1 CADANGAN 1 BLOK PANGSAPURI 41 TINGKAT (243 UNIT) 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 15.16 11.85 -3.31 57 days
2 MILESTONE 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 57 days
3 PROJECT MILESTONE 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 57 days
7 CONSTRUCTION MILESONE 680 days Thu 28/7/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 58 days
31 MILESTONE FOR AWARD OF DIRECTOR CONTRACTORS 585 days Tue 5/7/16 Sat 19/5/18 Tue 5/7/16 Sat 2/6/18 0 0 0 12 days
47 PRE-CONSTRUCTION WORKS 49 days Wed 1/6/16 Wed 27/7/16 Wed 1/6/16 Sun 31/7/16 100 100 0 0 days
48 PRELIMINARY 49 days Wed 1/6/16 Wed 27/7/16 Wed 1/6/16 Wed 27/7/16 100 100 0 0 days
58 CONSTRUCTION WORKS 709 days Fri 24/6/16 Sat 29/9/18 Fri 24/6/16 Tue 4/12/18 15.27 11.77 -3.5 57 days
59 PILECAPS AND STUMP 0 days Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 0 0 0 0 days 24/6
60 RC WORK COMPLETED AND VERIFIED BY SURVEYOR 0 days Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 0 0 0 0 days 24/6
61 CARPARK 535 days Thu 28/7/16 Thu 12/4/18 Thu 28/7/16 Tue 19/6/18 22.41 15.31 -7.1 58 days
62 RC WORKS/M&E CAST-IN 371 days Thu 28/7/16 Tue 3/10/17 Thu 28/7/16 Fri 1/12/17 78 53.28 -24.72 51 days
63 ZONE 1 (GL A-F/11-15) 314 days Thu 28/7/16 Fri 28/7/17 Thu 28/7/16 Wed 4/10/17 84.21 60.18 -24.03 58 days
64 GF 99 days Thu 28/7/16 Sat 19/11/16 Thu 28/7/16 Sat 19/11/16 100 100 0 0 days
65 GF BEAM 30 days Thu 28/7/16 Wed 31/8/16 Thu 28/7/16 Wed 31/8/16 100 100 0 0 days
66 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Thu 1/9/16 Sat 17/9/16 Thu 1/9/16 Sat 17/9/16 100 100 0 0 days
67 GF SLAB 21 days Mon 3/10/16 Wed 26/10/16 Mon 3/10/16 Wed 26/10/16 100 100 0 0 days
68 GF COLUMN 21 days Thu 27/10/16 Sat 19/11/16 Thu 27/10/16 Sat 19/11/16 100 100 0 0 days
69 1F 35 days Mon 21/11/16 Fri 30/12/16 Mon 21/11/16 Fri 30/12/16 100 100 0 0 days
70 1F BEAM AND SLAB 25 days Mon 21/11/16 Mon 19/12/16 Mon 21/11/16 Mon 19/12/16 100 100 0 0 days
71 1F Cast-in conduit, piping , Junction Box & Sleeves 10 days Mon 21/11/16 Thu 1/12/16 Mon 21/11/16 Thu 1/12/16 100 100 0 0 days
72 1F COLUMN 10 days Tue 20/12/16 Fri 30/12/16 Tue 20/12/16 Fri 30/12/16 100 100 0 0 days
73 2F 35 days Sat 31/12/16 Thu 9/2/17 Sat 31/12/16 Thu 9/2/17 100 100 0 0 days
74 2F BEAM AND SLAB 25 days Sat 31/12/16 Sat 28/1/17 Sat 31/12/16 Sat 28/1/17 100 100 0 0 days
75 2F Cast-in conduit, piping , Junction Box & Sleeves 10 days Sat 31/12/16 Wed 11/1/17 Sat 31/12/16 Wed 11/1/17 100 100 0 0 days
76 2F COLUMN 10 days Mon 30/1/17 Thu 9/2/17 Mon 30/1/17 Thu 9/2/17 100 100 0 0 days
77 3F 35 days Fri 10/2/17 Wed 22/3/17 Fri 10/2/17 Wed 22/3/17 100 100 0 0 days
78 3F BEAM AND SLAB 25 days Fri 10/2/17 Fri 10/3/17 Fri 10/2/17 Fri 10/3/17 100 100 0 0 days
79 3F Cast-in conduit, piping , Junction Box & Sleeves 10 days Fri 10/2/17 Tue 21/2/17 Fri 10/2/17 Tue 21/2/17 100 100 0 0 days
80 3F COLUMN 10 days Sat 11/3/17 Wed 22/3/17 Sat 11/3/17 Wed 22/3/17 100 100 0 0 days
81 4F 35 days Thu 23/3/17 Tue 2/5/17 Thu 23/3/17 Sat 8/7/17 100 11.11 -88.89 58 days
82 4F BEAM AND SLAB 25 days Thu 23/3/17 Thu 20/4/17 Thu 23/3/17 Tue 27/6/17 100 20 -80 58 days
83 4FCast-in conduit, piping , Junction Box & Sleeves 10 days Thu 23/3/17 Mon 3/4/17 Mon 5/6/17 Thu 15/6/17 100 0 -100 63 days
84 4FCOLUMN 10 days Fri 21/4/17 Tue 2/5/17 Wed 28/6/17 Sat 8/7/17 100 0 -100 58 days
85 5F 35 days Wed 3/5/17 Mon 12/6/17 Mon 10/7/17 Fri 18/8/17 84.45 0 -84.45 58 days
86 5F BEAM AND SLAB 25 days Wed 3/5/17 Wed 31/5/17 Mon 10/7/17 Mon 7/8/17 100 0 -100 58 days
87 5F Cast-in conduit, piping , Junction Box & Sleeves 10 days Wed 3/5/17 Sat 13/5/17 Mon 10/7/17 Thu 20/7/17 100 0 -100 58 days
