Sie sind auf Seite 1von 20

THE ARUP JOURNAL

4/"1994
Front cover:

THEARUP Fabric membrane. designed by Arups , on the Deliberatif at Marsei lle Hotel
du Departement. (Photo: Paul Rafferty)
Back cover:
Allt-Ruigh Bridge, Glencoe. (Photo: Jim Burridge)

JOURNAL
Vol.29 No.4 Editor:
4/ 1994 David J. Brown
Art Editor:
Published by Desmond Wyeth FCSD
Ove Arup Partnership
13 Fitzroy Street, Deputy Editor:
London W1 P 680 Helene Murphy
Editorial:
Tel : 0171 636 1531 Tel : 0171 465 3828
Fax: 0171 580 3924 Fax: 0171 465 3716

3
Hotel du The new county hall in Marseille for the Departement des Bouches-
Departement, du-Rhone is one of the most significant French public buildings of
Marseille recent years . Ove Arup & Partners designed the structure - derived
Bob Lang from a modular order that embraces the building's separate
Hugh Muirhead elements - and servicing , which incorporates an extensive use of
natural light and ventilation .

10
Motorway Widening existing motorways offers a huge range of engineering
widening and environmental challenges . Many parts of Arups have
projects contributed to the attempts to solve these problems, and the firm 's
Phil Hall expertise on major highways over the years has contributed to the
innovative approach needed to ensure that the widening programme
is handled in a sensitive but practical manner. The firm is currently
involved with widening sections of the M 1, M6. M25 , and M42.

16
Sellafield Ove Arup & Partners were commissioned by British Nuclear Fuels
geotechnical to investigate the geological suitability of a site at Sellafield for the
study construction of a proposed pressurized water reactor.
Colin Curtis
Andrew Law
David Pascall

17
Sellafield In another separate commission for BNFL. Arups carried out a
seawater comprehensive examination of the options for constructing
cooling tunnelling to convey seawater from the Irish Sea to the proposed
system PWR .
Martyn Stroud
Hakop Mirzabaigian

19
Allt-Ruigh This new arch bridge in the Highlands of Scotland was designed
Bridge, by Arups to blend unobtrusively with the natural beauty of its
Glencoe setting .
Jim Burridge

Note: The photo on p. 18of TheArupJournal 2/94]


captioned as Pagbllao p_ower sta. lion in fact showed a
model of Shenzhen lnternatiOnaJ Economic Trade
J Centre, Guangdong, China The scheme was
~igned by SOM with no Arup involvement.

2
1. The completed building from the east: Deliberatif in the foreground , Administratif behind.

Hotel du Departement, Marseille


Bob Lang Hugh Mu irhead
Introduction two atria, and a long, curved-section building ,
In early 1990 the French Departement des the Deliberatif, to house the council chambers .
Bouches-du-Rhone announced an open , The blocks were to be tall and thin , so much
international design competition for a new could be made of natural ventilation and ther-
local government headquarters in Marseille. mal control from buffer zones formed by
156 entries were received , from which five external corridors and circulation spaces.
were selected in April 1990 to extend their However. building height restrictions intro-
proposals. These were narrowed down to two duced after the competition finally called for a
in June, when the jury sat and the design much shorter. wider. treatment. using internal
teams presented their schemes in detail. circulation . The buffer zones were thus omit-
Alsop & Lyall (latterly William Alsop Architects). ted and attention focused on wind effects to
with Ove Arup & Partners as engineers and assist climate moderation.
Hanscomb Ltd. quantity surveyors, were suc-
By careful manipulation of the building cross-
cessful and announced as winners in July 1990.
section. pressure profiles and controlled
The competition-winning design made much aerodynamics could be grasped and used.
of the local climate of Marseille, where people
are used to wide temperature variation and Furthermore, the external environment around
strong winds: the notorious mistral is a feature such a building mass could be made more
of life in this part of France. Where possible, hospitable.
these natural phenomena were exploited to As seen today, the building has two major
articulate the form of the building and make a elements of office space, the Administratif; and
real contribution to how it would function . the long, profiled, Deliberatif, containing the
The essential elements of the brief were to chambers and conference space .
create 75 000m 2 of office and conference Though perceived as a piece of visionary archi-
space, (excluding terraces, plant areas and tecture, the building owes much to technical
storage) . and 1000 below-ground car parking rationale . Some of the issues and their solu-
spaces . Also the St Just metro station - well tions are described in the following pages; in
within the curtilage of the site - had to be such a short space, however, it is difficult to do
retained . All this led to a first scheme com- justice to the plethora of design challenges
prising three rows of office blocks spaced by and the processes involved in solving them .
THE ARUP JOURNAL 4/ 1994 3
Possible future
highrise building l The site
The building as a whole was conceived in
section. leading to an extruded form by virtue

I
of the section being repeated and so becom-
ing a linear building. When such a linear form
is superimposed on the site a number of fun-
damental design issues arise. The northern
one-third of the site is traversed obliquely by
the St. Just metro station; roughly orientated
2. south-west to north-east and semi-buried as it
Site p lan . was, the metro had to be built over to accom-
1-4 Adm1rnstratif modate a linear building. It was accepted that
1 Stock A transfer structures would be required and that
2 Atrtum these would play a fundamental role in how
3 Ovoid within Atrium the building was organized . The metro contin-
Salle de Rock 4 Block B with Aerofil
above ues its journey south below ground and the
Auditorium
5 Dellberatif
tunnel forms the site's western boundary.
Again. this gave clues as to how the building
might be arranged. if overly complex founda-
tions were to be avoided.
The eastern and southern boundaries are
bordered by highways raised 6-8m above a
generally flat site. Their retaining structures
made it preferable to keep them as they were.
which in turn implied that a new perimeter
' road might act as separation between new
,' ' ,/',
and old, again avoiding awkward foundations.
: som
The geography and geometry of the site, as
always, gave clues as to how any develop-
ment might function. Predominant winds. for
54 54 54 54 example. accelerate through and above val-
leys and hills to the north , arriving over subur-
ban terrain as the mistral. Potentially both
friend and foe, the wind effects obviously
required careful study, but if well understood
might be used to advantage. In terms of
climate, therefore, the approximately north-
south major axis of the site presented design
opportunities. An east-west axis naturally
prompted consideration of sun-path and light
intensity. Although the site was flanked by the
eastern highway, there was little natural shad-
3. ing; furthermore, traffic noise would require
Administratif
structural
special consideration , the highways being
d iagram . close to any future building. A considerable
area of flat land to the west was to be devel-
oped; here, significantly tall buildings could
affect late evening sun , as well as prevailing
west winds. It was accepted that the impact
of such development should be reviewed
retrospectively once plans were published .
Later in the design development, two options
for this land were defined and incorporated
into the wind model testing .
Geological conditions did not influence the
building form at all. Sandstone. the major
108 108 108 108 founding material. would carry load well . and
the remblais - granular material and river
deposits above this . some Sm deep - were
108 108 108 108 found to be dry and only requiring simple
excavation techniques. Fine river deposits
I and the former course of the River Jarret
explained the presence of a large culvert.
21-6
t installed to direct storm water from the north-

