AS OF 03/06/17
ID Task Name Baseline Duration Baseline Start Baseline Finish IMPACTED STARTIMPACTED FINISH SCH % ACT % % Varience Delay Days 2nd Quarter 1st Quarter 4th Quarter 3rd Quarter 2nd Quarter
J M S J M S J M S J
1 CADANGAN 1 BLOK PANGSAPURI 41 TINGKAT (243 UNIT) 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 15.16 11.85 -3.31 57 days
2 MILESTONE 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 57 days
3 PROJECT MILESTONE 730 days Wed 1/6/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 57 days
7 CONSTRUCTION MILESONE 680 days Thu 28/7/16 Sat 29/9/18 Wed 1/6/16 Tue 4/12/18 0 0 0 58 days
31 MILESTONE FOR AWARD OF DIRECTOR CONTRACTORS 585 days Tue 5/7/16 Sat 19/5/18 Tue 5/7/16 Sat 2/6/18 0 0 0 12 days
47 PRE-CONSTRUCTION WORKS 49 days Wed 1/6/16 Wed 27/7/16 Wed 1/6/16 Sun 31/7/16 100 100 0 0 days
48 PRELIMINARY 49 days Wed 1/6/16 Wed 27/7/16 Wed 1/6/16 Wed 27/7/16 100 100 0 0 days
58 CONSTRUCTION WORKS 709 days Fri 24/6/16 Sat 29/9/18 Fri 24/6/16 Tue 4/12/18 15.27 11.77 -3.5 57 days
59 PILECAPS AND STUMP 0 days Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 0 0 0 0 days 24/6
60 RC WORK COMPLETED AND VERIFIED BY SURVEYOR 0 days Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 Fri 24/6/16 0 0 0 0 days 24/6
61 CARPARK 535 days Thu 28/7/16 Thu 12/4/18 Thu 28/7/16 Tue 19/6/18 22.41 15.31 -7.1 58 days
62 RC WORKS/M&E CAST-IN 371 days Thu 28/7/16 Tue 3/10/17 Thu 28/7/16 Fri 1/12/17 78 53.28 -24.72 51 days
63 ZONE 1 (GL A-F/11-15) 314 days Thu 28/7/16 Fri 28/7/17 Thu 28/7/16 Wed 4/10/17 84.21 60.18 -24.03 58 days
64 GF 99 days Thu 28/7/16 Sat 19/11/16 Thu 28/7/16 Sat 19/11/16 100 100 0 0 days
65 GF BEAM 30 days Thu 28/7/16 Wed 31/8/16 Thu 28/7/16 Wed 31/8/16 100 100 0 0 days
66 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Thu 1/9/16 Sat 17/9/16 Thu 1/9/16 Sat 17/9/16 100 100 0 0 days
67 GF SLAB 21 days Mon 3/10/16 Wed 26/10/16 Mon 3/10/16 Wed 26/10/16 100 100 0 0 days
68 GF COLUMN 21 days Thu 27/10/16 Sat 19/11/16 Thu 27/10/16 Sat 19/11/16 100 100 0 0 days
69 1F 35 days Mon 21/11/16 Fri 30/12/16 Mon 21/11/16 Fri 30/12/16 100 100 0 0 days
70 1F BEAM AND SLAB 25 days Mon 21/11/16 Mon 19/12/16 Mon 21/11/16 Mon 19/12/16 100 100 0 0 days
71 1F Cast-in conduit, piping , Junction Box & Sleeves 10 days Mon 21/11/16 Thu 1/12/16 Mon 21/11/16 Thu 1/12/16 100 100 0 0 days
