Sie sind auf Seite 1von 19

SUPREME COURT REPORTS ANNOTATED temperate, liquidated, or compensatory damages.

They are recoverable in


criminal cases as part of the civil liability when the crime was committed
BPI Investment Corporation vs. D.G. Carreon Commercial Corp.
with one or more aggravating circumstances; in quasi-delicts, if the
G.R. No. 126524. November 29, 2001.* defendant acted with gross negligence; and in contracts and quasi-
BPI INVESTMENT CORPORATION, petitioner, vs. D.G. CARREON contracts, if the defendant acted in a wanton, fraudulent, reckless,
COMMERCIAL CORPORATION, DANIEL G. CARREON, AURORA J. CARREON, oppressive, or malevolent manner.
AND JOSEFA M. JECEIL, respondents. Same; Same; Moral damages may be awarded in a breach of contract
when the defendant acted in bad faith, or was guilty of gross negligence
Remedial Law; Certiorari; Instances when the findings of fact of the
amounting to bad faith or in wanton disregard of his contractual
trial court and/or Court of Appeals may be reviewed by the supreme Court.
obligation.The award of moral damages and attorneys fees is also not in
There are instances when the findings of fact of the trial court and/or Court
keeping with existing jurisprudence. Moral damages may be awarded in a
of Appeals may be reviewed by the Supreme Court, such as (1) when the
breach of contract when the defendant acted in bad faith, or was guilty of
conclusion is a finding grounded entirely on speculation, surmises and
gross negligence amounting to bad faith, or in wanton disregard of his
conjectures; (2) when the inference made is manifestly mistaken, absurd or
contractual obligation. Finally, with the elimination of award of moral
impossible; (3) where there is a grave abuse of discretion; (4) when the
damages, so must the award of attorneys fees be deleted.
judgment is based on a misapprehension of facts; (5) when the findings of
Same; Same; Temperate or moderate damages may be recovered
fact are conflicting; (6) when the Court of Appeals, in making its findings,
when the court finds that some pecuniary loss has been suffered but its
went beyond the issues of the case and the same is contrary to the
amount cannot form the nature of the case be proved with certainty.There
admissions of both appellant and appellee; (7) when the findings are
is no doubt, however, that the damages sustained by respondents were due
contrary to those of the trial court; (8) when the findings of fact are
to petitioners fault or negligence, short of gross negligence. Temperate or
conclusions without citation of specific evidence on which they are based;
moderate damages may be recovered when the court finds that some
(9) when the facts set forth in the petition as well as in the petitioners main
pecuniary loss has been suffered but its amount cannot, from the nature of
and reply briefs are not disputed by the respondents; and (10) the findings
the case, be proved with certainty. The Court deems it prudent to award
of fact of the Court of Appeals are premised on the supposed absence of
reasonable temperate damages to respondents under the circumstances.
evidence and contradicted by the evidence on record.
Civil Law; Damages; Negligence; Gross negligence evinces a
PETITION for review of a decision of the Court of Appeals.
thoughtless disregard of consequences without exerting any effort to avoid
them. We find petitioner not guilty of gross negligence in the handling of
The facts are stated in the opinion of the Court.
the money market placement of respondents. Gross negligence implies a
Bargas, Benedicto, Tale & Verzosa for petitioner.
want or absence of or failure to exercise slight care or diligence, or the entire
Belo, Gozon, Parel, Asuncion & Lucila for private respondents.
absence of care. It evinces a thoughtless disregard of consequences without
exerting any effort to avoid them.
PARDO, J.:
Same; Same; Same; Exemplary damages are recoverable in
quasidelicts if the defendant acted with gross negligence and in contracts
Before the Court is a petition for review on certiorari of the decision 1 of the
and quasi-delicts if he acted in a wanton, fraudulent, reckless, oppressive or
Court of Appeals reversing the ruling of the Regional Trial Court, Makati,
malevolent manner.The law on exemplary damages is found in Section 5,
dismissing petitioners complaint for recovery of a sum of money alleged as
Chapter 3, Title XVIII, Book IV of the Civil Code. These are imposed by way
overpayment of money market placements.
of example or correction for the public good, in addition to moral,
The Facts
Petitioner BPI Investment Corporation (BPI Investments), formerly known as order slip for 12-12. BPI Investments claimed that the same placement
Ayala Investment and Development Corporation, was engaged in money was also booked as maturing on December 12, 1979. Aurora Carreon
market operations. Respondent D.G. Commercial Corporation was a client instructed BPI Investments to roll over the whole amount ofP323,518.22 for
of petitioner and started its money market placements in September, 1978. another thirty days, or up to January 11, 1980, at 19% interest. BPI
The individual respondents, spouses Daniel and Aurora Carreon and Josefa Investments claimed that roll overs were subsequently made from maturing
M. Jeceil also placed with BPI Investments their personal money in money payments on which BPI Investments had made over payments at a total
market placements. amount of P410,937.09, as follows:
On November 15, 1979, D.G. Carreon Commercial Corporation (D.G. April 14, 1980 P 14,371.74
Carreon, for brevity) placed with BPI Investments P318,981.59 in money June 18, 1980 P 9,648.38
market placement with a maturity term of thirty two days, or up to
August 12, 1980 P100,000.00
December 17, 1979, at a maturity value of P323,518.22. BPI Investments
issued the corresponding sales order slip for straight sale and confirmation March 19, 1981 P 66,259.88
slip. October 19, 1981 P220,657.64
On December 12, 1979, there appeared in BPI Investments ledger due TOTAL P410,937.09
D.G. Carreon an amount of P323,518.22, which is the exact amount to All the above payments were evidenced by checks issued by BPI Investments
mature on December 17, 1979. D.G. Carreon did not make any money to respondents.
