Detailed Estimate for Construction of Pu Vanlalhruaia's Residential Building at Armed Veng.

(Based on MPWD, SOR 2013)

Length Breath Height Rate Amount


Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
Steel reinforcement for
RCC work including
straighthening, cutting,
4/5.21 bending, placing in
position and binding all
complete.

(c) Cold twisted bars


Column:
16mm vertical bar 16 8 3.20 1.58025 647.30
8mm stirrup @ 120c/c 16 28 0.89 0.39506 156.80
Beam:
X-dirn.
16mm 4 4 11.20 1.58 283.10
12mm 3 4 2.85 0.89 30.40
12 4 1.20 0.89 51.30
8mm stirrup @ 120c/c 90 4 0.90 0.39 126.40
Y-dirn.
16mm 4 4 8.20 1.58 207.30
12mm 2 4 2.20 0.89 15.70
1 4 2.00 0.89 7.10
5 4 1.10 0.89 19.60
8mm stirrup @ 120c/c 60 4 0.90 0.39 84.20
Slab:
10mm @ 150c/c
X-dirn. 2 16 3.95 0.62 78.40
Y-dirn. 2 25 2.60 0.62 80.60
Kg Total = 1788.20 83.70 149672.34

Centering and shuttering


including strutting,
5/5.11 propping, etc. and
removal of form works in
-(c) Columns, pillars,
piers, abutments,posts and
struts. Sqm 16 4 0.25 2.90 46.40 506.30 23492.32
(d) Lintels, beams, plinth
beams, girders,
bressumers and
cantilevers, etc.
Beam:
X-dirn. 1 4 11.45 0.25 11.50
2 4 11.45 0.25 22.90
Y-dirn. 1 4 7.95 0.25 8.00
2 4 7.95 0.25 15.90
Sqm Total = 58.30 400.10 23325.83
(e) Suspended floors,
roofs, landings, shelves
and their support,
balconies and chajjaj,etc
Slab : Sqm 1 3.30 1.93 - 6.40 536.30 3432.32
Providing and laying in
position machine batched,
machine mixed and
machine vibrated design
6/5.36 mix M-20 grade
reinforced cement
concrete excluding cost
of centering and
shuttering and
reinforcement in -
(b) All work above plinth
level upto floor V level

Column: 16 0.25 0.25 2.90 2.90


Beam :
X-dirn. 4 11.45 0.25 0.30 3.44
Y-dirn. 2 7.95 0.25 0.30 1.19
2 8.7 0.25 0.30 1.31
Slab: 1 3.80 2.43 0.12 1.11
Chajja: 1 3.80 0.48 0.075 0.14
Cum Net Qty. = 10.08 8952.30 90202.97

First class brickwork in


7/6.02 superstructure above
plinth level upto floor V
level in:
(a) in cement mortar 1: 3 (
1 cement : 3 fine sand )
Longer Dirn. 3 9.45 0.08 0.60 1.28
1 3.30 0.08 0.60 0.15
Shorter Dirn. 3 6.95 0.08 0.60 0.94
1 4.10 0.08 0.60 0.18
Cum 2.55
Deduction for opening :
D 1 1.2 0.08 0.60 0.05
D1 3 0.90 0.08 0.60 0.12
D2 2 0.75 0.08 0.60 0.07
0.24
Cum Net Qty. 2.30 9547.50 21997.44

Providing Ist class local


wood dressed in frames of
8/9.06 chaukat for doors,
windows, clerestory
windows fixed in
position.
D 1 2 0.10 0.075 2.10 0.032
1 2 0.10 0.075 1.20 0.018
D1 3 2 0.10 0.075 2.00 0.090
3 2 0.10 0.075 0.90 0.041
D2 2 2 0.10 0.075 2.00 0.060
2 2 0.10 0.075 0.75 0.023
W/V 14 2 0.10 0.075 1.95 0.410
14 3 0.10 0.075 0.90 0.284
V1 2 2 0.10 0.075 0.45 0.014
2 2 0.10 0.075 0.60 0.018
Cum 0.99 43660.30 43092.72