tI
I 36 36 ern area of the city. Evidence suggested that
a dry basement could be constructed and
traditional piles or barrettes used .
Modular order
I
I
Although it is not immediately obvious . a
module of rich order - not competing with the
more liberal volumes and surfaces - underlies
the building 's arrangement. Its origin is in the
4.
Deliberatif
office planning grid of 5.4m: by doubling this
structural to 10.8m in the basement, using an X-column
diagram. arrangement of transfer structures. four car
parking spaces and a column zone are
achieved . By again doubling to 21 .6m , the
main structural grid of the Deliberatif is
defined , and then a division of this yields six
3.6m panels of cladding between major grids.
In turn . this links well with the geometric
theme of the Deliberatif envelope and practi-
cal considerations of panel manufacture.
Furthermore. the lowest common dimension
of 300mm permits a neat transition between
large-scale structure and smaller elements of
construction within the building.
4 THE ARUP JOURNAL 4/1994
The Administratif escape stairs at approximately 32m intervals.
Some parts of the total project are complex, There are expansion joints at each end of the
not from technical vanity or design exuber- central 50m length, continuous throughout
ance , but from the defence of ordered ratio- the height of the building. A system of bayo-
nale that allows the vast majority of it to be net joints prevent excessive torsion in the two
realised with great economy. Protection of outer cores. The stability system and X-
this higher order simplicity yields pockets of columns interact longitudinally due to the high
complexity - the consequence, primarily, of shear stiffness of columns below level 1.
the way several simple elements interact. The In the basement, it was decided to avoid
Administratif, though , is a large but generally expensive and cumbersome transfer beams 5.
simple concrete building , housing amenities Detail of the Ovoid
and exploit instead the geometry of ex- within the Atrium .
and consolidated office space for the pressed structure. The X-columns at level 1
Departement. These are located in the two allowed an elegant transfer of load from 5.4m
blocks, separated by the continuous Atrium to 10.8m over three storeys , from the peri-
throughout their 150m length. For ease of ref- meter columns of the offices above. A series
erence the lower block and most westerly is of V-columns , commencing at lower mezza-
Block A The higher, Block B, also carries the nine level , transfer load over one storey from
Aerofoil building above terrace level , whilst the internal columns to those below.
the Atrium houses a free-standing structure,
the Ovoid. These five elements , Blocks A and Tapering in section , the X-columns were cast
8, the Aerofoil , the Ovoid , and the Atrium in situ using four specially fabricated steel
constitute the Administratif. shutters. two each for Blocks A and B. These
arrived on site in four pieces , complete with
Despite their geometric differences, Blocks A rolling gantry and jig. Access points at three
and Bare constructed identically. Common to levels allowed concrete to be poured and
both, and perhaps the key reference point, is compacted in three stages: from reinforcement
level 1, approximately 12m above the arrival cage construction to finished column took 2.5
floor and the level at which the X-columns days. The somewhat smaller V-columns are of
commence their work. The in situ concrete precast concrete with an in situ stitch at the
floors above are supported by four in situ/pre- lower knuckle, cast in a specially fabricated
cast columns, making three spans laterally. steel shutter. The two elements of the V were
The centre span , and that most penetrated by stabilized by temporary frames until the tie
services, uses pre-dalles. a form of concrete was made at mezzanine level.
permanent shuttering not dissimilar to the
Omnia system. Longitudinally, the columns The gable frame
are on the 5.4m grid, which balances well The ossature du pignon is very much a three-
with the glazing module, partitioning and pre- dimensional concrete structure. It gathers
ferred office module. The columns on the load from the external columns by a series of
perimeter have an elliptical section with two inclined struts and ties and transfers it back to
continuous slots for fixing partitions. the internal V-columns below mezzanine. at
the same time turning the forces through 90
The central, longitudinal beams were cast on plan . All this both protects the extruded
using a module of penetrations through the form of the Administratif and articulates the
web to allow free passage of services. The structure within the building. Clarity of line
system of beams and slab permitted the con- and the simplicity of the X-columns is, then, all
tractor to standardize and use rolling shutters that remains externally despite the apparent
for the two outer spans. cantilever of 7.5m beyond the last X. This
Each block is stabilized against horizontal feature is further emphasized by the glazing,
load by four cores, cantilevering over 90m deliberately set behind the X-columns to
from foundation level , arranged around leave their form exposed .

6.
Administratif gable
end structural
diagram.

7.
Gable under
construction.
January 1993.

THE ARUP JOURNAL 4/1994 5


The Aerofoil
The Aerofoil continues Block B's four-column
arrangement upward, though the blade-like
precast external pilotis which elevate it have
their own character.
They vary in section with height, a circle of
small diameter at the base transforming to a
long ellipse at their head. This form suggests
a portal structure for stability, but this is not
the case; the Aerofoil takes its stability from
cores, like the rest of Block B.
In section the Aerofoil has a curved profile ,
framed in structural steelwork bent to differing
radii , and arranged as a series of frames at
5.4m centres. Each frame, stable in its own
right, is bolted to the main concrete floors.The
Aerofoil includes two floors, levels 8 and 9,
and houses the presidential suite. It also
allows commanding views over Marseille and
to the sea beyond. A: Sun path Shading 8.
B: Sirocco Wind protection Response of building form to specific
The Atrium C: Mistral Wind protection
environmental criteria.
The Atrium is not only the cathedral-scale
dividing element between Blocks A and B. 9.
but also a piece of 'machinery' which actively End elevation, showing from left to right:
moderates its internal climate. This is in part Deliberatif. Administratif Block B with Aerofoil
achieved by static measures like roof and above, the Atrium, Administratif Block A.
gable glazing, but also actively via pro-
grammed sensors on the roof that track the
sun and measure wind velocity.
These enable maximum benefit to be derived
from natural phenomena, controlling and
adjusting shutters and blinds in response to
changing conditions and climate.
As with all large glazed spaces, the Atrium
can experience violent swings and steep gra-
dients of temperature. Due mainly to the
sheer volume of the space, it is difficult to
control the internal environment as a whole.
Those areas subject to frequent human occu-
pation were considered and addressed on
the basis of local control. Two major areas
were identified: the bridges (passere//es)
which traverse the Atrium (two groups on four
levels) and the Atrium floor.
Laid within the screed of the latter (rez-de-
chaussee) is a network of pipes for underfloor
heating. Radiated heat from these warms the
lower reaches of the Atrium in winter, whilst
in summer a secondary cooling circuit ,
using the same pipework, provides a radiant
cooling effect from the slab .
Cooling is supplied from the central chiller
plant. Serving the whole building, this com-
prises three 1152kW units and one 562kW,
the latter handling equipment loads from the
Administratif in winter.
The bridges link Blocks A and B across the
Atrium at each level. Elevated as they are,
they can experience large temperature varia-
tions due to stratification of air in summer and
cold draughts in winter. Rather than be left
exposed , each bridge is partially enclosed
and has an electric underfloor heating system.
The Atrium roof is at the highest level of Block
A and spans 1Bm to level 5 on Block B; these
highest office levels in each Block need pro-
tection from solar gain. This is achieved in two
ways : by static, raked, tensile screens
attached to each roof truss; and by a central
solar paddle whose angle is moved in
response to the sun's position by a computer
to give maximum shading.
The system is in turn linked to a Building
Management System (BMS).The Atrium venti-
lation and smoke extract system relies com-
pletely on natural means. More sensors on the
roof relay wind velocity to the BMS. Vents on
the roof open and close in response to the
wind-induced pressure distribution, control-
ling the intake and exit of air. In the event of
fire the solar paddles are rotated to the verti-
cal position to give maximum area for smoke
dissipation. The automatic venting control can
be over-ridden and manually controlled by
firemen from the fire control panel.
6 lliE ARUP JOURNAL 411994
The structural efficiency of the roof truss sec- The Deliberatif
tion and the overall geometry are in harmony A study in form
wi th the shading system. Two-point funicular The Deliberatif has a distinctive aerofoil-like
trusses, arranged to match the 5.4m grid, rtM l>'1Lblb rHC"1 cross-section that serves to smooth out east-
have a dual function . The top boom carries ~ ------ - ~~ E(}p,e-c,?R,"1-.J~ol,,
west wind flow, its shape the product of a
the glazing and window cleaning equipment, ::::C>r<:t>-. 8/:b,,u. l'rX.iY.../4
geometric study aimed to create a surface
whilst the three-part bottom boom has outer where each cladding panel is identical. The
elements supporting fabric shades and a structure , rather than being pre-defined,
centre portion supporting the axle of the solar would respond to panel size and section
paddle . In making the solar paddles aerofoil- geometry.
shaped and then mirroring this in the bottom The catalyst was an exercise in paper folding .
boom, local bending is resolved by the axle By scoring isosceles triangles onto a rectan-
taking its support at position of greatest depth. gular piece of card , cropping the corners to
Just as the Administratif Blocks are broken by create a symmetrical coffin-like shape , and
movement joints, so is its roof. Potential then folding into a wing profile , a geometric
stresses are relieved by sliding joints in the starting-point was defined . This exercise sug-
longitudinal members and strategically gested that each panel could be similar.
placed horizontal bracing. Lateral and inde- Form-finding techniques , similar to those
pendent movement of Blocks A and B is pos- used in membrane structures, demonstrated
sible by fixing roof trusses to the former and that extending this philosophy beyond 12 tri-
using a guided bearing on Block B. the oppo- angular panels would create distortion in
site side. Fabricated steel mountings termi- them. Furthermore, the accommodation to be
nate circular hollow sections which make up created inside the Deliberatif, as well as prac-
the principal elements of each truss. tical considerations in panel production , dic-
Gable glazing tated that a larger number of small panels
Given that lateral movement between the should be used. The distortion therefore had
Blocks could be significant and that the gable to be quantified and further tested .
glazing should fill the gap between Blocks A
and B, the roof, and the floor, it was decided ~ 11 .
very early that the glazing should be sus- Developing the Deliberatif geometric form.
pended. A system of jibs (similar to cranes)
were designed as part of the roof structure. At T 12.
roof level they have cables attached, each Computer image of Oeliberatif geometric form .
taking vertical load and preventing twist in the
horizontal wind girders, which give lateral
stiffness to the glazing and double as clean-
ing platforms. Due to possible differential hor-
izontal movement between A and B, each
girder sits in sliding bearings at each floor
level. A and B can then move independently,
with the glass suspended between, and only
longitudinal forces from wind transferred to
them . Differential longitudinal movement
between each Block is not significant and a
system of flexible gaskets form a resilient seal
to the glass and buildings.
It was predicted that the cables may loosen
under certain loads. To prevent this, the whole
structure was pre-loaded during erection ,
creating prestress in the cables and thus
controlling loss of tension.