88 5FCOLUMN 10 days Thu 1/6/17 Mon 12/6/17 Tue 8/8/17 Fri 18/8/17 30 0 -30 58 days
89 6F 35 days Tue 13/6/17 Sat 22/7/17 Sat 19/8/17 Thu 28/9/17 0 0 0 58 days
92 STAIRCASE 190 days Tue 20/12/16 Fri 28/7/17 Tue 20/12/16 Wed 4/10/17 70 40 -30 58 days
99 ZONE 2 (GL A-F/15-19) 329 days Wed 17/8/16 Mon 4/9/17 Wed 17/8/16 Sat 21/10/17 75.53 49.83 -25.7 41 days
100 GF 75 days Wed 17/8/16 Fri 11/11/16 Wed 17/8/16 Fri 11/11/16 100 100 0 0 days
101 GF BEAM 30 days Wed 17/8/16 Tue 20/9/16 Wed 17/8/16 Tue 20/9/16 100 100 0 0 days
102 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Wed 21/9/16 Fri 7/10/16 Wed 21/9/16 Fri 7/10/16 100 100 0 0 days
103 GF SLAB 21 days Tue 11/10/16 Thu 3/11/16 Tue 11/10/16 Thu 3/11/16 100 100 0 0 days
104 GF COLUMN 21 days Wed 19/10/16 Fri 11/11/16 Wed 19/10/16 Fri 11/11/16 100 100 0 0 days
105 1F 42 days Thu 8/12/16 Wed 25/1/17 Thu 8/12/16 Wed 25/1/17 100 100 0 0 days
106 1F BEAM AND SLAB 30 days Thu 8/12/16 Wed 11/1/17 Thu 8/12/16 Wed 11/1/17 100 100 0 0 days
107 1F COLUMN 12 days Thu 12/1/17 Wed 25/1/17 Thu 12/1/17 Wed 25/1/17 100 100 0 0 days
108 2F 35 days Thu 26/1/17 Tue 7/3/17 Thu 26/1/17 Tue 7/3/17 100 100 0 0 days
109 2F BEAM AND SLAB 25 days Thu 26/1/17 Thu 23/2/17 Thu 26/1/17 Thu 23/2/17 100 100 0 0 days
110 2F COLUMN 10 days Fri 24/2/17 Tue 7/3/17 Fri 24/2/17 Tue 7/3/17 100 100 0 0 days
111 3F 35 days Wed 8/3/17 Mon 17/4/17 Wed 8/3/17 Mon 17/4/17 100 100 0 0 days
112 3F BEAM AND SLAB 25 days Wed 8/3/17 Wed 5/4/17 Wed 8/3/17 Wed 5/4/17 100 100 0 0 days
113 3F COLUMN 10 days Thu 6/4/17 Mon 17/4/17 Thu 6/4/17 Mon 17/4/17 100 100 0 0 days
114 4F 35 days Tue 18/4/17 Sat 27/5/17 Mon 5/6/17 Fri 14/7/17 100 0 -100 41 days
115 4F BEAM AND SLAB 25 days Tue 18/4/17 Tue 16/5/17 Mon 5/6/17 Mon 3/7/17 100 0 -100 41 days
116 4FCOLUMN 10 days Wed 17/5/17 Sat 27/5/17 Tue 4/7/17 Fri 14/7/17 100 0 -100 41 days
117 5F 35 days Mon 29/5/17 Fri 7/7/17 Sat 15/7/17 Thu 24/8/17 17.14 0 -17.14 41 days
118 5F BEAM AND SLAB 25 days Mon 29/5/17 Mon 26/6/17 Sat 15/7/17 Sat 12/8/17 24 0 -24 41 days
119 5FCOLUMN 10 days Tue 27/6/17 Fri 7/7/17 Mon 14/8/17 Thu 24/8/17 0 0 0 41 days
120 6F 30 days Sat 8/7/17 Fri 11/8/17 Fri 25/8/17 Thu 28/9/17 0 0 0 41 days
122 RC RAMP (GL E-H/14-19) 162 days Thu 12/1/17 Wed 19/7/17 Thu 12/1/17 Tue 5/9/17 76 20 -56 41 days
128 STAIRCASE 202 days Thu 12/1/17 Mon 4/9/17 Thu 12/1/17 Sat 21/10/17 63.33 33 -30.33 41 days
135 ZONE 3 (GL F-K/15-19) 285 days Wed 31/8/16 Fri 28/7/17 Wed 31/8/16 Tue 10/10/17 86.65 63.07 -23.58 63 days
136 GF 70 days Wed 31/8/16 Sat 19/11/16 Wed 31/8/16 Sat 19/11/16 100 100 0 0 days
137 GF BEAM 30 days Wed 31/8/16 Tue 4/10/16 Wed 31/8/16 Tue 4/10/16 100 100 0 0 days
138 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Wed 5/10/16 Fri 21/10/16 Wed 5/10/16 Fri 21/10/16 100 100 0 0 days
139 GF SLAB 21 days Wed 19/10/16 Fri 11/11/16 Wed 19/10/16 Fri 11/11/16 100 100 0 0 days
140 GF COLUMN 21 days Thu 27/10/16 Sat 19/11/16 Thu 27/10/16 Sat 19/11/16 100 100 0 0 days
141 1F 35 days Mon 21/11/16 Fri 30/12/16 Mon 21/11/16 Fri 30/12/16 100 100 0 0 days
142 1F BEAM AND SLAB 25 days Mon 21/11/16 Mon 19/12/16 Mon 21/11/16 Mon 19/12/16 100 100 0 0 days
143 1F Cast-in conduit, piping , Junction Box & Sleeves 10 days Mon 21/11/16 Thu 1/12/16 Mon 21/11/16 Thu 1/12/16 100 100 0 0 days
144 1F COLUMN 10 days Tue 20/12/16 Fri 30/12/16 Tue 20/12/16 Fri 30/12/16 100 100 0 0 days
145 2F 35 days Sat 31/12/16 Thu 9/2/17 Sat 31/12/16 Thu 9/2/17 100 100 0 0 days
146 2F BEAM AND SLAB 25 days Sat 31/12/16 Sat 28/1/17 Sat 31/12/16 Sat 28/1/17 100 100 0 0 days
