Beruflich Dokumente
Kultur Dokumente
A method of advancing a mine working or tunnel in loose, caving, or watery ground, such as
quicksand, by driving sharp-pointed poles, timbers, sections of steel, or slabs into the ground ahead of,
or simultaneously with, the excavating; a method of supporting a very weak roof. It is useful in
tunneling and in extracting coal from under shale or clay.
A method of securing loose ground by driving poles, planks, etc., ahead of and on the top and sides of
the timbers.
forepoling
Definition
In heavy construction and excavation, horizontal boardsdriven into the crown of a
tunnel heading to establish a safety roof for heading work.
Methods of Tunnelling
Twin tunnel
Sometimes it proves more advantageous to have two small tunnels instead of single large tunnel.
Each of twin tunnel is excavated separately & tunnels are so spaced that disturbance caused in ground from
construction of one tunnel does not affect the other .
If one tunnel is blocked up due to any reason the other tunnel can be conveniently used.
Portals
The actual doorways or main entrance of the tunnel are known as portals.
Portals indicates the intersection point between the underground opening & the ground surface.
The portals should be made massive in appearance. They should look beautiful & attractive.
Such a construction would encourage a layman to enter the tunnel with confidence of safety.
Pilot tunnel
Sometimes it may be found that a horizontal approach to the tunnel line may be to closer & shorter compared to the
deep vertical shafts .
In such circumstances, a tunnel of small size called a pilot tunnel is driven parallel &close to the proposed main
tunnel & short cross connecting tunnels are driven from it reach the proposed main tunnel to create operational
faces.
The cross headings are convenient places to store tools & material during the construction work.
The chances of any material failing accidentally down the shaft in to the tunnel during the construction work are
considerable reduced
It avoids the dislocation of the strata at the sides of the tunnel after the work is completed, the cross headings may be
used as passage for the workers
The shaft can be used as means of artificial ventilation by the use of fans.
Forepoling method
American method
British method
Belgian method
it is very important that the sequence of operations has to be strictly adhered to , in the correct order.
It makes use of beams & bracings .Hence,there is difficulty in mechanical methods of concrete lining.
It requires large number of trench jacks & they interfere with the efficient working of the gang.
The only drawback of this method is that its use or application is limited for the construction of short tunnels of small
cross-section.
English method
This method involves the use of a lot of timber & frequent shifting of heavy timber logs back.
The masons & excavators have to work alternatively & thus , the process requires more time as compared to other
methods of tunneling.
If the soil is unstable , the excavation of full section of tunnel will increase the danger of caving.
particularly when the avoidable subsidence of the soil may take place , causing settlements can be reduced by
adopting R.C.C.arches.
Liner plates methods
It is also relatively weak as plates are attached with nuts & bolts.
It requires extreme care in carrying out the work as slight mistake may result in heavy loss of money.
It allows the tunneling operations to be carried out at many sections along the tunnel length.
Drift method
The enlargement work cannot be started until the central holr is constructed for the full length.
That as the enlarging & benching work commences , mucking tracks have to be shifted frequently from bench to
bench.
This method is extremely costly & it is generally recommended for ground conditions which are difficult to solve.
Factors affecting in heading & bench method
In this method enlargement work cannot be started until the central hole is constructed for full length.