~ 10.
The Atrium .
THE ARUP JOURNAL 4/1994 7
By simplifying the cross-section, using two hollow sections form a continuous element At the southern end of the Deliberatif is the
superimposed circles and varying the radii to that totally encloses the concrete frame. Over 'aviary' walkway, its name a legacy of earlier
follow the folded paper concept, it was possi- the majority of the surface the section is rein- proposals. This element cantilevers 12m from
ble to quantify panel distortion - or, equally, forced by welding on a T-section . This also the concrete structure, and consists of an
retain each panel identical and calculate serves as a surface to attach cladding. At the extruded circular section fabricated in tubular
distortion in the joints. sharp edge the T is omitted and a lattice steel and pre-tensioned against movement.
The latter concept was tested against a max- frame controls both strength and deflection. It is clad in glass whose blue tint varies in den-
imum panel size of 3-4m, enclosing a volume This is exposed arid free of cladding panels, sity as it progresses away from the building.
derived from planning the internal space instead carrying two levels of walkways and The end panels are clear.
required . The results of computer drawings giving support to a stretched membrane Climate control within the Deliberatif is
and mathematics revealed that distortions structure. The fabric membrane (PTFE-coated) achieved by conventional means. Chillers
could be readily absorbed by joints no wider extends for 21 .6m on the exposed, central, and boiler plant are remote from the building
than 25mm using a flat triangular panel of bay of the building. A network of stays and and part of the central system. Major public
3.6m x 1m. The trailing edge, however, con- cables translates imparted force back to the spaces and debating chambers are served
tained much greater imperfection and would principal frame. by dedicated all-air systems. Predicted occu-
require special panels or a closing strip. Conveniently located behind the membrane pancy levels of the major spaces can vary
Accepting distortion allowed the building structure is the longitudinal stability system for considerably. Consequently the ratio of fresh
envelope to be developed and the overall the steel rings. As elsewhere, lateral forces are air to re-circulated air is pre-programmed,
concept to proceed. carried by the concrete frame to which rings continually modulated by the central control
are attached around their perimeter. systems to meet demand.
The building The steel frame responds to expansion and Special attention was paid to designing a sys-
The Deliberatif is physically separated from contraction by through central braced bays. tem that meets stringently low noise levels.
the Administratif, from which it can only be Where steelwork is exposed , longitudinal ele- This required the selection of high perfor-
reached by escalator, stair or high level walk- ments are omitted at intervals to allow greater mance grilles and attenuators. Ductwork was
way. There is separate lift access, for restrict- freedom of movement. also sized for low velocity air-flow so that
ed use, from the car-park. It contains the noise is not regenerated within the system.
major debating chamber, public galleries, Each steel ring was pre-cambered to com-
pensate for the deflection that occurs when all Function suites, bars, library, and offices are
reception halls and functional suites - very served by four pipe fan coils to condition the
much a public space and a focal point of the permanent elements are installed. By so
doing the structure was designed on the space, each being fed from central plant.
design. The building is readily divisible into
two major elements: a concrete platform 8-1 Orn basis of strength and only in part stiffness. By By introducing a stretched fabric structure to
above the floor of arrival, and the aerofoil-like having a comparatively resilient cladding sys- the eastern exposed side, the walkways are
structure wrapping around it. tem such movement is readily absorbed. shaded . Furthermore, solar gain is controlled
Equally, each frame was checked to accom- for those areas immediately behind , which
Although some 160m in length, it was decided modate movement of the concrete frame. are enclosed by a large glass screen.
to build the concrete frame without movement
joints (contrary to common French practice).
This would help create the continuous shell-like 13. The Deliberatif under construction , showing the concrete platform.
cladding, an important feature of the design.
By careful understanding and manipulation of
stress levels, it was possible to estimate
shrinkage forces and design the structural
elements accordingly.
The concrete platform is supported on 16
columns, arranged in pairs, and spaced at
21 .6m. Each tapers with height and is based
on a cropped triangular section at its head
(approximately 3 x 3m). The section subtly
changes to a flattened hexagon at its base
(approximately 1.5 x 1m). Specially designed
steel gantries allowed each pair of columns to
be cast in one operation .
All the columns are linked by storey-height
concrete beams which complete portal
frames for lateral and longitudinal loads. At
the most northerly frame, the western leg
kicks out at 45 to permit the metro line to
pass below.
Generally, however. the western columns are
vertical and those to the east inclined. Due to
shrinkage of the structure , bending forces in
the columns and beams were minimized by
constructing from each end, leaving the central
zone free until much of the movement had
taken place. Thermal effects are less significant,
since the concrete frame is largely enclosed.
Accommodation is arranged on three floors , <111 15.
the lower two which house plant and storage Metal cladding panels
being continuous throughout the length. being laid over the white
membrane.
The upper floor is intermittently omitted to
allow large double-height volumes for the
debating chambers.
Surrounding the accommodation is a shell-like
outer skin of triangular metal cladding panels.
The weather seal lies beneath and consists of
a membrane laid over plywood panels of similar
geometry to the metal ones above. Insulation
and vapour barriers lie beneath the plywood
panels on separate chassis, again of the same
triangular geometry.
Panels are 3.6m long, supported at each cor-
ner by the main, steel annular frames. This
steel structure follows the aerofoil section. <111 14 Layers of Deliberatif roof;
top : insulation and vapour barriers
Each steel frame is bent to a specific radius, 1n steel frame ; middle: plywood
particular to that grid line and one other on panels; bottom: weather seal
the opposite side of the centre line. Circular membrane (white).
8 THE ARUP JOURJ,IAL 4/1994
11.
End view of transfer
beam over metro
station.

18. IJ,,
The Marseille context,
viewed from the north
east; behind the H6tel
is the Salle de Rock, a
new community facility;
1n the foreground . a
deep car park to serve
both buildings.

