Beruflich Dokumente
Kultur Dokumente
T
Luc Proulx he maintenance leader is often the key Toyota, the high-volume, high-tech plant of
Prosygma Inc. to a successful, reliable, and perform- more than 750 workers was implementing
ing maintenance department, such as the Lean method. You could find evidence of
in the case we are studying here. But 5S in every corner of the shop. (See Figure
success never happens by pure luck. It is the 1). The result was an empowerment environ-
result of bold moves, relentless work, and ment for operators in which the decision-
believing in human empowerment to solve making process was delegated to the lowest
problems. level and the Lean model was integrated by
The following case study is one example of stabilizing the 4Ms: manpower, machine,
how that can be accomplished. We used the method, and material, which are the corner-
Lean A3 process and nomenclature to follow stones of the philosophy. (See Figure 2).
step by step the exact formula
to achieve results.
As is often the case in Lean
methodology, it is important
to follow each exact step.
Also, using the plan-do-
check-act (PDCA) cycle to
attain goals ensures reach-
ing the optimum solution
and maximum success with
the tools at hand.
At the various phases of
the project, we integrated
total productive maintenance
(TPM) elements or tweaked
old ones that were already
in place, but we also closely
monitored the process over
a three-year period and its
impact on the crucial KPIs for
the business: percent uptime
(versus the more negative
term of percent downtime),
MTTR (mean time to repair),
MTBF (mean time between
failures), and maintenance
response time (MRT) to
emergency work order. Figure 1: A map of the Lean A3 process,
which creates a step-by-step formula. All
Background graphics courtesy: Prosygma
In the early 2000s, the production unit in
question embraced the Lean manufacturing With the pressure of producing and main-
philosophy, which is an adaptation of the taining improvement trends each budgeted
Japanese just-in-time philosophy described year (cost reduction, productivity, health and
in a book written by James Womack in safety (H&S), percent uptime, and quality)
1990. Adopting the value-added philosophy and competing in the global arena for higher
developed in the dire years after WWII by volume and technologically advanced equip-
Analysis
The first couple of weeks into the
project were dedicated to data min-
ing and patching holes. For emer-
gency planning, we had to redefine
the 24-hour service of each depart-
Figure 2: The corner store ment (to sustain those KPIs), management ment and the weekend overlap. The next step
of the Lean model is the had to focus its attention on the maintenance was to reorganize the next shutdown (to cut
4Ms: manpower, machine, side of the business since the gap between it from one week to one weekend) and to get
method, and material. production and maintenance support was a simple message out to the team: TPM for
widening. Managements decision was to all and we will have the best maintenance.
pursue total assets management instead of Our analysis provided the following input:
focusing solely on maintenance reactive
intervention or even spot improvements. 1. Machine criticality level was attrib-
uted by production people who were
Current conditions more aware of their own numbers than
The maintenance department was composed the overall budgeted plan. We found
of skilled workers split in two trades, where out that everything was treated at the
all the support services jobselectricity, highest level at all times, which even-
plumbing, cleaning, tribologywere handled tually resulted in eliminating the sense
by outside contractors. This created an envi- of urgency.
ronment of mistrust with the in-house full- 2. The other related issues were that the
time employees establishing a second-class MRT for an emergency work order was
citizenship role for the outsiders. It produced going up and was taking a major bite
a silo-type environment where everything out of the MTTR.
was connected by arduous communication 3. Technical maintenance issues were
lines and where projects were handled by sometimes handled by floor production
young engineers whose loose monitoring of people as part of the empowerment pro-
projects was significantly affecting the bud- cess, which was creating lots of com-
get and day-to-day maintenance operations. plaints since people with maintenance
H&S rules were documented, implement- experience had not been consulted.
ed, and disseminated, but human behaviors 4. The percent uptime was 94.2% with a
were not following the same path, and with negative outlook, and all the machines
the morale of the workers at its lowest point, were at the same level of critical-
problems were on the horizon. ity, including Kleenex machines (e.g.,
Other impeding problems were that the machines with a short life span, low
servicing of critical machines was controlled acquisition cost, and high maintenance
by production people driven only by daily costs at the end of their effective life
throughput numbers, the average age of main- span) that should have been disposed
tenance workers was more than 45 years, and of but were still in use.
new machines kept arriving with equipment 5. H&S rules were becoming tougher to
standards decided by the head office thousands apply and to follow and, at the same
of miles away. time, buy-in and behaviors were fol-
On the bright side, efforts had been made lowing a downward spiral as mainte-
years before to implement computerized main- nance employee morale followed the
1. 5S + 1(Safety)
Integrate concept by holding 5S + 1
Kaizen workshops every month for the
first year.
Audit process put in place to monitor
progress and sustainment over the next
two years.
Plan
The plan was prepared for the next
three years according to the Toyota
typical TPM roadmap and re-evaluated
every year based on the production
volume, new technology, and market
demand. (See Figure 5).
You can see in the next graph that the
roadmap worked out almost perfectly
for the entire project. However, a big factor guard, process change, or even redesign Figure 7: By Year 4, uptime
was overlooked at the outset of the imple- of a machine). for critical machines was
mentation phase: culture change resistance. Also, after benchmarking, we launched consistently above 98%.
The graph below shows a deterioration of an audit process that was prepared, con-
response time by workers in the first three trolled, and applied by the workers them-
quarters just as the percent uptime was selves. It took six months before the work-
improving. People were reluctant to scan ers became accustomed to it, but it gave
their badges when taking care of an emer- the project a zero accident record over the
gency work order, because they felt that by next 1,000 days.
showing improvement their jobs would be in By taking care of the human side of
jeopardy. Coupled with H&S problems (six our projectcommunications (everyday
accidents in half a year), it almost derailed roll call, mandatory participation in all
the whole project. See Figure 6. Kaizen training, evaluation, help ticket),
You should never underestimate the behaviors, and self-auditwe had more
strength of inertia and remember that H&S leverage for delivering the performance
problems are never solved by drawing up a message.
list of technical problems to be addressed. A As Figure 7 illustrates, the Percent
managers soft skills are needed to improve Uptime exceeded 98.8% at the end of the
readiness to change and H&S issues require project.
behavioral changes. The actual production time savings eval-
uated and stamped by the finance depart-
Monitoring ment were 99,000 hours for close to $12M
The lead KPIs were the same from start to in savings over three years.
finish, but the action taken was adapted
to the situation. Basic Cost $120/hr.
The first thing to do was to evaluate Year Uptime % Increase Hours Worked Recuperated Hours Benefit ($)
worker behavior before we even talked
0 94.2% 0.0% 783,000 14,000 1,680,000
about performance and WO completion.
It led to an evaluation form that was more 1 96.0% 1.8% 1,075,000 42,000 5,040,000
closely aligned with TPM values and bet- 2 98.1% 3.9% 1,025,000 43,000 5,160,000
ter H&S behaviors.
3 98.4% 4.2% 2,883,000 99,000 11,880,000
At the same time, we prepared the usual
list of technical problems encountered
by the workers and the impact on their The quality assurance department even
H&S, asking them to do a daily check of decided to follow our lead by benchmark-
everything that they considered awkward ing the Andon technology and carrying
or risky. The thinking behind it was that, out the same process with the operators. PE
after identifying the problem, 99% of the
time a behavior has to change before we Luc Proulx is with Quebec, Ontario-based
make any technical changes (machine Prosygma Inc.