72 1F COLUMN 10 days Tue 20/12/16 Fri 30/12/16 Tue 20/12/16 Fri 30/12/16 100 100 0 0 days
73 2F 35 days Sat 31/12/16 Thu 9/2/17 Sat 31/12/16 Thu 9/2/17 100 100 0 0 days
74 2F BEAM AND SLAB 25 days Sat 31/12/16 Sat 28/1/17 Sat 31/12/16 Sat 28/1/17 100 100 0 0 days
75 2F Cast-in conduit, piping , Junction Box & Sleeves 10 days Sat 31/12/16 Wed 11/1/17 Sat 31/12/16 Wed 11/1/17 100 100 0 0 days
76 2F COLUMN 10 days Mon 30/1/17 Thu 9/2/17 Mon 30/1/17 Thu 9/2/17 100 100 0 0 days
77 3F 35 days Fri 10/2/17 Wed 22/3/17 Fri 10/2/17 Wed 22/3/17 100 100 0 0 days
78 3F BEAM AND SLAB 25 days Fri 10/2/17 Fri 10/3/17 Fri 10/2/17 Fri 10/3/17 100 100 0 0 days
79 3F Cast-in conduit, piping , Junction Box & Sleeves 10 days Fri 10/2/17 Tue 21/2/17 Fri 10/2/17 Tue 21/2/17 100 100 0 0 days
80 3F COLUMN 10 days Sat 11/3/17 Wed 22/3/17 Sat 11/3/17 Wed 22/3/17 100 100 0 0 days
81 4F 35 days Thu 23/3/17 Tue 2/5/17 Thu 23/3/17 Sat 8/7/17 100 11.11 -88.89 58 days
82 4F BEAM AND SLAB 25 days Thu 23/3/17 Thu 20/4/17 Thu 23/3/17 Tue 27/6/17 100 20 -80 58 days
83 4FCast-in conduit, piping , Junction Box & Sleeves 10 days Thu 23/3/17 Mon 3/4/17 Mon 5/6/17 Thu 15/6/17 100 0 -100 63 days
84 4FCOLUMN 10 days Fri 21/4/17 Tue 2/5/17 Wed 28/6/17 Sat 8/7/17 100 0 -100 58 days
85 5F 35 days Wed 3/5/17 Mon 12/6/17 Mon 10/7/17 Fri 18/8/17 84.45 0 -84.45 58 days
86 5F BEAM AND SLAB 25 days Wed 3/5/17 Wed 31/5/17 Mon 10/7/17 Mon 7/8/17 100 0 -100 58 days
87 5F Cast-in conduit, piping , Junction Box & Sleeves 10 days Wed 3/5/17 Sat 13/5/17 Mon 10/7/17 Thu 20/7/17 100 0 -100 58 days
88 5FCOLUMN 10 days Thu 1/6/17 Mon 12/6/17 Tue 8/8/17 Fri 18/8/17 30 0 -30 58 days
89 6F 35 days Tue 13/6/17 Sat 22/7/17 Sat 19/8/17 Thu 28/9/17 0 0 0 58 days
92 STAIRCASE 190 days Tue 20/12/16 Fri 28/7/17 Tue 20/12/16 Wed 4/10/17 70 40 -30 58 days
99 ZONE 2 (GL A-F/15-19) 329 days Wed 17/8/16 Mon 4/9/17 Wed 17/8/16 Sat 21/10/17 75.53 49.83 -25.7 41 days
100 GF 75 days Wed 17/8/16 Fri 11/11/16 Wed 17/8/16 Fri 11/11/16 100 100 0 0 days
101 GF BEAM 30 days Wed 17/8/16 Tue 20/9/16 Wed 17/8/16 Tue 20/9/16 100 100 0 0 days
102 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Wed 21/9/16 Fri 7/10/16 Wed 21/9/16 Fri 7/10/16 100 100 0 0 days
103 GF SLAB 21 days Tue 11/10/16 Thu 3/11/16 Tue 11/10/16 Thu 3/11/16 100 100 0 0 days