147 2F Cast-in conduit, piping , Junction Box & Sleeves 10 days Sat 31/12/16 Wed 11/1/17 Sat 31/12/16 Wed 11/1/17 100 100 0 0 days
148 2F COLUMN 10 days Mon 30/1/17 Thu 9/2/17 Mon 30/1/17 Thu 9/2/17 100 100 0 0 days
149 3F 35 days Fri 10/2/17 Wed 22/3/17 Fri 10/2/17 Wed 22/3/17 100 100 0 0 days
150 3F BEAM AND SLAB 25 days Fri 10/2/17 Fri 10/3/17 Fri 10/2/17 Fri 10/3/17 100 100 0 0 days
151 3F Cast-in conduit, piping , Junction Box & Sleeves 10 days Fri 10/2/17 Tue 21/2/17 Fri 10/2/17 Tue 21/2/17 100 100 0 0 days
152 3F COLUMN 10 days Sat 11/3/17 Wed 22/3/17 Sat 11/3/17 Wed 22/3/17 100 100 0 0 days
153 4F 35 days Thu 23/3/17 Tue 2/5/17 Mon 5/6/17 Fri 14/7/17 100 0 -100 63 days
154 4F BEAM AND SLAB 25 days Thu 23/3/17 Thu 20/4/17 Mon 5/6/17 Mon 3/7/17 100 0 -100 63 days
155 4FCast-in conduit, piping , Junction Box & Sleeves 10 days Thu 23/3/17 Mon 3/4/17 Mon 5/6/17 Thu 15/6/17 100 0 -100 63 days
156 4FCOLUMN 10 days Fri 21/4/17 Tue 2/5/17 Tue 4/7/17 Fri 14/7/17 100 0 -100 63 days
157 5F 35 days Wed 3/5/17 Mon 12/6/17 Sat 15/7/17 Thu 24/8/17 84.45 0 -84.45 63 days
158 5F BEAM AND SLAB 25 days Wed 3/5/17 Wed 31/5/17 Sat 15/7/17 Sat 12/8/17 100 0 -100 63 days
159 5F Cast-in conduit, piping , Junction Box & Sleeves 10 days Wed 3/5/17 Sat 13/5/17 Sat 15/7/17 Wed 26/7/17 100 0 -100 63 days
160 5FCOLUMN 10 days Thu 1/6/17 Mon 12/6/17 Mon 14/8/17 Thu 24/8/17 30 0 -30 63 days
161 6F 40 days Tue 13/6/17 Fri 28/7/17 Fri 25/8/17 Tue 10/10/17 0 0 0 63 days
164 ZONE 4 (GL F-K/11-15) 330 days Wed 14/9/16 Tue 3/10/17 Wed 14/9/16 Fri 1/12/17 69.74 44.65 -25.09 51 days

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress

Prepared by : HSB Engineering Sdn Bhd Page 1 REVISION 3A


MIP (BASELINE)
AS OF 03/06/17
ID Task Name Baseline Duration Baseline Start Baseline Finish IMPACTED STARTIMPACTED FINISH SCH % ACT % % Varience Delay Days 2nd Quarter 1st Quarter 4th Quarter 3rd Quarter 2nd Quarter
J M S J M S J M S J
165 GF 65 days Wed 14/9/16 Mon 28/11/16 Wed 14/9/16 Mon 28/11/16 100 100 0 0 days
166 GF BEAM 30 days Wed 14/9/16 Tue 18/10/16 Wed 14/9/16 Tue 18/10/16 100 100 0 0 days
167 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Wed 19/10/16 Fri 4/11/16 Wed 19/10/16 Fri 4/11/16 100 100 0 0 days
168 GF SLAB 21 days Thu 27/10/16 Sat 19/11/16 Thu 27/10/16 Sat 19/11/16 100 100 0 0 days
169 GF COLUMN 21 days Fri 4/11/16 Mon 28/11/16 Fri 4/11/16 Mon 28/11/16 100 100 0 0 days
170 1F 35 days Tue 29/11/16 Sat 7/1/17 Tue 29/11/16 Sat 7/1/17 100 100 0 0 days
171 1F BEAM AND SLAB 25 days Tue 29/11/16 Tue 27/12/16 Tue 29/11/16 Tue 27/12/16 100 100 0 0 days
172 1F Cast-in conduit, piping , Junction Box & Sleeves 10 days Tue 29/11/16 Fri 9/12/16 Tue 29/11/16 Fri 9/12/16 100 100 0 0 days
173 1F COLUMN 10 days Wed 28/12/16 Sat 7/1/17 Wed 28/12/16 Sat 7/1/17 100 100 0 0 days
174 2F 35 days Mon 9/1/17 Fri 17/2/17 Mon 9/1/17 Fri 17/2/17 100 100 0 0 days
175 2F BEAM AND SLAB 25 days Mon 9/1/17 Mon 6/2/17 Mon 9/1/17 Mon 6/2/17 100 100 0 0 days
176 2F Cast-in conduit, piping , Junction Box & Sleeves 10 days Mon 9/1/17 Thu 19/1/17 Mon 9/1/17 Thu 19/1/17 100 100 0 0 days
177 2F COLUMN 10 days Tue 7/2/17 Fri 17/2/17 Tue 7/2/17 Fri 17/2/17 100 100 0 0 days
178 3F 35 days Sat 18/2/17 Thu 30/3/17 Sat 18/2/17 Thu 30/3/17 100 100 0 0 days
179 3F BEAM AND SLAB 25 days Sat 18/2/17 Sat 18/3/17 Sat 18/2/17 Sat 18/3/17 100 100 0 0 days
180 3F Cast-in conduit, piping , Junction Box & Sleeves 10 days Sat 18/2/17 Wed 1/3/17 Sat 18/2/17 Wed 1/3/17 100 100 0 0 days
181 3F COLUMN 10 days Mon 20/3/17 Thu 30/3/17 Mon 20/3/17 Thu 30/3/17 100 100 0 0 days
182 4F 35 days Fri 31/3/17 Wed 10/5/17 Fri 31/3/17 Sat 8/7/17 100 11.11 -88.89 51 days