placement maturing on December 12, 1979. As a result of this, Mr. Celso On April 21, 1982, BPI Investments wrote respondents Daniel Carreon
Abrantes, an officer of BPI Investments called up Aurora Carreon about the and Aurora Carreon, demanding the return of the overpayment of
money market placement supposedly maturing on December 12, 1979. P410,937.09.2 They discussed the matter with BPI Investments. The
Aurora Carreon instructed Abrantes to roll over the amount of P323,518.22, respondents asserted that there was no overpayment and asked for time to
for another thirty days at 19% interest to mature on January 11, 1980. A look for the papers. Upon the request of BPI Investments, the spouses
sales order slip and a confirmation slip were executed dated December 12, Daniel and Aurora Carreon sent to BPI Investments a proposed
1979. memorandum of agreement, dated May 7, 1982, stating that:
On December 17, 1979, BPI Investments credited D.G. Carreon with NOW, THEREFORE, and for (sic) in consideration of the foregoing, the
another P323,518.22 via roll over of P300,000.00, for a term of one hundred parties herein agree as follows:
twenty days at 19% interest maturing on April 15, 1980, and P23,518.22, 1. Because of the age and retrieval difficulty of the transactions on this
paid out in cash. A sales order slip for straight sale and a confirmation slip placement, the Company has a five-year option to determine if the said
were executed. BPI Investments paid the money placement on April 16, placement referred to as funded, and if so, to submit to AIDC (Now BPI
1980. The money placement in the amount of P319,000.00 that matured on Investments) documents to this effect. And if such documents support the
April 16, 1980 was again rolled over for a term of sixty one days at 19% funding of side placement, AIDC (BPI Investments) shall pay the company
interest maturing on June 16, 1980, with a maturity value of P329,443.81. the stated amount being temporarily reimbursed by the Company with a
The amount was again rolled over for a term of thirty days at 18% interest 12% p.a. interest. In the spirit of goodwill the company hereby agrees to
maturing on July 16, 1980, and again rolled over for another thirty days at temporarily reimburse AIDC the amount of FOUR HUNDRED TEN
18% interest. THOUSAND NINE HUNDRED THIRTY SEVEN and 9/100 PESOS (P410,937.09)
BPI Investments paid D.G. Carreon twice in interest of the amount of representing the full amount of the claim of AIDC as mentioned above. 3
P323,518.22, representing a single money market placement, the first on
December 12, 1979, and the second on December 17, 1979. According to On May 10, 1982, BPI Investments, without responding to the memorandum
petitioner, their bookkeeper made an error in posting 12-17 on the sales and proposal of D.G. Carreon filed with the Court of First Instance of Rizal,
Branch 36, Makati, a complaint4 for recovery of a sum of money against D.G. cannot be denied or disapproved as against the person relying thereon.
Carreon with preliminary attachment. On May 14, 1982, the trial court Accordingly, plaintiff having thus clearly stated in several documents duly
issued an order5 for preliminary attachment after submission of affidavit of signed by its responsible officers cannot now vary their contents and claim
merit to support the petition, and the posting of a bond in the amount of that they were received without value having been received for the same.
P200,000.00. However, on October 8, 1982, the trial court lifted the writ of Lastly, it is incumbent upon plaintiff corporation to provide for
attachment.6 On October 28, 1982, BPI Investments moved for competent employees possessed with adequate skills in implementing
reconsideration, but the trial court denied the motion after finding the effective safeguards and measures that ensure the non-occurrence of errors
absence of double payment to the defendants. of this nature, it would be gross negligence on the part of plaintiff if it fails
On July 30, 1982, respondents D.G. Carreon filed with the trial court an to provide for the same considering that it is primarily engaged in the
answer7 to the complaint, with counterclaim. D.G. Carreon asked for solicitation of money market placements.
compensatory damages in an amount to be proven during the trial; spouses In view of the foregoing, the case is hereby DISMISSED with cost against
Daniel and Aurora Carreon asked for moral damages of P1,000,000.00 plaintiff. The attachment previously issued is likewise lifted.
because of the humiliation, great mental anguish, sleepless nights and
deterioration of health due to the filing of the complaint and indiscriminate It appearing that plaintiff was not motivated by malice in filing this case,
and wrongful attachment of their property, especially their residential the counterclaim is likewise DISMISSED.