Basement transfer Although traditional piling is used, the piles People


structure foundations were installed using an interesting technique The building was completed within budget in
The basement covers an area equivalent to called the Starsol system. While the bored October 1994 and is now fully occupied.
five football pitches. Arranged on two levels, it piles were being installed , ground strength Architecture is about creating buildings, but it
shelters plantrooms, kitchens. workshops and was monitored continually by measuring is also about people: people who design,
technical facilities, as well as the car parking boring resistance , monitored directly by a people who build , people who use, people
spaces. To the north there are nine major computer in the cab of the machine. who observe, people who comment. A task
transfer beams, spanning up to 30m and sup- Comparison to the design parameters then on this scale touches many hundreds, all of
porting the full weight of the buildings above. permitted the pile to be terminated once the whom contribute in their own way to the
Built around and through these beams is St required level of resistance had been creation of something enormous , complex ,
Just metro station. Below them passes the reached . Barrettes are generally used where and unique.
twin metro tracks and platforms. The transfer high bending or shear forces exist and piles Credits
beams were cast in situ some 0.5m above take primarily vertical load . Client
their final position over the railway, and then Wind study Conseil General des Bouches-du-RhOne
lowered by jacks to their final resting position. The design team suspected that French reg- Architect:
The contractor chose to prestress the transfer ulations provided an overly simplistic mea- William Alsop Architects
beams , done in three phases to avoid tem- sure of wind effects. Statistical data on wind Consulting engineers:
porary over-stress of the concrete . Ove Arup & Partners: Pierre Balosso. Mike Banh,
speed and direction were therefore gathered Peter Chapman, Marcial Echenique. Marlin Fenn, Brian Forster,
By carefully co-ordinating the time at which from the local airport and used in a separate Ahstair Hughes. Colin Jackson, Chns Judd Man Kang.
analysis using recent work by the Engineering Bob Lang. Ruth Lees, Joanna Massey, Chns McCarthy.
stressing could occur and relating this to the Hugh Muirhead , Maurice Mullaly. Dominic Munro, Neil Noble.
construction above, an economic and not Sciences Data Unit. John Pllk1ng1on. Ian Smith, Jean-Paul Velon (structural)
excessively deep transfer system was David Anderson. Sean Billings (fa~ades)
This related ground roughness and local John Ducke. C W U , Paul Pomp1li, Manan Shah.
achieved . The overall depth of beams varies geography to judge wind speed as a function Mike Summers (elec1ncal)
between 3.0 and 4.2m to follow the gradient of direction. so achieving a more realistic set Guy Banle, Alan Burfoot, Lee Carter. Phil Connor.
of the railway below. Cohn Darlington. Alan Foster, Clodagh Ryan, Martin Walton
of conditions to assess the building section. (mechanical)
Between each transfer beam are either plant- Once complete, the analysis could be used in Jonathan Ward. Terry Walson (public health)
Rachel Kelly, Alain Marceneau. Howard Roscoe (geotechnical)
rooms or access to the metro station. To the wind tunnel tests. These were commissioned Cohn English (acoustics)
east the core of Block A rises above. Given and carried out by Bristol University. The Andrew Allsop (wind studies)
that the station traversed the full width of object was to understand the pattern of wind Terence Has1e11 (computing)
Ghislaine Frayss,gnes (adm1nistrahon)
building , it was possible to arrange the stabil- flow. so as to judge the effectiveness of pas-
Project manager:
ity so that only one core (the shortest and sive ventilation and the local effects around
SCIC-AMO/G3A
lightest) sat over the railway. The rhythm of the base of the building. It would also serve to Foundations:
Quantity surveyor:
the buildings above was therefore undis- govern the strategy for locating wind deflec- Hanscomb Ltd. Soletanche
turbed and an economy of scale achieved . tors which would manage flow. Engineering Fire security
A rotating table was used for scale model sub-consultant: consultant:
The foundations are of two principal types: Casso Gaudin
barrettes, constructed as mini diaphragm tests, which allowed varying directions to be OTH Mediterranee
assessed. Concrete structure Kitchen consultant:
walls, and more conventional bored piles. Jolyon Drury
The wind studies also modelled the effect on contractor:
Barrettes allow the designer great scope to MCB/CBC Illustrations:
create various geometric plan forms made up the building of two different options for future 1, 5, 9, 13: Paul Rafferty;
development on the adjacent , vacant site to Deliberat,f cladding
from a rectangular block shape. H, I, T, X and contractor: 2: Denis Kirtley;
other shapes can be constructed to reflect the west. The study enabled the most Cabrol 3-4. 6, 8. 17: William
the most efficient medium for retaining loads effective position of vents to be chosen and Mechanical contractor:
Alsop Architects ;
imposed on them. This opportunity was exploit- provided pressure contours around the 7, 14-16: Hugh
Albouy/AIC/TNEE Muirhead ; 10: John
ed to the full beneath the Deliberatif, where the Atrium. Electrical contractor: Edward Linden;
foundations are subject to considerable lateral Furthermore, although not modelled for this pur- Cegelec/EI/SNVD/CIREM 11 : Bob Lang ;
load - due to geometry, and to shrinkage and pose, some knowledge was gained of local Lifts contractor: 12: Ove Arup & Partners;
thermal effects from the structure above. pressures around the Deliberatif structure. Otis Elevator Co. 18: Cerf Blanc
TttE ARUP JOURNAL 4/1994 9
Motorway 1. Congestion on the westbound carriageway of the M25 at Junction 25 with the A10. The current projects are:
M1 Junctions 15 to 19 (35km)
widening M6 Junctions 11 to 16 (53km)
projects M25 Junctions 23 to 28 (40km)
M42 Junctions 1 to 7 (34 km).
Phil Hall - - - - Motorway widening schemes
In addition, the Cardiff office are
examining a new route for the
J23
-..,............- Arup widening schemes
section of the M4 which at present
passes through north Newport. This
Introduction new route would provide a direct link
In its 1989 White Paper entitled Al(M) from Cardiff to the Second Severn
Crossing, now under construction.
'Roads for Prosperity', the
Government announced a major M6 Key factors in widening
programme of motorway widening, The basis of the 'need' to widen
the implementation of which pre- motorways is quite simply the sheer
sented a huge range of engineering pressure of traffic demand (Fig.1),
and environmental challenges. Arups' M65
both now and into the future, but a
experience over the years on major ,I comprehensive response to this
highway schemes, as well as their
expertise in option studies and econo-
M6z Manchester
Ml requires the deployment of a wide
range of skills, preferably within one
M62
mic and environmental assessments, M66
M67
organization.
made the firm well-placed to win a Sheffield Traffic forecasting
major share of the work, particularly as 16 Whether this is seen as an art or a
the Department of Transport (Do T) Stoke science, certain skilled forecasting
had set up its own Motorway

}
procedures have to be followed to
Widening Unit (MWU) within 5km of predict future traffic levels. Arups
the principal Arup office concerned M54
J11
have developed extensive and
with highway and bridge design. detailed mathematical traffic models
Birmingham
Widening studies M42 using geographical information to
One of the Government's very early Jj M45 delineate road networks, and data on
feasibility studies looked at the travel patterns gained from surveys
whole 290km length of the M1 motor- MSO designed and supervised in-house.
way from London to Leeds. Arups
were awarded this study, which
provided the ground rules for much
Swansea l.J
'--\._ MS
Oxford
These surveys, consisting of road-
side interviews with drivers, clarify
traffic demands; traffic modelling for
subsequent work, and were also ~ Bri: ::ndon M the M6 scheme, for example, used
appointed by the MWU to join a data from interviews covering the