183 4F BEAM AND SLAB 25 days Fri 31/3/17 Fri 28/4/17 Fri 31/3/17 Tue 27/6/17 100 20 -80 51 days
184 4FCast-in conduit, piping , Junction Box & Sleeves 10 days Fri 31/3/17 Tue 11/4/17 Mon 5/6/17 Thu 15/6/17 100 0 -100 56 days
185 4FCOLUMN 10 days Sat 29/4/17 Wed 10/5/17 Wed 28/6/17 Sat 8/7/17 100 0 -100 51 days
186 5F 35 days Thu 11/5/17 Tue 20/6/17 Mon 10/7/17 Fri 18/8/17 68.89 0 -68.89 51 days
187 5F BEAM AND SLAB 25 days Thu 11/5/17 Thu 8/6/17 Mon 10/7/17 Mon 7/8/17 84 0 -84 51 days
188 5F Cast-in conduit, piping , Junction Box & Sleeves 10 days Thu 11/5/17 Mon 22/5/17 Mon 10/7/17 Thu 20/7/17 100 0 -100 51 days
189 5FCOLUMN 10 days Fri 9/6/17 Tue 20/6/17 Tue 8/8/17 Fri 18/8/17 0 0 0 51 days
190 6F 90 days Wed 21/6/17 Tue 3/10/17 Sat 19/8/17 Fri 1/12/17 0 0 0 51 days
195 RC RAMP (GL E-H/10-14) 160 days Wed 28/12/16 Sat 1/7/17 Wed 28/12/16 Mon 11/9/17 80 15 -65 61 days
201 ARCHITECTURE WORKS & M&E WORKS 221 days Sat 29/7/17 Thu 12/4/18 Thu 5/10/17 Tue 19/6/18 0 0 0 58 days
1347 TNB SUBSTATION (LEVEL GF) 120 days Tue 7/2/17 Mon 26/6/17 Tue 7/2/17 Wed 6/9/17 90.21 6.08 -84.13 61.2 days
1373 RESIDENTIAL BLOCK 681 days Thu 28/7/16 Sat 29/9/18 Thu 28/7/16 Fri 30/11/18 11.84 8.59 -3.25 53 days
1374 RC WORKS/M&E CAST-IN 550 days Thu 28/7/16 Tue 1/5/18 Thu 28/7/16 Sat 30/6/18 51.62 39.29 -12.33 53 days
1375 ROUND COLUMN 135 days Mon 8/8/16 Wed 11/1/17 Mon 8/8/16 Wed 11/1/17 100 100 0 0 days
1384 LEVEL GF 60 days Thu 28/7/16 Wed 5/10/16 Thu 28/7/16 Wed 5/10/16 100 100 0 0 days
1395 LEVEL 1F 18 days Mon 3/10/16 Sat 22/10/16 Mon 3/10/16 Sat 22/10/16 100 100 0 0 days
1401 LEVEL 2F 18 days Mon 17/10/16 Sat 5/11/16 Mon 17/10/16 Sat 5/11/16 100 100 0 0 days
1407 LEVEL 3F 19 days Thu 27/10/16 Thu 17/11/16 Thu 27/10/16 Thu 17/11/16 100 100 0 0 days
1413 LEVEL 4F 20 days Mon 7/11/16 Tue 29/11/16 Mon 7/11/16 Tue 29/11/16 100 100 0 0 days
1419 LEVEL 5F 21 days Thu 17/11/16 Sat 10/12/16 Thu 17/11/16 Sat 10/12/16 100 100 0 0 days
1425 LEVEL 6F 114 days Mon 19/9/16 Sat 28/1/17 Mon 19/9/16 Sat 28/1/17 100 100 0 0 days
1433 TRANSFER BEAM 50 days Tue 17/1/17 Wed 15/3/17 Tue 17/1/17 Wed 15/3/17 100 100 0 0 days
1435 Level 7F 138 days Mon 14/11/16 Sat 22/4/17 Mon 14/11/16 Wed 28/6/17 100 78.16 -21.84 57 days
1436 Design Submission & Approval 30 days Mon 14/11/16 Mon 19/12/16 Mon 14/11/16 Sat 17/12/16 100 100 0 0 days
1437 Fabrication & Delivery 75 days Mon 19/12/16 Thu 16/3/17 Mon 19/12/16 Wed 15/3/17 100 100 0 0 days
1438 Zone 1 14 days Thu 16/3/17 Fri 31/3/17 Thu 16/3/17 Thu 1/6/17 100 100 0 53 days
1439 Setting Out/Wall BRC/M&E 3 days Thu 16/3/17 Sat 18/3/17 Thu 16/3/17 Sat 18/3/17 100 100 0 0 days
1440 M&E to walls 2 days Sat 18/3/17 Mon 20/3/17 Sat 18/3/17 Mon 20/3/17 100 100 0 0 days
1441 Erect Wall Formwork 2 days Tue 21/3/17 Wed 22/3/17 Tue 21/3/17 Wed 22/3/17 100 100 0 0 days
1442 Erect Deck Formwork 2 days Wed 22/3/17 Thu 23/3/17 Wed 22/3/17 Thu 23/3/17 100 100 0 0 days
1443 Bottom BRC / M&E 2 days Fri 24/3/17 Sat 25/3/17 Fri 24/3/17 Sat 25/3/17 100 100 0 0 days
1444 M&E / Top BRC 2 days Sat 25/3/17 Mon 27/3/17 Sat 25/3/17 Mon 27/3/17 100 100 0 0 days
1445 Inspection/Concrete Wall & Slab/Staircase 2 days Tue 28/3/17 Wed 29/3/17 Tue 28/3/17 Wed 29/3/17 100 100 0 0 days
1446 Strip & Re-erect Props 2 days Thu 30/3/17 Fri 31/3/17 Thu 30/3/17 Thu 1/6/17 100 100 0 53 days
1447 Zone 2 13 days Wed 22/3/17 Wed 5/4/17 Wed 22/3/17 Fri 9/6/17 100 56.25 -43.75 56 days
1448 Setting Out/Wall BRC/M&E 2 days Wed 22/3/17 Thu 23/3/17 Wed 22/3/17 Thu 23/3/17 100 100 0 0 days
1449 M&E to walls 2 days Thu 23/3/17 Fri 24/3/17 Thu 23/3/17 Fri 24/3/17 100 100 0 0 days
1450 Erect Wall Formwork 2 days Sat 25/3/17 Mon 27/3/17 Sat 25/3/17 Mon 27/3/17 100 100 0 0 days