house and payment of their money market placement of P109,283.75. SO ORDERED.8
Josefa Jeceil asked for moral damages of P500,000.00, because of sleepless
nights and mental anguish, and payment of her money market placement of Both parties appealed the above decision to the Court of Appeals. 9
P73,857.57; all defendants claimed for exemplary damages and attorneys After due proceedings, on July 19, 1996, the Court of Appeals
fees of P100,000.00. promulgated a decision, the dispositive portion of which reads as follows:
On May 25, 1993, the trial court rendered a decision, the pertinent WHEREFORE, the appealed judgment of the trial court dismissing the
portions of which read as follows: plaintiff s complaint is hereby AFFIRMED while its dismissal of the
Plaintiff s case is unmeritorious. counterclaim of defendants is REVERSED and SET ASIDE and judgment is
The court agrees with defendants counsels observation that plaintiff hereby rendered as follows:
did not prove by clear and convincing evidence that defendants indeed 1. Ordering plaintiff BPI to pay the following amounts of damages:
received money in excess of what is due them as it utterly failed to show Moral Damages
and present any proof what was actually due defendants. As pointed out by a) P1,000,000.00 to the late Daniel G. Carreon or his estate represented
the same counsel, the summary of the money market placement submitted by Aurora J. Carreon;
as evidence by plaintiff (Exh. A) is at best self-serving as it was admittedly b) P1,000,000.00 to Aurora J. Carreon; P500,000.00 to the late Josefa
prepared by plaintiff s own accounting department without any M. Jeceil or her estate represented by Aurora J. Carreon;
participation of defendants. (TSN of October 15, 1985, p. 4) Compensatory Damages
Moreover, the alleged payments in the complaint were admitted by P1,500,000.00 to D.G. Carreon Commercial Corporation;
plaintiff itself to be withdrawals from validly issued commercial papers (TSN Exemplary Damages
of August 12, 1986, pp. 3-5) for value received (Exhs. 1-B, 2-B up to 11-B) P1,000,000.00 to all defendants;
duly verified and signed by at least two (2) authorized high ranking officers Attorneys Fees
of plaintiff s corporation. Again, as correctly stated by defendants, Art. 1431 P500,000.00 to all defendants
of the New Civil Code provides that through estoppel an admission or
representation is rendered conclusive upon the person making it, and
2. Ordering plaintiff BPI to pay to the estate of Daniel G. Carreon, the maturity date benefited D.G. Carreon. And as soon as petitioner
represented by Aurora J. Carreon, the money market placement of discovered the wrong posting, it immediately wrote D.G. Carreon to inform
P109,238.75 with 12% interest per annum from June 3, 1982 until fully paid; the latter of the error in the posting of the maturity dates on its money
3. Ordering plaintiff BPI to pay to the estate of Josefa M. Jeceil, market placements.15
represented by Aurora J. Carreon, the money market placement in the Third, the manner of execution of the writ of attachment is not the fault
amount of P73,857.57 at 12% interest per annum from maturity on July 12, of BPI Investments. The sheriff of the trial court implemented the writ. The
1982 until fully paid; only participation BPI Investments had in the process was the application
4. Ordering plaintiff BPI to pay for the costs of the suit. for a writ of preliminary attachment. BPI Investments did not have a hand in
SO ORDERED.10 its implementation.16
Fourth, the Court of Appeals blamed BPI Investments for the
Hence, this appeal.11 deterioration of the health of two respondents who died pendente lite. The
Petitioner BPI Investments raises the following issues: award of moral and exemplary damages and attorneys fees in favor of
respondents is bereft of factual and legal bases. 17
1. 1.Whether there was an over payment of respondents money Petitioner filed the case below to recover the overpayment arising from
market placements. an unfunded placement. The respondents failed to show proof that the
2. 2.Whether petitioner abused its right in implementing the writ of December 12, 1979 placement was different from the December 17, 1979
preliminary attachment; placement.
