Beruflich Dokumente
Kultur Dokumente
Energy
16.1 Vision
To provide uninterrupted, assured, affordable and sustainable energy to all the consumers
leading to accelerated Socio - Economic growth of the district
India is the fifth largest producer of energy in the world, however it is still one of the lowest among per capita
consumption which is around 660 KWH. India has an installed capacity of 1,52,000 MW as on 2009. This is
about 4% of the global power generation.
Power sector assumes priority, in the five year plans, with the result, India has reached a level of 1,67,317 MW
To provide Reliable, (Nov 2010) of installed capacity. Still the shortage is in the order of 12%. Domestic consumers in India
Affordable and sustainable constitute only 57%.
energy to all the customer
The other top four power generating countries are US, Japan, China and Russia. The average per capita power
consumption of India was estimated to about 700 KWh in year 2008-09. Indian government has set an
ambitious target of generating additional 78,000 MW of Power in 11th Plan due to which huge power
generation capacity is expected to come up. However the achievement till March 2009 was 12,467 MW.
The inter grid transmission is only about 13% of the capacity of the total installed capacity of the country,
which pose limitations on transmission.
Transmission and distribution loss, which amounts to 33% of the total power transmitted, is a cause of
concern in this sector. Efforts are on to reduce or lower down the T&D losses. With new technologies and
privatization the losses are expected to be reduced.
327
Energy
Power Generation in India
The Mahanirmiti or MAHAGENCO (Maharashtra State Power Generation Company Limited - MSPGCL) is the
major power generating company in the state of Maharashtra. With a total generation of 10,400 MW, it is the
second largest power producing company in India. The power generated by MSPGCL is supplied to the State.
Maharashtra has 20,415 MW of electricity available from all the sources including central and private sectors.
Government of Maharashtra through MSEDCL has undertaken development programmes under various
schemes having an outlay of Rs. 473 Cr for improving the districts electricity scenario. To further improvise
the situation and to meet the target of 100% electrification, out lay of Rs. 1,643 Cr will be required.
Aurangabad urban areas receives 24 hrs power supply, however, the case is not so in the rural areas which faces
on an average 12 hrs of load shedding. It has 97% of its villages electrified and 54% of households possess electric
connection.
328
Aurangabad has various sites which can be tapped to generate green energy. Nath Sagar has 12 MW installed
capacity by way of hydel power. Sites having Wind energy potential include Thokal Malegaon, Mhaismal and
Kankora which have capacity of around 50 MW. Kannad can contribute to 4.35 MW of electricity generation by
bio mass project. Deo Giri SSK has installed capacity of Biogas power generation of 5 MW against potential of 12
MW. The other potential biogas co-generation sites include two sugar mills at Sillod, one each in Aurangabad,
Vaijapur and Paithan.
The peak requirement for power in the state stood at 17,489 MW in 2007-08. As of March 2008, the state had
granted approval to set up 163 conventional energy projects with a total capacity of 1,757 MW for captive
electricity generation. Of these, 78 projects had been commissioned by the end of 2007-08 and 550 Mn KWh
electricity was being generated.
In 2008-09, the state had an installed power generation capacity of 15,030 MW including the central and
private sectors. The total power capacity available to Maharashtra was 20,415.4 MW, as of May 2009, mostly
through, state owned hydro and thermal plants. Independent Power Producers (IPPs) and private non
conventional power generators contributed 4466.4 MW.
The inter grid transmission Electricity consumption of Maharashtra has increased from 29,971 Million KWh in 1990-91 to 69,838 million
is only about 13% of the
KWh in 2007-08.
capacity of the total
installed capacity of the The state has a potential of 7,852 MW through renewable energy sources.
country
14,500 14,326
14,053
14,000 13,838
13,500 13,369
13,153 13,180 13,189
13,000
12,500
12,000
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
Sources: Central Electricity Authority, Ministry of Power,
Maharashtra State Electricity Board Holding Co. Limited
329
Energy Requirement: Aurangabad Energy
Aurangabad district is one of the premiere industrial districts of Maharashtra. Aurangabad is emerging as one
of the developed districts after Pune and Nagpur. It is also the regional education and health care hub serving
surrounding 10 districts. Therefore, the energy need of the district is quite high and is likely to grow in future.
In this context, continuous supply of energy is the key driver for the development.
The power supply in Urban Areas is adequate to meet the current demand but to ensure quality of supply in
future capacity augmentation is required. The rural area faces load shedding of 12 Hrs. Continuous power
supply to the urban and rural areas is the need of the day. This entails augmentation of supply infrastructure
from the current installed infrastructure of 1004 MW transmission capacities to 1627 MW by 2020.
As regards to rural areas the supply is grossly inadequate and the peak deficit is around 95 MW leading to an
average load shedding of 12 hours a day.
