Sie sind auf Seite 1von 8

Offshore South East Asia 82 Conference PRODUCTION II

9 - 12 February, Singapore
SESSION

Erawan Field Project


ManageDlent
by R A Nordquist, Union Oil Co of Thailand
Union onCompany, along with its co-venturer South East Asia Petroleum Exploration Company,
were "on time" and within the original cost estimate upon start-up of gas production facilities in
Erawan Field, Gulf of Thailand. 1bis paper analyzes the planning and strategies used to achieve this
task.

Introduction Project Objectives


Union Oil Company involvement in Thailand dates back to The project had three primary objectives:
September 20, 1962 when Union signed the first agreement with the 1. Production to start on or before the contract date of October 1,
Royal Department of Mines to explore for petroleum in Thai- 1981.
land. Union Oil's first offshore exploratory well drilled in the Gulf
of Thailand in 1973 was the discovery well for the Erawan Gas 2, Facilities cost to be consistent with the estimate used in project
Field. economics.

Erawan Field is located in the central portion of the Gulf of Thai- 3. Field facilities were to be efficient and consistent with establish-
land in waters 64 meters deep, and 193 kms. east of the Malay l!d industry safety and environmental codes.
Peninsula and 550 kms. south of Bangkok (see Plate 1). The field is It was obvious that in order to achieve the "startup'" goal" it would
a north..gouth-trending anticline with east-west structural reversal be necessary for drilling to start January 1980, and that
of approximately 610 meters, and is approximately 28 kms. long simultaneous drilling, construction and production activities would
and 8 kms. wide. have to occur.
A gas sales agreement was signed with the Thai government in The timing for installation of a well platfonn and a process facility is
September 1978. The agreement required drilling the necessary not simultaneous. Our experience has been that after receipt of
delineation wells to confinn a minimum of 1.0 trillion cubic feet of drawings, a well platfonn can be fabricated, transported and in-
gas reserves. By April 1979, sufficient reserves had been confinned stalled in nine months in South East Asia. However, procurement
so that development of the project could be initiated. The gas con of critical process items can take more than 14 months. Drilling,
tract date for starting production was October 1, 1981 with best production and construction activities interfere with each other.
efforts by both parties to produce and receive production 90 days Muds and other corrosive materials from drilling operations are
prior to the contract date. hard on delicate process equipment and instrumentation. These
The government of Thailand installed a 425-km, 34-inch submarine timing and intetface problems were solved by separating the weU
pipeline from the Erawan Field to onshore power generation plants platforms from the process platforms. The well platfonns were
near Bangkok. In addition to power generation, other possible installed first so that drilling could start as soon as possible. The
future uses for the gas are a gas separation plant, ethylene cracking wells are drilled from the well platforms with drilling tender
plant, a fertilizer complex, a soda ash plant, and a sponge iron assistance.
plant. Natural gas has a key role in reducing Thailand's future The project was analyzed to identify the cost sensitive variables that
dependence on imported energy. would require close control to stay within the budget and minimize
contractor overruns. These variables are:
The natural gas from this project is sold to the Petroleum Authority
of Thailand (PTI) on an energy unit (BTU) price basis. 1. Preparation of bid documents,
Project Definition 2. Continuity between the onshore and offshore work,
The Erawan Field surface facilities consist of: (See Plate 2) 3. Qualifications of vendors and contractors,
Five well platfonns, each with the capacity for 12 wells. 4. Governmental regulations and permits,
Four remote process platfonns bridge-connected to the well 5. 10b..gite inspection,
platfonns with the necessary equipment to separate the gas well 6. Changes in plans and scope of work,
stream and dehydrate the gas.
7. Adherence to work sched ules,
One central process platfonns (CPP) to receive production
from each remote well I process platfonn. CPP's support equip- 8. Standardization of facilities,
ment includes condensate stabilization, gas dehydration, gas 9. Competitiveness of bids.
compression and metering facilities for gas custody transfer to
PTl';, ':":"i!1';~ pipeline. Project Environment
One storage barge which receives stabilized condensate from The Petroleum Act of 1971 vested powers in a Petroleum Commit-
'CPP' and has equipment un board to meter and pump the tee to advise, render opinions and interpretations of regulations,
condensate into shuttle tankers that moor alongside. and secure duty exemptions for imported materials and equipment.
This effective policy resulted in no lost time to the Company or its
One 122man living quarters with satellite communications contractors with Customs clearances or any delays with the entry .
equipment and recreation facilities. and departure of personnel and marine equipment.
One flare structure. Project Schedule
- Field pipeline gathering system. A work schedule was prepared working backwards from the gas
contract date of October 1, 1981 (see Plate 3). The work schedule 3. Fire and Safety.
was analyzed for compression to assure timely completion.
4. Legal.
Engineering and design time was compressed by the following