~
Motorway Widening Steering Group area from Oxford to Liverpool and
of leading DoT specialists in particu- Manchester. These forecasting
lar aspects of scheme evaluation. procedures have been consistent
Arups' contribution to this 'think-tank' with national prediction methods, but
also extended their capability in the the models also reflect the specific
field of widening. circumstances of the scheme being
Following these two initiatives the developed. For example, major
firm has been appointed for four development projects such as the
major widening studies ( three from expansion of the National Exhibition
the MWU and one from the DoT's Centre near Birmingham have been
2. The motorway network and current widening programme.
Eastern Regional Office, who handle incorporated to identify local effects
part of the M25) (Fig.2). at nearby junctions.
10 TtiE ARUP JOURNAL 4/ 1994
The prediction techniques required influence on the form of widening, develop traffic management layouts new lanes are provided on the outside
to forecast traffic may require months and the choice between options. which help to ensure the safety of of each carriageway. For asymmetrical
of painstaking effort and major Delays during future road main- both the motorist and of the work- widening, one boundary remains and
computing exercises. Transport tenance operations have also been force. Experience gained on the new the widening is concentrated on the
modelling and traffic engineering calculated , in order to establish the motorway construction of the '70s other. However, the third option is
skills have been used to understand ability of a widened motorway to and '80s was very relevant, since increasingly favoured, and this is
the consequences of margins of handle traffic more readily. much of this work necessitated new called 'parallel' widening. Flg.4 shows
uncertainty in these forecasts on the construction adjacent to or connecting the construction stages.
need for the scheme and the scale of Methods of widening with existing motorways. The scope Arups have devoted a major effort to
the proposed widening. This trans- 'Rapid' widening for environmental enhancement is looking at alternative forms of parallel
portation planning advice is crucial in Pressure of existing traffic on limited. however. since no land is widening , and have made compre-
guiding highway engineers so that London's M25 Orbital Motorway led available outside the present boundary. hensive recommendations to the
safe and satisfactory road and junc- the DoT to seek, for the section from MWU. This report concluded that the
South Mimms in Hertfordshire to Nevertheless, the 'rapid' technique still
tion layouts can be designed. The technique provides considerable
elements of uncertainty also impinge Brentwood, Essex, a widening requires the full range of engineering
investigation and design, particularly in flexibility to avoid sensitive features.
on the work of Arup Acoustics and method capable of quick implemen- and that even small changes in
tation; development of the 'rapid' relation to geotechnical issues and the
Arup Environmental, who use this position can have major benefits in
traffic data for several types of technique (Fig.3) was the outcome. design of retaining structures, areas
where a sensitive approach is needed terms of drainage, structural
environmental assessment (e.g. Its key feature is that it will be carried demolition and construction, and
noise and air quality issues) which in difficult locations.
out entirely within the existing fence both worker and driver safety.
are the subject of national debate. lines, with no land acquisition. Parallel widening Work on developing the 'parallel'
Economic justification Existing bridges will be retained and For the most heavily trafficked routes, form of widening has established that
Motorway widening schemes require much of the carriageway re-used. It and where land is more readily avail- the layout takes longer to build, and
large amounts of public expenditure, will therefore be quick to build, at able, alternative widening techniques the need for land means longer lead-
typically from 3M-7M/km. The least in the sense that no land have been examined. Three major in times. All existing structures need
majority of the work on the justification acquisition procedures are needed. options have been extensively studied to be replaced or extended, and
of schemes has been undertaken The adverse aspect of 'rapid' widening and compared in terms of disruption, most of the existing carriageway and
using relatively standardized DoT is that traffic disruption may be intense, safety, costing and environmental drainage has to be renewed. The
procedures, but it has become and it is therefore necessary to issues. For symmetrical widening, landtake is also greater. However
normal practice to extrapolate the there are major opportunities to incor-
computer programs used beyond porate substantial landscape and
their normal parameters. Arups have acoustic measures. existing traffic is
developed novel approaches to eco- barely disrupted, and safety for con-
nomic justification, and have prepared struction workers is greatly enhanced.
discussion papers for the DoT to help
Junction design
resolve the emerging issues.
The forecast levels of traffic have
The economic benefits of widening caused major problems for the high-
have been determined using the two way engineer in designing junctions
programs COBA and OUADRO to which are adequate in terms of
evaluate savings in drivers' time, capacity and safety, but which are
accidents, and vehicle operating sensible and reasonable in terms of
costs. The major consideration in landtake and impact (Fig.5).
widening schemes is the immense
The problem has been particularly
disruption which may have to be
acute on the M42 widening, since
faced during construction, and the
this serves as an orbital route around
reduction of this disruption is a major
south and east Birmingham. It is
heavily used by relatively local traffic,
which uses junctions to 'hop' from
Verge Hard shoulder Central one radial route to another. Increasing
use is likely to be made of complex,
traffic signal-controlled junctions, with
some traffic movements segregated.
In the vicinity of the National
Exhibition Centre, additional links
need to be provided to meet the
31anes 31anes massive traffic problem experienced
on major show days. A more general
3. Above: existing dual three-lane motorway; below: symmetrical widening without land take (rapid widening). problem which has been addressed
is the need to develop traffic models
which are increasingly sensitive to
Hard shoulder Central peak period travel demands and the
reserve
ability of the road network to sustain
growth. Detailed discussions about
the future traffic modelling tech-
niques are under way with the DoT.
to ensure that junction designs for
peak hours are compatible with the
41anes 41anes
capacity of the rest of the network.

Central
Verge Hard shoulder reserve

r---..._--- -------- ----


--'---.:.dli~~=:1~-dia.-----r----....!!ia;;;ir;::;:=:::::::m:1Siili:::;::!;:~.---<--. -. --- --------------------
Redundant carriageway: allows
space for landscape treatment
and/or noise mitigation works
41anes 41anes

4. Parallel widening.

THE ARUP JOURNAL 4/ 1994 11


Landscape While a widened motorway remains
a narrow strip, its effects on the land-
consideration of its cultural, historical,
and amenity value. Arups' own land-
for the scheme to be designed in the
context of the environmental setting,
Tom Armour scape can nevertheless extend over scape architects advised the rather than needing add-on mitigation
a wide area. Over the length of the engineers and client on appropriate measures in response to adverse
scheme, a variety of landscape forms treatments and detailing, and inform effects. Arup Environmental also have
are likely to be encountered - from the project team of the potential an important role in advising on the
rolling countryside, through open, impacts, benefits and disbenefits of aesthetic implications of motorway struc-
agricultural land, to urban and subur- widening alternatives and the best way tures. bridges, retaining walls, noise
ban fringe areas - and consequently forward in landscape terms. As with all barriers, etc. Considerable liaison has
a variety of design approaches are environmental considerations, environ- been achieved between the landscape
required. Each type of landscape mental design is an integral part of the architect, the traffic noise specialist,
needs detailed assessment and overall engineering design. The aim is the ecologist, and the engineer.

Varies 9 to 14m

Proposed tree, shrub,


groundcover planting varies

Hard
1.5m 1700mm 800 shoulder
Retained
lanes
Drainage
channel
or land
drain

6. Existing location on the M6, and right: 7. Landscape treatment of widened median: these were introduced lo reduce the apparent extent of road surface.

Existing woodland

I Woodland planting
on proposed 4m
false cutting
Northbound Southbound
carriageway carriageway
View from
Special
Landscape Area

---
enhanced

8. Proposed scheme for widening on the M6 (see Fig.6): it provides the opportunity to create a false cutting to screen trattic and enhance features within a Special Landscape Area.

9. Splitting the carriageway provides the opportunity to reduce the impact for motorists and visual impact from the surrounding landscape.