1451 Erect Deck Formwork 2 days Mon 27/3/17 Tue 28/3/17 Mon 27/3/17 Mon 5/6/17 100 50 -50 59 days
1452 Bottom BRC / M&E 2 days Wed 29/3/17 Thu 30/3/17 Wed 29/3/17 Tue 6/6/17 100 50 -50 58 days
1453 M&E / Top BRC 2 days Thu 30/3/17 Fri 31/3/17 Thu 30/3/17 Mon 5/6/17 100 50 -50 56 days
1454 Inspection/Concrete Wall & Slab/Staircase/Liftwall 2 days Sat 1/4/17 Mon 3/4/17 Tue 6/6/17 Wed 7/6/17 100 0 -100 56 days
1455 Strip & Re-erect Props 2 days Tue 4/4/17 Wed 5/4/17 Thu 8/6/17 Fri 9/6/17 100 0 -100 56 days
1456 Zone 3 13 days Mon 27/3/17 Mon 10/4/17 Mon 27/3/17 Mon 12/6/17 100 56.67 -43.33 54 days
1457 Setting Out/Wall BRC/M&E 2 days Mon 27/3/17 Tue 28/3/17 Mon 27/3/17 Tue 28/3/17 100 100 0 0 days
1458 M&E to walls 2 days Tue 28/3/17 Wed 29/3/17 Tue 28/3/17 Wed 29/3/17 100 100 0 0 days
1459 Erect Wall Formwork 2 days Thu 30/3/17 Fri 31/3/17 Thu 30/3/17 Fri 31/3/17 100 100 0 0 days
1460 Erect Deck Formwork 1 day Sat 1/4/17 Sat 1/4/17 Sat 1/4/17 Tue 6/6/17 100 50 -50 55.5 days
1461 Bottom BRC / M&E 2 days Mon 3/4/17 Tue 4/4/17 Mon 3/4/17 Wed 7/6/17 100 50 -50 55 days
1462 M&E / Top BRC 2 days Tue 4/4/17 Wed 5/4/17 Tue 4/4/17 Tue 6/6/17 100 50 -50 53 days
1463 Inspection/Concrete Wall & Slab/Staircase/Liftwall 2 days Thu 6/4/17 Fri 7/4/17 Thu 8/6/17 Fri 9/6/17 100 0 -100 54 days
1464 Strip & Re-erect Props 2 days Sat 8/4/17 Mon 10/4/17 Sat 10/6/17 Mon 12/6/17 100 0 -100 54 days
1465 Zone 4 13 days Fri 31/3/17 Fri 14/4/17 Fri 31/3/17 Wed 14/6/17 100 56.25 -43.75 52 days
1466 Setting Out/Wall BRC/M&E 2 days Fri 31/3/17 Sat 1/4/17 Fri 31/3/17 Sat 1/4/17 100 100 0 0 days
1467 M&E to walls 2 days Sat 1/4/17 Mon 3/4/17 Sat 1/4/17 Mon 3/4/17 100 100 0 0 days
1468 Erect Wall Formwork 2 days Tue 4/4/17 Wed 5/4/17 Tue 4/4/17 Wed 5/4/17 100 100 0 0 days
1469 Erect Deck Formwork 2 days Wed 5/4/17 Thu 6/4/17 Wed 5/4/17 Wed 7/6/17 100 50 -50 52.5 days
1470 Bottom BRC / M&E 2 days Fri 7/4/17 Sat 8/4/17 Fri 7/4/17 Thu 8/6/17 100 50 -50 52 days
1471 M&E / Top BRC 2 days Sat 8/4/17 Mon 10/4/17 Sat 8/4/17 Wed 7/6/17 100 50 -50 50 days
1472 Inspection/Concrete Wall & Slab/Staircase 2 days Tue 11/4/17 Wed 12/4/17 Sat 10/6/17 Mon 12/6/17 100 0 -100 52 days
1473 Strip & Re-erect Props 2 days Thu 13/4/17 Fri 14/4/17 Tue 13/6/17 Wed 14/6/17 100 0 -100 52 days
1474 Sky gardens 21 days Thu 30/3/17 Sat 22/4/17 Mon 5/6/17 Wed 28/6/17 100 0 -100 57 days
1475 Level 8F 12 days Tue 4/4/17 Mon 17/4/17 Mon 5/6/17 Wed 21/6/17 100 0 -100 57 days
1476 Zone 1 6 days Tue 4/4/17 Mon 10/4/17 Mon 5/6/17 Wed 14/6/17 100 0 -100 57 days
1477 Setting Out/Wall BRC/M&E 1 day Tue 4/4/17 Tue 4/4/17 Mon 5/6/17 Fri 9/6/17 100 0 -100 57 days
1478 M&E to walls 1 day Wed 5/4/17 Wed 5/4/17 Tue 6/6/17 Sat 10/6/17 100 0 -100 57 days
1479 Erect Wall Formwork 1 day Wed 5/4/17 Wed 5/4/17 Tue 6/6/17 Sat 10/6/17 100 0 -100 57 days
1480 Erect Deck Formwork 2 days Thu 6/4/17 Fri 7/4/17 Wed 7/6/17 Mon 12/6/17 100 0 -100 57 days
1481 Bottom BRC / M&E 1 day Fri 7/4/17 Fri 7/4/17 Thu 8/6/17 Mon 12/6/17 100 0 -100 57 days
1482 M&E / Top BRC 1 day Sat 8/4/17 Sat 8/4/17 Fri 9/6/17 Tue 13/6/17 100 0 -100 57 days
1483 Inspection/Concrete Wall & Slab/Staircase 1 day Sat 8/4/17 Sat 8/4/17 Fri 9/6/17 Tue 13/6/17 100 0 -100 57 days
1484 Strip & Re-erect Props 1 day Mon 10/4/17 Mon 10/4/17 Sat 10/6/17 Wed 14/6/17 100 0 -100 57 days
1485 Zone 2 6 days Thu 6/4/17 Wed 12/4/17 Wed 7/6/17 Sat 17/6/17 100 0 -100 57 days
1486 Setting Out/Wall BRC/M&E 1 day Thu 6/4/17 Thu 6/4/17 Wed 7/6/17 Sun 11/6/17 100 0 -100 57 days

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress

Prepared by : HSB Engineering Sdn Bhd Page 2 REVISION 3A