Providing 1st class local


wood in trusses etc.
including hoisting fixing
in position supplying
9.08 necessary fittings such as
spikes bolts and nuts,
nails etc and applying
wood preservative for
unexposed surface etc.
complete.
Principal Rafter 2 5 4.30 0.10 0.075 0.323
Rafter 4 2 5.80 0.05 0.075 0.174
6 2 4.00 0.05 0.075 0.180
2 1 4.42 0.10 0.075 0.066
2 4 2.22 0.10 0.075 0.133
Coller 1 5 3.96 0.10 0.075 0.149
Purlin 2 6 8.83 0.05 0.05 0.265
2 5 4.00 0.05 0.05 0.100
4 4 1.50 0.05 0.05 0.060
2 4 2.88 0.05 0.05 0.058
Cum 1.51 38740.90 58372.85

Providing 1st class local


wood work dressed in
9.03 frames of sill, upright,
batten, post, beams, etc. as
structural members fixed
in position complete.
Post 15 0.075 0.10 2.30 0.259
Batten 2 4 11.20 0.075 0.10 0.672
2 4 7.70 0.075 0.10 0.462
Cum 1.39 35281.40 49138.17

Providing 1st class local


wood work dressed in
9.43 frames of false ceiling,
partitions, etc. sawn and
fixed in position.
Partition 1 4 0.05 0.05 2.60 0.026
1 3 0.05 0.05 3.70 0.028
1 4 0.05 0.05 2.30 0.023
1 3 0.05 0.05 3.70 0.028
1 3 0.05 0.05 2.30 0.017
1 3 0.05 0.05 2.88 0.022
1 4 0.05 0.05 2.30 0.023
1 3 0.05 0.05 3.45 0.026
1 3 0.05 0.05 2.30 0.017
1 3 0.05 0.05 2.50 0.019
Sqm Total = 0.21 35891.80 7518.61

Providing and fixing


asbestos cement plain
sheet board fixed with
50mm x 12mm thick
dressed beading with
13.9 50mm wide plain sheet
flashing at the horizontal
joints including supply of
beading and flashing
complete excluding cost
of timber frame work
using -
(b) 5 mm thick A.C. plain
sheet
Longer Dirn. 2 10.45 - 2.30 48.07
2 2.50 - 2.30 11.50
Shorter Dirn. 2 6.95 - 2.30 31.97
2 1.50 - 2.30 6.90
Total = 98.44
Deduct openings D 1 1.20 - 2.10 2.52
D2 2 1.20 - 2.00 4.80
Sqm Net Qty. 91.12 479.10 43655.59

Providing and fixing 3mm


13.18 thick plywood walling
lining with necessary
screws complete -
(a) With teakply facing of
approved manufacture 1 3.70 - 2.60 9.62
3 2.85 - 2.30 19.67
1 3.45 - 2.30 7.94
Total = 37.22
Deduct openings D1 3 0.90 - 2.00 5.40
Sqm Net Qty. 31.82 888.00 28256.16
Providing corrugated G.S.
sheet roofing fixed with
polymer coated J or L
hooks, bolts and nuts 8
mm diameter with
bitumen and G.I. limpet
washers or with G.I.
16.01 limpet washers filled with
white lead and including a
coat of approved steel
primer and two coats of
approved paint on
overlapping of sheets
complete (upto a pitch of
60 degrees) excluding the
cost of purlins, rafters and
trusses.
(e) - 0.63mm thick with
zinc coating not less than
275gm/m
2 8.83 - 4.37 77.13
4 4.42 - 3.83 67.71
4 1.50 - 3.16 18.96
Total = 163.80 432.60 70862.00

