GOBIERNO REGIONAL PUNO


PRORRIDRE

VALORIZACION DE OBRA N 01
OBRA : MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA DEPARTAMENTO : PUNO
ENT. EJEC. : PRORRIDRE FECHA DE INICIO DE OBRA : PROVINCIA :
ENT. FIN. : GOBIERNO REGIONAL PLAZO DE EJECUCION : DISTRITO :
FECHA : FECHA DE TERMINO DE LA OBRA : SECTOR :

PRESUPUESTO ( S/. ) AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO ACTUAL
ITEM DESCRIPCION
UNIDAD METRADO C.U. PRESUPUESTO METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE METRADO VALORIZADO %DE AVANCE
CONSTRUCCION DE CANAL PRINCIPAL IRRIGACION YANARICO 2,308,688.76 - 0.00% 0.00 0.00% 0.00 0.00% 2,308,688.76 100.00%
01.00.00 TRABAJOS PRELIMINARES 62,472.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 62,472.76 100.00%
01.01.00 CAMPAMENTO GLB 1.00 2,500.00 2,500.00 0.00% - 0.00 0.00% 1.00 2,500.00 100.00%
01.02.00 CARTEL DE OBRA 5.0X3.0 M UND 1.00 2,922.38 2,922.38 0.00% - 0.00 0.00% 1.00 2,922.38 1.00
01.03.00 TRANSPORTE DE MAQUINARIA Y EQUIPO_CP GLB 2.00 4,074.31 8,148.62 0.00% - 0.00 0.00% 2.00 8,148.62 100.00%
01.04.00 TRAZO Y REPLANTEO M 22,710.26 0.85 19,303.72 0.00% 0.00% 0.00 0.00% 22,710.26 19,303.72 100.00%
01.05.00 TRAZO Y REPLANTEO OBRAS DE ARTE M2 2,664.91 0.80 2,131.93 0.00% 0.00% 0.00 0.00% 2,664.91 2,131.93 100.00%
01.06.00 LIMPIEZA Y DESBROCE A MANO M2 2,589.91 0.99 2,564.01 0.00% 0.00% 0.00 0.00% 2,589.91 2,564.01 100.00%
01.07.00 LIMPIEZA Y DESBROCE A MAQUINA e=0.20M M2 88,936.07 0.28 24,902.10 0.00% 0.00% 0.00 0.00% 88,936.07 24,902.10 100.00%
02.00.00 MOVIMIENTO DE TIERRAS 740,627.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 740,627.32 100.00%
02.01.00 DEMOLICION DE ESTRUCTURAS M3 34.42 32.38 1,114.52 0.00% - 0.00 0.00% 34.42 1,114.52 100.00%
02.02.00 EXCAVACION DE PLATAFORMA EN MATERIAL SUELTO A MAQ. M3 10,592.33 3.83 40,568.62 0.00% 0.00% 0.00 0.00% 10,592.33 40,568.62 100.00%
02.03.00 EXCAVACION DE CORTE PARA REEMPLAZO M3 15,660.75 4.07 63,739.25 0.00% 0.00% 0.00 0.00% 15,660.75 63,739.25 100.00%
02.04.00 TERRAPLEN COMPACTADO M3 50,179.95 7.14 358,284.84 0.00% 0.00% 0.00 0.00% 50,179.95 358,284.84 100.00%
02.05.00 EXCAVACION DE CAJA DE CANAL A MAQUINA M3 21,818.37 4.05 88,364.40 0.00% 0.00% 0.00 0.00% 21,818.37 88,364.40 100.00%
02.06.00 EXCAVACION Y REFINE DE CAJA DE CANAL EN MATERIAL SUELTO A MANO M3 9,350.73 15.95 149,144.14 0.00% 0.00% 0.00 0.00% 9,350.73 149,144.14 100.00%
02.07.00 EXCAVACION PARA CIMENTACION DE OBRAS DE ARTE M3 2,186.21 11.77 25,731.69 0.00% 0.00% 0.00 0.00% 2,186.21 25,731.69 100.00%
02.08.00 RELLENO COMPACTADO DE OBRAS DE ARTE M3 1,089.16 12.56 13,679.85 0.00% 0.00% 0.00 0.00% 1,089.16 13,679.85 100.00%
03.00.00 DRENAJES 9,273.50 - - - - - 9,273.50 100.00%
03.01.00 EXCAVACION DE ZANJA DE DRENAJE A MANO M3 225.00 9.74 2,191.50 - - - - - - 225.00 2,191.50 100.00%
03.02.00 COLOCACION DE DRENAJE EN ZONA DE BOFEDAL M 200.00 21.28 4,256.00 - - - - - - 200.00 4,256.00 100.00%
03.03.00 RELLENO COMPACTADO A MANO CON MATERIAL SELECCIONADO M3 225.00 12.56 2,826.00 - - - - - - 225.00 2,826.00 100.00%
04.00.00 CONCRETOS 1,190,358.54 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,190,358.54 100.00%
04.01.00 CONCRETO F'C= 210 Kg/cm2 M3 148.53 278.29 41,334.41 0.00% 0.00% 0.00 0.00% 148.53 41,334.41 100.00%
04.02.00 CONCRETO FC=175 KG/CM2 REVESTIDO DE CANAL M3 3,838.94 273.36 1,049,412.64 0.00% 0.00% 0.00 0.00% 3,838.94 1,049,412.64 100.00%
04.03.00 CONCRETO F'C= 175 Kg/cm2 EN OBRAS DE ARTE M3 234.95 254.07 59,693.75 0.00% 0.00% 0.00 0.00% 234.95 59,693.75 100.00%
04.05.00 CONCRETO F'C= 140 KG/CM2 + 30% PM M3 226.15 176.51 39,917.74 0.00% 0.00% 0.00 0.00% 226.15 39,917.74 100.00%
05.00.00 ENCOFRADO Y DESENCOFRADO 99,818.73 - 0.00% 0.00 0.00% 0.00 0.00% 99,818.73 100.00%
05.01.00 ENCOFRADO Y DESENCOFRADO DE OBRAS DE ARTE M2 3,920.61 25.46 99,818.73 0.00% 0.00% 0.00 0.00% 3,920.61 99,818.73 100.00%
06.00.00 ACERO DE REFUERZO 68,359.33 - 0.00% 0.00 0.00% 0.00 0.00% 68,359.33 100.00%
06.01.00 ACERO DE REFUERZO KG 19,365.25 3.53 68,359.33 0.00% 0.00% 0.00 0.00% 19,365.25 68,359.33 100.00%
07.00.00 JUNTAS Y SELLOS 98,350.94 - 0.00% 0.00 0.00% 0.00 0.00% 98,350.94 100.00%
07.01.00 JUNTA WATER STOP 6" M 288.77 26.54 7,663.96 0.00% 0.00% 0.00 0.00% 288.77 7,663.96 100.00%
07.02.00 JUNTAS ASFALTICAS e=1" M 20,704.79 4.38 90,686.98 0.00% 0.00% 0.00 0.00% 20,704.79 90,686.98 100.00%
08.00.00 VARIOS 29,903.62 0.00 0.00% 0.00 0.00% 0.00 0.00% 29,903.62 100.00%
08.01.00 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) UND 156.00 21.20 3,307.20 0.00% 0.00% 0.00 0.00% 156.00 3,307.20 100.00%
08.02.00 PRUEBAS DE CONTROL DE COMPACTACION DE TERRAPLEN UND 1,673.00 15.60 26,098.80 0.00% 0.00% 0.00 0.00% 1,673.00 26,098.80 100.00%
08.03.00 COMPUERTA LATER. TIPO IZAJE 0.40 X 0.40 M UND 1.00 497.62 497.62 - - - - 1.00 497.62 100.00%
09.00.00 MEDIDAS DE MITIGACION AMBIENTAL 9,524.02 0.00 0.00% - - 0.00 0.00% 9,524.02 100.00%
09.01.00 REMEDIACION AMBIENTAL 2,444.02
09.01.01 RIEGO PARA CAMINOS DE ACCESO HM 20.00 97.03 1,940.60 0.00% - - - 0.00 0.00 0.00% 20.00 1,940.60 100.00%
09.01.02 ESPARCIIMIENTO DE TERRENO CON MAQ. Y CUBRIR CON SUELO ORGANICO HA 2.00 251.71 503.42 - - - - - - - 2.00 503.42 100.00%
09.02.00 MANEJO AMBIENTAl 3,090.00
09.02.01 CAPACITACION EN CONSERV. DE RR. NN. Y MEDIO AMBIENTE EVT 1.00 2,090.00 2,090.00 - - - - - - - - - 1.00 2,090.00 100.00%
09.02.02 CONSTRUCCION DE LETRINAS EN CAMPAMENTO UND 2.00 500.00 1,000.00 0.00% - - - 0.00 0.00 0.00% 2.00 1,000.00 1.00
09.03.00 PLAN DE CONTINGENCIA 3,990.00
09.03.01 CAPACITACION EN MEDIDAS DE CONTINGENCIA EVT 1.00 2,090.00 2,090.00 - - - - - - - 1.00 2,090.00 100.00%
09.03.02 EQUIPOS DE EMERGENCIA GLB 1.00 1,900.00 1,900.00 - - - - - - - 1.00 1,900.00 100.00%

COSTO DIRECTO 2,308,688.76 - 0.00 0.00 2,299,164.74


GASTOS GENERALES 6.70% 0.00 - 0.00 0.00 0.00
SUPERVISION 1.46 % 2,308,688.76 - - - 2,299,164.74
VALORIZACION TOTAL S/. 4,617,377.51 - - - 4,598,329.47
% DE AVANCE FISICO DE OBRA % 0.00% 0.00% 0.00% 99.59%

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


GOBIERNO REGIONAL PUNO
PRORRIDRE

RESUMEN DE VALORIZACIONES DE AVANCE DE OBRA N 05


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
EJECUTA FECHA DE INICIO DE OBRA PROVINCIA
ENTIDAD FINANCIERA PLAZO DE EJECUCION DISTRITOS
FECHA FECHA DE TERMINO DE LA OBRA LOCALIDAD