MIP (BASELINE)
AS OF 03/06/17
ID Task Name Baseline Duration Baseline Start Baseline Finish IMPACTED STARTIMPACTED FINISH SCH % ACT % % Varience Delay Days 2nd Quarter 1st Quarter 4th Quarter 3rd Quarter 2nd Quarter
J M S J M S J M S J
1487 M&E to walls 1 day Fri 7/4/17 Fri 7/4/17 Thu 8/6/17 Mon 12/6/17 100 0 -100 57 days
1488 Erect Wall Formwork 1 day Fri 7/4/17 Fri 7/4/17 Thu 8/6/17 Mon 12/6/17 100 0 -100 57 days
1489 Erect Deck Formwork 2 days Sat 8/4/17 Mon 10/4/17 Fri 9/6/17 Wed 14/6/17 100 0 -100 57 days
1490 Bottom BRC / M&E 1 day Mon 10/4/17 Mon 10/4/17 Sat 10/6/17 Wed 14/6/17 100 0 -100 57 days
1491 M&E / Top BRC 1 day Tue 11/4/17 Tue 11/4/17 Mon 12/6/17 Fri 16/6/17 100 0 -100 57 days
1492 Inspection/Concrete Wall & Slab/Staircase/Liftwall 1 day Tue 11/4/17 Tue 11/4/17 Mon 12/6/17 Fri 16/6/17 100 0 -100 57 days
1493 Strip & Re-erect Props 1 day Wed 12/4/17 Wed 12/4/17 Tue 13/6/17 Sat 17/6/17 100 0 -100 57 days
1494 Zone 3 6 days Sat 8/4/17 Fri 14/4/17 Fri 9/6/17 Mon 19/6/17 100 0 -100 57 days
1495 Setting Out/Wall BRC/M&E 1 day Sat 8/4/17 Sat 8/4/17 Fri 9/6/17 Tue 13/6/17 100 0 -100 57 days
1496 M&E to walls 1 day Mon 10/4/17 Mon 10/4/17 Sat 10/6/17 Wed 14/6/17 100 0 -100 57 days
1497 Erect Wall Formwork 1 day Mon 10/4/17 Mon 10/4/17 Sat 10/6/17 Wed 14/6/17 100 0 -100 57 days
1498 Erect Deck Formwork 2 days Tue 11/4/17 Wed 12/4/17 Mon 12/6/17 Sat 17/6/17 100 0 -100 57 days
1499 Bottom BRC / M&E 1 day Wed 12/4/17 Wed 12/4/17 Tue 13/6/17 Sat 17/6/17 100 0 -100 57 days
1500 M&E / Top BRC 1 day Thu 13/4/17 Thu 13/4/17 Wed 14/6/17 Sun 18/6/17 100 0 -100 57 days
1501 Inspection/Concrete Wall & Slab/Staircase/Liftwall 1 day Thu 13/4/17 Thu 13/4/17 Wed 14/6/17 Sun 18/6/17 100 0 -100 57 days
1502 Strip & Re-erect Props 1 day Fri 14/4/17 Fri 14/4/17 Thu 15/6/17 Mon 19/6/17 100 0 -100 57 days
1503 Zone 4 6 days Tue 11/4/17 Mon 17/4/17 Mon 12/6/17 Wed 21/6/17 100 0 -100 57 days
1504 Setting Out/Wall BRC/M&E 1 day Tue 11/4/17 Tue 11/4/17 Mon 12/6/17 Fri 16/6/17 100 0 -100 57 days
1505 M&E to walls 1 day Wed 12/4/17 Wed 12/4/17 Tue 13/6/17 Sat 17/6/17 100 0 -100 57 days
1506 Erect Wall Formwork 1 day Wed 12/4/17 Wed 12/4/17 Tue 13/6/17 Sat 17/6/17 100 0 -100 57 days
1507 Erect Deck Formwork 2 days Thu 13/4/17 Fri 14/4/17 Wed 14/6/17 Mon 19/6/17 100 0 -100 57 days
1508 Bottom BRC / M&E 1 day Fri 14/4/17 Fri 14/4/17 Thu 15/6/17 Mon 19/6/17 100 0 -100 57 days
1509 M&E / Top BRC 1 day Sat 15/4/17 Sat 15/4/17 Fri 16/6/17 Tue 20/6/17 100 0 -100 57 days
1510 Inspection/Concrete Wall & Slab/Staircase 1 day Sat 15/4/17 Sat 15/4/17 Fri 16/6/17 Tue 20/6/17 100 0 -100 57 days
1511 Strip & Re-erect Props 1 day Mon 17/4/17 Mon 17/4/17 Sat 17/6/17 Wed 21/6/17 100 0 -100 57 days
1512 Level 9F 12 days Thu 13/4/17 Wed 26/4/17 Wed 14/6/17 Sat 1/7/17 100 0 -100 57 days
1513 Zone 1 6 days Thu 13/4/17 Wed 19/4/17 Wed 14/6/17 Sat 24/6/17 100 0 -100 57 days
1514 Setting Out/Wall BRC/M&E 1 day Thu 13/4/17 Thu 13/4/17 Wed 14/6/17 Sun 18/6/17 100 0 -100 57 days
1515 M&E to walls 1 day Fri 14/4/17 Fri 14/4/17 Thu 15/6/17 Mon 19/6/17 100 0 -100 57 days
1516 Erect Wall Formwork 1 day Fri 14/4/17 Fri 14/4/17 Thu 15/6/17 Mon 19/6/17 100 0 -100 57 days
1517 Erect Deck Formwork 2 days Sat 15/4/17 Mon 17/4/17 Fri 16/6/17 Wed 21/6/17 100 0 -100 57 days
1518 Bottom BRC / M&E 1 day Mon 17/4/17 Mon 17/4/17 Sat 17/6/17 Wed 21/6/17 100 0 -100 57 days
1519 M&E / Top BRC 1 day Tue 18/4/17 Tue 18/4/17 Mon 19/6/17 Fri 23/6/17 100 0 -100 57 days
1520 Inspection/Concrete Wall & Slab/Staircase 1 day Tue 18/4/17 Tue 18/4/17 Mon 19/6/17 Fri 23/6/17 100 0 -100 57 days
1521 Strip & Re-erect Props 1 day Wed 19/4/17 Wed 19/4/17 Tue 20/6/17 Sat 24/6/17 100 0 -100 57 days