Providing ridges or hips


of width 60 cm over all
width plain G.S. sheet
16.07 fixed with polymer coated
J. or L hooks, bolts and
nuts 8 mm dia. G.I. limpet
and bitumen washers
complete.
(a) 1.60mm thick with
zinc coating not less than
350gm/m 1 5.00 5.00
4 4.42 17.68
3 3.16 9.48
Rm Total = 32.16 699.90 22508.78
Providing and fixing 15
cm wide 45 cm over all
semi circular plain G.S.
sheet gutter with iron
16.09 brackets 40x3mm size,
bolts, nuts and washers
etc. including making
necessary connections
with rain water pipes
complete.
(b) 0.63mm thuck with
zinc coating not less than
275gm/m 2 12.65 25.30
2 9.15 18.30
2 1.50 3.00
Rm Total = 46.60 404.80 18863.68
12mm cement plaster 1 : 3
11/21.06
(1 cement : 3 fine sand).
Column: 16 4 0.25 - 2.3 36.80
Beam: 2 4 7.95 - 0.30 19.10
2 4 11.45 - 0.30 27.50
Skirting: 0.00
Longer Dirn. 3 2 11.45 - 0.60 41.20
1 2 3.55 - 0.60 4.30
Shorter Dirn. 3 2 7.95 - 0.60 9.50
1 2 2.85 - 0.60 3.40
1 2 1.25 - 0.60 1.50
Sqm 143.30
Deduction for opening :
D 1 2 1.20 - 0.60 1.40
D1 3 2 0.90 - 0.60 3.20
D2 2 2 0.75 - 0.60 1.80
6.40
Sqm Net Qty. 136.90 210.00 28749.00
6mm cement plaster to
21.25 ceiling 1 : 4 (1 cement : 4
fine sand)
Varanda Ceiling: 1 3.6 2.45 - 8.80 153.10 1347.28
Providing and fixing brass
single acting/ double
acting Spring hinges
12/14.27
bright finished with
necessary screws, etc.
complete.
(a) Single acting
(i) 150mm No 120 120.00 446.80 53616.00

Providing and fixing brass


sliding door bolts
13/14.28 (aldrops) bright finished
with nuts and screws etc.
complete.
(a) 250 x 16 mm No 1 1 928.30 928.30

Providing and fixing


bright finished brass two
14.33 lever mortise door lock
with necessary screws,
etc. complete.
(b) Knob type No 3 3 2059.70 6179.10

Providing and fixing


Brass Tower Bolts (Socket
14/14.29 Bolts) bright finished with
necessary screws etc.
complete.
(a) 300 mm No 34 34.00 334.30 11366.20

15/14.32 Providing and fixing brass


handles with necessary
screws, etc. complete
(a) 150mm No 34 34.00 238.10 8095.40
16/14.67 Providing and fixing brass
hooks and eyes.
(a) 200 mm No 40 40.00 86.50 3460.00

Total Amount Rs. = 768133.07


Say Rs. = 768,100.00

Rupees (Thirteen lakhs and Twelve Thousand) only.

Prepared by :
Detailed Estimate for Construction of Vertical extension of Armed Veng Branch YMA
Building. (Rate are based on SOR 2007 plus Cost index of 26.06% )

Length Breath Height Rate Amount


Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR

Earthwork in excavation
in foundation trenches or
drains etc. (not exceeding
1.5m in width or 10sqm
on plan) including
dressing of sides and
1/2.07 ramming of bottoms, lift
upto 1.5m including
getting out excavated soil
and disposal of surplus
excavated soil as directed
within a lead of 50 metres.

(a) Oridinary Soil


Column Foundation Cum 9 1.20 1.20 1.80 23.30 191.49 4461.72

Providing and laying


cement concrete 1:4:8 (1
cement : 4 coarse sand : 8
2/4.07 graded stone aggregate
40mm nominal size)
excluding cost of
centering and shuttering
in
(a)- All work upto foundation
& plinth level : Cum 9 1.20 1.20 0.15 1.90 4237.63 8051.50

Filling available
excavated earth
(excluding rock) in
trenches, plinth, sides of
3/2.18 foundations etc. in layers
not exceeding 20cm in
depth, consolidating each
deposited layer by
ramming and watering,
lead up to 50 m and lift
upto 1.5 m.
Column Cum 9 1.20 1.20 0.90 11.70 58.87 688.78
HYSD bars like
TATA/SAIL (ISI/ISO
certified) or equivalent
reinforcement for RCC
1/5.07 work including
straighthening, cutting,
bending, placing in
position and binding all
complete.
Column Footing :
12mm @ 200c/c 18 1.00 0.89 16.00
Length Breath Height Rate Amount
Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR

Column:
20mm vertical bar 24 10.65 2.47 631.30
24 9.77 2.47 579.20
24 8.58 2.47 508.60
8mm stirrup @ 120c/c 80 1.10 0.39 34.30
73 1.10 0.39 31.30
63 1.10 0.39 27.00

Ground Floor, First Floor & Roof beam :