Sr No Particulars No
1 Total Villages 1344
2 Villages Electrified 1302
3 Rural Households 255794
4 Rural Households electrified 182411
5 Villages to be electrified 42
6 Electrification of RH under RGGVY 58533
7 Agricultural Pumps Electrified 150079
Source: Maharashtra State Electricity Distribution Co. Ltd.
As seen from the above table the villages which remain to be electrified are 42 in numbers.
330
Aurangabad Electricity Distribution
23%
Residential
Commercial
Industrial
18% 59%
Electricity is required for Maximum power is drawn by residential consumers at 59%, followed by Industrial and Commercial consumers
the growth in which is 23% and 18% respectively.
industrialization, health,
education and other sectors Existing/Projected Consumers, Load and Infrastructure
EHV: Extra High Voltage, LT: Low Tension, HV: High Voltage, S/S: Substation,
331
Energy
16.3 Major Ongoing Development Programmes/ Schemes
Clean, reliable and affordable energy services are indispensable for overall prosperity and development and is a
part of core infrastructure. For future growth of the district to be both speedy and sustainable, it needs to be as
resource-efficient and environmentally harmless as possible. Underlying intention of this document is to bring a
more cohesive approach to energy generation and consumption by increased participation of industry,
institutions and public (consumers).
Major source of energy in current scenario is thermal power plants which are dependent on renewable sources
like coal. Non renewable energy generation is thus located around the resource intensive areas thus creating
imbalance in power generation centers.
Setting up and maintaining power generation infrastructure requires huge influx of investment. Current energy
generation would be unable to meet the exponential growth. To offset this demand in the future for cheap,
efficient and continuous power generation and distribution, it is proposed increase participation of private
players by encouraging power generation on PPP.
Also, increased focus should be put on the alternative and renewable source of energy to maintain the
ecosystem. Due fast depleting natural resources, it justifies to implement technologies involving renewable
resources. To provide sustainable and clean energy for the exploding growth, interventions to introduce
renewable mode of power generation is necessary. Major source of energy
in current scenario is
Some of the modes of renewable modes of power generation are: thermal power plants,
Solar dependent on renewable
Small Hydro sources
Biomass
Biogas
Power generation through Municipal/industrial solid Waste
Optimal level of exploitation of above mentioned resources would greatly reduce the dependability on non
renewable energy thus leading to sustainable, green and continuous power supply.
Comprehensive demand assessment for usage pattern should be undertaken for institutional users like
Hospitals, Hotels and Education institutes so that power allocation to be prioritized.
332
Infrastructure under Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY):
Rural Electricity Distribution Backbone (REDB) with 33/11 KV (or 66/11 KV) sub-station of adequate capacity
in blocks where these do not exist.
Village Electrification Infrastructure (VEI) with provision of distribution transformer of appropriate capacity in
villages/habitations.
Decentralized Distributed Generation (DDG) Systems based on conventional & non conventional energy
sources where grid supply is not feasible or cost-effective.
333
Status of Existing & Potential for Green Energy in the District: Energy
Small Hydro Power Project
Name : Nath Sagar
Taluka : Paithan
Total Installed Capacity : 12 MW
1
Thokalmalegon
Kannad 3 2
5 4
Kankora 6
Mhismal Aurangabad
Khultabad 50 MW
5.5 m/s 6.2 m/s Name: Deo Giri SSK Ltd. Energy to be used
Crushing Capacity (TCD): 2500 most efficiently
Taluka: Kannad Power Potential: 12 MW
Surplus Bio-Mass: 65,310 Tonnes/yr Installed Capacity: 5 MW
Power Potential: 4.35 MW Location: Phulambri
334
Vainayak SSK Ltd, Vaijapur
Shri Sant Eknath SSK Ltd, Paithan
335
Renewable energy can be used in various institutions like Hospitals, Educational Institutes, Government Energy
Buildings among others
336
The role of the GTL is:
Build the infrastructure in the franchisee area to lower the distribution losses and improve the quality of
supply
Calibration of Meters
Use and maintain the existing assets of the MSEDCL for distribution of energy
Plan and implement capital expenditure for efficient distribution of energy
Periodic Forecast of Demand and Load
Carry out energy Audit on Monthly basis
Handle Consumer Complaints etc
337
Energy
16.4 Summary of Action Plan & Outcomes
Vision
To provide uninterrupted, assured, affordable and sustainable energy to all the consumers
leading to accelerated Socio - Economic growth of the district
Action Plan
Erecting 50 Nos 33/11 KV S/Stn
Outcome
100% adequacy in Supply Availability in Urban / Rural for 24 Hrs
338
Now 2010 Then 2020
339
Energy
Now 2010 Then 2020
340