GASTOS
VALORIZACIONES FECHA DE COSTO GASTOS DE VALORIZACION VALORIZACION % DE AVANCE
GENERALES SALDO DE % DE AVANCE
MENSUALES VALORIZACION DIRECTO PROGRAMADO SUPERVISION TOTAL ACUMULADA MENSUAL
PROGRAAMADO

PPTO. DE OBRA 3,052,785.50 204,437.22 44,509.14 3,301,731.86 100.00%


VALORIZACION N 01 SEPTIEMBRE 0.00% 100.00%

VALORIZACION N 02 OCTUBRE 0.00% 100.00%

VALORIZACION N 03 NOVIEMBRE 0.00% 100.00%

VALORIZACION N 04 DICIEMBRE 0.00% 100.00%

VALORIZACION N 05 ENERO 0.00% 100.00%

VALORIZACION N 06 FEBRERO

VALORIZACION N 07 MARZO

VALORIZACION N 08 ABRIL

VALORIZACION N 09 MAYO

VALORIZACION ACUMULADA 0.00 0.00 0.00 0.00


VALORIZACION SALDO 3,052,785.50 204,437.22 44,509.14 3,301,731.86
% DE AVANCE ACUMULADA 0.00% 0.00% 0.00% 0.00% 0.00% 100.00%

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS

PRORRIDRE PRASTER
Informe Mensual Construccin Canal Principal Irrigacin Yanarico Prog. 3+156.55 al 14+511.68 Correspondiente al Mes de Enero del 2,008
GOBIERNO REGIONAL PUNO
PRORRIDRE - PRASTER

CUADRO DE CONTROL DE VALORIZACIONES ACUMULADAS


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITOS
FECHA FECHA DE TERMINO DE LA OBRA LOCALIDAD

3,500,000.00
1,800,000.00
MONTOS (N/S.)

3,000,000.00
1,600,000.00

1,400,000.00
2,500,000.00

1,200,000.00
2,000,000.00 PROGRAMADO
EN NUEVOS SOLES

EJECUTADO
1,000,000.00 DESEMBOLSO
1,500,000.00

800,000.00
1,000,000.00

600,000.00
500,000.00

400,000.00

0.00
SEPTIEMBRE
200,000.00 OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO

MESES

VALORIZAC. ACUMUL. PROGAMADA 18,923.09 166,399.33 1,161,152.75 1,360,209.18 532,606.90 62,440.61


VALORIZAC. ACUMUL. EJECUTADA 18,923.09 166,453.41 572,188.62 688,842.77 717,762.05 -
DESEMBOLSO 565,870.95 1,020,458.64 295,214.10 585,427.38 - -
MES SEPTIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO
AO 2,007 2,008
LEYENDA PROGRAMADO: EJECUTADO: DESEMBOLSO:

ING. RESIDENTE DE OBRA VALORIZACION


ING. SUPERVISOR DE OBRA N VAL. ACTUAL VAL. ACUMUL. VAL. SALDO
01 18,923.09 18,923.09 3,282,808.77
02 166,453.41 185,376.50 3,116,355.36
03 572,188.62 757,565.11 2,544,166.75
04 688,842.77 1,446,407.89 -1,446,407.89

% AVANCE 20.86% 43.81% 77.06%

PRORRIDRE - PRASTER 2,008


Informe Mensual Construccin Canal Principal Irrigacin Yanarico Prog. 3+156.55 al 14+511.68 Correspondiente al Mes de Enero del 2,008

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS

PRORRIDRE - PRASTER 2,008


Informe Mensual Construccin Canal Principal Irrigacin Yanarico Prog. 3+156.55 al 14+511.68 Correspondiente al Mes de Enero del 2,008
GOBIERNO REGIONAL PUNO
PRORRIDRE

CUADRO DE CONTROL DE METAS FISICAS

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

CANT. AVANCE AVANCE AVANCE SALDO DESCRIPCION DEL AVANCE DE


N META FISICA UND ANTERIOR ACTUAL ACUMUL. ACTUAL
PROG. LA META FISICA
CANT. % CANT. % CANT. % CANT. %
1 Construccin Canal Principal IRRIGACION YANARICO Ml. 11355.13 4,550.00 40.07% 2500.00 22.02% 7050 62.09% 4305.13 37.91%
Revestido de Canal Principal KM 3+156.55 al 14+511.68
Ml. 11,355.13 4,550.00 40.07% 2500.00 22.02% 7,050.00 62.09% 4,305.13 37.91% Revestido del canal principal
seccion Trapezoidal

2 Obras de Arte Und 130 1.70 0.01 52.00 0.40 113.70 0.87 16.3 12.54%
Acueducto Und 1 - - - - - - 1 100.00%
Alcantarilla Und 11 1.70 0.15 3.00 0.27 4.70 0.43 6.3 57.27%
Cada Und 4 - - 1.00 0.25 1.00 0.25 3 75.00%
Canoa A = 1.5 m. Und 2 - - - - - - 2 100.00%
Canoa Tipo Vehicular Und 3 - - - - - - 3 100.00%
Cruce Puente Vehicular CABANA Und 1 1.00 1.00 - - 1.00 1.00 0 0.00%
Entrega Pluvial Und 13 - - 13.00 1.00 13.00 1.00 0 0.00%
Entrega Pluvial + Salvavidas Und 6 2.00 0.33 - - 2.00 0.33 4 66.67%
Pase Peatonal Und 47 42.00 0.89 23.00 0.49 65.00 1.38 -18 -38.30%
Puente Vehicular Und 4 1.00 0.25 - - 1.00 0.25 3 75.00%
Salvavidas Und 16 14.00 0.88 12.00 0.75 26.00 1.63 -10 -62.50%
Toma Lateral Und 11 - - - - - - 11 100.00%
Toma Simple Und 11 - - - - - - 11 100.00%

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS

PRORRIDRE - PRASTER 2,008


CONSOLIDADO DE VALORIZACIN FISICA - MARZO 2010
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
UBICACIN FECHA DE INICIO DE OBRA PROVINCIA
EJECUTA PLAZO DE EJECUCION DISTRITO
RESIDENTE FECHA DE TERMINO DE LA OBRA SECTOR
SUPERVISOR

PRESUPUESTO DEL AVANCE


ACUMULADO ANTERIOR ACUMULADO ACTUAL SALDO
EXPEDIENTE TECNICO DEL MES
ITEM DESCRIPCION DE PARTIDAS
Parcial Parcial % Parcial % Monto % Monto %

PARTIDAS EJECUTADAS DEL EXPEDIENTE APROBADO


FORMULA 01 3,477,814.22 0.00 0.00% 0.00 0.00 2,463,584.00 70.84%
COSTO DIRECTO (S/.) 3,477,814.22 250,000.00 7.19% 128,500.00 3.69% 378,500.00 10.88% 3,099,314.22 89.12%
GASTOS GENERALES (xxx %) 206,205.73 14,822.94 7,618.99 22,441.93 183,763.80
GASTOS DE SUPERVISIN DE OBRA (xxx %) 66,078.47 4,750.00 2,441.50 7,191.50 58,886.97
COSTO TOTAL (A) 3,750,098.42 269,573.01 138,560.53 408,133.54 3,341,965.88
PORCENTAJE DE AVANCE 100.00% 7.19% 3.69% 10.88% 89.12%

PARTIDAS EJECUTADAS POR SER OBRAS NECESARIAS


FORMULA 02 OBRAS NECESARIAS POR MAYORES METRADOS (*) 350,000.00
COSTO DIRECTO (S/.) 350,000.00 150,000.00 42.86% 10,000.00 2.86% 160,000.00 45.71% 190,000.00 54.29%
GASTOS GENERALES (xxx %) 20,752.12 8,893.76 592.92 9,486.68 11,265.43
GASTOS DE SUPERVISIN DE OBRA (xxx %) 6,650.00 2,850.00 190.00 3,040.00 3,610.00
COSTO TOTAL (B) 377,402.12 161,743.76 10,782.92 172,526.68 204,875.98
FORMULA 03 OBRAS NECESARIAS POR PARTIDAS NUEVAS (*) 0.00
COSTO DIRECTO (S/.) 25,000.00 10,000.00 40.00% 3,500.00 14.00% 13,500.00 54.00% 11,500.00 46.00%
GASTOS GENERALES (xxx %) 1,482.29 592.92 207.52 800.44 681.86
GASTOS DE SUPERVISIN DE OBRA (xxx %) 475.00 190.00 66.50 256.50 218.50
COSTO TOTAL (C) 26,957.29 10,782.92 3,774.02 14,556.94 12,400.36
FORMULA 04 DEDUCTIVOS DE OBRAS POR PARTIDAS NO EJECUTADAS (*) 0.00
COSTO DIRECTO (S/.) 78,000.00 45,000.00 57.69% 7,000.00 8.97% 52,000.00 66.67% 26,000.00 33.33%
GASTOS GENERALES (xxx %) 4,624.76 2,668.13 415.04 3,083.17 1,541.59
GASTOS DE SUPERVISIN DE OBRA (xxx %) 1,482.00 855.00 133.00 988.00 494.00
COSTO TOTAL (D) 84,106.76 48,523.13 7,548.04 56,071.17 28,035.59
COSTO TOTAL DEDUCIDO ( E ) = (B+C-D) 320,252.65 131,012.45

COSTO TOTAL ACUMULADO (A) + (E) 4,070,351.07 539,145.99


PORCENTAJE ACUMULADO 108.54% 0.00% 0.00% 14.38% 0.00%

CUADRO DE RESUMEN
COSTO REFERENCIAL DEL EXPEDIENTE (A) 3,750,098.42
COSTO ADICIONAL EJECUTADO POR OBRAS NECESARIAS (E) 320,252.65
COSTO TOTAL DE OBRA ACUMULADO (A)+(E) 4,070,351.07
PORCENTAJE DE ADICIONAL EJECUTADO (E)/(A) 8.54%
VALORIZACIN ACUMULADA AL MES (E) 539,145.99
% AVANCE FISICO ACTUAL ACUMULADO (C)/(A)*100 14.38%

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS

....................................... ............................................. ..............................................