policies: Development and training of 'Thai Nationals was considered an
essential part of the resource development for operation of the
1. Company representatives at the engineering contractor site Erawan Field. A Human Resources Department was established in
were given authority to approve all drawings and technical 1979, a training center built, and 1bai Nationals recruited and
specifications. This "on the spot" approval eliminated time trained to work on the facilities, both onshore and offshore. The
required to seek Company approvals elsewhere. This primary objective of the training program is to develop a skilled
expedited sequential type design work where step--by-step work force to supplement' and eventually replace most of the
Company approvals were required. expatriates.
2. Standardization of design. Singapore was selected as the staging area for the project because of
- One basic design for five well platforms, its proximity to the job site and its excellent port and Customs fad
- One basic design for four production jackets, lities. The excellent communication facilities and access to vendor
- One basic design for four process decks. representatives certainly contributed to the project execution and
time compression.
The basic design for the well platforms had to be modified
only for water depths. The environmental and drilling rig Contracting Plan
loads criteria remained the same. Similarly. the basic design
for the production jackets was modified only for water depths The contracting plan for the Erawan project was to obtain
and pipeline riser clamp locations. The process deck layouts competitive lump sum bids to control expenditures and to minimize
were identical. The custom engineering items such as uncertainty in the final cost of the project. The plan included early
separators, glycol sklds, power generator paCKages, etc., were selection of a derrick barge to obtain a guaranteed time slot and
all laid out and designed to identical criteria. This standardisa- maximum allowable lifting weights. Thus, the design was compati-
tion resulted in most drawings requiring only title changes, ble with the selected derrick barge crane capacities.
thereby reducing the design manhours.
The project was divided into lump sum bid categories to assure
3. Spool drawings and material take-offs. continuity of work and to fit contractor specilities. These categories
were: jackets, process decks, tanker loading facilities, heavy lifts.
The design contractor used the time while the bids were being living quarters building and pipe laying.
solicited and evaluated, to prepare spool drawings and
material take-offs. The contracts were written to include Contractors interested in bidding were required to submit quali-
dimensional checks, material take-offs and minor piping fying credentials. Information required financial reports, equip-
changes as part of the contractors' scope of work. As a result. ment specifications, yard capabilities, organizational charts, work
the contractors were able to order most of the material shortly experiences and completion dates. Credentials were examined by
after contract awards. the project team, references were checked and only prequalified
contractors were allowed to bid.
Bid review and award time compression was more difficult to
achieve. Technical and economic bid reviews were accomplished in
the Home Office so that negotiations and awards could be Material Procurement Plan
completed at "one spot." As a result, most of the contract awards
were made within seven days after receipt. The procurement plan required identification and priority purchase
of all long-lead items and custom engineering items.
Oose on-site surveillance at the shop and floor level of vendors
supplying material was maintained for early signs of slippage so The longest lead items required 14 months for delivery to the
that corrective actions such as longer work hours, more manpower, fabrication site. Last minute material substitutions were avoided
air freight, etc. could be taken. This action did not always result in and uniformity of materials throughout the field was ensured by
faster material procurement, but did prevent unexpected vendor early procurement of long~lead items.
delays. The custom engineering items such as separators, condensate
The fabrication and installation work schedule time compression heaters, glycol systems, power generators were all skid~mounted
was obtained by scheduling a continuous work program with flexi with inter-connecting piping and instrumentation. Skid work was
bility of alternate work in the event that bad weather or other spread out among several shops for simultaneous construction to
meet the delivery dates.
intenuptions prevented performing the scheduled work.
High cost items were furnished by the Company. These items such
The start-up of facilities was expedited by early selection of the
operating personnel. The start-up and operation manuals were as cranes, water makers power generators, etc. were Company
provided several months prior to production start-up for training preferences and were off-the-shelf items.
and orientation sessions. Vendors were called in to explain their Union required full documentation of all materials purchased for
equipment. This compressed start-up time by having operating .he project. A frequent problem of material furnished by the
personnel familiar with the equipment and the process system. contractors is inadequate documentation. The contractor is
Resource Requirements frequently considered to be the end buyer and if warmty problems
occur, the Company must work through the contractor to obtain