104 GF COLUMN 21 days Wed 19/10/16 Fri 11/11/16 Wed 19/10/16 Fri 11/11/16 100 100 0 0 days
105 1F 42 days Thu 8/12/16 Wed 25/1/17 Thu 8/12/16 Wed 25/1/17 100 100 0 0 days
106 1F BEAM AND SLAB 30 days Thu 8/12/16 Wed 11/1/17 Thu 8/12/16 Wed 11/1/17 100 100 0 0 days
107 1F COLUMN 12 days Thu 12/1/17 Wed 25/1/17 Thu 12/1/17 Wed 25/1/17 100 100 0 0 days
108 2F 35 days Thu 26/1/17 Tue 7/3/17 Thu 26/1/17 Tue 7/3/17 100 100 0 0 days
109 2F BEAM AND SLAB 25 days Thu 26/1/17 Thu 23/2/17 Thu 26/1/17 Thu 23/2/17 100 100 0 0 days
110 2F COLUMN 10 days Fri 24/2/17 Tue 7/3/17 Fri 24/2/17 Tue 7/3/17 100 100 0 0 days
111 3F 35 days Wed 8/3/17 Mon 17/4/17 Wed 8/3/17 Mon 17/4/17 100 100 0 0 days
112 3F BEAM AND SLAB 25 days Wed 8/3/17 Wed 5/4/17 Wed 8/3/17 Wed 5/4/17 100 100 0 0 days
113 3F COLUMN 10 days Thu 6/4/17 Mon 17/4/17 Thu 6/4/17 Mon 17/4/17 100 100 0 0 days
114 4F 35 days Tue 18/4/17 Sat 27/5/17 Mon 5/6/17 Fri 14/7/17 100 0 -100 41 days
115 4F BEAM AND SLAB 25 days Tue 18/4/17 Tue 16/5/17 Mon 5/6/17 Mon 3/7/17 100 0 -100 41 days
116 4FCOLUMN 10 days Wed 17/5/17 Sat 27/5/17 Tue 4/7/17 Fri 14/7/17 100 0 -100 41 days
117 5F 35 days Mon 29/5/17 Fri 7/7/17 Sat 15/7/17 Thu 24/8/17 17.14 0 -17.14 41 days
118 5F BEAM AND SLAB 25 days Mon 29/5/17 Mon 26/6/17 Sat 15/7/17 Sat 12/8/17 24 0 -24 41 days
119 5FCOLUMN 10 days Tue 27/6/17 Fri 7/7/17 Mon 14/8/17 Thu 24/8/17 0 0 0 41 days
120 6F 30 days Sat 8/7/17 Fri 11/8/17 Fri 25/8/17 Thu 28/9/17 0 0 0 41 days
122 RC RAMP (GL E-H/14-19) 162 days Thu 12/1/17 Wed 19/7/17 Thu 12/1/17 Tue 5/9/17 76 20 -56 41 days
128 STAIRCASE 202 days Thu 12/1/17 Mon 4/9/17 Thu 12/1/17 Sat 21/10/17 63.33 33 -30.33 41 days
135 ZONE 3 (GL F-K/15-19) 285 days Wed 31/8/16 Fri 28/7/17 Wed 31/8/16 Tue 10/10/17 86.65 63.07 -23.58 63 days
136 GF 70 days Wed 31/8/16 Sat 19/11/16 Wed 31/8/16 Sat 19/11/16 100 100 0 0 days
137 GF BEAM 30 days Wed 31/8/16 Tue 4/10/16 Wed 31/8/16 Tue 4/10/16 100 100 0 0 days
138 GF Cast-in conduit, piping , Junction Box & Sleeves 15 days Wed 5/10/16 Fri 21/10/16 Wed 5/10/16 Fri 21/10/16 100 100 0 0 days
139 GF SLAB 21 days Wed 19/10/16 Fri 11/11/16 Wed 19/10/16 Fri 11/11/16 100 100 0 0 days
140 GF COLUMN 21 days Thu 27/10/16 Sat 19/11/16 Thu 27/10/16 Sat 19/11/16 100 100 0 0 days
141 1F 35 days Mon 21/11/16 Fri 30/12/16 Mon 21/11/16 Fri 30/12/16 100 100 0 0 days
