Beruflich Dokumente
Kultur Dokumente
Determining the critical path, total duration, and amount of slack for each activity. (Slack or float is
the difference between the latest start date of an activity and the earliest start date OR the difference
between the latest finish date and earliest finish date of an activity).
Slack for Activity A: _______ days. Slack for Activity D: _______ days.
Slack for Activity B: _______ days. Slack for Activity E: _______ days.
Slack for Activity C: _______ days. Slack for Activity F: _______ days.
Exercise 2
Crashing a project. First consider the cost/time slope for each activity: where slope is equal to crash
cost minus normal cost divided by crash time minus normal time.
Duration Cost
Activity Predecessor Normal/crash Normal/Crash
A -- 3/2 $ 40 / 80
B A 2/1 $ 20 / 80
C A 2/2 $ 20 / 20
D A 4/1 $ 30 / 120
E B 3/1 $ 10 / 80
What would be the minimal cost to crash the project by one day? $ __30____
What would be the maximum number of days you could crash the project? __2____
E
A C H
G
B F
D
A -- 3/2 $ 20 / 60
B -- 3/1 $ 20 / 80
C A 2/1 $ 40 / 60
D B 5/3 $ 70 / 170
E A 3/2 $ 50 / 90
F C, D 4/2 $ 35 / 85
G F 3/3 $ 80 / 80
H E, G 2/1 $ 40 / 120
What is the:
Slack for Activity A: _______ days. Slack for Activity E: _______ days.
Slack for Activity B: _______ days. Slack for Activity F: _______ days.
Slack for Activity C: _______ days. Slack for Activity G: _______ days.
Slack for Activity D: _______ days. Slack for Activity H: _______days
Critical Path: ____________________________________
What would be the minimal cost to crash the project by one day? $________
What would be the minimal cost to crash the project by two days? $________
Exercise 4
Development of a new deluxe version of a particular software product is being considered. The
activities necessary for the completion of this project are listed in the table below along with their
costs and completion times in weeks.
A 4 3 2,000 2,600 -
B 2 1 2,200 2,800 A
C 3 3 500 500 A
D 8 4 2,300 2,600 A
E 6 3 900 1,200 B, D
F 3 2 3,000 4,200 C, E
G 4 2 1,400 2,000 F
Normal Crashed
Exercise 6
When deciding on whether or not to crash project activities, a project manager was faced with the
following information. Activities of the critical path are highlighted with an asterisk:
Normal Crashed
Activity Cost Duration Extra Cost Duration
A 5,000 4 weeks 4,000 3 weeks
B* 10,000 5 weeks 3,000 4 weeks
C 3,500 2 weeks 3,500 1 week
D* 4,500 6 weeks 4,000 4 weeks
E* 1,500 3 weeks 2,500 2 weeks
F 7,500 8 weeks 5,000 7 weeks
G* 3,000 7 weeks 2,500 6 weeks
H 2,500 6 weeks 3,000 5 weeks
a. Identify the sequencing of the activities to be crashed in the first four steps.
Which of the critical activities should be crashed first? Why?
b. What is the projects critical path? After four iterations involving crashing
project activities, what has the critical path shrunk to?
c. Suppose project overhead costs accrued at a fixed rate of $500 per week. Chart
the decline in direct costs over the project life relative to the increase in
overhead expenses.
d. Assume that a project penalty clause kicks in after 19 weeks. The penalty
charged is $5,000 per week after 19 weeks. When the penalty charges are
added, what does the total project cost curve look like? Develop a table listing
the costs accruing on a per week basis.
e. If there were no penalty payments accruing to the project, would it make sense
to crash any project activities? Show your work.
Exercise 7
The activities, duration, and direct activity cost of a project are shown in the below mention table.
Time in Weeks Cost
Activity Normal Crash Normal ($) Crash ($)
12 8 4 3000 6000
13 5 3 4000 8000
24 9 6 4000 5500
35 7 5 2000 3200
25 5 1 8000 12000
46 3 2.5 10000 11200
56 6 2 4000 6800
67 10 7 6000 8700
57 9 5 4200 9000
Exercise 8
The activities, duration, and direct activity cost of a project are shown in the below mention table.
Time in Weeks Cost
Activity Normal Crash Normal ($) Crash ($)
12 5 2 6000 9000
24 6 3 7000 10000
13 4 2 1000 2000
34 7 4 4000 8000
47 9 5 6000 9200
35 12 3 16000 19600
46 10 6 15000 18000
67 7 4 4000 4900
79 6 4 3000 4200
59 12 7 4000 8500