Union elected to manage the project with Company personnel service. On this project, Union procured all major equipment with
rather than to employ a project management contractor. Company instructions to ensure that vendors provided complete dossiers. The
personnel were eager to achieve the project goals and were familiar dossiers were compiled in hardbound job books and distributed to
with Company policies. Staffing of the project team came from the all the maintenance and purchasing centers. This concept ensured
Operations Group of the Company. After completion of the effective communication between centers to obtain maintenance
project, most of the personnel were transferred into Erawan Field replacements and spare parts. All vendors also submitted
operations. recommended lists of spare parts for commissioning and first year
The following Company support groups were used to complement operation.
and subsititute for activities which can be performed by During the project life, a bi-monthly material status report was
contractors: issued to all project control centers (see Plate 4). To make this
1. Purchasing, report accurate, it was necessary to make shop visits. It was
frequently found that vendor information obtained over the
2. Research, telephone was not as accurate as a job-site visit. lltis intelligence
gathering system provided an early warning so that management president. Force account work could only be initiated by prior
could react to a schedule or quality control problem in time for written instructions. The intention was to hold the plan and reduce
corrective action. costly changes.
Operations Planning
Quality Assurance Plan
Commissioning and start-up of facilities was the responsibility of
The Company retained the right to inspect all materials, equipment the Operations! Production group, with technical assistance
and workmanship incorporated into the work. Contractors were provided by vendors of the major equipment. Start-up and
required to replace or repair at no cost to the Company any operating manuals were prepared several months prior to start-up
material or workmanship found to be not in accordance with the for review by the operating personnel. Involvement of production
contract. and maintenance personnel early in the project through the
fabrication site visits and work as quality control inspectors made
A certifying agent was selected to classify all offshore structures and
these personnel familiar with the operation and the remover very
pressure vessels. This provided a third party review of the design
easy. The Thai Nationals had all received intensive English
and surveillance during fabrication and installation.
language training for effective communication.
Company personnel were at all major fabrication sites as
Contingency Plans
engineering representatives. Contract inspectors were hired to
provide technical expertise for welding, civil, electrical and instru The contingency plans in the project centered around the lifting
mentation inspection. schedule. Alternate work was scheduled so that the arrival of the
living quarters or the deck modules did not result in lost time for the
Safety drrick barge. As it turned out. the living quarters and central
Safety is a line management responsibility. Offsite contractor's process decks did arrive late, but the alternate work of setting the
scope of work included working in a safe and prudent manner. On mooring system resulted in no lost time for the project.
site safety was the Company responsibility, a complex situation
with simultaneous drilling, production and construction. Post-Project Reviews
Setting anchors was a major problem interfacing drilling tenders, Preliminary reports indicate that a wide spectrum of . . in-house ..
construction barges. platform and pipelines (see Plate 5). It was quality control exists among contractors in Southeast Asia.
necessary to employ a fulltime survey vessel to preplot anchor Standardization of design has its advantages. but an error, if made,
locations and confirm locations before anchors were dropped to is multiplied by the number of units installed. Experienced
ensure that pipelines were not damaged during barge moves. personnel are spread thin in the industry and the contractors'
organizations and resumes have to be carefully scrutinized prior to
When construction activities began to interface with drilling and
production activities, a Company fire permit system was initiated. bid awards.
All parties would meet prior to starting work to discuss the Conclusions
activities and the interface problems from :l safety standpoint. As a
The decision was made to manage the project with Company
result of these meetings and the resultant preventivt: measures, no
serious injures or fires occured during the construction phase of the personnel and utilize existing Company support departments to the
maximum. It was confirmed that lump sum work tends to control
project.
expenditures. Schedule compression was achieved by early
Project Organization (Owner) procurement of longlead materials and rescheduling of normally
sequential activities to simultaneous activities. The essentials of a
The project team concept was selected for the design, fabrication
well planned and executed project are : qualified contractors,
and installation of the Erawan facilities. The project manager was
responsible to coordinate the activities of the engineering, con accurate and complete drawings, clear and understandable
struction and the Company support groups (see Plate 6). contracts, minimum of changes and coordinated inspections.

