BAR CHART AND S-CURVE

Weighted No. of
Item No. DESCRIPTION % Days Amount 15 Days 30 Days 30 Days
100 %
B.5 Project Billboard/ Signboard 0.21 1 10,000.00 0.21

B.7 Occupational Safety and Health Program 0.50 35 23,400.00 0.16 0.17 0.17

B.9 Mobilization/ Demobilization 0.44 2 20,568.20 0.22 0.22

105(1)a Subgrade Preparation - Common Material 1.88 12 88,263.00 1.88


50 %
200(1) Aggregate Subbase Course, 0.20m thk. (for carriageway and shouldering) 17.70 29 830,652.90 4.06 12.42 1.22

201(1) Aggregate Base Course, Crushed Grading A, 0.15m thk. (for shouldering) 4.86 28 228,017.40 1.40 3.11 0.35

311(1)a PCC Pavement (Unreinforced), 0.15m thk. 70.71 21 3,318,035.00 2.85 63.11 4.75

612(1) Reflectorized Thermoplastic Pavement Marking (White)-GAD Related 3.70 1 173,663.50 3.70
0%
TOTAL 4,692,600.00
10.78 78.81 10.41
PROGRESSIVE
505,862.28 3,698,238.06 488,499.66
CASHFLOW 10.78 89.59 100.00
CUMULATIVE
505,862.28 4,204,100.34 4,692,600.00

FROM THE OFFICE OF: PROJECT TITLE: PREPARED BY: CHECKED BY: SUBMMITED: APPROVAL RECOMMENDED: APPROVED: SHEET NO.

FIRST GRANDEUR BUILDERS 01 of 01


ROAD IMPROVEMENT OF SAN ANTONIO, BOLJOON-CERDEA GAVINO T. UMALI BEETHOVEN XAVIER B. EGOS MARLON D. MAROLLANO RENULT G. RICARDO JAMES D. DELLOSA Lt. Col. PA Res
GEN. ENGINEERING & BUILDING CONTRACTOR
Pakigne, Minglanilla Cebu PROJECT ENGINEER ARCHITECT II CHIEF, PLANNING & DESIGN SECTION ASSISTANT DISTRICT ENGINEER DISTRICT ENGINEER SET NO.
Tel. No. (032) 272-0661 Telefax No. (032) 490-4323
LOCATION : MALABUYOC, CEBU ADDRESS: PAKIGNE, MINGLANILLA CEBU DATE: DATE: DATE:

Das könnte Ihnen auch gefallen