1. Properly filled-up application forms duly signed and sealed by engineers concerned:
Structural Design Analysis signed and sealed by Civil Engineer at every page
Seismic Analysis
5. Proof of Property
Contract of Lease
Contract of Sale
7. Locational Clearance
7. Photocopy of PTR # and PRC license of all concerned engineers and architects
7. Clearance from the DPWH if the construction is located along National Highway
7. DOLE Clearance
Those are the usual application forms you need gather and prepare.
Note:
1. All Application Forms, plans, specification, design and
computation, bill of materials should be sign and sealed by duly
licensed CE, ARCH, SE, PEE, Master plumber, master
Electrician.
( ) Tax Declaration
(Electrical Plans)
(Mechanical Plans)
Estimated Cost of the Project (Prepared, Signed and Sealed by a Duly Licensed Architect or
Engineer)
( ) Building Permit
( ) Electrical Permit
( ) Sanitary Permit
( ) Mechanical Permit
Initiate, review and recommend changes in policies and objectives, plans and program, techniques,
procedures and practices in infrastructure development and public works in general of the local government
unit concerned.
Advise the governor or mayor, as the case may be, on infrastructure, public works, and other engineering
matters.
Administer, coordinate, supervise and control the construction, maintenance, improvement and repair of
roads, bridges and other engineering and public works projects of the local government unit concerned.
Provide engineering services to the local government unit concerned, including investigation and survey,
engineering designs, feasibility studies and project management.
In the case of the provincial engineers, exercise technical supervision over all engineering offices of
component cities and municipalities.
A BUILDING Permit is required prior to the construction, erection, alteration, major repair, or renovation or conversion
of any building/structure owned by government of private entities.
The permit becomes null and void if work does not commence within one year from the date of such permit, or if the
building or work is suspended or abandoned at any time after it has been commenced for a period of 120 days.
GENERAL REQUIREMENTS:
Application Forms (Building, Sanitary/Plumbing, Electrical, Mechanical) - 4 copies.
Lot Plan with certification of a Geodetic Engineer (GE) that the proposed building will not encroach on adjoining
properties 4 copies.
Site Development Plan indicating the setback/yard distances at the front, sides and back with Perspective 4
copies.
Building Plans (Architectural, Structural, Sanitary/Plumbing, Electrical, Mechanical) 4 sets.
Bill of Materials and Cost Estimates.
Specifications 3 copies.
Title of Property (Transfer Certificate of Title) 3 copies.
Deed of Sale/Lease Contract/Contract to Sell, if the TCT is not in the name
of
the owner/applicant 3 copies.
Latest Tax Declaration and Certificate of Real Property Tax Payment 4 copies.
Construction Logbook 1 piece.
Structural Design Computations with seismic analysis which conform to the latest NSCP for 2 storeys and above
or 1 storey with attic/mezzanine/roof deck/penthouse 2 copies.
Previous approved plan or permit in case of addition, alteration and renovation 2 copies.
Certification regarding structural stability of existing foundation in case of addition 2 copies.
Plate Load Test Analysis for 3 storeys of 2 storeys with attic /mezzanine/roof deck/penthouse
-2 copies.
Soil Boring Test Result for 4 storeys and above or 4 storeys with attic /mezzanine/roof deck/penthouse 2 copies.
Clearances from other government agencies exercising regulatory functions 2 copies. Such regulatory agencies
are:
City Planning and Development Office for zoning and land use of all types of building/structures.
Bureau of Fire Protection for all types of buildings/structures.
Department of Environment and Natural Resources for all commercial and industrial buildings.
Department of Health for health-hazard related buildings/structures.
Air Transportation Office for buildings/structures exceeding 45 meters in height.
Philippine Tourism Authority for tourist-oriented projects.
Department of Education for education buildings.
Energy Regulatory Board for gasoline stations.
To facilitate processing, please take note of the following before submitting the plans and other requirements above to
the CEO.
FEE(S)
5. Inquiry on the Status of Application 2 days from receipt Building Official Staff
Inquire about the results of evaluation and
assessment after 2 days from submission of
requirements.
of documents
If there are no deficiencies, proceed to step
9.