Company personnel compiled bidder's lists. qualified bidders, There was no domestic market for natural gas when the Erawan
Field was discovered. It was recognized as a mutual problem by the
solicited bids. awarded bids, did the major purchasing. wrote the
contracts and were available at all major fabrication sites as the Government of Thailand and Union Oil Company. It took five
authorized representatives. years of co--operative effort before a domestic market could be
established. This cooperative attitude continued to prevail during
The design consultant did the design of structures and process, the development phase of Erawan project. Cooperating spirit
prepared specifications, bid documents, performed technical review between government and private industry from concept to start-up
of bids. compiled dossier materials and provided on-site expertise and utilizing in-house expertise has resulted in an economical and
when required. timely installation.
Project Control Procedures
Acknowledgements
Fiscal control was promoted by well prepared bid documents, lump
We thank Union Oil Company of California and South East Asia
sum bids and avoidance of force account work. The only planned
Petroleum Exploration Co .. Ltd. for the privilege of publishing this
force account involved the heavy lifting of the decks and installation
paper.
of the barge mooring system.
We also thank Vickland and Craft of Exxon Production Research
Weight control of the process decks was essential to construction of
Co. for the use of their 14 elements of a project executive plan as
the facilities in view of offshore liftir:g,c'-':,abilities. Contractors were
described in their article, "'Management of Major Offshore Projects
required to establish an effective weight control procedure to
An Industry Challenge," Society of Petroleum Engineers, April
estimate the final lifting weights within 5%
1981.
Change Orders required approval of an authorized Company vice
,.. ........... "-.. .-'.- ..-.....,r.:. LOCATION MAP
''. THAILAND ( \... ERAWAN FI ELO
'"\ BANGKOK PLATE I.
UNION OIl. THAILAND
\ ERAWAN GAS FIELD
(
I
..::1\.
~.~~ KAMPUCHEA \