GOBIERNO REGIONAL PUNO
PRORRIDRE

HOJA RESUMEN DE METRADOS DE OBRAS DE ARTE


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

Excavacin Manual

Comp.P/Estructura

Acero de Refuerzo
Trazos y replanteo

Cf'c=210 kg/cm2

Piedra asentada y

Baranda Metlica
Cf'c=175 kg/cm2

Plancha Metalica

Plancha Metalica
de obras de arte

Compuerta Tipo

Compuerta Tipo

Compuerta Tipo
Compuerta Tipo

Compuerta Tipo
proteccion (m3)

f'c=140+30%PM

f'c=175+30%PM
Mat.Excedente

Izaje 0.50x0.50

Izaje 0.40x0.30
Izaje 0.50x0.40

Izaje 0.40x0.35

Izaje 0.20x0.20
Enrrocado de

emboquillada

6.10x1.25m

3.80x1.20m
Ydesencof.
N Progrevisva Obra de Arte

Limpieza y

J.Asfaltica
Encofrado
desbroce

J.W.stop
P/Estruc.

Relleno

kg/cm2
kg/cm2

CC
Elim.

CC
s
1 6+275.80 Toma lateral 14 MD
2 6+536.05 Salvavidas
3 6+677.55 Alcantarilla (cruce ro porotoyo)
4 6+823.50 Toma lateral 15 MD
5 6+885.55 Pase peatonal 21.30 21.30 6.29 3.12 3.50 6.29 1.93 38.91 122.62 11.10
6 6+905.65 Salvavidas
7 7+066.75 Toma simple MD
8 7+153.00 Alcantarilla cruce dren
9 7+158.28 Partidor ( canal A Canal -B )
10 7+196.27 Puente vehicular
11 7+525.00 Toma lateral 16 MD
12 7+570.65 Pase peatonal 11.10
13 7+664.25 Toma simple - MI
14 7+674.45 Pase peatonal 11.10
15 7+750.00 Rpida
16 7+840.00 Puente vehicular
47 9+871.20 Toma simple MD
48 9+898.50 Rpida
49 9+997.50 Puente vehicular
51 0+235.40 Pase peatonal
52 0+239.15 Entrega superficial
53 0+477.50 Pase peatonal
54 0+557.75 Toma simple MD
55 0+691.55 Pase peatonal
56 0+704.25 Entrega superficial
57 0+793.55 Pase peatonal
58 0+933.50 Puente vehicular
59 0+983.00 Toma simple - MI
60 1+007.40 Pase peatonal
61 1+023.00 Partidor
TOTAL 21.30 21.30 0.00 6.29 3.12 3.50 0.00 6.29 1.93 0.00 0.00 38.91 122.62 0.00 0.00 33.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00

ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


HOJA RESUMEN DE METRADOS

Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA

Item Descripcin Nro. Ve Largo Ancho Alto Parcial Total Unidad

01.00.00 TRABAJOS PRELIMINARES


01.01.00 CAMPAMENTO 1.00 GLB
ubicado en la zona (alquilado) 1 1

01.02.00 CARTEL DE OBRA 1.00 UND


cartel de obra de 5x3 M 1 1.00 1

01.03.00 TRANSPORTE DE MAQUINARIA Y EQUIPO 2.00 GLB


2 2
01.04.00 TRAZO Y REPLANTEO 1.00 M
1 1
01.05.00 TRAZO Y REPLANTEO OBRAS DE ARTE 1,620.30 M2
de la hoja resumen de obras de arte 1 1,200.30 1200.3
de la alcantarilla de Collana 1 420.00 420

01.06.00 LIMPIEZA Y DESBROCE 620.45 M2


limpieza y desbroce de canal 2 0.75 1.50
limpieza y desbroce de obras de arte 1 618.95 618.95

01.07.00 APERTURA DE CAMINOS DE ACCESO 3,000.00 M


caminos de acceso hacia las canteras 1 3,000.00 3000

01.08.00 MANTENIMIENTO DE CAMINOS DE ACCESO 4,500.00 M


de todos los caminos dentro del proyecto 1 4,500.00 4500

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 EXCAVACION EN MATERIAL SUELTO PARA AMPLIACION DE PLATAFORMA - M3
del movimiento de tierras 1 - 0.00

02.02.00 EXCAVACION EN MATERIAL SUELTO 2,511.84 M3


de la alcantarilla de Collana 2,511.84 2511.84
1
02.03.00 RELLENO COMPACTADO PARA ESTRUCTURAS CON MATERIAL PROPIO 931.00 M3
de la hoja de metrados de la alcantarilla 1 931.00 931.00

02.04.00 TRANSPORTE DE MATERIAL DE PRESTAMO (1) 0.60 M3


de las canteras de material impermeable 0.5 1.00 1.20 0.60

02.05.00 TRANSPORTE DE MATERIAL DE PRESTAMO (2) 0.60 M3


de las canteras de material granular 0.5 1.20 0.60

02.06.00 TERRAPLEN COMPACTADO 1.00 M3


del movimiento de tierras 1 1.00

02.07.00 EXCAVACION DE CAJA DE CANAL A MAQUINA 1,732.19 M3


De excavacin de caja 1 1,732.19 1732.19

02.08.00 EXCAVACION DE CAJA DE CANAL A MANO 7,690.76 M3


De excavacin de caja 1 7,690.76 7690.76

02.09.00 EXCAVACION DE ZANJAS DE CORONACION 500.00 ML


metrado general 1 500.00 500

02.10.00 PICADO DE FISURAS DE CANAL 64.00 ML


de la hoja de metrado correspondiente 1 64.00 64

02.11.00 PICADO PARA ADHERENCIA DE ESTRUCTURAS 214.80 M2


tramo de canal en concreto a ser encimado 1 214.80 214.80

02.12.00 ACOMODO DE ENROCADO DE PROTECCION 54.00 M3


de la hoja resumen de metrado de obras de arte 1 54.00 54

02.13.00 EXCAVACION PARA CIMENTACION DE OBRAS DE ARTE 869.59 M3


de la hoja resumen de metrado de obras de arte 1 869.59 869.5941

02.14.00 RELLENO COMPACTADO DE OBRAS DE ARTE 140.64 M3


de la hoja resumen de metrado de obras de arte 1 140.64 140.6406

02.15.00 ELIMINACION DE MATERIAL EXCEDENTE DE CORTE (a carretilla) 499.42 M3


eliminaxion de material de corte para ampliar la plataforma 1 - 1.20 0.00
eliminacion de mat. excedente de obras de arte 1 416.18 1.20 499.42

02.16.00 ELIMINACION DE MAERIAL EXCEDENTE DE CORTE A MAQUINA 3,652.78 M3


de la eliminacion de material de la alcantarilla 1 3,652.78 3652.78

02.17.00 ELIMINACION Y REPOSICION DE MATERIAL SATURADO 843.70 M3


de la hoja de metrados respectiva 1 843.70 843.70

03.00.00 DEMOLICION DE ESTRUCTURAS


03.01.00 DEMOLICION DE ALBAILERIA 501.03 M3
demolicion de las obras de arte 1 308.34 308.34
del metrado de alcantarilla Illpa(Porotoyo) 192.69 192.69
HOJA RESUMEN DE METRADOS

Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA

Item Descripcin Nro. Ve Largo Ancho Alto Parcial Total Unidad

03.02.00 DEMOLICION DE ESTRUCTURAS 190.25 M3


demolicin de obras de arte de concreto armado 1 167.36 167.36
del metrado de alcantarilla Illpa(Porotoyo) 22.89 22.89

03.03.00 DEMOLICION DE CANAL EN CONCRETO A MAQUINA 240.44 M3


de la hoja de metrados respectiva 1 240.44 240.44

03.04.00 DEMOLICION DE CANAL EN CONCRETO A MANO 193.16 M3


de la hoja de metrados respectiva 1 193.16 193.16

03.05.00 DEMOLICION DE CANAL EN MAMPOSTERIA A MAQUINA 1,945.39 M3


de la hoja de metrados respectiva 1 1,945.39 1945.39

03.06.00 DEMOLICION DE CANAL EN MAMPOSTERIA A MANO 1,047.52 M3


de la hoja de metrados respectiva 1 1,047.52 1047.52

03.07.00 ELIMINACION DE DEMOLICIONES DE ESTRUCTURAS 982.74 M3


eliminacion de escombros
de albaileria 1.3 308.34 400.84
de estructuras 1.3 167.36 217.57
del metrado de alcantarilla Illpa(Porotoyo) 1.3 280.26 364.34

03.08.00 ELIMINACION DE DEMOL. DE CANAL EN CONCRETO 563.69 M3


de la hoja de metrados respectiva 1 563.69 563.69

03.09.00 ELIMINACION DE DEMOL. DE CANAL EN MAMPOSTERIA 3,890.79 M3


de la hoja de metrados respectiva 1 3,890.79 3890.79

04.00.00 CONCRETOS
04.01.00 CONCRETO F'C= 140 KG/CM2 + 30% PM - M3
de la hoja de metrados resumen de obras de arte 1 - 0.00

04.02.00 CONCRETO FC=175 KG/CM2 PARA REVESTIMIENTO DE CANALES 1,331.92 M3


de la hoja de metrados correspondiente 1 1,331.92 1331.92

04.03.00 CONCRETO F'C= 175 Kg/cm2 P/OBRAS DE ARTE 316.36 M3


de la hoja de metrados de obras de arte 1 104.87 104.8701
del metrado de la alcantarilla 1 211.49 211.49

04.04.00 CONCRETO F'C= 175 Kg/cm2 + 30% PM 426.55 M3


de la hoja de metrado de obras de arte 1 426.55 426.5506

04.05.00 CONCRETO F'C= 210 Kg/cm2 P/OBRAS DE ARTE 65.76 M3


de la hoja de metrado de obras de arte 1 65.76 65.75625

04.06.00 PIEDRA ASENTADA Y EMBOQUILLADA 20.90 M3


de la relacion de obras de arte 1 20.90 20.9025
del metrado de movimiento de tierras 1 - 0.00

04.07.00 RELLENO DE FISURAS 0.24 M3


en el canal lateral A en los tramos indicados en su resp. Me 1 64.00 0.05 0.08 0.24