The technical staff reviews the corrected 1 day Building Official Staff
plans and checks completeness of
documents.
9. Processing of Permits
Building Staff processes the plans and 2 days Building Official Staff
pertinent documents and prepares the Order
of Payment for final approval of the Building
Official.
15.Release of Permit
30 minutes Releasing Clerk
The Building Permit is issued 4 hours after
submission of the Official Receipt.
Aside from a building permit, the Office of the Building Official/City Engineers Office issues other permits that are
required before the renovation, construction or demolition of any structure. Office of issues other permits that are
required before the renovation, construction or demolition of any structure.
ELECTRICAL PERMIT
This document is required before putting up new or additional, or altering electrical installations involving at least 20
outlets or a capacity of 4 Kw. For new buildings, this form as part of the requirements for a Building Permit
application.
REQUIREMENTS:
MECHANICAL PERMIT
This is required before the installation of new or additional, removal or alteration of machinery of at least 20 HP. For
new buildings, this forms part of the requirements for a Building Permit application.
REQUIREMENTS:
Mechanical Permit Application Form signed by a professional Mechanical Engineer.
Mechanical Plans
Mechanical Specifications
SANITARY/PLUMBING PERMIT
This document is required before the construction of new or additional, or altering existing plumbing installations,
water supply, storm drainage, water purification and sewerage treatment plants. For new buildings, this forms part of
the requirements for a Building Permit application.
REQUIREMENTS:
Sanitary/Plumbing Plans
Sanitary/Plumbing Specifications
FENCING PERMIT
REQUIREMENTS:
Fencing Plan
Lot Plan with certification of a Geodetic Engineer that the proposed fence will not encroach on adjoining
properties
Deed of Sale/Lease Contract/Contract to Sell (if the TCT is not in the name of the owner/applicant)
DEMOLITION PERMIT
This permit is secured prior to the systematic dismantling or destruction of a building or structure in whole or in part.
REQUIREMENTS:
This permit is secured for temporary service connection to a power utility for lighting and power for construction,
Christmas decorative lighting, lighting of cemeteries, temporary lighting for carnivals/fiestas, testing, etc.
REQUIREMENTS:
Electrical Plan/Layout
This permit is secured prior to actual ground preparation and excavation after the building line is established. It is also
a requirement for a water connection request to Manilad Water Services, Inc. (MWSI).
REQUIREMENTS:
REQUIREMENTS:
SCAFFOLDING PERMIT
This permit is secured whenever the erection of scaffolding occupies street lines
REQUIREMENTS:
Accomplished Permit Form (MPW Form No. 77-017-B)
SIGN PERMIT
This permit is secured prior to the installation, erection, attachment painting of any form of signage.
REQUIREMENTS:
Structural Analysis
Zoning Clearance
Location/vicinity plan
FEE(S)
3. Processing of Permits
Building Staff processes the plans and
pertinent documents and prepares the 2 days Building Official Staff
Order of Payment for final approval of the
Building Official.
5. Payment of Fees
Proceed to the City Treasurers Office and
pay the requisite fees. Cashier, City
30 minutes
Treasurers Office
You will be issued an Official Receipt
8. Approval of Permit
4 hours Building Official
Building Official approves the permit.
9. Release of Permit
The Building Permit is issued 4 hours after 30 minutes Releasing Clerk
submission of the Official Receipt.
A Occupancy Permit is required before any building/structure is used or occupied. It is usually secured after the
completion of a structure. It is also required if there is any change in the existing use or occupancy classification of a
building, structure or any portion thereof.
GENERAL REQUIREMENTS:
Logbook of building construction and Building Inspection Sheet duly accomplished by the contractor (if
undertaken by contract) and signed and sealed by the architect or civil engineer in charge of construction
FEE(S)
3. Review/Evaluation
Technical staff reviews the forms and the 2 hours Building Official Staff
construction activity entries in the
construction logbook.
5. Preparation of Inspection
Report (optional, if the building inspectors
find no deviations/violations)
Return to Step 3.
7. Processing of Permits
Building Staff processes the plans and 2 days Building Official Staff
pertinent documents and prepares the Order
of Payment for final approval of the Building
Official.