Beruflich Dokumente
Kultur Dokumente
15-0
Project Management: Network Models
Project: A primarily non-repetitive set of interrelated activities whose
combined performance accomplishes desired objectives:
- may involve hundreds of organizational units and thousands of
different activities,
- may need a few decades or longer to complete.
Project Management: Planning, Scheduling, Controlling process to
meet project objectives under given constraints. Great efforts in
coordination/cooperation are needed for a successful project.
15-1
Project Management Characteristics
15-2
Project: Objectives and Constraints
Major Objectives of Project Management:
* Time: To complete the project on the scheduled time.
* Cost/Budget: Within the budget or minimize the total cost.
* "Quality": To meet the specifications and requirements.
* ..............................
15-3
Project Network Models
15-4
Constructing A Network: CPM and PERT
Construct A Network: (Activity-Oriented vs. Event-Oriented)
1. Activity-on-Node/Event-on-Arc: easy to construct, focus on
activities, used in CPM where activity times are relatively certain,
no dummy activity are needed.
2. Event-on-Node/Activity-on-Arc: focus on events, used in PERT
where activity times are relatively uncertain, dummy activities may
be needed to show complex precedence relationships.
CPM (Critical Path Method): All activity times are known with a
higher certainty (deterministic), so that cost/time analysis and
tradeoffs can be conducted.
15-5
Questions That May Be Addressed by PERT and CPM
Network Relationships
15-6
PERT network for the Response 1000 introduction
15-7
Project Planning Procedure
15-8
1. Identify all activities in the Project.
2. Determine the sequence and precedence of activities.
3. Ascertain the time estimate for each activity.
4. Ascertain the cost estimate for each activity.
5. Establish the major objectives and tradeoffs.
6. Select project scheduling techniques.
7. Construct the network for the project.
8. Forward/Backward scheduling: identify the critical path and
critical activities and determine the project completion time.
9. Evaluate the solution: cost/time analysis - Meet objectives? Need
change? What changes should be made?
10. Monitoring and Controllingcontrolling the project progress:
reevaluation and adjustments.
15-9
Estimating Activity Duration
15-10
Estimating Activity Times
Normal Activity Time: the time that results the lowest activity cost.
Normal Activity Cost: the lowest activity cost.
15-11
Critical Path Method- Computation Procedure
15-12
Basic Terms in Project Network Models
For each activity: (in CPM) (ti - activity time)
ES: Earliest Start time (under precedence requirements).
EF: Earliest Finish time (EF = ES + ti).
LS: Latest Start time (under precedence requirements).
LF: Latest Finish time (LF = LS + ti).
Slack: the time difference between LS and ES (or LF & EF).
Slack = LS - ES = LF - EF
For each Node: (in PERT)
ET: Earliest Event time (under precedence requirements).
LT: Latest Event time (LT = ET + ti).
Slack = LT - ET - ti
All activities that on the critical path have "zero" slack times.
15-13
A) Compute the early start and finish times and the late start and finish times
for each activity in the CPM network above. Place your answer in the boxes
provided.
(B) What is the length on the critical path through the network?____________
(C) Darken in arrows connecting activities on the critical path.
(D) What is the total slack for activity B?____For activity F?__________
(E) What is the free slack for activity B?________ For activity F?___________
15-14
15-15
15-16
15-17
Time/Cost Analysis and Tradeoffs in CPM
15-18
Time and Cost Information
Normal Crash
Activity Time Cost Time Cost Cost
Slope
A 5 $100 4 $140 40
B 9 200 7 300 50
C 7 250 4 340 30
D 9 280 7 340 30
E 5 250 2 460 70
F 11 400 7 720 80
G 6 300 4 420 60
I 8 80 6 140 30
Total $1,860 $2,860
15-20
Estimation of Activity Time under Uncertainty:
*Three-point Average Approach: [ te = (to+4tm+tp)/6 ]
te = Expected Activity Time
to = Optimistic Estimate (shortest possible time - a )
tm = Most likely Estimate (most possible time - m)
tp = Pessimistic Estimate (longest possible time - b)
Standard deviation of activity time: = (tp - to)/6
The variance of activity time: 2= [(tp - to)/6]2
The variance of a (critical) path: i 2= i [(tp - to)/6]2
(When te = to = tm = tp, deterministic case: PERT CPM )
15-21
Probability Analysis:
Project Completion Time in PERT
Due to the variations in activity time estimates, the project completion
time is a "random variable" in PERT model. That is, the actual
project completion time will be different (earlier or later) from the
"expected" that is calculated based on "expected" activity times.
In practice, knowing the probability of project completion time is
of great interest to project management.
15-22
Activity time estimated in weeks
15-23
15-24
Determination of Critical Path/
Results of Forward and Backward Pass
15-25
15-26
15-27
Project Network Models: Managerial Insights
*Project network models (CPM/PERT) help project management to
focus attentions on critical path and activities:
- Transferring resources from non-critical activities to critical ones.