Proposed wildlife protective


fencing/motorway boundary Proposed planting

Proposed grass Retained lanes


and wild flowers

---
"
Northbound Southbound
carriageway carriageway

12 THE ARUP JOURNAL 4/1994


Structures
Richard Cooke
Widened motorways, particularly
the 'parallel' schemes, require long-
span bridges, with potentially un-
balanced span arrangements, and
the aesthetics of these need very
careful consideration.
Experience gained on the recently
completed M40 was the basis for the
design approach, and presentation
of the motorway widening bridge
proposals to the Royal Fine Art
Commission has been undertaken,
with a highly satisfactory response
from the RFAC. Overbridges will
have spans in excess of 40m, so 10.+11.
speed of erection and ease of Model of new overbridge
designed by Arups for the M6.
construction point almost entirely
in favour of steel composite
construction.
Computer modelling techniques were
used initially to investigate the
appearance of these structures. and
subsequently physical models have
been built. Equal attention is being
paid to underbridges. Although they
are not always visible to the motor-
way user they often have a greater
impact on the local surroundings.
Bridges crossing existing junctions.
railways or rivers present difficult
problems which have been carefully
considered in the design.

~~~-=-====-------------
Management and
Geotechnical issues multi-disciplinary activities
Highway design is hugely interactive,
John Gabryliszyn depending on a range of engineer-
Some of the existing motorway poorer ground and contaminated there is no alternative other than to ing, transport planning, geotechnical,
network was built with only the most sites. The limited nature of the early develop an engineering solution. The structural, environmental, and elec-
sparse geotechnical information. data presents its own challenges situation is unlike, tor example, a by- tronic skills. As with most other
For example, on the original (1959) in relation to proposed widening pass proposal, where route alignment engineering designs. the solution
section of the M1, boreholes were schemes, as a need for much more variations can overcome the more which is eventually adopted is always
regularly spaced at about 1OOm detailed information now exists due severe constraints. The widening pro- a compromise. It is the sheer scale of
intervals along the centre line, with to the requirement to extend the posals also deal with the addition of the effort required in motorway widen-
maybe one at each structure. On all existing works. In addition, the long, thin strips of new construction ing schemes, and the range of skills
these projects, widening is having to proposed designs have to meet adjacent to existing embankments and throughout Arups that have had to be
take place where earthwork failures increasingly stringent codes of structures, and it has been necessary deployed. which make this work
have occurred both during and practice, and the amount of environ- to develop solutions to overcome the almost unique.
subsequent to construction. Rock mental protection legislation is a problems of differential settlement. The firm's project management skills
cuttings. which had originally been major determinant of geotechnical and highly restricted working space. therefore have to be concentrated in
designed on an empirical basis. are treatments. Arups' geotechnical engi- Particular problems also arise in site the hands of the highways project
now subject to a more rigorous neers are therefore having to pay investigation, since the investigatory
managers, who have sufficiently
analysis. Restraints on the routing of particular attention to the need to work has often to be undertaken detailed knowledge of a wide range
more recent motorways have resulted develop practical ways of dealing under the severe constraints of
of disciplines so that informed debate
in them passing through areas of with the problems that arise. since working adjacent to a live motorway.
and probing of views can occur. It
is however, not only the project
12. Existing rock cutting at Trentham in Staffordshire, on the M6 molorway. manager who needs this ability; all
team members across all the Arup
disciplines have become aware of,
and developed an interest in, the
activities of other specialists. This
multi-disciplined, integrated team
~xistlng embankment
planting approach is a key feature of Arups'
approach to projects, and is vital in
building and maintaining client and
public confidence.

THE ARUP JOURNAL 4/19M 13


Traffic noise and
mitigation measures
Colin English
Although there are standardized
techniques for predicting traffic
noise. they are not instantly adapt-
able to multi-lane carriageways, nor
do the basic research sources deal
with roads with the high levels of
traffic flow now forecast.
Arup Acoustics have been closely
involved with a wide range of road
schemes, and they are at the fore-
front of extrapolating, developing, 13. High steel barrier in Paris, and right: 14. Transparent barrier in Holland: this reduces noise but also allows views out for the motorist.
and adapting traffic noise prediction
techniques to the special case of
motorway widening.
While most of the techniques for
environmental assessment and
design are described in the DoT
Design Manuals, it was felt
necessary to develop a series of
environmental design and mitigation
objectives specifically for each
motorway widening project.
In relation to noise, a key objective
has been to actually reduce the high
levels forecast at the roadside to
acceptable levels at residential
properties. and at all other noise-
sensitive locations (e.g. schools,
hospitals, etc.). Such a noise 15.+16.
reduction runs counter to the wide- Another Dutch solution:
spread popular belief that widening this salt' hedge-like construction
would increase noise levels. reduces the visual impact
However, the sheer scale of the of a large barrier.
mitigation measures is becoming
apparent. Acoustic barriers of 8-10m
height are having to be considered ,
and these present significant visual
and architectural challenges.
However, good design can do much
to ameliorate their impact.
Arup Acoustics and Arup
Environmental have looked at the
best European practice, and have
visited France and Holland to see
how other countries are tackling this
common problem.

Driver
communication
systems
lain Bell
The traditional system of matrix (NMCS2), automatic incident detection
signals mounted in the central reserve (MIDAS). and variable message
conceals a largely hidden electronic signing (VMS). The emphasis will be
network, but the information conveyed on real-time continuously updated
is quite limited, and often lags behind information, and in-house expertise
what is actually happening at that puts Arup Communications in an
moment on the motorway. The next advantageous position in this field of
generation of widened motorways will transport informatics. Loomi~g
need to be 'intelligent highways'. The on the horizon is the possibility of
range of information to be provided will tolling all motorways, which will add
need to embrace a new version of the to the electronic networks within
national communications network the road system.

17. Typical gantry over a dual four-lane


motorway, with matrix signals for
lane control and a variable message sign.

14 THE ARUP JOURNAL 4/1994


Public involvement
A particular feature of the planning are rapidly exposed, and cross-
process for road scheme is the examination at a Public Inquiry is the
involvement of the public. There are ultimate test of professional belief and
many stages throughout the life of a skills. Since a road scheme can involve
road scheme when contact with the demolition of homes, acquisition of
public is needed. This starts from farming land, impact on industry, and
data collection, via inteNiews, adverse environmental effects, it is
continues through consultations with absolutely necessary to ensure that
statutory and other interest groups, only the most thorough and pro-
embraces exhibitions at various fessional work has been undertaken.
stages, and culminates at Public Appearing at a major Public Inquiry,
Inquiry. All of these require presenta- lasting probably several months,
tional and graphic skills of the highest concentrates the pressure to produce
order, but over and above this, only the highest quality work. Few other
professional judgements are being professions face that degree of chal-
continually challenged and probed. lenge to their judgements, but it is a
Errors of judgement and faulty logic fascinating aspect to highway work.

Credits
Ecological issues Clients:
Andrew Bascombe Highways Agency Motorway Widening Unit
(M1 , M6. M42)
While widened motorways have a designs are chosen, also that mitiga- treatments, monitoring of construction. Highways Agency Eastern Regional Office
similar risk of affecting sensitive tion and enhancement measures are habitat management plans, and (M25)
ecological sites or protected species designated into the scheme. Ecologists advice on balancing ponds, water Consulting engineers:
to that of a new road, the fact that no from Arup Environmental have provid- quality issues and pollution con- Ove Arup & Partners: John Bevan, Tony
new severance or pollution risk is ed a wide range of specialist skills trol. Close liaison has been necessary Gibson. Phil Hall, Alan Hughes. Tony Jones,
caused is an advantage. Motorway which have been applied at all stages in respect to ecologcal issues, for Mervyn Raisbeck, Terry Rawnsley, Colin
Stewart, Andy Walker (highways), Richard
widening can also provide the of motorway widening - seNices example in the design of balancing Cooke, Tony Evans, Mike Larvin, Allen Paul,
opportunity to create new habitats. ranging from field survey and route ponds, where drainage engineers, Colin Wilson (bridges). Aidan Eaglestone,
Detailed ecological advice is essential landscape architects, and ecologists Dave Thompson, Peter Webster (traffic
appraisal, guidance on listed forecasting), Phil Hall (economics), John
to ensure that sympathetic engineering sites, species and habitats, design need to maintain close liaison. Gabryliszyn, Tony Snedker (geolechnics),
Paul Tomlinson, Simon Witney (environmental
planning), Tom Armour, Benz Kotzen
(landscape), Colin English, Clive Swift (noise
studies), Andy Bascombe (ecology studies).
Rob Paris (air quality), lain Bell (communica-
tions). Peter Speleers (graphics)
(plus many other staff members,
too numerous to list, in the Highways.
Bridges. Environmental. Transportation. and
Communications groups, and Arup Acoustics)
Landscape architects:
Landscape Design Associates
(sub-consultants for the M1 widening only)
Illustrations:
1 Department of Transport
2 Denis Kirtley
5, 10, 11 Peter Mackinven
6TomArmour
3, 4, 7-9. 19
Trevor Slydel/Peter Speleers/Jon Carver
12, 17, 18 Ove Arup & Partners
18. Balancing ponds have been designed lo fit into the existing landscape. 13-16 Benz Kotzen

Gently sloping ground and


flat shelves for emergent Normal water
planting
25 year flood level

1 :10