05.00.00 ENCOFRADO Y DESENCOFRADO


05.01.00 ENCOFRADO Y DESENCOFRADO NORMAL 2,565.62 M2
de la hoja de metrados de obras de arte 1 1,801.34 1801.3405
del metrado de alcantarilla Illpa(Porotoyo) 1 764.28 764.278

06.00.00 ACERO DE REFUERZO


06.01.00 ACERO DE REFUERZO 23,406.02 KG
de la hoja de metrados de obras de arte 1 10,774.23 10,774.23
del metrado de alcantarilla Illpa(Porotoyo) 1 12,631.79 12,631.79

07.00.00 JUNTAS Y SELLOS


07.01.00 JUNTA WATER STOP 274.50 ML
de la hoja de metrados de obras de arte 1 147.10 147.1
del metrado de alcantarilla Illpa(Porotoyo) 1 127.40 127.4

07.02.00 JUNTAS ASFALTICAS 7,895.99 ML


Total juntas asfalticas del canal 1 7,895.99 7895.99
de las obras de arte 1 - 0.00

08.00.00 VARIOS

08.01.00 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) 214.00 UND


de los volumenes de concreto 1 2,140.59 10.00 214.00

08.02.00 PRUEBAS DE CONTROL DE COMPACTACION - UND


en el canal principal y tramos a ser reemplazados 1 - 25.00 -

08.03.00 COMPUERTA LATERAL TIPO IZAJE0.50X0.50 M - UND


de la hoja resumen de metrados 0.00 0

08.04.00 COMPUERTA LATERAL TIPO IZAJE0.50X0.40 M - UND


de la hoja resumen de metrados 0.00 0
HOJA RESUMEN DE METRADOS

Obra :
META
Departament Puno Provincia LAMPA Distrito CABANILLA

Item Descripcin Nro. Ve Largo Ancho Alto Parcial Total Unidad

ING. RESIDENTE DE OBRA V B SUPERVISOR VB DIRECTOR DE OBRAS


CUADRO DE METRADOS PASE PEATONAL
OBRA :
META : 6+170 al 10+000 , 0+000 al 1+023 C.P. - A
PROGRESIVA : 6+885.55 , 7+570065, 7+674.45, y C.P. - A 0+235.40, 0+447.50, 0+691.55, 0+793.55, 1+007.40
N COQUIS OBRA ARTE PARTIDA UNIDAD CANTIDAD LARGO ANCHO ALTO PARCIAL TOTAL
1.00 MOVIMIENTO DE TIERRAS 0.00
1.01 Estribos m3 0.00
1.02 Zapata m3 0.00

2.00 C Fc`=175 kg/cm2 +30% PM 0.00


2.01 Estribos m3 0.00
2.02 Zapata m3 0.00

3.00 C Fc`=175 kg/cm2 0.00


3.01 losa m3 0.00
3.02 sardinel m3 0.00

4.00 ENCOFRADOS 0.00


4.01 losa m2 0
4.02 tapas costado m2 0
4.03 tapas interior m2 0
4.04 estribos m2 0
4.05 costados m2 0
4.06 tapas costado zapata m2 0
4.07 tapas laterales zapata m2 0

5.00 eliminacin mat. Excedente 0.00


5.01 estribos y zapata m3 0.00

6.00 relleno compactado 0.00


6.01 losa costados m3 0.00

7.00 barabndas 11.10


7.01 baranda F 1 1/2^ ML 2.00 5.55 11.10

ACEROS DE REFUERZO
N PARTIDA UNIDAD N VECES CANTIDAD LONGITUD PESO F` PARCIAL TOTAL
1.00 ACEROS 0.00
1.01 f long. inferior losa kg 0.56 0.00
1.02 f trans. inferior losa kg 1.02 0.00
1.03 f long.superior losa kg 0.56 0.00
1.04 f trans.superior losa kg 0.56 0.00
1.05 As sardinel kg 1.02 0.00
1.06 As sardinel estribos kg 0.56 0.00

ING. RESIDENTE DE OBRA VB SUPERVISOR VB DIRECTOR DE OBRAS


GOBIERNO REGIONAL PUNO
PRORRIDRE

TAREO PERSONAL DEL MES DE NOVIEMBRE - 2009


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

AFEC. PPTAL :

MES - NOVIEMBRE
FECHA DE FECHA D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
No APELLIDOS Y NOMBRES CARGO D.N.I. AFP COD.AFILIADO TOTAL
INGRESO NACIMIENTO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

1 XXXXXXXX TOPOGRAFO 01231736 01/11/09 5/20/1963 HORIZONTE 231491CSYMR0 X X X X X X D X X X X X X D X X X X X X D X X X X X X X 25

LEYENDA.
DIAS LABORADOS : (X), FERIADOS : (FE), DIAS NO LABORADOS : ( ) DOMINICALES (D)

ING. RESIDENTE ASISTENTE ADMINISTRATIVO V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


GOBIERNO REGIONAL PUNO
PRORRIDRE

CUADRO CONTROL DE PERSONAL DE OBRA


OBRA : CONSTRUCCION DE CANAL PRINCIPAL PROG. 10+820 AL 15+820 MODALIDAD DE EJECUCION : ADMINISTRACION DIRECTA DEPARTAMENTO : PUNO
ENT. EJEC. : PRORRIDRE - PRASTER FECHA DE INICIO DE OBRA : 17 DE ABRIL DEL 2010 PROVINCIA : AYAVIRI - AZANGARO
ENT. FIN. : GOBIERNO REGIONAL PLAZO DE EJECUCION : 165 DIAS CALENDARIOS DISTRITO : ORURILLO - ASILLO
FECHA : SETIEMBRE DEL 2010 FECHA DE TERMINO DE LA OBRA : 28 DE OCTUBRE DEL 2010 SECTOR : POSOCONI

JORNAL JORNAL
M E S E S ACUMULADO SALDO
N
N JORNAL
N DESCRIPCION DEL PERSONAL PERSONAL
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE
PROG. PROG.
NJ % N J %
N P N J N P N J N P N J N P N J N P N J N P N J N P N J N P N J N P N J

A) PERSONAL PROFESIONAL 3 495.00 3 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 495 100.00%


1 Ing. Supervisor 1 165 1 0 0.00% 165 100.00%
2 Ing Residente de Obra 1 165 1 0 0.00% 165 100.00%
3 Ing. Asistente de Obra 1 165 1 0 0.00% 165 100.00%
B) PERSONAL ADMINISTRATIVO 2 330.00 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 330 100.00%
1 Asistente Administrativo 1 165 0 0.00% 165 100.00%
2 Almacenero 1 165 0 0.00% 165 100.00%
3 Chofer Camioneta 1 165 0 0.00% 165 100.00%
C) PERSONAL TECNICO 6 825.00 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 660 80.00%
1 Topografo 1 165 0 0.00% 165 100.00%
2 Nivelador 1 165 0 0.00% 165 100.00%
3 Maestro de Obra/ Capataz 1 165 0 0.00% 165 100.00%
4 Tecnico Laboratorista 1 165 0 0.00% 165 100.00%
5 Tecnico en Ingenieria 1 165 0 0.00% 165 100.00%
6 Controlador Oficial 1 165 0 0.00% 165 100.00%
D) PERSONAL OBRERO 78 148,003.52 0 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 137,678 93.02%
1 Operario 10 19,641.60 0 0.00% 19,642 100.00%
2 Oficial 10 18,402.71 0 0.00% 18,403 100.00%
3 Peon 52 99,633.36 0 0.00% 99,633 100.00%
4 Peon (para curado y proteccion) 4 8,100.69 0 0.00% 8,101 100.00%
5 Auxiliar Perforista 1 24.94 - - 25 100.00%
6 Oficial Cerchero 1 2,200.23 - - 2,200 100.00%

TOTAL 89 149,654 3 0 0 0 0 0 0 0 0 0 - - - - - - - - 0 0.00% 139,163 92.99%


AVANCE (%) 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% - - - - 0.00% 100.00%

N P: N DE PERSONAL
N J: N DE JORNAL

ING. RESIDENTE ASISTENTE ADMINISTRATIVO V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


GOBIERNO REGIONAL PUNO
PRORRIDRE

CUADRO DE RESUMEN DE PLANILLA DE PAGOS


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA DE TERMINO DE LA OBRA SECTOR

A.- PERSONAL TEC. ADMINIS. SEGN EXP. TECNICO TIEMPO DE EJECUCION DE OBRA PROGRAMADO RESUMEN
SUB TOTAL
SUB TOTAL
ITEM CARGO CANT. MES COSTO CONTRATO DETALLE JUN JUL AGO SET OCT NOV DIC ACUMULADO OBS.
1 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%
SUPERVISOR DE OBRA
MONTO - - - - 0.00 -
2 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 8.75% 5.25% 0.00% 14.00% 14.00%
RESIDENTE DE OBRA
MONTO - - 3,499.90 2,100.00 - 5,599.90 5,599.90
3 S/. 40,000.00 PORCENTAJE 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% -
ASISTENTE TECNICO DE OBRA 01
MONTO - - - - - - 0.00 -
4 S/. 20,000.00 PORCENTAJE
ADMINISTRADOR DE OBRA
MONTO
5 S/. 20,000.00 PORCENTAJE
ASISTENTE ADMINISTRATIVO
MONTO
6 S/. 20,000.00 PORCENTAJE
MAESTRO DE OBRA B
MONTO
7 S/. 22,000.00 PORCENTAJE
TECNICO LABORATORISTA
MONTO - - - - - 0.00 -