X-dirn.
16mm
Main bar: 3 3 4 10.22 1.58 581.30
12mm
Bott. Bar 3 3 4 2.00 0.89 64.10
Top Bar 3 3 4 7.20 0.89 76.90
8mm stirrup @ 120c/c 3 3 70 0.92 0.39 226.00
Y-dirn.
16mm
Main bar: 3 3 4 8.40 1.58 477.80
12mm
Bott. Bar 3 3 4 2.00 0.89 64.10
Top Bar 3 3 4 4.80 0.89 51.30
8mm stirrup @ 120c/c 3 3 54 0.92 0.39 174.40
Slab:
10mm @ 200c/c
X-dirn. 2 2 38 10.22 0.62 963.10
Y-dirn. 2 2 46 8.40 0.62 958.30
Staircase:
2 8 4.65 0.62 46.10
2 8 2.85 0.62 28.30
2 50 1.00 0.62 62.00
Kg 5601.40 68.45 383419.08

Centering and shuttering


including strutting,
2/5.08 propping, etc. and
removal of form works in
-
(a) Foundations, footings,
bases of columns etc. for
mass concrete.
(c) Columns, pillars, Sqm 4 9 1.10 0.2 7.90 168.79 1333.48
piers, abutments,posts and
struts. 2 3 9.27 0.3 16.70
2 3 9.27 0.35 19.50
2 3 7.80 0.3 14.00
2 3 7.80 0.35 16.40
2 3 6.60 0.3 11.90
2 3 6.60 0.35 13.90
Sqm 36.20
304.57 11025.56
Length Breath Height Rate Amount
Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
(d) Lintels, beams, plinth
beams, girders,
bressumers and
cantilevers, etc.
Beam:
X-dirn. 3 3 10.22 0.25 23.00
2 6 10.22 0.30 36.80
Y-dirn. 3 3 8.40 0.25 18.90
2 6 8.40 0.30 30.20
Sqm 108.90 232.20 25286.85
(e) Suspended floors,
roofs, landings, shelves
and their support,
balconies and chajjaj,etc
Slab : Sqm 2 10.22 8.40 - 171.70 347.93 59738.83
(f) Staircases (except
spiral staircase) excluding
landings.
Waist slab : 1 3.45 1.00 3.50
1 3.45 0.125 0.40
1 1.65 1.00 1.70
1 1.65 0.125 0.20
steps : 0.5 16 0.185 0.254 0.40
1 16 1.00 0.185 3.00
Sqm 9.20 267.63 2462.15

Providing and laying in


position machine batched,
machine mixed and
machine vibrated design
mix M-25 grade
3/5.43 reinforced cement
concrete excluding cost
of centering and
shuttering and
reinforcement in -
(a) All work upto
foundation and plinth.
Column Footing: 9 1.1 1.1 0.2 2.20
a1 = 1.21 m 2
H = 0.30m
a2 = 0.105 m2
Volume : 0.05 (1.212+0.1052+(1.21x0.105)) 0.10
2.30 7055.33 16227.25
(b) Walls, columns,
pillars, posts and struts
upto floor five level.
Column: 3 0.3 0.35 8.64 2.70
3 0.3 0.35 7.76 2.40
3 0.3 0.35 6.56 2.10
Cum 7.20 6987.51 50310.04
Length Breath Height Rate Amount
Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
(c) Beams, plinth beams,
girders, bressumers,
cantilevers, suspended
floors, lintels, roofs,
staircases, spiral
staircases, shelves, etc.

Ground Floor, First Floor & Roof beam :


X-dirn. 3 10.22 0.3 0.25 2.30
Y-dirn. 3 8.40 0.3 0.25 1.90
Slab: 2 10.22 8.40 0.125 21.50

Stairs:
Waist slab 1 3.45 1.00 0.125 0.40
1 1.65 1.00 0.125 0.20
Landing 3 1.00 1.00 0.125 0.40
Steps 0.5 16 1.00 0.185 0.25 0.40
27.10
Deduct Staircase 1 7.57 1.00 0.125 0.90
26.20 7081.17 185526.61