3. 3.Whether the Court of Appeals awarded excessive moral and The Court of Appeals ruling that the filing of the case aggravated and
exemplary damages as well as attorneys fees to respondents; caused the death of respondents Daniel Carreon and Josefa Jeceil is
and completely unfounded and farfetched. Daniel Carreon, prior to the filing of
4. 4.Whether petitioner was obliged to pay the estate of Josefa Jeceil the case, was suffering from nasopharyngeal cancer from which he died in
the amount of her money market placement.12 1984. Whereas Josefa Jeceil died from various heart ailments in 1987,
almost five years since the case was filed. No causal relation whatsoever was
Petitioners Submissions established between the health of the respondents and the filing of the
First, BPI Investments submits that the summary of the money market case.18 The award of damages in favor of the respondent corporation was
placements and the checks issued to D.G. Carreon are sufficient to show that also without basis. There was no proof adduced that the credit standing of
one renewal or roll over of the money market placement dated November the respondent corporation was affected by the filing of the case. There was
15, 1979, for a period of thirty-two days gave rise to two placements no proof of bad faith or malice on the part of BPI Investments. What
maturing on two dates, that is, December 12, 1979 and December 17, happened was an honest mistake.19
1979.13 Fifth, the order of the Court of Appeals for BPI Investments to pay the
After several roll overs and withdrawals by D.G. Carreon, BPI money market placement of Josefa Jeceil was also without basis. The
Investments discovered that respondent corporation has overpaid amount of P73,857.57 was placed and deposited by BPI Investments with
P410,937.09 since the December 12, 1979 placement was not funded. BPI the sheriff of the Court of First Instance of Rizal in compliance with the order
Investments stressed that in a money market transaction an official receipt of the court. Respondent Jeceil knew of this fact but she failed to withdraw
must support maturing placements. The December 12, 1979 placement was the amount in the custody of the trial court.20
unsupported by any fund.14 Respondents Position
Second, a mistake caused the overpayment in the posting of the Respondents submit that the issues raised are factual, hence, not
maturity date of 12-12 instead of 12-17. The mistake in the posting of reviewable in this case.
Only questions of law, distinctly set forth, may be raised in a petition for As to the order to pay the long overdue money market placement of the
review on certiorari, subject to clearly settled exceptions in case law. The late Josefa Jeceil, petitioners contention that respondent failed to withdraw
case at bar does not fall within any of the exceptions.21 the amount deposited with the sheriff is not correct. First, the deposit does
BPI Investments was guilty of bad faith, malice and gross negligence in not amount to payment; indeed, consignation was not proper. Josefa Jeceil
the management of respondents money market placements. According to had no right to withdraw such deposit because of the pending litigation. As
respondents, this is not a mere case of misreading 12-17 as 12-12. The a consequence, the Court of Appeals directed the petitioner to pay the
sloppy accounting and recording of the ledger was a clear case of gross matured money market placement of the late Josefa Jeceil. 26
negligence in the exercise of petitioners primary business of accepting The Courts Ruling
money market placements. BPI Investments was remiss in its duty to treat After a careful consideration of the facts and the evidence presented by
respondents money market placements with the highest degree of care, both parties, we consider the petition partly meritorious.
considering the fiduciary nature of their relationship.22 There are instances when the findings of fact of the trial court and/or
The Court of Appeals correctly ruled that petitioner abused its right in Court of Appeals may be reviewed by the Supreme Court, such as (1) when
executing the writ of attachment against respondents. Notwithstanding the the conclusion is a finding grounded entirely on speculation, surmises and
fact that petitioners claim amounted only up to P410,937.09, petitioner conjectures; (2) when the inference made is manifestly mistaken, absurd or
caused the levy on property of respondents valued at more than impossible; (3) where there is a grave abuse of discretion; (4) when the
P40,000,000.00, in a harsh, unjust, inhuman and oppressive manner. This judgment is based on a misapprehension of facts; (5) when the findings of
constitutes an abuse that justifies the award of damages to the respondents. fact are conflicting; (6) when the Court of Appeals, in making its findings,
Articles 19, 20 and 21 of the Civil Code constitute the legal basis for the went beyond the issues of the case and the same is contrary to the
award of damages to respondents.23 admissions of both appellant and appellee; (7) when the findings are
As to the alleged excessive award of moral and exemplary damages as contrary to those of the trial court; (8) when the findings of fact are
well as attorneys fees, respondents submit that the same is supported by conclusions without citation of specific evidence on which they are based;
proofs. As to the moral damages awarded to Daniel G. Carreon and Aurora (9) when the facts set forth in the petition as well as in the petitioners main
J. Carreon, both in the amount of P1,000,000.00, and to Josefa M. Jeceil in and reply briefs are not disputed by the respondents; and (10) the findings
the amount of P500,000.00, the awards are reasonable and supported by of fact of the Court of Appeals are premised on the supposed absence of
evidence. evidence and contradicted by the evidence on record.27
All the respondents are persons of high reputation in the community. In the case at bar, the Court of Appeals committed errors in the
Each of them suffered mental anguish, embarrassment and humiliation due apprehension of the facts of the case, hence, we review its findings of facts.
to the case filed by petitioner and two of them deteriorated in their health We find petitioner not guilty of gross negligence in the handling of the
and died during the pendency of the case. As to the compensatory damages money market placement of respondents. Gross negligence implies a want
awarded to the corporation, the same is proper. It was proved that D.G. or absence of or failure to exercise slight care or diligence, or the entire
Carreon is a reputable corporation with good credit standing in the business absence of care. It evinces a thoughtless disregard of consequences without
community and this reputation was damaged due to the malicious charges exerting any effort to avoid them.28
filed by petitioner.24 However, while petitioner BPI Investments may not be guilty of gross
As to the award of exemplary damages, the same is not excessive. It negligence, it failed to prove by clear and convincing evidence that D.G.