1522 Zone 2 6 days Sat 15/4/17 Fri 21/4/17 Fri 16/6/17 Mon 26/6/17 100 0 -100 57 days
1523 Setting Out/Wall BRC/M&E 1 day Sat 15/4/17 Sat 15/4/17 Fri 16/6/17 Tue 20/6/17 100 0 -100 57 days
1524 M&E to walls 1 day Mon 17/4/17 Mon 17/4/17 Sat 17/6/17 Wed 21/6/17 100 0 -100 57 days
1525 Erect Wall Formwork 1 day Mon 17/4/17 Mon 17/4/17 Sat 17/6/17 Wed 21/6/17 100 0 -100 57 days
1526 Erect Deck Formwork 2 days Tue 18/4/17 Wed 19/4/17 Mon 19/6/17 Sat 24/6/17 100 0 -100 57 days
1527 Bottom BRC / M&E 1 day Wed 19/4/17 Wed 19/4/17 Tue 20/6/17 Sat 24/6/17 100 0 -100 57 days
1528 M&E / Top BRC 1 day Thu 20/4/17 Thu 20/4/17 Wed 21/6/17 Sun 25/6/17 100 0 -100 57 days
1529 Inspection/Concrete Wall & Slab/Staircase/Liftwall 1 day Thu 20/4/17 Thu 20/4/17 Wed 21/6/17 Sun 25/6/17 100 0 -100 57 days
1530 Strip & Re-erect Props 1 day Fri 21/4/17 Fri 21/4/17 Thu 22/6/17 Mon 26/6/17 100 0 -100 57 days
1531 Zone 3 6 days Tue 18/4/17 Mon 24/4/17 Mon 19/6/17 Wed 28/6/17 100 0 -100 57 days
1532 Setting Out/Wall BRC/M&E 1 day Tue 18/4/17 Tue 18/4/17 Mon 19/6/17 Fri 23/6/17 100 0 -100 57 days
1533 M&E to walls 1 day Wed 19/4/17 Wed 19/4/17 Tue 20/6/17 Sat 24/6/17 100 0 -100 57 days
1534 Erect Wall Formwork 1 day Wed 19/4/17 Wed 19/4/17 Tue 20/6/17 Sat 24/6/17 100 0 -100 57 days
1535 Erect Deck Formwork 2 days Thu 20/4/17 Fri 21/4/17 Wed 21/6/17 Mon 26/6/17 100 0 -100 57 days
1536 Bottom BRC / M&E 1 day Fri 21/4/17 Fri 21/4/17 Thu 22/6/17 Mon 26/6/17 100 0 -100 57 days
1537 M&E / Top BRC 1 day Sat 22/4/17 Sat 22/4/17 Fri 23/6/17 Tue 27/6/17 100 0 -100 57 days
1538 Inspection/Concrete Wall & Slab/Staircase/Liftwall 1 day Sat 22/4/17 Sat 22/4/17 Fri 23/6/17 Tue 27/6/17 100 0 -100 57 days
1539 Strip & Re-erect Props 1 day Mon 24/4/17 Mon 24/4/17 Sat 24/6/17 Wed 28/6/17 100 0 -100 57 days
1540 Zone 4 6 days Thu 20/4/17 Wed 26/4/17 Wed 21/6/17 Sat 1/7/17 100 0 -100 57 days
1541 Setting Out/Wall BRC/M&E 1 day Thu 20/4/17 Thu 20/4/17 Wed 21/6/17 Sun 25/6/17 100 0 -100 57 days
1542 M&E to walls 1 day Fri 21/4/17 Fri 21/4/17 Thu 22/6/17 Mon 26/6/17 100 0 -100 57 days
1543 Erect Wall Formwork 1 day Fri 21/4/17 Fri 21/4/17 Thu 22/6/17 Mon 26/6/17 100 0 -100 57 days
1544 Erect Deck Formwork 2 days Sat 22/4/17 Mon 24/4/17 Fri 23/6/17 Wed 28/6/17 100 0 -100 57 days
1545 Bottom BRC / M&E 1 day Mon 24/4/17 Mon 24/4/17 Sat 24/6/17 Wed 28/6/17 100 0 -100 57 days
1546 M&E / Top BRC 1 day Tue 25/4/17 Tue 25/4/17 Mon 26/6/17 Fri 30/6/17 100 0 -100 57 days
1547 Inspection/Concrete Wall & Slab/Staircase 1 day Tue 25/4/17 Tue 25/4/17 Mon 26/6/17 Fri 30/6/17 100 0 -100 57 days
1548 Strip & Re-erect Props 1 day Wed 26/4/17 Wed 26/4/17 Tue 27/6/17 Sat 1/7/17 100 0 -100 57 days
1549 Level 10F 12 days Sat 22/4/17 Fri 5/5/17 Fri 23/6/17 Mon 10/7/17 100 0 -100 57 days
1586 Level 11F 12 days Tue 2/5/17 Mon 15/5/17 Mon 3/7/17 Wed 19/7/17 100 0 -100 57 days
1623 Level 12F 12 days Thu 11/5/17 Wed 24/5/17 Wed 12/7/17 Sat 29/7/17 100 0 -100 57 days
1660 Level 13F 12 days Sat 20/5/17 Fri 2/6/17 Fri 21/7/17 Mon 7/8/17 100 0 -100 57 days
1697 Level 14F 12 days Tue 30/5/17 Mon 12/6/17 Mon 31/7/17 Wed 16/8/17 36.11 0 -36.11 57 days
1734 Level 15F 12 days Thu 8/6/17 Wed 21/6/17 Wed 9/8/17 Sat 26/8/17 0 0 0 57 days
1771 Level 16F 12 days Sat 17/6/17 Fri 30/6/17 Fri 18/8/17 Mon 4/9/17 0 0 0 57 days
1808 Level 17F 12 days Tue 27/6/17 Mon 10/7/17 Mon 28/8/17 Wed 13/9/17 0 0 0 57 days
1845 Level 18F 12 days Thu 6/7/17 Wed 19/7/17 Wed 6/9/17 Sat 23/9/17 0 0 0 57 days
1882 Level 19F 12 days Sat 15/7/17 Fri 28/7/17 Fri 15/9/17 Mon 2/10/17 0 0 0 57 days
1919 Level 20F 12 days Tue 25/7/17 Mon 7/8/17 Mon 25/9/17 Wed 11/10/17 0 0 0 57 days