TOTAL S/. S/. 0.00 - - - - 3,499.90 2,100.00 - 5,599.90 5,599.90

C.- PERSONAL OBRERO EXPEDIENTE TIEMPO DE EJECUCION DE OBRA PROGRAMADO RESUMEN


DETALLE
ITEM CARGO HH COSTO JUN JUL AGO SET OCT NOV DIC CANT-HH SUB TOTAL EJECUTADO
1 TOPOGRAFO 4,004.70 CANTIDAD (HH) 0.00 313.04 313.04 313.04 939.13 23.45%
S/. 23,027.00 MONTO 1,800.00 1,800.00 1,800.00 5,400.00
2 NIVELADOR CANTIDAD (HH) 438.07 1,420.65 611.21 2,469.93 18.48%
MONTO 2,475.10 8,026.67 3,453.33 13,955.10
3 OPERARIO S/. 75,534.60 CANTIDAD (HH) 1,720.35 1,332.74 1,136.28 4,189.38 31.34%
13,368.96
MONTO 9,720.00 7,530.00 6,420.00 23,670.00
5 OFICIAL 13,172.40 CANTIDAD (HH) 1,438.89 1,188.89 1,194.44 3,822.22 29.02%
S/. 59,275.81 MONTO 6,475.00 5,350.00 5,375.00 17,200.00
6 PEON 47,257.91 CANTIDAD (HH) 3,631.75 2,838.10 3,873.02 10,342.86 21.89%
S/. 148,862.43 MONTO 11,440.00 8,940.00 12,200.00 32,580.00
7 TAREADOR PORCENTAJE 0.00
MONTO 0.00

TOTAL S/. 77,803.97 S/. 306,699.84 0.00 0.00 0.00 0.00 31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%

TOTAL PAGADO PLANILLAS S/. 0.00 0.00 31,910.10 31,646.67 29,248.33 21,763.52 92,805.10 30.26%

RESUMEN DE REPORTE DE PERSONAL TECNICO ADMINISTRATIVO RESUMEN DE REPORTE DE PERSONAL OBRERO


GASTO DE PERSONAL T. A. MENSUAL S/. 0.00 USO DE HORAS HOMBRE DE PERSONAL OBRERO 21,763.52
GASTO DE PERSONAL T.A. ACUMULADO S/. 5,599.90 GASTO DE MANO DE OBRA MENSUAL 29,248.33
PORCENTAJE DE GASTO DE PERSONAL T.A. ACUMULADO 559990.00% GASTO DE MANO DE OBRA ACUMULADO 92,805.10
PORCENTAJE DE USO DE MANO DE OBRA ACUMULADO 30.26%

ING. RESIDENTE ASISTENTE ADMINISTRATIVO V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


RESUMEN DE HORAS MAQUINA

OBRA :
EJECUTA : PRORRIDRE
EQUIPO : VOLQUETE DOBLE EJE MARCA : VOLVO MODELO :
PROPIETARIO PLACA :
OPERADOR MODELO :
FECHA PERIODO Desde: 01/09/09 Hasta: 30/09/09

FECHA HORAS DESCRIPCION CANT VIAJES TOTAL M3


9/1/2009 4:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 10 150
9/2/2009 5:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 9 135
9/3/2009 5:00:00 TRASLADO DE MATERIAL AGREGADO (HORMIGN) DESDE CANTERA - OBRA 6 90
9/4/2009
9/5/2009
9/7/2009
9/8/2009
9/9/2009
9/10/2009
9/11/2009
9/12/2009
9/14/2009
9/15/2009
9/16/2009
9/17/2009
9/18/2009
9/19/2009

TOTAL 14:00:00 25.00 375.00

VALORIZACION DE HORAS MAQUINA

MAQUINA TOTAL HORAS P.U. MONTO TOTAL OBSERVACION


VOLQUETE CAP. 15 M3 14.00 120.00 1,680.00 SIN OBSERVACION

CONTROLADOR MAQUINARIA ING. RESIDENTE ING. SUPERVISOR DIRECTOR DE OBRAS


RESUMEN DE HORAS MAQUINA
(EQUIPO LIVIANO)
OBRA
EJECUTA : PRORRIDRE
EQUIPO : MEZCLADORA DE 9 P3 MARCA : MODELO :
PROPIET : PRORRIDRE CODIGO
OPERADOR MODELO :
FECHA PERIODO Desde: 01/09/09 Hasta: 30/09/09

FECHA HORAS COMBUSTIBLE DESCRIPCION


9/1/2009 8:00:00 2 Preparado de concreto para obras de arte Pase Peatonal Prog. 0+500 Ds- 01
9/2/2009 5:00:00 2 Preparado de concreto para obras de arte Pase Peatonal Prog. 0+750 Ds- 03
9/3/2009 5:00:00 1
9/4/2009 4:30:00 3
9/5/2009 4:00:00 2

TOTAL 26:30:00 10.00

VALORIZACION DE HORAS MAQUINA

MAQUINA TOTAL HORAS P.U. MONTO TOTAL OBSERVACION


MEZCLADORA DE CONCRETO 0.00 SIN OBSERVACION

CONTROLADOR MAQUINARIA ING. RESIDENTE ING. SUPERVISOR DIRECTOR DE OBRAS


CUADRO DEL CONTROL DEL EQUIPO MECANICO
(HORAS - COMBUSTIBLE - KILOMETRAJE)

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

N MARCA PROPIETARIO UND. REND. D I A S TOTAL REND.


EQUIPO Y/O MAQUINARIA
PLACA H-M/COMBUST. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 COMBUST.
PRORIDRE COMBUSTIBLE 2.00 2.00 2.00 2.00 2.00 2.00 2.00 14.000 0.24
1 MEZC. 01 DE CONCRETO DE 9 - 11 P3 HORAS 8:10:00 8:10:00 8:10:00 8:10:00 8:10:00 8:10:00 8:00:00 57:00:00 Gal./Hora
PRORIDRE COMBUSTIBLE 0.000
2 MEZC. 02 DE CONCRETO DE 9 - 11 P3 HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
3 MEZC. 03 DE CONCRETO DE 9 - 11 P3 HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
4 CAMIONETA HORAS 0.000
COMISION DE REGANTES COMBUSTIBLE 0.000
5 CAMION DE APOYO HORAS 0.000
PRORIDRE COMBUSTIBLE 0.000
6 VPMPACTADORA HORAS 0.000

RESUMEN COMBUSTIBLE
TOTAL PETROLEO 200 GALONES
TOTAL GASOLINA 120 GALONES

CONTROLADOR DE MAQUINARIA ING RESIDENTE DE OBRA ING SUPERVISOR DE OBRA DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE

CONTROL DE VALORIZACION DE ALQUILER DE MAQUINARIA

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

TOTAL SALDO TOTAL VALORIZACIONES DE SALDO DE


VALORIZACION
CONTRATO TOTAL VALORIAZADO MENSUAL (HM) ACUMULADO RESPECTO AL ALQUILER DE MAQUINARIA VALORIZACION
CONTRATO ACUMULADO
N MAQUINARIA PROPIETARIO UND EN (S/.) OBSERVACION

(H-M) MONTO
CANT. P.U. PARCIAL DIC ENE FEB MAR ABR (H - M) V-1 V-2 V-3 (H-M) (S/.) (H-M) (S/.)
(S/.)
1 TRACTOR SOBRE ORUGA MUNICIPALIDADA NUOA HM 1000.00 170.00 170,000.00 20.00 50.00 80.00 100.00 10.00 260.00 44,200.00 740.00 3,400 8,500 13,600 260.00 44,200.00 740.00 125,800.00
2 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
3 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
4 CARGADOR FRONTAL MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
5 VOLQUETE MUNICIPALIDADA NUOA - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
6 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
7 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
8 - 0.00 0.00 0.00 0 0 0 0.00 0.00 0.00 0.00
9 - 0.00 0.00 0.00 0 0 0.00 0.00 0.00 0.00
TOTAL S/. 170,000.00 44,200.00 44,200.00 125,800.00

CONTROLADOR MAQUINARIA ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


RESUMEN DE RECURSOS DE MAQUINARIA Y EQUIPOS

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

MAQUINARIA, EQUIPO Y COMBUSTIBLE FECHA

RESUMEN RESUMEN

N COMBUSTIBLE UNIDAD AO 2,009 AO 2,010 HORAS MAQ CANT COMBUST

JUN JUL AG SET OCT NOV DIC ENE FEB MAR TOTAL
A EQUIPO PESADO

1.00 Volquete Volvo FM Petroleo Galn 320.00 320.00


Ope. Sr. Emiliano HM 96.66 96.66
2.00 Volquete Volvo FM Petroleo Galn 575.00 575.00
Ope. Sr. Emiliano HM 201.92 201.92
3.00 Volquete Volvo FM Petroleo Galn 585.00 585.00
Ope. Sr. Emiliano HM 193.42 193.42
4.00 Volquete Volvo FM Petroleo Galn - -
Ope. Sr. Emiliano HM - -
5.00 Cargador Frontal Cat 935G Petroleo Galn 385.00 385.00
Ope. Sr. Emiliano HM 130.00 130.00
6.00 Motoniveladora Komatsu Petroleo Galn 210.00 210.00
HM 126.75 126.75
7.00 Rodillo Liso Vibratorio Petroleo Galn 135.00 135.00
HM 84.66 84.66
8.00 Cisterna Ford Petroleo Galn 245.00 245.00
HM 69.75 69.75
9.00 cargador Frontal Fiattalis (agua) Petroleo Galn 20.00 20.00
HM 8.00 8.00
10.00 Tractor Oruga Petroleo Galn - -
HM - -
11.00 Petroleo Galn 55.00 55.00
HM 36.00 36.00
13.00 otros (encofrado) Petroleo Galn 40.00 40.00
- - -
Total Combustible - 2,570.00 - - - 947.15 2,570.00

B EQUIPO PESADO ALQUILADO


1 Excavadora Sobre Oruga Volvo Petroleo Galn -
Ope. Sr. Emiliano HM -
2 Excavadora Sobre Oruga Cat 325 B Petroleo Galn -
Ope. Sr. Emiliano HM -
3 Cargador Frontal Cat 950F Petroleo Galn 315.00 315.00
Ope. Sr. Emiliano HM 90.00 90.00
4 Volquete F12 (Cisterna) Petroleo Galn 375.00 375.00
Ope. Sr. Emiliano HM 120.00 120.00
5 Excavadora Pequea Jhon Deeree 490E Petroleo Galn 410.00 410.00
Ope. Sr. Emiliano HM 91.83 91.83
TOTAL - 1,100.00 - - - 301.83 1,100.00
0.00 3,670.00 0.00 0.00 0.00
B EQUIPO LIVIANO
1.00 Mezcladora 11P3 -12 HP Gasolina Galn 20.50 20.50
HM 0.00
2.00 Vibradora de Mang . 1 1/2" - 8HP Gasolina Galn 9.00 9.00
HM 0.00
3.00 Motocicleta Fortte 200 Gasolina Galn 3.00 3.00
HM 0.00
4.00 Motobomba Gasolina Galn 7.00 7.00
HM 0.00
5.00 Otros(gasolina) Gasolina Galn 18.00 18.00
HM 0.00
Total Combustible 0.00 57.50 0.00 0.00 0.00 0.00 57.50
RESUMEN