- Making tradeoffs between activity times and activity costs.
- Allocate additional resources to the critical activities so that the
whole project completion time can be reduced.
*When one (or more) activity time(s) on the "original" critical path is
reduced, another path may become "critical".
*There may be more than one "Starting" event and more than one
"Ending" event in a network.
15-28
Project: Monitoring and Controlling
*Budget/Resources allocation among competing activities that require
same resources at the same time period. (Bar Chart)
15-29
Project Management Cost Analysis
15-30
15-31
Cumulative Budget Demands vs. Time
15-32
Trend Analysis
15-33
Application of Project Network Models
*CPM/PERT techniques have been widely used in almost all types of
project management.
15-34
Maximal Flow
15-35
Minimal Spanning Tree
15-36
Shortest Route
15-37
Network for General Foundry, Inc.
15-38
Results of PERT Activities Alongalong Critical
Path
15-39
PERT and Budgeting
15-40
Advantages of PERT/CPM
Useful at several stages of project management
Straightforward in concept, and not mathematically complex
Uses graphical displays employing networks to help user
perceive relationships among project activities
Critical math and slack time analyses help pinpoint activities
that need to be closely watched
Networks generated provide valuable projects documentation
and graphically points out who is responsible for various project
activities
Applicable to a wide variety of projects and industries
Useful in monitoring not only schedules but costs as well
Limitations of PERT/CPM
15-41
Project activities must be clearly defined, independent, and
stable in their relationships
Precedence relationships must be specified and networked
together
Time activities in PERT are assumed to follow the beta
probability distribution- this may be difficult to verify
Time estimates tend to be subjective, and are subject to fudging
by managers
There is inherent danger in too much emphasis being placed on
the critical path
Problems
1. The following event completion times have been estimated by a contracting firm:
15-42
a. 10 b. 12 c. 14 d. 16 e. None of these
3. The earliest time that the entire project can be completed if activity cd takes two extra weeks
is:
a. 7 b. 9 c. 10 d. 11 e. 12
5. The earliest time that the entire project can be completed is:
a. 7 b. 8 c. 9 d. 10 e. 11
6. Suppose activity cd takes two extra weeks; by how much will the earliest date of completion
be delayed?
a. 0 b. 1 c. 2 d. 3
15-43
Times (weeks)
Activity to tm tp te
Optimistic Likely Pessimistic Expected
ab 5 11 11 10
ac 10 10 10 10
Dummy ad 2 5 8 5
bf 1 7 13 7
cf 4 4 10 5
cg 4 7 10 7
ce 2 2 2 2
dc 0 0 0 0
de 0 6 6 5
eg 2 8 14 8
fg 1 4 7 4
15-44
a 1 2 3 None
b 1 3 6 None
c 1 4 8 None
d 2 5 7 a
e 3 5 5 b
f 4 5 10 c
g 4 6 4 c
h 5 7 5 d, e, f
i 6 7 6 g
5. Given the following schedule for a liability work package done as part of an
accounting audit in a corporation:
Activity Duration (Days) Preceding Activities
a. Obtain schedule of liabilities 3 None
b. Mail confirmation 15 a
c. Test pension plan 5 a
d. Vouch selected liabilities 60 a
e. Test accruals and amortization 6 d
f. Process confirmations 40 b
g. Reconcile interest expense to debt 10 c, e
h. Verify debt restriction compliance 7 f
i. Investigate debit balances 6 g
j. Review subsequent payments 12 h, i
15-45
Activity te (Weeks) Preceding Activities
a 3 None
b 1 None
c 3 a
d 4 a
e 4 b
f 5 b
g 2 c, e
h 3 f
Times (Weeks)
Activity Optimistic Most Likely Pessimistic
1-2 5 11 11
1-3 10 10 10
1-4 2 5 8
2-6 1 7 13
3-6 4 4 10
3-7 4 7 10
3-5 2 2 2
4-5 0 6 6
15-46
5-7 2 8 14
6-7 1 4 7
a) Find all earliest dates, including project completion (TES for all
events).
b) Find all latest dates (TLS for all events).
c) Determine the critical path and the event slack values.
d) What is the critical path leading to event 5?
e) What will happen if activity 4-5s actual time slips to 9?
f) What will be the slack on activity 3-5 if activity 4-5 slips to 9 weeks
and activity 5-7 takes 6 weeks?
g) Find the probability of finishing the project in 19 weeks. In 17
weeks, Inin 24 weeks.
h) What is the probability of completing event 5 by5 by 9 weeks?
i) If management wants to be 80 percent sure that the project will be
completed by a guaranteed date, what date should be quoted?
8. Given a PERT network:
Find:
15-47
c. The slack in events 2 and 3.
d. The slack on activities 1-4 and 2-5.
e. The probability the project will be completed in 20 weeks or less.
f. The probability the project will be completed in 30 weeks or less.
g. The number of weeks required to complete the project with 95
percent certainty.
15-48