First class brickwork in


foundation upto one
4/6.01 storey above and below
ground level including
curing, etc. complete.
(a) in cement mortar 1: 3 (
1 cement : 3 fine sand )
Ground Floor :
Longer Wall 2 9.10 0.112 3.00 6.10
Shorter Wall 3 6.40 0.112 3.00 6.50
Partition wall 1 10.24 0.112 3.00 3.40
First Floor :
Shorter Wall 2 9.10 0.112 3.00 6.10
2 6.40 0.112 3.00 4.30
1 12.97 0.112 3.00 4.40
Cum 30.80
Deduction for opening :
D 1 1.2 0.112 2.1 0.30
D1 4 0.90 0.112 2.1 0.80
D2 4 0.75 0.112 2.1 0.70
W/V 8 1.8 0.112 1.95 3.10
W1/V1 6 0.9 0.112 1.95 1.20
V3 4 0.6 0.112 0.45 0.10
6.20
Cum Net Qty. 24.60 6878.97 169222.62

Length Breath Height Rate Amount


Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
Providing Ist class local
wood dressed in frames of
chaukat for doors,
5/9.06 windows, clerestory
windows fixed in
position.

D 1 2 0.10 0.075 2.10 0.032


1 1 0.10 0.075 1.20 0.009
D1 4 2 0.10 0.075 2.10 0.126
4 1 0.10 0.075 0.90 0.027
D2 4 2 0.10 0.075 2.10 0.126
4 1 0.10 0.075 0.75 0.023
W1/V1 2 10 0.10 0.075 1.95 0.293
3 10 0.10 0.075 1.80 0.405
W2/V2 2 8 0.10 0.075 1.95 0.234
3 8 0.10 0.075 0.90 0.162
V3 2 4 0.10 0.075 0.45 0.027
2 4 0.10 0.076 0.60 0.036
Principal Rafter: 2 4 4.76 0.075 0.10 0.286
8 6.28 0.075 0.10 0.38
2 4.65 0.075 0.10 0.07
8 5 2.10 0.075 0.10 0.63
4 3.75 0.075 0.10 0.11
King Post: 4 1.00 0.075 0.10 0.03
Purlin: 2 6 6.70 0.05 0.05 0.20
2 6 4.20 0.05 0.05 0.13
Cum 3.33 21792.24 72581.90
Providing corrugated G.S.
sheet roofing fixed with
polymer coated J or L
hooks, bolts and nuts 8
mm diameter with
bitumen and G.I. limpet
washers or with G.I.
6/16.01 limpet washers filled with
white lead and including a
coat of approved steel
primer and two coats of
approved paint on
overlapping of sheets
complete (upto a pitch of
60 degrees) excluding the
cost of purlins, rafters and
trusses.
(e) 0.63mm thick with
zinc coating not less than
275gm/m 2 4.76 10.91 + 2.51 63.88
2
4 0.5 4.2 5.94 - 49.90
Sqm 113.78
403.27 45881.66
Length Breath Height Rate Amount
Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR

Providing ridges or hips


of width 60 cm over all
width plain G.S. sheet
7/16.06 fixed with polymer coated
J. or L hooks, bolts and
nuts 8 mm dia. G.I. limpet
and bitumen washers
complete.
(b) 0.63mm thick with
zinc coating not less than
275gm/m Rm 1 27.63 27.63 157.95 4364.25

Providing and fixing 1st


class local wood panelled
shutters for doors etc.
including M.S. butt hinges
6/9.11
with necessary screws,
etc. complete.

(a) 40 mm thick.
D 1 1.05 1.95 2.05
D1 4 0.75 1.95 5.85
D2 4 0.6 1.95 4.68
Sqm 12.58 1495.58 18810.61
Providing and fixing 1st
class local wood panelled
and glazed shutters using
3mm thick plate sheet
glass for doors and
7/9.13 windows etc. including
M.S. butt hinges with
necessary screws, etc.
complete.

(a) 40 mm thick.
W/V 8 1.65 1.73 22.84
W1/V1 6 0.75 1.73 7.79
V3 4 0.45 0.3 0.54
Sqm 31.16 1546.38 48186.69