TIPO DE COMBUSTIBLE CANTIDAD H/M


RESUMEN
PETROLEO 3,670.00 1,248.98
GASOLINA 57.50 0.00
GOBIERNO REGIONAL PUNO
PRORRIDRE

RESUMEN DE HORAS EQUIPO LIVIANO - MENSUAL

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

SALDOS SALDOS
EJECUCION MENSUAL
DESCRIPCION EQUIPO LIVIANO SEGN EXPEDIENTE TOTAL ACUMULADO TOTAL SALDO TOTAL ACUMULADO TOTAL SALDO
U.M. P.U. CANT. H/M MONTO S/. JUN JUL AGO SET OCT NOV H/M % H/M % MONTO. S/. % MONTO. S/. %
CAMIONETA PU-2325 HM 170.00 12000:00:00 85,000.00 158:20:00 158:20:00
MEZCALDORA DE CONCRETO
VIBRADORA DE CONCRETO
TEODOLITO

TOTAL 85,000.00 0.00 0.00 0.00 0.00

CONTROLADOR MAQUINARIA ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS


GOBIERNO REGIONAL DE PUNO
PRORRIDRE

RESUMEN DE MOVIMIENTO MENSUAL DE ALMACEN CORRESPONDIENTE AL MES DE MARZO -2008

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

MOVIMIENTO MES DE MARZO


EG SAL INGR TOTAL SALID SALD
DESCRIPCION (Especificaciones Tcnicas) UND. S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
O/C FEB MAR. INGR MES ACT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
MATERI DE FABRICACION DE BARANDA
SOLDADURA SUPERCITO E-7018 e=1/8 KLG 9 9.00 5 5 4
PINTURTA ESMALTE COLOR NARANJA GLN 2.00 2.00 0 2
PINTURA ANTI CORROSIVA GLN 2.00 2.00 0 2
THINER ESTNDAR GLN 4.00 4.00 0 4
BROCHA DE 4" UND. 6.00 6.00 0 6
MATERIALES DE FERRETERIA
CILINDROS VACIOS DE 55 gls. UND 0.00 0 0.00
BALDES VACIOS DE ACEITE DE 5 Gls. UND 0.00 0 0.00
LINTERNAS GRANDES UND 0 0 0
PILAS GRANDES X 24 UNIDADES CAJA 1 1.00 1 1 0
PLASTICO GRUESO DOBLE ANCHO, 2,5 X 100 M. ROLLO 1 1.00 1 1 0
COLCHONES DE ESPONJA PLAZA MEDIA UND 0 0 0
MATERIALES PARA CARTEL DE OBRA TOPGRAFIA
OCRE KG. 1.00 1.00 1 1 0
PINTURA ESMALTE SINTETICO ROJO GLN 2.00 2.00 1 1 1
PINTURA ESMALTE SINTETICO. BLANCO. GLN 0 0 0
PINTURA ESMALTE SINTETICO NEGRO. GLN 1 1.00 0 1
BROCHA DE 4". UND 0 0 0
BROCHA DE 2". UND 2 2.00 2 2 0
THINER GLN 3 3.00 0 3
MATERIAL PINTADO DE BARANDA
PINRURA ANTICORROSIVA ROJO OXIDO GLN 2.00 2.00 0 2
PINTURA SINTETICO ANARANJADO GLN 2.00 2.00 0 2
BROCHA DE 4" UND 0.00 0 0.00
BROCHA DE 2". UND 0.00 0 0.00
THINER GLN 4.00 4.00 0 4
4 MATERIALES DE CONSTRUCCION
YESO EN BOLSA DE 30KLG BOLSA 26 26.00 3 3 2 3 11 15
ADITIVO INCORPORADO
3
ATERE 2AER GLN 70 70.00 6 5 11 59
19 MATERIAL DE CONSTRUCCION
PLANCHA METALICA DE 2,40MX1,2MM E=1ASTM UND 1.00 1.00 0 1
TUBERIA DE FIERRO GALVANIZADO D=11/2 E=2,00MM, UND 0.00 0.00 0 0
TUBERIA DE FIERRO GALVANIZADO D=1/2 E=2,00MM, UND 2 2.00 0 2
20 MATERIALES DE CONSTRUCCION 0
WATER STOP PVC DE 6" METR 104 104.00 6 24 50 24 104 0
25 MATERIALES DE CONSTRUCCION
ALAMBRON DE CONSTRUCCION DE =1/4" KG. 800 800.00 50 100 100 50 100 70 470 330
FIERRO CORRUGADO DE 3/8 X9ML VARILLA 455 455.00 5 10 6 10 10 2 5 20 10 2 13 5 32 25 9 30 194 261
FIERRO CORRUGADO DE = 1/2 X 9 ml. VARILLA 557 557.00 10 5 10 8 8 30 21 10 32 51 8 50 243 314
FIERRO CORRUGADO DE = 5/8 X 9 ml. VARILLA 31 31.00 0 31
FIERRO CORRUGADO DE 3/4X9ML VARILLA 36 36.00 0 36
ALAMBRE NEGRO N 16 KG. 2 2.00 2 2 0
ALAMBRE NEGRO N 8 KG. 224.00 224.00 15 30 20 15 30 25 35 20 5 5 24 224 0
CLAVOS DE 2" KG. 0.00 0.00 0 0
CLAVOS DE 3" KG. 94.00 94.00 20 5 10 10 5 10 1 20 5 8 94 0
CLAVOS DE 4". KG. 312 312.00 10 10 10 10 10 20 5 40 10 125 187
26 MATERIALES DE CONSTRUCCION
GOBIERNO REGIONAL DE PUNO
PRORRIDRE

RESUMEN DE MOVIMIENTO MENSUAL DE ALMACEN CORRESPONDIENTE AL MES DE MARZO -2008

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

MOVIMIENTO MES DE MARZO


EG SAL INGR TOTAL SALID SALD
DESCRIPCION (Especificaciones Tcnicas) UND. S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
O/C FEB MAR. INGR MES ACT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
CLAVO DE CALAMINA KG. 5 5.00 5 5 0
GOBIERNO REGIONAL DE PUNO
PRORRIDRE

RESUMEN DE MOVIMIENTO MENSUAL DE ALMACEN CORRESPONDIENTE AL MES DE MARZO -2008

OBRA MODALIDAD DE EJECUCION DEPARTAMENTO


ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR

MOVIMIENTO MES DE MARZO


EG SAL INGR TOTAL SALID SALD
DESCRIPCION (Especificaciones Tcnicas) UND. S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L
O/C FEB MAR. INGR MES ACT
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
27 MATERIALES DE CONSTRUCCION
MADERAS
MADERA 2" X 3"X 10' AGUANO. UND. 0 0.00 0 0
MADERA 1" X 8" X 10' AGUANO. UND. 50 50.00 5 15 5 8 2 10 5 50 0
MADERA 1 1/2" X 8" X 10' AGUANO. UND. 16 16.00 6 10 16 0
ESTACAS DE MADERA 2"X 2"X 30 CM. UND 175 175.00 25 25 50 125
TRIPAY DE 4' X 8' X 18 mm, LUPUNA, CLASES D/D, (para
PLANCHA 20 20.00 5 8 5 2 20 0
MADERA 2" X 3"X 10' CORRIENTE UND. 387 387.00 22 55 20 15 10 40 30 30 20 40 30 312 75
28 MATERIALES DE CONSTRUCCION
MADERA RROLISO V=4"X5M UND 46 46.00 6 6 40
29 MATERIALES DE CONSTRUCCION
CEMENTO PORTLAND TIPE IP X42,5KG BOLSAS 382 3000 3,382.00 178 276 178 107 156 88 128 78 280 176 150 370 350 2,515 867
36 MATERIALES DE CONSTRUCCION
ASFALTO LIQUIDO RC-250 GLN 650 650.00 0 650
INSUMOS PARA MANTENIMIENTO DE TRACTOR ORUGA
ACEITE MOTOR SAE 15W40 CAT GLN 0 0.00 0
FILTRO DE ACEITE MOTOR 1R-0739 CAT UNID 3 3.00 0 3
FILTRO DE PETROLEO 1R-0750 CAT UNID 3 3.00 0 3
FILTRO DE AIRE PRIMARIO 61-2501 CAT UNID 3 3.00 0 3
GRASA VOLVO EP-2 (36 LIBR) libras 0 0.00 0 0
HIDROLINA SHELL DONAX TC-10 W GLN 30 30.00 10 10 30
INSUMO PARA MANTENIMIENTO DE VOLQUETE
ACEITE DE MOTOR 15W40 GENUINO VOLVO GLN 0 0.00 0.0 0
FILTRO DE ACEITE L466634-3 VOLVO UNID 0 0
FILTRO DE ACEITE BY PASS 477536 VOLVO UNID 0 0.00 0 0
PERNO DE 9/16 22 ORDINARIO UNID 15 15.00 0 15
PERNO DE 9/16 21/2 ORDINARIO GRADO 8 UNID 15 15.00 0 15
CORZETAS DE TREN JUEGO DE TOLVA UNID 0 0.00 0 0
MATERIALES DE CONSTRUCCION
TUBERIA CORRUGADO HDPE N12 IBWT SOLIDA 30"X20UNID 53 53.00 4 2 2 8 45
INSUMOS PARA MANTENIMIENTO DE MOTONIVELADORA
ACEITE DE MOTOR 15W40 SAE GLN 7 7.00 0 7
ANTICONGELANTE GLN 2 2.00 0 2
ACCESORIOS DE TURBO GGO 1 1.00 0 1
FOCOS DE FAROS DELANTEROS UND 2 2.00 0 2
GRASA ROJA AMR-3 LBS 36 36.00 2 1 2 5 31
RETEN DE CIGEAL DELANTERO UND 1 1.00 0 1
GRASA EPMLG1 LBS 10 10.00 0 10

