Beruflich Dokumente
Kultur Dokumente
Sr. Cl.
Characteristic Description Characteristic
No. No.
Construction (General The gas (heat) input to the pilot alone shall not exceed Operational
4 Requirements) - Gas heat 4.1.9 8 litres / hour at a gas inlet pressure of 30 gf/cm2 at requirements (Minimum
(Input) temperature of 25 to 30 deg C, wherever applicable. heat input)
Constructional
Construction (General The appliance shall be provided with a safety device,
requirements
5 Requirements) - Safety 4.1.10 which cuts off the supply of gas in case water does
(Automatic water-
Device not flow or stops flowing while in operation.
operated gas valve)
Construction (General The appliance shall have a provision such that gas
6 Requirements) - Cut-off 4.1.11 shall be cut off and the burner extinguished after 20
Device (+1, -2) minutes of uninterrupted use.
Copper and copper alloy forged and cast parts shall Constructional
7 Construction (Material) 5.2
pass mercurous nitrite test (season cracking test) requirements (Material)
Constructional
Construction (Flame Ignition, correct burner performance and the length of
9 7 requirements (Checking
Visibility) the pilot flames, if any, should be visible at all times.
the state of operation)
Appliance shall have a device (Gas Tap) allowing
Constructional
manual interruption of the supply of the gas to the
requirements (Shut-off
10 Construction (Gas Taps) 8 burner and the pilot, if available in case of exigency.
valves and / or gas rate
Gas shall not enter to the main burner and the pilot (if
adjusters)
provided) until it is reset to the original position.
Construction (Flame Failure Total gas leakage should not exceed 1.5 litres per hour
11 9
Device) at the standard pressure using LPG.
Constructional
Construction (Protection Overheat protection device shall switch off the supply requirements (Protection
12 against accidental 11 of gas if the temperature of the delivered water against accidental
overheating) reaches 95 (+0, -10) deg C. overheating of
thermostatic appliances)
Constructional
13 requirements (Pressure
test point)
Operational
Performance Requirements Well-ventilated, draught-free room, which has an
14 13.1.1 requirements (Test room
(Test room conditions) ambient tempreature of 20 to 30 deg C.
conditions)
Operational
Performance Requirements
requirements
15 (Accuracy of 13.1.2 Water termperature: +/- 0.5 deg C
(Measurement
measurements)
uncertainties)
Surface temperature: +/- 2 deg C
Gas temperature: +/- 0.5 deg C
Operational
Performance Requirements Ignition should be smooth and flame travel shall be requirements (Ignition -
23 19
(Ignition and Flame Travel) complete for all pressures from 25-35 gf/cm2. Cross-lighting - Flame
stability)
Operational
requirements
24 (Adjusting, control and
safety devices) - Safety
times
Operational
Performance Requirements Smooth operation with tap fully open at gas inlet requirements (Ignition -
25 20
(Flame Stability) pressures from 2.452-3.432 kN/m2 (25-35 gf/cm2). Cross-lighting - Flame
stability)
Operational
requirements (Ignition -
26
Cross-lighting - Flame
stability)
Operational
27 requirements
(Endurance)
Performance Requirements
28 21 No undue or excessive noise during all operations
(Noise Control)
Performance Requirements
29 22 No flash-back at pressures from 25-35 gf/cm2