19. Cross-section through typical balancing pond.

Summary
The attraction of the motorway The roads programme, and the
widening programme, as of many widening of existing motorways, is
other major civil engineering schemes, likely to be an increasingly politicized
is the ability to work in a challenging activity calling for managerial and
environment, to interact with a wide technical skills of the highest order.
range of specialist staff, and eventually This is the challenge that the firm is
to have one's professional judgement facing with utmost determination to
seriously criticised by informed laymen design a product which will, in its own
and interest groups. field, represent the Arup ideals.
TliE ARUP JOURNAL 4/1 994 15
Sellafield
geotechnical
study
Colin Curtis
Andrew Law
David Pascall
Objectives
British Nuclear Fuels pie (BNFL) are 2. above: Coarse-grained, well-rounded,
examining the feasibility of building windblown Calder Sandstone,
and below: typical St. Bees Sandstone.
new pressurized water reactors
(PWR) at Chapelcross, Scotland, and
Sellafield in Cumbria. Part of Arups'
involvement has been to carry out,
from October 1991 , a geotechnical
study at the latter site. The main
objectives included:
input into an
Environmental Statement
support to Site Licence and
Planning Consent applications
and subsequent Public Inquiry
supply of data for the site safety
case preparation
input to the seismic hazard 1. above, Wireline drilling to 300m depth. 3. below, Sample correlation of four boreholes across c.1km of site.
assessment study.
These were to be achieved through a
major site investigation. concentrating Key
on the geological structure and the
150m Electrical Rock types
hydrogeological and geotechnical resistivity
Increasing grain size

r~
aspects. Low High
Site constraints
The investigation area, north of the
<!'=~ ~ Identified
sedimentary
existing Sellafield complex, is partly units
on the floodplain of the River Ehen,
by the coast. and partly on higher Undifferentiated wind
blown sandstone
ground to the east. BNFL obtained
planning permission for the investi-
gation, but this subsequently con- -
~a~~opera~M. S~~the~o~
1
2oom 1-~~~-~L=o~w=~~~~~-~F=~~~:~:~~i-~~~~~--~~~~-~~~~~~
Sandstone
~ C 4 ~ ---::---:-----::b=~R~o~ck~h~ea~d

plain was of environmental interest


(it contained a natterjack toad colony),
an ecological method statement for Calder
operating there was prepared as a Sandstone
condition of the planning permission.
Operations were checked
periodically by an ecologist. 100m
Site investigation
Following a desk study, the
investigation was tendered and
250m
awarded to Norwest Holst who
started on site in January 1992. St. Bees Sandstone
Initially the investigation was to be in
one stage for a specific PWR station
site selected by BNFL. However. this (c.200M years). One of the prime waves being recorded on strings of been planned to lower wireline
was modified by widening the concerns at the start of the study geophones. The refraction was geophysical sondes down all the
scope of location for the station. The was whether a stratigraphical followed by a reflection survey to deep boreholes to measure electrical,
investigation was carried out in two correlation could be obtained in look at the deep geological structure acoustic and radioactive properties
stages: Stage A, which took six eitherthe drift or sandstones. Apart to depths of about 1km - the base of the rocks.
months, primarily concentrated on from conventional investigation of the Permo-Triassic rock. After Using these, plus information from
establishing the geological structure. techniques of boring and core interpretation of the results of these investigation work at the neighbour-
The 10-week Stage B comprised drilling, the fieldwork was to include two surveys, a further reflection ing NIREX repository, the first bore-
special geological sampling by a seismic geophysical survey to survey took place in the area of hole was continued to 300m depth to
drilling, together with limited sampling examine the deep rock structure. most suitable rockhead to gain a ensure it had penetrated the upper-
and in situ testing for geotechnical Stage A investigation more detailed picture of the structure. most seismic reflector within the
purposes. After initial boreholes a seismic Simultaneously with the geophysical Permo-Trias. This reflector was the
The Sellafield ground conditions refraction survey was performed to survey, drilling the first borehole interface between the Calder Sand-
comprise a variable thickness of gain a rapid picture of the variation proceeded. At 150m depth, signs stone and the underlying St Bees
glacial drift over a thick succession in drift thickness over the site and of a change in the sandstone Sandstone. This was penetrated by
of relatively featureless red sand- surrounding area. Small dynamite were observed that would permit the deep boreholes and the sand-
stones of Permo-Triassic age charges were set off, their refracted stratigraphical correlation. It had stones were correlated (Fig.3)
16 THE ARUP JOURNAL 4/1994
using lithological and geo-physical Geotechnical considerations soft lenses. This could be dealt with
sonde logs. Deep drilling permitted Sellafield The general ground conditions by grouting and/or freezing the rock
the geological structure to be ascer-
tained independently of the geo- seawater encountered inland during site inves-
tigation were sedimentary deposits.
ahead of the tunnel face to increase
stability and reduce water inflow.
physical survey and delineated
features not identified on the seismic
cooling both glacial and marine. as sands
and gravels with boulders overlaying
However. this would increase con-
struction programme and consequent
interpretation. Trial pitting and static
cone penetration tests were used to
system sandstone. Chiselling was necessary cost increases.
to keep construction of the boreholes
examine the drift materials. Two going, and the evidence from the site Soft ground bored
suites of downhole and crosshole Martyn Stroud investigation and visual inspection of To ensure that they would be in
geophysics gave velocity control for reasonably competent ground, the
seismic processing and provided
Hakop Mirzabaigian the site area was that large boulders
could be encountered during study for such shallow tunnels
dynamic moduli values. tunnelling. In addition, geophysical aligned them with around two
Introduction data from offshore indicated that the diameters' minimum cover, below
Stage B investigation both ground and seabed, throughout
The main geological features iden- BNFL's possible new PWR site is rock outcropped out to sea. Fig.1 also
situated north of their existing site at shows the typical geology of the site. their length. Tunnelling machinery
tified by the seismic survey were exists that is capable of dealing with
investigated by drillholes during Sellafield. Because of its potential Tunnelling techniques
location close to the Irish Sea, the the water pressure in the gravels,
Stage 8, and a potential fault zone Three were evaluated. for their sands, silts and clays likely to be
was successfully cored over about intention would be to supply cooling environmental impact, costs, and
by seawater, which can either be encountered. It can be adapted to
SOm depth interval. Stratigraphical risks and uncertainties during deal with sandstone intrusion, and
correlations indicated that any provided direct or as a make-up construction. The techniques were
water for cooling towers. incorporates crushing equipment to
movement had ceased during the immersed, bored through rock, and deal with boulders up to a.Sm in
Triassic period. Up to three piezo- A comprehensive feasibility study bored through overlying sedimentary diameter. It can cut through larger
meters were installed in selected was carried out to examine whether materials. ones if they remain stationary. but if
boreh.oles at different depths to immersed or bored tunnelling tech- Immersed tunnel they are not sufficiently well fixed in
facilitate monitoring of the ground- niques would be appropriate, with In this option the intake and outfall the surrounding ground they could
water pressures to examine season- particular attention to construction tunnels would be provided by: become dislodged and rotate with
al and tidal influences. This informa- costs, risks and uncertainties, and the cutting head. Some would be
tion was incorporated in a hydro- environmental issues. Cut and cover
double tube (onshore): 1000m broken by the cutting head. but
geological model. Included in the The cooling system stronger boulders might have to be
laboratory testing was the produc- This was proposed to comprise Thrustbore double tube under dealt with by men entering the face
tion of photomicrographs from thin intake and outfall tunnels, connected the railway and River Ehen: 100m under compressed air at compara-
sections of rock core. to the pumphouse and the surge Double immersed tube: 1900m tively high pressures to break up
Interaction with other parties chamber at the power station site, Single immersed tube 700m manually the obstruction.
During the study there were five and extending from the station facility
into the Irish Sea. The water require- The onshore section of the tunnel The selected technique
meetings with the Seismic Hazard The immersed tube option was not
ment for one PWR station is would involve major dewatering and
Assessment Team. Arups' desk chosen because of uncertainties
66m3!sec .. and the hydraulics of a excavation support work, in an
study and final interpretative reports from weather conditions, and
cooling system from pumphouse to operation that would also involve
were reviewed by members of environmental impact during con-
intake and outfall structures were dealing with large boulders. The
Atkins, Mouchel, British Geological struction. The rock tunnel option,
an~lyzed to give an optimum design, offshore section was proposed to be
Survey, Moffat Associates, . though feasible, had inherent
taking into account tunnel diameters, dredged, though dredging through
and Gibbs. Two meetings with uncertainties due to zones of
multi or single inlets and outfalls, and rock was considered to be difficult
NIREX have been convened fractured rock, the need for grouting,
tunnel entry and exit design. Based and expensive. The other risk
for them to assimilate the study and resulting costs. Because of the
on this work the tunnel diameter was involved with the immersed option
findings into their regional structural depth, the access shaft for
established at 6m, with a flow velo- was the weather conditions. The
geology maps. tunnelling , not to mention the intake
city of 2.Sm/sec. Computer modelling environmental impacts of using this
Conclusions located the possible outfall and technique, although mitigatable, and outfall shafts themselves. would
The study was completed in intake at 2.Skm and 1.Bkm offshore were judged to be considerable be very deep and consequently
August 1994. A study of this scope, respectively, making the overall compared to those of the bored expensive to construct. Construction
