Sie sind auf Seite 1von 1

Remark Performance Worst Coal

Coal
Coal consumption of 30 MW (net) CPP TPH As per ISGEC DBR 15.50 18.38
plant
Predicted coal consumption of 150 MW TPH As per preliminary SCAT run by B&V 62.27 74.06
(nominal capacity)
Total station coal consumption (30 MW + Ton / day Assumed 90% PLF and 24 hour 1,680.00 1,997.00
150 MW) for 90% PLF operation

Planned storage at site Ton As per MCM requirement 100,000.00


No. of days storage available at site days 59.00 50.00

Average capacity of Panamex cargo vessel Ton Typical capacities are 65,000 DWT 65,000.00
for coal
Assumed Ship unloader capacity at Aqaba tph Assumption 2,000.00
port
Average unloading to rated capacity Typical average capacity achieved are 0.90
factor less than rated capacity

Time required to unload Panamex at port hours 37.00

No. of days for which vessel is berthed at days Assuming 16 hours of unloading 2.40
port operation

Carrying capacity of Road Train Ton Assuming 6 axle road train with max. 50.00
length of 18.35 m
Distance from Aqaba port to MCM Power kms Assuming fastest route through Route 265.00
Plant site 15

Average speed of road train kmph Assumed 50% of peak speed for LCV 45.00

Average time to reach site from port hours 1 hour contingency assumed 7.00
Road train required to meet station coal nos. 34.00 40.00
consumption
Time for unloading coal train at site minutes 20.00
No. of road trains that can be unloaded in nos. Assuming 16 hours of operation 48.00
a day
Coal that can be unloaded at site Ton/day 2,400.00
Coal to reserved storage Ton/day 720.00 403.00

Das könnte Ihnen auch gefallen