ALMECENERO DE OBRA ASISTENTE ADMINISTRATIVO ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE

CONTROL DE COMBUSTIBLE DIARIO - MES DE FEBRERO DEL 2008


(GASOLINA DE 84 - OCT)
OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL . COSTO DIRECTO
MOVIMIENTO MES DE FEBRERO
SALIDA
SALD INGR TOTAL SALDO
N MAQUINARIA V S D L M M J V S D L M M J V S D L M M J V S D L M M J V TOTAL
DC FEB. INGR ACTUAL
MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

CARTAS DE ADMINISTRACION 27.5 250 277.5


1 CAMIONETA PU-2325 3 11 10 10 10 10 15 15 84
2 CAMIONETA PU-2326 0
3 MEZCLADORA DE PRORRIDRE N 01 8 8
4 MEZCLADORA DE PRORRIDRE N 02 0
5 MEZCLADORA MARCO A. ARI ARI 2 1 2 2 2 2 2 3 1 1 1 2 1 1 21
6 MEZCLADORA MARCO A. ARI ARI 2 1 1 1 5
7 MANTENIMIENTO DE VOLQUETE XU- 2885 2 2 3 2 3 3 3 3 3 4 3 2 33
8 MOTOCICLETA PRORRIBRE 2 2 4 4 12
9 MOTOBOMBA MUNICIPIO 5 5
TOTAL 2 0 0 0 0 0 0 0 0 0 0 13 6 9 8 3 0 5 5 6 7 16 19 0 16 11 11 16 17 0 0 168 109.50

CONTROL DE COMBUSTIBLE DIARIO - MES DE FEBRERO DEL 2008


(PETROLEO D-2)
AFEC. PPTAL . COSTO DIRECTO
MOVIMIENTO MES DE FEBRERO
SALIDA
SALD INGR TOTAL SALDO
N MAQUINARIA V S D L M M J V S D L M M J V S D L M M J V S D L M M J V TOTAL
DC FEB. INGR ACTUAL
MES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

CARTAS DE ADMINISTRACION 27.5 250 277.5


1 CAMION DE APOYO 3 11 10 10 10 10 15 15 84
2 0
3 2 2 4 4 12
4 5 5
TOTAL 0 0 0 0 0 0 0 0 0 0 0 2 2 4 4 0 0 0 0 0 3 11 15 0 10 10 10 15 15 0 0 101 176.50
ALMECENERO DE OBRA ASISTENTE ADMINISTRATIVO ING. RESIDENTE DE OBRA V B ING. SUPERVISOR V B DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE

CUADRO DE RESUMEN DEL MOVIMIENTO DIARIO DE ALMACEN


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL :

INGRESO EGRESO
SALDO INGRESO
ITEM MATERIAL UND ACUMULADO SALDO
ANTERIOR FECHA PROVEEDOR CANT FECHA PARTIDAS CANT

1.00 CLAVO CON CABEZA DE 2 1/2 Kg 0 1-Apr 25 25 25


25 1-Apr 1 24
25 2-Apr 1 23
25 3-Apr 1 22
25 4-Apr 1/2 21 1/2
25 5-Apr 1 20 1/2
25 6-Apr 1 19 1/2
25 7-Apr 1 18 1/2
25 8-Apr 1 17 1/2
25 9-Apr 1 16 1/2
25 10-Apr 1 15 1/2
25 11-Apr 1 14 1/2
25 12-Apr 1/2 14
10 35 13-Apr 1 23
35 14-Apr 1 22
35 15-Apr 1 21
35 16-Apr 1/2 20 1/2
35 17-Apr 1/2 20
35 18-Apr 1/2 19 1/2
35 19-Apr 1/2 19
35 20-Apr 1/2 18 1/2
35 21-Apr 1 17 1/2
35 22-Apr 1/2 17
35 23-Apr 1/2 16 1/2
35 24-Apr 1/2 16
35 25-Apr 1 15
35 26-Apr 1 14
35 27-Apr 1/2 13 1/2
35 28-Apr 1 12 1/2
35 29-Apr 1/2 12
35 30-Apr 1 11
2.5 37.5 1-May 1/2 13
37.5 2-May 1 12
37.5 3-May 1/2 11 1/2
37.5 20-Oct 1/2 11
2.00 ALAMBRE N 16 KG 37.5 20-Oct 1/2 10 1/2

ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
GOBIERNO REGIONAL PUNO
PRORRIDRE

CUADRO DE RESUMEN DEL MOVIMIENTO MENSUAL DE ALMACEN


OBRA MODALIDAD DE EJECUCION DEPARTAMENTO
ENT. EJEC. FECHA DE INICIO DE OBRA PROVINCIA
ENT. FIN. PLAZO DE EJECUCION DISTRITO
FECHA FECHA DE TERMINO DE LA OBRA SECTOR
AFEC. PPTAL :

AO - 2010 CANTIDAD
CANTIDAD
ACUMULADA
ITEM MATERIALES UND SEGN SALDO
EXPEDIENTE ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE

1.00 CLAVO CON CABEZA DE 2 1/2 Kg 0


2.00 CEMENTO PORTALND TIPO I X 42.5 KG Und. 7000 100 250 350 6650
3.00 FIERRO DE 3/8 Var. 250
4.00 FIERRO DE 1/2 Var. 300
5.00 FIERRO DE 5/8 Var. 200
6.00 FIERRO DE 3/4 Var. 30
7.00 ALAMBRE N 16 Kg 50
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00

ALMACENERO DE OBRA ASISTENTE ADMINISTRATVO RESIDENTE DE OBRA SUPERVISOR DE OBRA DIRECTOR DE OBRAS
Pgina 29

REPORTE FINANCIERO DE RECURSOS EMPLEADOS DEL COSTO DIRECTO

OBRA MODALIDAD DE EJECUCION

ENT. EJEC. FECHA DE INICIO DE OBRA

ENT. FIN. PLAZO DE EJECUCION

FECHA FECHA DE TERMINO DE LA OBRA

1.00 RECURSOS DE MANO DE OBRA


MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
N CATEGORIA REFERENCIAL ACUMULADO H/H ACUMULADO UNIT. REAL PARCIAL
(S/.) H/H H/H S/. S/.
6.5.11.10 RETRIBUCIONES Y COMPLEMENTOS - CONTRATOS A PLAZO FIJO
1 TOPOGRAFO 23,027.00 1,643.86 313.04 1,956.90 5.75 11,252.20
2 NEVELADOR 3,155.89 611.21 3,767.10 5.65 21,284.10
3 MAESTRO DE OBTRA / CAPATAZ 75,534.60 6,159.29 1,136.28 7,295.58 5.65 41,220.00
4 OPERARIO 59,275.81 7,300.00 1,194.44 8,494.44 4.50 38,225.00
5 OFICIAL 148,862.43 13,746.03 3,873.02 17,619.05 3.15 55,500.00
6 PEON 248.00 0.00 248.00 5.00 1,240.00
TOTAL S./ 306,699.84 32,253.07 7,128.00 39381.07 168,721.30
(*) El Operador de Maquinaria segn Expediente Tcnico se considerara su aporte en el Rubro de Maquinaria y Equipo

2.00 RECURSOS DE MATERIALES


MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
N DESCRIPCIN UND REFERENCIAL ACUMULADO CANTIDAD ACUMULADO UNITARIO PARCIAL
CANTIDAD CANTIDAD S/. S/.
6.5.11.29 MATERIALES DE CONSTRUCCIN

MATERIAL CONSIDERADO EN EL EXPEDIENTE


1 Alambre negro # 16 kg S/. 8,939.51 447.00 80.00 527.00 3.30 S/. 1,739.10
2 Alambre negro # 8 kg S/. 2,961.56 499.00 86.00 585.00 3.20 S/. 1,872.00
3 Clavos para madera con cabeza de 3" kg S/. 2,190.81 221.00 58.00 279.00 3.50 S/. 976.50
4 Tuberia pvc sel para instalaciones electricas de 1" m S/. 1,859.55 0.00 S/. 0.00
65 Grass kg S/. 1,406.16 0.00 S/. 0.00
MATERIAL NO CONSIDERADO EN EL EXPEDIENTE 0.00 S/. 0.00
INSUMOS PARA REPARACION DE TUBERIAS 0.00 S/. 0.00
1 Tuberia Pvc Iso 4422 Uf C-7.5 Dn 200 Mm C/Anillo Und 0.00 S/. 0.00
6 Union De Reparacion Pvc Uf Dn 200 Mm C/Anillo Und. 0.00 S/. 0.00
7 Union Reparacion Pvc Uf Dn 63 Mm C/Anillo Und 0.00 S/. 0.00
SUB-TOTAL S./ S/. 17,357.58 #REF!