1956 Level 21F 12 days Thu 3/8/17 Wed 16/8/17 Wed 4/10/17 Sat 21/10/17 0 0 0 57 days
1993 Level 22F 12 days Sat 12/8/17 Fri 25/8/17 Fri 13/10/17 Mon 30/10/17 0 0 0 57 days
2030 Sky Gardens LV. 19,20,21 35 days Sat 26/8/17 Thu 5/10/17 Fri 27/10/17 Sun 10/12/17 0 0 0 57 days
2031 Level 23F 12 days Tue 22/8/17 Mon 4/9/17 Mon 23/10/17 Wed 8/11/17 0 0 0 57 days
2068 Level 24F 12 days Thu 31/8/17 Wed 13/9/17 Wed 1/11/17 Sat 18/11/17 0 0 0 57 days
2105 Level 25F 12 days Sat 9/9/17 Fri 22/9/17 Fri 10/11/17 Mon 27/11/17 0 0 0 57 days
2142 Level 26F 12 days Tue 19/9/17 Mon 2/10/17 Mon 20/11/17 Wed 6/12/17 0 0 0 57 days
2179 Level 27F 12 days Thu 28/9/17 Wed 11/10/17 Wed 29/11/17 Sat 16/12/17 0 0 0 57 days
2216 Level 28F 12 days Sat 7/10/17 Fri 20/10/17 Fri 8/12/17 Mon 25/12/17 0 0 0 57 days
2253 Level 29F 12 days Tue 17/10/17 Mon 30/10/17 Mon 18/12/17 Wed 3/1/18 0 0 0 57 days
2290 Level 30F 12 days Thu 26/10/17 Wed 8/11/17 Wed 27/12/17 Sat 13/1/18 0 0 0 57 days
2327 Level 31F 12 days Sat 4/11/17 Fri 17/11/17 Fri 5/1/18 Mon 22/1/18 0 0 0 57 days
2364 Sky Garden LV. 29,30,31 35 days Sat 18/11/17 Thu 28/12/17 Fri 19/1/18 Sun 4/3/18 0 0 0 57 days
2365 Level 32F 12 days Tue 14/11/17 Mon 27/11/17 Mon 15/1/18 Wed 31/1/18 0 0 0 57 days
2402 Level 33F 10 days Thu 23/11/17 Mon 4/12/17 Wed 24/1/18 Wed 7/2/18 0 0 0 57 days
2439 Level 34F 10 days Thu 30/11/17 Mon 11/12/17 Wed 31/1/18 Wed 14/2/18 0 0 0 57 days
2476 Level 35F 10 days Thu 7/12/17 Mon 18/12/17 Wed 7/2/18 Wed 21/2/18 0 0 0 57 days
2513 Level 36F 10 days Thu 14/12/17 Mon 25/12/17 Wed 14/2/18 Wed 28/2/18 0 0 0 57 days
2550 Level 37F 10 days Thu 21/12/17 Mon 1/1/18 Wed 21/2/18 Wed 7/3/18 0 0 0 57 days

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress

Prepared by : HSB Engineering Sdn Bhd Page 3 REVISION 3A


MIP (BASELINE)
AS OF 03/06/17
ID Task Name Baseline Duration Baseline Start Baseline Finish IMPACTED STARTIMPACTED FINISH SCH % ACT % % Varience Delay Days 2nd Quarter 1st Quarter 4th Quarter 3rd Quarter 2nd Quarter
J M S J M S J M S J
2587 Level 38F 10 days Thu 28/12/17 Mon 8/1/18 Wed 28/2/18 Wed 14/3/18 0 0 0 57 days
2624 Level 39F 10 days Thu 4/1/18 Mon 15/1/18 Wed 7/3/18 Wed 21/3/18 0 0 0 57 days
2661 Level 40F 10 days Thu 11/1/18 Mon 22/1/18 Wed 14/3/18 Wed 28/3/18 0 0 0 57 days
2698 LEVEL 41F 12 days Thu 18/1/18 Wed 31/1/18 Wed 21/3/18 Sat 7/4/18 0 0 0 57 days
2702 LEVEL RF 13 days Mon 29/1/18 Mon 12/2/18 Sat 31/3/18 Wed 18/4/18 0 0 0 57 days
2707 Tower Crane Dismantling 0 days Tue 1/5/18 Tue 1/5/18 Sat 30/6/18 Wed 4/7/18 0 0 0 57 days 30/6
2708 MOCK-UP 79 days Mon 17/4/17 Mon 17/7/17 Sat 17/6/17 Wed 20/9/17 54.59 0 -54.59 57 days
2771 ARCHITECTURE WORKS / M&E 1ST AND 2ND FIX (1-11/A-P)
415 days Sat 4/3/17 Sat 30/6/18 Sat 4/3/17 Wed 4/7/18 2.7 2.7 0 4 days
4573 Loose Fitting 192 days Mon 27/11/17 Sat 7/7/18 Mon 27/11/17 Wed 11/7/18 0 0 0 4 days
4581 Aluminum Faade 120 days Sat 24/3/18 Fri 10/8/18 Sat 24/3/18 Tue 14/8/18 0 0 0 4 days
4583 BUILDING CLEANUP 5 days Fri 10/8/18 Thu 16/8/18 Sat 11/8/18 Mon 20/8/18 0 0 0 4 days
4585 EXTERNAL WALL 397 days Mon 15/5/17 Mon 20/8/18 Mon 22/5/17 Tue 23/10/18 3.5 0 -3.5 56 days
4609 MECHANICAL AND ELECTRICAL WORKS -FINAL FIX 357 days Thu 10/8/17 Sat 29/9/18 Thu 10/8/17 Tue 4/12/18 0 0 0 57 days
4849 EXTERNAL WORKS 455 days Thu 2/3/17 Tue 14/8/18 Thu 2/3/17 Tue 4/9/18 4.71 4.01 -0.7 19 days
4929 DEMOBILISATION & HANDOVER 100 days Wed 6/6/18 Sat 29/9/18 Wed 20/6/18 Tue 4/12/18 0 0 0 57 days

Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress

Prepared by : HSB Engineering Sdn Bhd Page 4 REVISION 3A

Das könnte Ihnen auch gefallen