PROJECT SUMMARY

SERIAL NAME OF PROJECT CONTRACT NO PROJECT STATUS WORK DONE ONGOING WORK WORK TO BE DONE
NO.
1 Improvements to AUM road project-stage-II RDA/DW/EP/JICA/2011/05 Completed.
2 Construction of new bridge over Pallanoya RDA/DW/EP/GOSL/2012/118 Completed.
3 Widening and improvements on Uththarama road project RDA/DW/PD(AKK)/CE(AMP)WO/MNRCE/2013/10 Completed.

4 Widening and improvements to Moragahapallama to Pathagoda road RDA/DW/PD(AKK)/CE(AMP)WO/MNRCE/2013/08 In progress. 1.5km asphalt 500m ABC 3km asphalt paving.
completed. overlaying and final
cutting.

2.5km section Embankment Road marking.


primed. construction.

4km shoulder Turfing. 500m shoulder


completed. construction.

5 Improvements to construction of bridge No. 39/4 on SDA road RDA/UKSBP2/EP/ATLAS/002 In progress. Bridge launching Ballast wall & End
completed. Formwork & pillaster concrete.
Reinforcement for
ballast wall.
Construction of
Embankment approaches.
construction for
approaches.
Construction of
headwall, catch pit &
Construction of concrete drain.
filter layer behind
abutment.
6 Construction of bridge across Dambe-Ela at Namal oya RDA/RBCD/EP/GOSL/019 In progress. Excavation for Rock blasting for Bridge construction.
foundation pocket filling.
completed.

7 Construction of bridge across Irrigation canal at Ambagahawela RDA/RBCD/EP/GOSL/020 Not yet started.
8 Construction of bridge across Meda oya at Pannalgama, Bakmittiyawa RDA/RBCD/EP/GOSL/021 In progress. Excavation for Reinforcement for Bridge construction.
foundation & base at pannalgama
pocket filling end.
completed in
Pannalgama end.

9 Construction of bridge across Namal Oya at Gamapaha Koloniya RDA/RBCD/EP/GOSL/024 In progress. Setting out Excavation for Bridge construction.
completed. foundation of pier.

10 Improvements to Bakmittiyawa bridge RDA/RBCD/EP/GOSL/023 Not yet started.

Prepared by :- Eng.S.Sanjeevkanth
Chief Engineer's office,
RDA, Ampara.