must be stressed that the amount of P1,000,000.00 was awarded to four Carreon indeed received money in excess of what was due them. The
respondents. The attorneys fees in the amount of P500,000.00 is not alleged payments in the complaint were admitted by plaintiff itself to be
excessive considering that the case dragged on from 1981 up to the present, withdrawals from validly issued commercial papers, duly verified and signed
over fifteen years.25 by at least two authorized high-ranking officers of BPI Investments. 29
The law on exemplary damages is found in Section 5, Chapter 3, Title placement of P109,238.75, with legal interest of twelve (12%) percent per
XVIII, Book IV of the Civil Code. These are imposed by way of example or annum from June 3, 1982, until fully paid; to pay the estate of Josefa M.
correction for the public good, in addition to moral, temperate, liquidated, Jeceil, the money market placement in the amount of P73,857.57, with legal
or compensatory damages. They are recoverable in criminal cases as part of interest at twelve (12%) percent per annum from maturity on July 12, 1982,
the civil liability when the crime was committed with one or more until fully paid. The petitioner may withdraw its deposit from the lower court
aggravating circumstances; in quasi-delicts, if the defendant acted with at its peril. BPI Investments is likewise ordered to pay temperate damages
gross negligence; and in contracts and quasi-contracts, if the defendant to the estate of the late Daniel G. Carreon in the amount of P300,000.00,
acted in a wanton, fraudulent, reckless, oppressive, or malevolent manner. 30 and to the estate of Aurora J. Carreon in the amount of P300,000.00, and to
BPI Investments did not act in a wanton, fraudulent, reckless, the estate of Josefa M. Jeceil in the amount of P150,000.00.
oppressive, or malevolent manner, when it asked for preliminary No costs.
attachment. It was just exercising a legal option. The sheriff of the issuing SO ORDERED.
court did the execution and the attachment. Hence, BPI Investments is not Davide, Jr. (C.J., Chairman), Puno, Kapunan and Ynares-Santiago,
to be blamed for the excessive and wrongful attachment. JJ., concur.
As to the finding of the appellate court that the filing of the case
aggravated and eventually caused the death of two of the respondents, we Judgment affirmed with modification.
agree with the petitioner that such correlation is bereft of basis and is far Note.The Supreme Court has the full discretionary power to take
fetched. cognizance of the petition filed directly to it if compelling reasons, or the
The award of moral damages and attorneys fees is also not in keeping nature and importance of the issues raised warrant. (Malonzo vs.
with existing jurisprudence. Moral damages may be awarded in a breach of Zamora, 311 SCRA 224 [1999])
contract when the defendant acted in bad faith, or was guilty of gross
negligence amounting to bad faith, or in wanton disregard of his contractual
obligation. Finally, with the elimination of award of moral damages, so must
the award of attorneys fees be deleted.31
There is no doubt, however, that the damages sustained by respondents
were due to petitioners fault or negligence, short of gross negligence.
Temperate or moderate damages may be recovered when the court finds
that some pecuniary loss has been suffered but its amount cannot, from the
nature of the case, be proved with certainty.32 The Court deems it prudent
to award reasonable temperate damages to respondents under the
circumstances.33
As to the claim for payment of the money market placement of Josefa
Jeceil, the trial court may release the deposited amount of P73,857.57 to
petitioner as the consignation was not proper or warranted.
The Fallo
IN VIEW WHEREOF, the decision of the Court of Appeals is hereby AFFIRMED
with MODIFICATION. The award of moral, compensatory and exemplary
damages and attorneys fees are deleted. BPI Investments is ordered to pay
to the estate of Daniel G. Carreon and Aurora J. Carreon the money market
VOL. 429, MAY 25, 2004 courts
153 to give force and effect thereto. Not being contrary to law,
morals, good customs, public order, or public policy, Section 8 of the
Philippine Communications Satellite Corporation vs. Globe Telecom, Inc.
Agreement which Philcomsat and Globe freely agreed upon has the
G.R. No. 147324. May 25, 2004.* force of law between them.
PHILIPPINE COMMUNICATIONS SATELLITE Same; Same; Same; Requisites; The concurrence of the
CORPORATION, petitioner, vs. GLOBE TELECOM, INC. following elements must be established.In order that Globe may
(formerly and Globe Mckay Cable and Radio Corporation), be exempt from non compliance with its obligation to pay rentals
respondents. under Section 8, the concurrence of the following elements must be
established: (1) the event must be independent of the human will;
G.R. No. 147334. May 25, 2004.* (2) the occurrence must render it impossible for the debtor to fulfill
GLOBE TELECOM, INC., petitioner, vs. PHILIPPINE the obligation in a normal manner; and (3) the obligor must be free
COMMUNICATION SATELLITE CORPORATION, respondent. of participation in, or aggravation of, the injury to the creditor.