covering nearly three years, is not a lengths of the two tunnels 3km and tunnelling technique. of the shafts would take longer, and
usual occurrence. With a total cost 3.7km, measured from the proposed be vulnerable to weather conditions.
Rock-bored
of 2.2M, it included some 21km of site to the intake and outfall shafts Based on available information about The soft tunnelling option was
seismic survey and 1BOOm of core offshore. Their vertical alignments the quality of rock, the tunnels would therefore chosen, but to take
drilling. It provided a chance to use were dictated by the system be some BOm below the Highest account of uncertainties due to
in situ testing techniques, such as hydraulics (Fig.1). Astronomical Tide (HAT). Available boulders the anticipated rate of
wireline sonde logging, not common- information on the rock quality progress was deliberately under-
ly used in site investigations, as well indicated that it was fractured with estimated by 25%.
1. Tunnel alignment.
as concentrate on establishing the
deep geological structure.
The main conclusion was that the
geological structure of the site would Access shafts
be suitable for a nuclear power
station development.
MHWS +5.0m AOD
Credits MLWS -4 .2m AOD
Client: Intake shafts
British Nuclear Fuels pie
Geotechnical consultants:
~--,------i11 t=====~----===============;1
Ove Arup & Partners Martyn Stroud, Glacial sands, Gravels and Tills
David Pascall, Andrew Law. Colin Curtis
Geophysics sub-consultant: Calder Sandstone
Quad Consulting Ltd.
Geotechnical contractor: Horizontal Scale 1 :500 Vertical Scale 1 :5000
Norwest Holst Soils Engineering
Illustrations:
1 Andrew Law.
2. British Geological SuNey.
3. Jon Shillibeer.
THE ARUP JOURNAL 4/1994 17
Bentonite tunnel boring machines
(TBMs) were proposed (Fig.2).
suitably equipped to drive through
both superficial deposits and rock.
They would be designed to use a
thixotropic bentonite fluid both to
support the excavation face and
remove the spoil cutting. Face
support is maintained by pressuriz-
ing the bentonite to give the correct
support pressure for ground and
water load, but the TBM's design
restricts pressurization to the cutter
head and so allows work in the
tunnel in free air. The fluid containing
the spoil cuttings is pumped from the
face to the surface; the spoil is
extracted and the fluid returned to a
reservoir for re-use in the tunnel.
2. Tunnel boring machine.
Intake and outfall shafts
3. (a f) Intake shaft construction. Intake would be by four 3m diameter
shafts. the riser and diffuser for each
being built inland. The shafts would
be constructed and capped off to
render them watertight before the
.. (a) tunnel reached their location. The
Excavate shafts by construction sequence is shown in
auger and chisel using Fig.3. The advantage of this is that
temporary casings
keyed into rock. the shafts could be constructed early
on, during suitable weather windows,
(b)IJ,, and independent of tunnelling
Place concrete plugs. operations. Tunnel/shaft connections
Install precast concrete could be made once both operations
tube onto concrete plugs. were complete.
Pressure grout annulus Programme and cost
and cut off casings. The construction period for the whole
Install precast concrete system from the date of placing the
tubes onto concrete plugs. order for the TBM is estimated at 45
months, whilst the cost estimate for
its elements is as follows:
Access shaft 3100 OOO
Tunnels 46 790 OOO
Intake shaft 2 200 OOO
.. (c)
Place lower section Outfall shaft 3 100 OOO
of diffuser caps with Design and
temporary sealing plates. engineering costs 925 OOO
Bore tunnel and install
'knock-out' panels. Conclusions
This study was very important to the
(d)IJ,, overall feasibility of building the PWR
Remove jack-up barge. at Sellafield, and the techniques
Abandon non-salvageable proposed by Arups were discussed
elements of TBM. in detail with international contractors
Construct end of tunnel. who have extensive experience in
Break through into shafts this field, to ensure the buildability of
and drain off water. the cooling system. Further work
would only be undertaken if BNFL
formally decided to proceed with any
development.
Credits
Client.
le) British Nuclear Fuels pie
Flood tunnel when
connection is complete Tunnelling consultants:
and remove temporary Ove Arup & Partners Ian Askew.
sealing plates. Ohver Bevan, Utric Gerry, Paul Holder,
Robert Hyde. Roger Milburn,
Install top section of Hakop Mlrzabaigian, Douglas Parl<es.
diffuser caps. John Senior. Martyn Stroud, Mike Willen

(f) ... Illustrations:


1. & 3 Nigel Whale
Completed intake tunnel. 2: Hakop Mirzabaig,an

18 THE ARUP JOURNAL A/ 1994


location. All this gives a flexible 'kit of parts'
for 7-20m spans, with variable angles of skew
up to 30, and allows alternative finishes and
parapet forms . Variations in ground condition
make the in situ foundations the only element
that inevitably alters from site to site.
Integration into the landscape
Study of the area led towards orientating the
arch to emphasize the gorge-like nature of the
stream at this location. The wing walls were
kept parallel to the road to minimize visual
intrusion on the gorge, as well as maintain a
focus upon the arch .
Minimal disturbance
of the site during construction
This was achieved by locating the new wider
bridge in almost the same position as the
existing. One new section was to be built
alongside. with single-lane traffic transferred
to it whilst the existing bridge was demolished
and the second phase of the new bridge con-
structed. Existing flora and fauna were surveyed
before commencing work, to identify how
1 The bridge 1n its Highland setting, with the slopes of Am Bodach rising behind existing topsoil and plants could be removed ,
stored and re-used in landscaping and
restoration at the end of the project.
Introduction strip footings for the wing walls similarly follow Appropriate appearance
In 1992 the Scottish Ottice Industry Department the ground profile. With the precast wing walls The weatherin g of the existing b ri d ge d is-
Roads Directorate launched a national two- and arch elements erected, the spandrel guised very well the originally pink granite
stage competition for a new bridge to take the walls were placed on the arch and the per- cladding to its concrete structure. To meet
A82 over the Allt-Ru1gh (red burn), replacing manent 'formwork ' thus created infilled with client concern over durability and concrete
an existing 1930s reinforced concrete. gran- mass concrete to provide severally a com- protection. as well as aesthetic considerations,
ite-clad structure. The site lies nearly 150km posite arch , restraint to the spandrel walls, masonry cladding was required for the new
north west of Glasgow. The first stage estab- and a base to the road. This composite bridge. A modern equivalent to the original was
lished design principles. and five submissions approach made for efficiency, buildability found west of Aberdeen and used to provide
were chosen to be developed . The winner. by and robustness, the simplicity of the design the pink granite cladding finally chosen. Stone
Ove Arup & Partners' Newcastle office, was allowing very short construction time in poten- patterning, textures. and parapet profiling were
selected in May 1993 by the client and his tially difficult weather conditions. all considered in some detail before the final
advisers. after which a presentation to the A design with adaptability choice, as were other principal elements.
Royal Fine Art Commission for Scotland was for use on other sites Suitable finishes
made. The design/build fixed cost contract was The same precast 'formwork' can be used Corrienie pink granite is well known for its dura-
awarded to Laing Scotland in June 1993 with because different spans are possible from bility. A split-faced appearance was chosen for
a programmed start on site the same August. greater or lesser sections of the same radius the main walls, whilst the feature elements have
The design arch. Arches of variable skew could also be a smoother finish . The soffit of the arch is the
The remote Highland location, weather. access achieved by a similar approach. whilst wall only unclad exposed concrete element.
constraints, and environmental issues all pointed units of variable height could be cast from the Very high levels of durability
to maximum off-site preparation. In addition, same form . Finishes could either be integrally These were sought by using stainless steel for
eight criteria had been laid down in the competi- cast with the wall units or an exposed concrete the reinforcement; grade C50 concrete with
tion, addressed by Arups' design as follows : surface provided , depending on budget and aggregates of proven durability; granite facing;
Arched form and by factory precasting the main concrete
2. Cross-section. 6 .3m roadway
The concept used precast reinforced concrete elements to achieve greater quality control.
between 0 .6m and 1 6 pavements.
arch units to create a structure able to take Construction
the maximum highway loading requirements. Precast concrete spandrel wall Work commenced in August 1993, with two-lane
Rigorous analysis confirmed the robustness of unit and integral granite cladding
traffic having to be maintained until the begin-
the design for a long and useful life. lnsitu ning of September. In the event the two-stage
Wall
Innovation in design and construction construction approach was revised due to
Path Road surface
The design aimed for maximum repetition. with supply difficulties: a bailey bridge carried
Granite
two forms only being used - one for the arches Mass concrete infill cladding single-lane traffic while the existing brid ge
and the other for the wing and spandrel wall was demolished, and both phases of the
elements. Finishes to the wing walls were Precast arch units new were built in one operation. The p re-
integrally cast and arrived factory-finished cast approach proved itself with fabrication,
ready for erection . In s1tu reinforced concrete Granite stone cladding delivery and erection taking some six weeks,
foundations support the precast arch units, to foundation
Rock and the new Allt-Ruigh was opened to two-
accomodating various ground levels, and the lane traffic on 24 December 1993.

3 . Long section The clear span of the arch 1s 11m.


Credits
Client
Mass concrete infill Waterproof layer Scottish Office Industry Department
Roads Directorate
Road surfacin Designer & engineer
New compacted fill Ove Arup & Partners Robin Anderson.
Jim Burridge . David Jameson Steve Pearce

Contractor & design/build client.


Existing ftll Laing Scotland
Precast reinforced Environmental consultant.
concrete arch
Institute of Terrestrial Ecology

Existing masonry
abutment cut down Gorge rockface
/ Existing masonry
abutment cut down

lnsitu reinforced
Cilen/'s advisers.
Scotlish Natural Heritage
Gillespies
National Trust for Scotland
Burn Crouch Hogg Waterman
concrete foundation
Rock /1/ustrat,ons:
1 Jim Burridge
2. 3: Sean McDermotVTrevor Slydel
THE ARUP JOURNAL 411994 19

Das könnte Ihnen auch gefallen