.. ,,,:)
a: \" -",/
........."
::J ~ J-" I
a ,~_"'-
Q'J.I PHNOM PENH ~. ~~-
i
(..,..;.vJ ~~
> ~~ OSA'GOH

ERA WAN GAS FI ELD

00 "'"
: '.""'''1
."....,... ...
. ~ ,)
(' ...r"\ .. ;
' ....,,,,

MALAYSIA

o KUALA LUMPUR

~SINGAPORE
100 200 QO~
C)O ~-W
50 100 C)
'0'
..,...t.l 1'01.' II'OQrAIM aOlQT
tt'}

'B'
/ ~~uc(,;..
"-;~ .$5:::~

~
~ ." .. '"'"
~1iA.S\'jJt{fO!io.TTA"'ji

~,

~~~
'~~~
'~
'~,~
'e'

fTPIC"'" '::...o"'1'fI",,'IO#l:)
"tilL ... "" /III'

PICTORIAL SURFACE FACILITIES


PLATE 2
UNION OIL THAILAND
ERAWAN GAS FIELD
PROJECT SCHEDULE
PLATE 3
UNION OIL THAILAND
ERAWAN GAS FIELD

UNION OIL COMPANY OF THAILAND I SEAPEC


THAILAND GAS PROJECT
1 919 1 960 1 9 8 1
ACTIVITY

ENGINEERING AND DESIGN


JACKEfS
I
LQ DECK S BLDG
PROD DECKS 6 fACiLITIES
PiPELINES r------ -
BiD AND AWARD
1
I

I~~~ I~~
I! I WELL Pl ATfOAMS 'A'S'S'
(Z) WELL PLAT FOAMS 'c' 8 '0' l
PRuOUCTION JKTS '8':C':D' )
I J )'CPP' ,'LQ':FlARE' JKTS
('I) IN ffRFIELf) PIPELINES
1 --
(5) PRODUCTION DECKS
(6) LIFT CONTRACT
(11 'La' BLDG
~L~
(8) WELL PLATFORM 'E' \
N~~!~/'
PRODUCTION

PROCURE MAT' LS / EQU!PMENT


JKT E' l I I !V
I
fABRICATE AND INSTALL
(j J WELL PLATFORMS 'A'6'a'
(2) WELL PLATfORMS 'C'6'0' :
Pk0DUCTlON JKTS '9';C':D' i
----

___ ---- _
I
I I
I-"'--I~......-!J
I I
I j
(31 CPP,l<.l, FLAREJKTS
(4) INTERFlflO PIPELINES -- -~-f ---+-1- ,- j
I
(5 i PRODUCTION DECKS
r-~ ~---t . -j 1'--1- ~
I
(6) LIfTiNG

.~
(n 'to' lJLOG

~
(8) WELL PLATFORM E I
PRODUCTION JilT E I START
I
START UP OF FACILITIES
MOB
De I I
I
~'j
l~
<@>
DERRIC~ BARGE SCHEDULE

HOOKUP BARGE SCHEDULE

DEVEL0PMENT DRILLING
II
, I I IJ I
8R~'/1
I
OMt
"

I I I

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ ,_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _----J
,. ATE II. J A l S 1 A f U S R E P 0 R T
---------------------------~--.------------
REI' 01\ f DA- If unO/DO P --GE U 08

1\ E QUI S I , l o ti P U 1\ t HAS 01\0 E R


--- 5 I I U S A-
--------------------- -- --- ---------
-------------------------------------------
IUH NUM8ER OA lE QTY UNIT OE sc. DAU
----~-----------------------------
NUMOER DA 1E REV 1$ I Uti VENDOR rl\O"1S EU --REC~lVtO-- - - - - - Sltll'PE U------
REO "D DAlE OHaVEf\Y t10 -oA lOC Q1Y 110-0'" VI HEl Q1Y
OAiC CUI\I\
1010 02 EA $lA6tl.ll\ Ott Il 0 kO lQ V2 t4.l1 CO OJ Il
08 P.EtJOILER I, 12 PROCR fS S IS llr
80 lAG NO 80 10 UI 10 80
II 2GB 66)-9 lOO
C 1't~O

1031 01 , EA. Gl YC Ol 10 11010H OZ NAitO to Il


15
Ole
80
OEIIY ORA T
owe R.
VIObOA-E
"
110
H
10
UN lFl\ANC

61)-7100
'118
15
10 80

, Eo' GLI'COL 810l01l HAleO 10 .,


11
OElIlOI\4.
sYStEH
PROGI\U S
"eo eo
1032 02 ~ EA SERVICE 08 810 lOU OZ GOULOS 01 lZ Of-l6l 611DS PI 10-02 HURl bPi
21 HA IfR 01 16 PUHPS IS 12
80 rVHP 80 10 tll eo 10
P12208-1 6U-1400
Pl"O
lOll 02 EA WAfER DD IU010n 01 GOUlOS 01 lZ De -lOl lMlR P1 08-lf, SAMOA I PI
Zl sPRAY 01 26 PUMPS as 11 U-26l aHO P2 10-02 Al U lR f 1P2
aD PUIiP 110 .0 918 10 10
TMi NO 621-20\00
P2 "0

I D34 02 ! u DIESel 09 81010lll 03 PENDER 0' 08-o8H !C 08-11 ARNOLD 5C


19 fUel 01 06 GRAPH fl 01
aD lRMUFEI\ 80 80 Al 'lie eo
rUMPS 835-11"0)
P-!!JOO

1035 02
01
80
All S lAO LILli.
tRAYS
06
01
00
81 Olon Of
08
10
GlIlSt"

214
.,
06

80
OK
04
ot
Al-l PI
P2
P]
5111 r (0
m1 (OfU
IRA~ISl1r
PI
P2
P3
6l1-UH Ptc 10 SPOR PI,

1036 02 10 EA CIIEM. UiJ 09 elOiOn HCFARLND U


18 PUtWS Ii 01
80 TAG NO. eo lU ao
P-lHO 1,602081 MATERIAL STATUS REPORT
P-ilTO PLATE 4
1031 02 EA fEEU ap 111010)1 02 APr 11 EO
UNION OIL THAILAND
08
01 BOTTOM S 01 11 SPORE 01 ERAWAN GAS FIELD
60 El<CH;'NGR 110 80 aD
T An .u~
- ,'" oLe

'OOm

ANCHOR l.AYOUT
PLATE 5
UNION OIL THAIl.AND
ERAWAN GAS FIELD

GENERAL MANAGER
VICE PRESIDENT
THAILAND

I
MANAGER
MANAGER MANAGER
OPERATIONS
EXP. a DEY. THAILAND Ace'T

I
DRILLING PROJECT MANAGER FIRE a SAFETY
MANAGER THAll.AND MANAGER

-----------~I
I
I PROCESS DESIGN
SUPT,
I FAB, a INSTAL
SUPT
COMPANY
SUPPORT
U,SA - s' PORE
I THAILAND
I I GROUPS \

I
I I I I I
I CaNST I I ENGR
CONST I
CaNST SITE SITE SITE
ENGR'S S
I ENGR'S
I
SUPV
I SUPV
I I SUPV,
\

I I
ORGA NIZATION CHART
I CONSULlAN TS
i
CONTRACTORS
I PLATE .;
UNION OIL THAILAND
ERAWAN GAS FIELD

Das könnte Ihnen auch gefallen