6.5.11.30 BIENES DE CONSUMO


1 Herramientas manuales Glb S/. 8,392.21 9,669.00 0.00 9,669.00 1.00 S/. 9,669.00
TOTAL S/. 8,392.21 S/. 9,669.00

6.5.11.32 PASAJES Y GASTOS DE TRANSPORTE


1 Transporte de materiales a obra Glb S/. 25,000.00 S/. 0.00
2 Movilizacion y desmovilizacion de maquinaria y equipo Glb S/. 60,000.00
TOTAL S/. 85,000.00 S/. 0.00

6.5.11.39 OTROS SERVICIOS DE TERCEROS


1 Control de calidad en conformacion de sub-base Glb S/. 7,500.00 0.00 0.00 0.00 S/. 0.00
2 Control de calidad en conformacion de base Glb S/. 10,000.00 0.00 0.00 0.00 S/. 0.00
3 Control de calidad en asfaltos Glb S/. 5,000.00 0.00 0.00 0.00 S/. 0.00
4 Control de calidad en concretos Glb 3000 0.00 0.00 0.00 S/. 0.00
TOTAL S/. 25,500.00 S/. 0.00

3.00 MAQUINARIAY EQUIPO


MONTO ANTERIOR DEL MES ACTUAL PRECIO PRECIO
6.5.11.52 ALQUILER DE DE BIENES MUEBLES UND REFERENCIAL ACUMULADO CANTIDAD ACUMULADO UNITARIO PARCIAL
CANTIDAD(HM/HH) (HM/HH) CANTIDAD (HM/HH) S/. S/.
EQUIPO PESADO (MAQUINARIA PROPIA)
1 Volquete Volvo FM 750006 (**) S/. 565,384.67 1,144.89 96.66 96.66 60.00 5,799.60
2 Volquete Volvo FM 750007 (**) S/. 0.00 1,048.14 201.92 201.92 60.00 12,115.08
11 Camioneta Verde (**) S/. 0.00 - 36.00 36.00 14.10 507.50
12 Operadores de Maquinaria Pesada (*) 7,635.98 1,518.70 9,154.68 5.65 51,723.96
SUB-TOTAL S/. S/. 565,384.67 TOTAL S/. S/. 70,146.14
Pgina 30

EQUIPO PESADO (MAQUINARIA ALQUILADA)


1 Rodillo Neumatico Autopropulsado 81-100hp 5.5-20 Ton S/. 9,369.17 0.00 0.00 16.00 0.00
2 Rodillo Tandem Vibratorio Autopropulsado 70-100hp 7-9 Ton S/. 9,759.55 0.00 0.00 14.00 0.00
3 Excavadora Sobre Oruga Volvo S/. 305,938.19 199.91 0.00 199.91 206.00 41,181.46
Planta de asfalto de 30/60 ton/h S/. 32,792.09 0.00 0.00 13.00 0.00
Secador de aridos S/. 6,636.49 0.00 0.00 14.00 0.00
Camion cisterna F12 0.00 120.00 120.00 75.00 9,000.00
SUB-TOTAL S/. S/. 364,495.49 S/. 50,181.46

COMBUSTIBLES Y LUBRICANTES (CORRESPONDIENTE A LA MAQUINARIA Y EQUIPOS)


1 Petroleo(no contemplados en el expediente tecnico) 17,767.00 3,670.00 21,437.00 9.95 213,298.15
2 lubricantes y repuestos(no contemplados en el expediente tecnico) 18,295.93 0.00 18,295.93 1.00 18,295.93
3 Gasolina 0.00 57.50 57.50 10.00 575.00
4 OTROS GLB 0.00 0.00 0.00 1.00 0.00
SUB-TOTAL S/. S/. 0.00 S/. 232,169.08
(**); El costo de Hora Maquina del equipo pesado unicamente se asume el costo de mantenimiento aproximado

EQUIPO LIVIANO
1 Mezcladora De Concreto 9 -11 P3 17,099.18 0.00 0.00 -
2 Vibradora de Concreto 8HP con manguera de1 1/2 x6m (*) 1,105.41 4,224.00 0.00 4,224.00 1.00 4,224.00
4 Motobomba Cent. 4"x4" de 13HP Marca Honda(*) 2,121.95 3,996.00 0.00 3,996.00 1.00 3,996.00
5 Manguera de Succion de agua de 4" x 6m 0.00 0.00 -
6 Manguera de Descarga de agua de 4" x 40m PVC Tipo Manga 0.00 0.00 -
7 Miras y jalones 6,246.45 0.00 0.00 -
16 Tanque Estacionario/incluye pintado (*) 19,178.50 0.00 19,178.50 1.00 19,178.50
17 Cortadora de madera (encofrado)(*) 178.00 0.00 178.00 1.00 178.00
SUB-TOTAL S/. S/. 26,572.98 SUB-TOTAL S./ S/. 27,576.50
TOTAL BIENES MUEBLES S/. 956,453.13 S/. 380,073.18
(*); COMPRA DE EQUIPO LIVIANO
6.5.11.65 ALQUILER DE BIENES INMUEBLES
1 Amacen y/o residencia Glb 3,000.00 600.00 100.00 700.00 1.00 700.00
SUB-TOTAL S/. S/. 3,000.00 S/. 700.00

COSTO DIRECTO TOTAL S./ S/. 1,402,402.77 TOTAL S./ #REF!


REPORTE FINANCIERO DE RECURSOS EMPLEADOS DEL COSTO INDIRECTO
OBRA MODALIDAD DE EJECUCION
ENT. EJEC. FECHA DE INICIO DE OBRA
ENT. FIN. PLAZO DE EJECUCION
FECHA FECHA DE TERMINO DE LA OBRA

1.00 GASTOS GENERALES


MONTO ANTERIOR ACTUAL PORCENTAJE
N CATEGORIA SEGN EXPEDIENTE ACUMULADO MES ACTUAL ACUMULADO ACUMULADO
(S/.) (%)
6.5.11.27 SERVICIOS NO PERSONALES 136,000.00 21,889.36 7,220.00 29,109.36 21.40%
1.00 RESIDENTE DE OBRA 40,000.00 0.00 0.00%
3.00 ASISTENTE TECNICO DE OBRA 01 40,000.00 3,253.23 1,600.00 4,853.23 12.13%
4.00 ASISTENTE ADMINISTRATIVO 3,253.23 1,600.00 4,853.23 12.13%
5.00 MAESTRO DE OBRA A 22,000.00 0.00 0.00 0.00 0.00%
6.00 ALMACENERO DE OBRA 16,000.00 1,830.00 900.00 2,730.00 17.06%
7.00 GUARDIAN 18,000.00 3,074.00 1,730.00 4,804.00 26.69%
12.00 1,525.00 750.00 2,275.00 #REF!
13.00 5,273.90 640.00 5,913.90 #REF!
14.00 3,680.00 0.00 3,680.00 #REF!

6.5.11.30 BIENES DE CONSUMO 17,205.73 12,225.00 0.00 12,225.00 71.05%


1.00 Cuaderno de obra incluye legalizado 300.00 300.00 0.00 300.00 100.00%
2.00 Papel A4 ( 4 millares) 360.00 360.00 0.00 360.00 100.00%
3.00 toner para impresora laser 2,000.00 0.00 0.00 0.00%
4.00 tinta para plotter(juego) 800.00 0.00 0.00 0.00%
5.00 computadora c/impresora 2,750.00 2,648.00 0.00 2,648.00 96.29%
6.00 Utiles varios 3,495.73 2,802.00 0.00 2,802.00 80.15%
7.00 Implemento de Seguridad 7,500.00 6,115.00 0.00 6,115.00 81.53%

6.5.11.51 EQUIPAMIENTO Y BIENES DURADEROS 2,000.00 1,547.00 0.00 1,547.00 77.35%


2.00 Mobiliario de oficinas de supervision y Residencia 2,000.00 1,547.00 1,547.00 77.35%
TOTAL GASTOS GENERALES(S/.) 155,205.73 35,661.36 7,220.00 42,881.36 27.63%

3.00 SUPERVISION DE OBRA


MONTO ANTERIOR ACTUAL PORCENTAJE
N CATEGORIA REFERENCIAL ACUMULADO MES ACTUAL ACUMULADO ACUMULADO
(S/.) (%)
6.5.11.33 GASTOS DE ESTUDIO 66,078.47 0.00 0.00 0.00 0.00%
1.00 Ingeniero Supervisor de Obra 40,000.00
2.00 Asistente Tecnico de Supervision 20,000.00
3.00 Utiles de Escritorio 6,078.47

6.5.11.49 LIQUIDACION DE OBRA 27,822.51 0.00 0.00 0.00 0.00%

1.00 Servicio de Liquidacion tecnico financiero 27,822.51

TOTAL MENSUAL DEL COSTO INDIRECTO DEL EXPEDIENTE S/. #REF!


TOTAL MENSUAL DEL COSTO INDIRECTO MENSUAl S/. #REF! #REF!
TOTAL MENSUAL DEL COSTO INDIRECTO ACUMULADO S/. #REF! #REF!

ING RESIDENTE ASIETNTE ADMINISTRATIVO VB SUPERVISOR V B DIRECTOR DE OBRAS


RESUMEN DE INVERSION - FINANCIERA

OBRA MODALIDAD DE EJECUCION

ENT. EJEC. FECHA DE INICIO DE OBRA Monto de Financiamiento S/. 3,795,310.00


ENT. FIN. PLAZO DE EJECUCION

FECHA FECHA DE TERMINO DE LA OBRA

Inversin Total S/. 55,106.56


GASTO PORC. CALCULADO 1.45%

MONTO VALOR VALOR ACTUAL VALOR SALDOS


ITEM R U B R O REFERENCIAL ANTERIOR ( Segn doc probatorios ) ACUMULADO % OBSERVACIONES
S/- S/. S/. S/. S/.
1.0 COSTO DIRECTO 3,477,814.22 139,472.97 (139,472.97) - 0.00% 3,477,814.22
2.6.23.43 PERSONAL 306,699.84 139,472.97 (139,472.97) - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 SERVICIOS 1,682,309.52 - 0.00 - 0.00% 1,682,309.52
2.6.23.46 OTROS 1,488,804.86 - - - 0.00% 1,488,804.86
2.0 GASTOS GENERALES (5.92918% CD) 206,205.73 43,436.56 11,670.00 55,106.56 26.72% 151,099.17
2.6.23.43 PERSONAL 306,699.84 PRECIO #VALUE! - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 SERVICIOS 1,682,309.52 - 0.00 - 0.00% 1,682,309.52
2.6.23.46 OTROS 1,488,804.86 - - - 0.00% 1,488,804.86

3.0 GASTOS DE SUPERVISION DE OBRA (1.90%) 66,078.47 - - - 0.00% 66,078.47


2.6.23.43 PERSONAL 306,699.84 1,475.10 (1,475.10) - 0.00% 306,699.84
2.6.23.44 BIENES
2.6.23.45 SERVICIOS 1,682,309.52 - #VALUE! IMPORTE 0.00% -
2.6.23.46 OTROS 1,488,804.86 - - - 0.00% 1,488,804.86
TOTAL INVERSION 10,705,726.86 0.00 - 127,802.97 55,106.56 0.51% 10,650,620.30

AVANCE FINANCIERO ACUMULADO 0.51%


AVANCE FISICO ACUMULADO 1.41%

ING. RESIDENTE V B SUPWEVISOR V B DIRECCION DE OBRAS