Same; Same; Damages; Attorneys Fees; In cases where both
Civil Law; Contracts; Force Majeure; Article 1174 exempts an
parties have legitimate claims against each other, an award of
obligor from liability not only to events that are unforeseeable, but
attorneys fees would not be warranted.The award of attorneys
also to those which are foreseeable, but inevitable.Article 1174,
fees is the exception rather than the rule, and must be supported
which exempts an obligor from liability on account of fortuitous
by factual, legal and equitable justifications. In previously decided
events or force majeure, refers not only to events that are
cases, the Court awarded attorneys fees where a party acted in
unforeseeable, but also to those which are foreseeable, but
gross and evident bad faith in refusing to satisfy the other partys
inevitable: Art. 1174. Except in cases specified by the law, or when claims and compelled the former to litigate to protect his rights;
it is otherwise declared by stipulation, or when the nature of the
when the action filed is clearly unfounded, or where moral or
obligation requires the assumption of risk, no person shall be
exemplary damages are awarded. However, in cases where both
responsible for those events which, could not be foreseen, or which,
parties have legitimate claims against each other and no party
though foreseen were inevitable. A fortuitous event under Article
actually prevailed, such as in the present case where the claims of
1174 may either be an act of God, or natural occurrences such as
both parties were sustained in part, an award of attorneys fees
floods or typhoons, or an act of man, such as riots, strikes or wars.
would not be warranted.
Same; Same; Same; Terms and Conditions; Parties may
stipulate on terms and conditions as they may see fit, and these have PETITION for review on certiorari of a decision of the Court of
the force of law between them.Under Article 1306 of the Civil
Appeals.
Code, parties to a contract may establish such stipulations, clauses,
terms and conditions as they may deem fit, as long as the same do The facts are stated in the opinion of the Court.
not run counter to the law, morals, good customs, public order or Rillorga, Africa, De Ocampo and Africa for Phil.
public policy. Article 1159 of the Civil Code also provides that Communications Satellite Corp.
[o]bligations arising from contracts have the force of law between
Salalima and Castelo for Globe Telecom, Inc.
the contracting parties and should be complied with in good faith.
Courts cannot stipulate for the parties nor amend their agreement
TINGA, J.:
where the same does not contravene law, morals, good customs,
public order or public policy, for to do so would be to alter the real
intent of the parties, and would run contrary to the function of the
Before the Court are two Petitions for Review assailing Subsequently, Philcomsat installed and established the earth
the Decision of the Court of Appeals, dated 27 February 2001, station at Cubi Point and the USDCA made use of the same.
in CA-G.R. CV No. 63619.1 On 16 September 1991, the Senate passed and adopted Senate
The facts of the case are undisputed. Resolution No. 141, expressing its decision not to concur in the
For several years prior to 1991, Globe Mackay Cable and Radio ratification of the Treaty of Friendship, Cooperation and Security
Corporation, now Globe Telecom, Inc. (Globe), had been engaged in and its Supplementary Agreements that was supposed to extend
the coordination of the provision of various communication the term of the use by the US of Subic Naval Base, among
facilities for the military bases of the United States of America (US) others.5 The last two paragraphs of the Resolution state:
in Clark Air Base, Angeles, Pampanga and Subic Naval Base in FINDING that the Treaty constitutes a defective framework for
Cubi Point, Zambales. The said communication facilities were the continuing relationship between the two countries in the spirit
installed and configured for the exclusive use of the US Defense of friendship, cooperation and sovereign equality: Now, therefore,
Communications Agency (USDCA), and for security reasons, were be it
operated only by its personnel or those of American companies Resolved by the Senate, as it is hereby resolved, To express its
contracted by it to operate said facilities. The USDCA contracted decision not to concur in the ratification of the Treaty of
with said American companies, and the latter, in turn, contracted Friendship, Cooperation and Security and its Supplementary
with Globe for the use of the communication facilities. Globe, on Agreements, at the same time reaffirming its desire to continue
the other hand, contracted with local service providers such as the friendly relations with the government and people of the United
Philippine Communications Satellite Corporation (Philcomsat) for States of America.6
the provision of the communication facilities.
On 07 May 1991, Philcomsat and Globe entered into an On 31 December 1991, the Philippine Government sent a Note
Agreement whereby Philcomsat obligated itself to establish, Verbale to the US Government through the US Embassy, notifying
operate and provide an IBS Standard B earth station (earth it of the Philippines termination of the RP-US Military Bases
station) within Cubi Point for the exclusive use of the Agreement. The Note Verbale stated that since the RP-US Military
USDCA.2 The term of the contract was for 60 months, or five (5) Bases Agreement, as amended, shall terminate on 31 December
years.3 In turn, Globe promised to pay Philcomsat monthly rentals 1992, the withdrawal of all US military forces from Subic Naval
for each leased circuit involved.4 Base should be completed by said date.
