel indicator with registration in liters, and overfill alarm. Include gage volume range
that covers fuel-oil storage capacity.
B A 100 mesh metal screen flanged strainer shall be fitted upstream of the meter, with Exclude
inlet and outlet valves and full-bore lockable valved by-pass.
C Pumps that are not part of an appliance shall be of a positive-displacement type. The Exclude
pump shall automatically shut off the supply when not in operation. Pumps shall be
listed and labeled in accordance with approved listing agency requirement.
3.9 LIQUID-LEVEL GAGE SYSTEM INSTALLATION
Install liquid-level gage system. Locate panel inside building where indicated. Control room. To be Exclude
confirmed
3.10 LEAK-DETECTION AND MONITORING SYSTEM INSTALLATION
Install leak-detection and monitoring system. Install alarm panel inside building where Exclude
indicated.
1. Double-Wall, Fuel-Oil Storage Tanks: Install probes or use factory-installed integral
probes in interstitial space.
2. Single-Wall, Fuel-Oil Storage Tanks: Install probes as indicated.
3. Double-Containment, Fuel-Oil Piping: Install leak-detection sensor cable probes in
interstitial space of double-containment piping.
4. Install liquid-level gage.
Spec. Section Materials / Equipment Recommended Bid Manufacturer / Supplier Offered Manufacturer
15062 Concrete Inserts and Anchors Hilti fastening systems
Phillips Red Head self- drilling anchors
Or equal and approved
15062 Escutcheons Grinnell
Beaton-Corbin
or equal and approved
15062 Pipe sleeve backfill material Metraflex
Metraseal
Fabricated seals
Thunderline Link-Seal
Or equal and approved
15062 Floor penetrations and fire and Pipe Shields
smoke rated wall penetrations ProSet
assembly Or equal and approved
15075 Pipe Identification Markers Brady Perma-Code
Setmark Type "SNA"
Or equal and approved
Pipe expansion joints Hyspan
Metraflex
Metraloop
Megaflex
Microflex
Flexonics
Or equal and approved
Flexible Piping Braided Hose Milmac,
Metraloop
Metraflex
Megaflex
Microflex
Flexonics
Or equal and approved
Expansion Joint for Equipment Mason
Connection Starpipe
Metraflex
Or equal and approved
Expansion Joint for Equipment Mason
Connection Starpipe
Metraflex
Or equal and approved
Pipe Guides Pipe Support Ltd.
Logstor
Carpenter Paterson Ltd.
Precision Pipe Support
QPS Ltd
Or equal and approved
Steel Pipes Supreme Steel Pipe Corp
Mayer Steel Pipe Corp
RNW Pacific Pipes
Or equal and approved
Delivery Time
Spec. Section Materials / Equipment Recommended Bid Manufacturer / Supplier
Pump Motor ABB
AEG
Brook Crompton
Mitsubishi
Siemens
Toshiba
Vem
Relief Valves BERMAD
CLA-VAL
Kunkle
OCV
Watts Regulator
Zurn
Kenned
Central Spraysafe