12mm cement plaster 1 : 3


8/21.08
(1 cement : 3 fine sand).
Ground Floor :
Longer Wall 2 2 9.55 - 3.00 57.30
Shorter Wall 2 3 7.50 - 3.00 67.50
Partition wall 2 1 11.14 - 3.00 33.40
First Floor :
Shorter Wall 2 2 9.55 - 3.00 57.30
2 2 7.50 - 3.00 45.00
2 113.87 - 3.00 41.60
Floor 2 10.2 8.40 - 171.70
Length Breath Height Rate Amount
Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
Stairs:
Waist slab 1 3.45 1.00 - 3.50
1 3.45 0.125 - 0.40
1 1.65 1.00 - 1.70
1 1.65 0.125 - 0.20
Landing 3 1.00 1.00 - 3.00
Steps 0.5 16 0.25 0.185 - 0.40
Sqm 483.00
Deduction for opening :
Deduct Staircase 1 7.57 1.00 - 7.60
D 2 1 1.2 - 2.1 5.00
D1 2 4 0.90 - 2.1 15.10
D2 2 4 0.75 - 2.1 12.60
W/V 2 8 1.8 - 1.95 56.20
W1/V1 2 6 0.9 - 1.95 21.10
V3 2 4 0.6 - 0.45 2.20
119.80
Sqm Net Qty. 363.20 181.78 66021.96

6mm cement plaster to


9/21.26 ceiling 1 : 3 (1 cement : 3
fine sand) 1 10.2 8.4 - 85.70
Deduct Staircase 1 7.57 1.00 - 7.60
Sqm Net Qty. 78.10 127.95 9992.97

Providing and fixing M.S.


pressed butt hinges bright
12/14.02 finished with necessary
screws, etc. complete.

(a) 200 x 65 x 2.12 mm


(Medium type) No 106 106.00 103.24 10943.77

Providing and fixing M.S.


sliding door bolts
(aldrops) bright finished
13/14.06 or/ and black enamelled
with nuts and screws etc.
complete.

(a) 300 x 16 mm No 5 5.00 186.78 933.92

Providing and fixing M.S.


Tower bolts (socket bolts)
14/14.07 bright finished with
necessary screws etc.
complete.

(a) 300 mm No 98 98.00 107.66 10550.21

Length Breath Height Rate Amount


Sl No. Description Unit Nos. Quantity
in (m) in (m) in (m) in INR in INR
Providing and fixing M.S.
handles with necessary
15/14.10 screws, etc. complete

(a) 150mm No 82 82.00 54.21 4444.88

Providing and fixing M.S.


16/14.57 hooks and eyes.
(a) 200 mm No 88 88.00 31.89 2806.60

White washing with lime


17/21.59 on new work (three or
more coats)to give an
even shade.
Ground Floor :
Longer Wall 2 2 9.55 - 3.00 57.30
Shorter Wall 2 3 7.50 - 3.00 67.50
Partition wall 2 1 11.14 - 3.00 33.40
First Floor :
Shorter Wall 2 2 9.55 - 3.00 57.30
2 2 7.50 - 3.00 45.00
2 1 13.87 - 3.00 41.60
Floor 3 10.2 8.40 - 257.50
Stairs:
Waist slab 1 3.45 1.00 - 3.50
1 3.45 0.125 - 0.40
1 1.65 1.00 - 1.70
1 1.65 0.125 - 0.20
Landing 3 1.00 1.00 - 3.00
Steps 0.5 16 0.25 0.185 - 0.40
Sqm 568.80 13.24 7528.81

Finishing walls with water


proofing cement paint of
approved brand and
17/21.89 manufacture and of
required shade on new
work (three or more
coats) to give an even
shade.
Ground Floor :
Longer Wall 2 2 9.55 - 3.00 57.30
Shorter Wall 2 3 7.50 - 3.00 67.50
Partition wall 2 1 11.14 - 3.00 33.40
First Floor :
Shorter Wall 2 2 9.55 - 3.00 57.30
2 2 7.50 - 3.00 45.00
2 1 13.87 - 3.00 41.60
Floor 3 10.2 8.40 - 257.50
Stairs:
Waist slab 1 3.45 1.00 - 3.50
1 3.45 0.125 - 0.40
1 1.65 1.00 - 1.70
1 1.65 0.125 - 0.20
Landing 3 1.00 1.00 - 3.00
Steps 0.5 16 0.25 0.185 - 0.40
Sqm 568.80 82.70 47037.12

Painting two or more


coats on G.I sheet with
18/21.90 antifungus roof paint of
approved brand and
manufacture on new work
to give an even shade. 2 4.76 10.91 + 2.51 63.88
2
4 0.5 4.2 5.94 - 49.90
Sqm 113.78 61.64 7013.48

TOTAL ESTIMATED AMOUNT Rs. = 1274853.28