At the time of the execution of the Agreement, both parties In a letter dated 06 August 1992, Globe notified Philcomsat of
knew that the Military Bases Agreement between the Republic of its intention to discontinue the use of the earth station effective 08
the Philippines and the US (RP-US Military Bases Agreement), November 1992 in view of the withdrawal of US military personnel
which was the basis for the occupancy of the Clark Air Base and from Subic Naval Base after the termination of the RP-US Military
Subic Naval Base in Cubi Point, was to expire in 1991. Under Bases Agreement. Globe invoked as basis for the letter of
Section 25, Article XVIII of the 1987 Constitution, foreign military termination Section 8 (Default) of the Agreement, which provides:
bases, troops or facilities, which include those located at the US Neither party shall be held liable or deemed to be in default for any
Naval Facility in Cubi Point, shall not be allowed in the Philippines failure to perform its obligation under this Agreement if such
unless a new treaty is duly concurred in by the Senate and ratified failure results directly or indirectly from force majeure or
by a majority of the votes cast by the people in a national fortuitous event. Either party is thus precluded from performing
referendum when the Congress so requires, and such new treaty is its obligation until such force majeure or fortuitous event shall
recognized as such by the US Government. terminate. For the purpose of this paragraph, force majeure shall
mean circumstances beyond the control of the party involved
including, but not limited to, any law, order, regulation, direction constituted force majeure under the Agreement. Globe explained
or request of the Government of the Philippines, strikes or other that the occurrence of said events exempted it from paying rentals
labor difficulties, insurrection riots, national emergencies, war, for the remaining period of the Agreement.
acts of public enemies, fire, floods, typhoons or other catastrophies On 05 January 1999, the trial court rendered its Decision,the
or acts of God. Philcomsat sent a reply letter dated 10 August 1992 dispositive portion of which reads:
to Globe, stating that we expect [Globe] to know its commitment
to pay the stipulated rentals for the remaining terms of the WHEREFORE, premises considered, judgment is hereby
Agreement even after [Globe] shall have discontinue[d] the use of rendered as follows:
the earth station after November 08, 1992.7 Philcomsat referred
to Section 7 of the Agreement, stating as follows: 1. 1.Ordering the defendant to pay the plaintiff the amount
of Ninety Two Thousand Two Hundred Thirty Eight US
7. DISCONTINUANCE OF SERVICE Dollars (US$92,238.00) or its equivalent in Philippine
Should [Globe] decide to discontinue with the use of the earth Currency (computed at the exchange rate prevailing at
station after it has been put into operation, a written notice shall the time of compliance or payment) representing rentals
be served to PHILCOMSAT at least sixty (60) days prior to the for the month of December 1992 with interest thereon at
expected date of termination. Notwithstanding the non-use of the the legal rate of twelve percent (12%) per annum starting
earth station, [Globe] shall continue to pay PHILCOMSAT for the December 1992 until the amount is fully paid;
rental of the actual number of T1 circuits in use, but in no case 2. 2.Ordering the defendant to pay the plaintiff the amount
shall be less than the first two (2) Tl circuits, for the remaining life of Three Hundred Thousand (P300,000.00) Pesos as and
of the agreement. However, should PHILCOMSAT make use or sell for attorneys fees;
the earth station subject to this agreement, the obligation of 3. 3.Ordering the DISMISSAL of defendants counterclaim
[Globe] to pay the rental for the remaining life of the agreement for lack of merit; and
shall be at such monthly rate as may be agreed upon by the 4. 4.With costs against the defendant.
parties.8

After the US military forces left Subic Naval Base, Philcomsat sent SO ORDERED.9
Globe a letter dated 24 November 1993 demanding payment of its
Both parties appealed the trial courts Decision to the Court of
outstanding obligations under the Agreement amounting to
Appeals.
US$4,910,136.00 plus interest and attorneys fees. However, Globe
Philcomsat claimed that the trial court erred in ruling that: (1)
refused to heed Philcomsats demand.
the non-ratification by the Senate of the Treaty of Friendship,
On 27 January 1995, Philcomsat filed with the Regional Trial
Cooperation and Security and its Supplementary Agreements
Court of Makati a Complaint against Globe, praying that the latter
constitutes force majeure which exempts Globe from complying
be ordered to pay liquidated damages under the Agreement, with
with its obligations under the Agreement; (2) Globe is not liable to
legal interest, exemplary damages, attorneys fees and costs of suit.
pay the rentals for the remainder of the term of the Agreement;
The case was raffled to Branch 59 of said court.
and (3) Globe is not liable to Philcomsat for exemplary damages.
Globe filed an Answer to the Complaint, insisting that it was
Globe, on the other hand, contended that the RTC erred in
constrained to end the Agreement due to the termination of the RP-
holding it liable for payment of rent of the earth station for
US Military Bases Agreement and the non-ratification by the
December 1992 and of attorneys fees. It explained that it
Senate of the Treaty of Friendship and Cooperation, which events
terminated Philcomsats services on 08 November 1992; hence, it TELECOM FROM COMPLYING WITH ITS
had no reason to pay for rentals beyond that date. OBLIGATIONS UNDER THE SUBJECT AGREEMENT.