142 1F BEAM AND SLAB 25 days Mon 21/11/16 Mon 19/12/16 Mon 21/11/16 Mon 19/12/16 100 100 0 0 days
143 1F Cast-in conduit, piping , Junction Box & Sleeves 10 days Mon 21/11/16 Thu 1/12/16 Mon 21/11/16 Thu 1/12/16 100 100 0 0 days
144 1F COLUMN 10 days Tue 20/12/16 Fri 30/12/16 Tue 20/12/16 Fri 30/12/16 100 100 0 0 days
145 2F 35 days Sat 31/12/16 Thu 9/2/17 Sat 31/12/16 Thu 9/2/17 100 100 0 0 days
146 2F BEAM AND SLAB 25 days Sat 31/12/16 Sat 28/1/17 Sat 31/12/16 Sat 28/1/17 100 100 0 0 days
147 2F Cast-in conduit, piping , Junction Box & Sleeves 10 days Sat 31/12/16 Wed 11/1/17 Sat 31/12/16 Wed 11/1/17 100 100 0 0 days
148 2F COLUMN 10 days Mon 30/1/17 Thu 9/2/17 Mon 30/1/17 Thu 9/2/17 100 100 0 0 days
149 3F 35 days Fri 10/2/17 Wed 22/3/17 Fri 10/2/17 Wed 22/3/17 100 100 0 0 days
150 3F BEAM AND SLAB 25 days Fri 10/2/17 Fri 10/3/17 Fri 10/2/17 Fri 10/3/17 100 100 0 0 days
151 3F Cast-in conduit, piping , Junction Box & Sleeves 10 days Fri 10/2/17 Tue 21/2/17 Fri 10/2/17 Tue 21/2/17 100 100 0 0 days
152 3F COLUMN 10 days Sat 11/3/17 Wed 22/3/17 Sat 11/3/17 Wed 22/3/17 100 100 0 0 days
153 4F 35 days Thu 23/3/17 Tue 2/5/17 Mon 5/6/17 Fri 14/7/17 100 0 -100 63 days
154 4F BEAM AND SLAB 25 days Thu 23/3/17 Thu 20/4/17 Mon 5/6/17 Mon 3/7/17 100 0 -100 63 days
155 4FCast-in conduit, piping , Junction Box & Sleeves 10 days Thu 23/3/17 Mon 3/4/17 Mon 5/6/17 Thu 15/6/17 100 0 -100 63 days
156 4FCOLUMN 10 days Fri 21/4/17 Tue 2/5/17 Tue 4/7/17 Fri 14/7/17 100 0 -100 63 days
157 5F 35 days Wed 3/5/17 Mon 12/6/17 Sat 15/7/17 Thu 24/8/17 84.45 0 -84.45 63 days
158 5F BEAM AND SLAB 25 days Wed 3/5/17 Wed 31/5/17 Sat 15/7/17 Sat 12/8/17 100 0 -100 63 days
159 5F Cast-in conduit, piping , Junction Box & Sleeves 10 days Wed 3/5/17 Sat 13/5/17 Sat 15/7/17 Wed 26/7/17 100 0 -100 63 days
160 5FCOLUMN 10 days Thu 1/6/17 Mon 12/6/17 Mon 14/8/17 Thu 24/8/17 30 0 -30 63 days
161 6F 40 days Tue 13/6/17 Fri 28/7/17 Fri 25/8/17 Tue 10/10/17 0 0 0 63 days
164 ZONE 4 (GL F-K/11-15) 330 days Wed 14/9/16 Tue 3/10/17 Wed 14/9/16 Fri 1/12/17 69.74 44.65 -25.09 51 days
Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress
Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress
Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress
Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline Critical Split
Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Progress