On 27 February 2001, the Court of Appeals promulgated 2. B.THE HONORABLE COURT OF APPEALS ERRED IN
its Decision dismissing Philcomsats appeal for lack of merit and RULING THAT GLOBE TELECOM IS NOT LIABLE TO
affirming the trial courts finding that certain events PHILCOMSAT FOR RENTALS FOR THE REMAINING
constituting force majeure under Section 8 the Agreement occurred TERM OF THE AGREEMENT, DESPITE THE CLEAR
and justified the non-payment by Globe of rentals for the TENOR OF SECTION 7 OF THE AGREEMENT.
remainder of the term of the Agreement. The appellate court ruled
that the non-ratification by the Senate of the Treaty of Friendship, 1. C.THE HONORABLE COURT OF APPEALS ERRED IN
Cooperation and Security, and its Supplementary Agreements, and DELETING THE TRIAL COURTS AWARD OF
the termination by the Philippine Government of the RP-US ATTORNEYS FEES IN FAVOR OF PHILCOMSAT.
Military Bases Agreement effective 31 December 1991 as stated in 2. D.THE HONORABLE COURT OF APPEALS ERRED IN
the Philippine Governments Note Verbale to the US Government, RULING THAT GLOBE TELECOM IS NOT LIABLE TO
are acts, directions, or requests of the Government of the PHILCOMSAT FOR EXEMPLARY DAMAGES.12
Philippines which constitute force majeure. In addition, there were
circumstances beyond the control of the parties, such as the Philcomsat argues that the termination of the RP-US Military
issuance of a formal order by Cdr. Walter Corliss of the US Navy, Bases Agreement cannot be considered a fortuitous event because
the issuance of the letter notification from ATT and the complete the happening thereof was foreseeable. Although the Agreement
withdrawal of all US military forces and personnel from Cubi was freely entered into by both parties, Section 8 should be deemed
Point, which prevented further use of the earth station under the ineffective because it is contrary to Article 1174 of the Civil Code.
Agreement. Philcomsat posits the view that the validity of the parties
However, the Court of Appeals ruled that although Globe definition of force majeure in Section 8 of the Agreement as
sought to terminate Philcomsats services by 08 November 1992, it circumstances beyond the control of the party involved including,
is still liable to pay rentals for the December 1992, amounting to but not limited to, any law, order, regulation, direction or request
US$92,238.00 plus interest, considering that the US military of the Government of the Philippines, strikes or other labor
forces and personnel completely withdrew from Cubi Point only on difficulties, insurrection riots, national emergencies, war, acts of
31 December 1992.10 public enemies, fire, floods, typhoons or other catastrophies or acts
Both parties filed their respective Petitions for Review assailing of God, should be deemed subject to Article 1174 which defines
the Decision of the Court of Appeals. fortuitous events as events which could not be foreseen, or which,
In G.R. No. 147324,11 petitioner Philcomsat raises the following though foreseen, were inevitable.13
assignments of error: Philcomsat further claims that the Court of Appeals erred in
holding that Globe is not liable to pay for the rental of the earth
1. A.THE HONORABLE COURT OF APPEALS ERRED IN station for the entire term of the Agreement because it runs
ADOPTING A DEFINITION OF FORCE counter to what was plainly stipulated by the parties in Section 7
MAJEURE DIFFERENT FROM WHAT ITS LEGAL thereof. Moreover, said ruling is inconsistent with the appellate
DEFINITION FOUND IN ARTICLE 1174 OF THE courts pronouncement that Globe is liable to pay rentals for
CIVIL CODE, PROVIDES, SO AS TO EXEMPT GLOBE December 1992 even though it terminated Philcomsats services
effective 08 November 1992, because the US military and
personnel completely withdrew from Cubi Point only in December The above-mentioned monthly lease of circuits become due and
1992. Philcomsat points out that it was Globe which proposed the payable within fifteen (15) days from service establishment date or
five-year term of the Agreement, and that the other provisions of availment of the service whichever comes earlier and within the
the Agreement, such as Section 4.114 thereof, evince the intent of fifteenth day of each month thereafter. Philcomsats services were
Globe to be bound to pay rentals for the entire five-year term.15 actually terminated on 08 November 1992.20
Philcomsat also maintains that contrary to the appellate courts
findings, it is entitled to attorneys fees and exemplary damages. 16 In its Comment, Philcomsat claims that Globes petition should
In its Comment to Philcomsats Petition, Globe asserts that be dismissed as it raises a factual issue which is not cognizable by
Section 8 of the Agreement is not contrary to Article 1174 of the the Court in a petition for review on certiorari.21
Civil Code because said provision does not prohibit parties to a On 15 August 2001, the Court issued a Resolution giving due
contract from providing for other instances when they would be course to Philcomsats Petition in G.R. No. 147324 and required
exempt from fulfilling their contractual obligations. Globe also the parties to submit their respective memoranda.22
claims that the termination of the RP-US Military Bases Similarly, on 20 August 2001, the Court issued
Agreement constitutes force majeure and exempts it from a Resolution giving due course to the Petition filed by Globe in G.R.
complying with its obligations under the Agreement.17 On the issue No. 147334 and required both parties to submit their
of the propriety of awarding attorneys fees and exemplary memoranda.23
damages to Philcomsat, Globe maintains that Philcomsat is not Philcomsat and Globe thereafter filed their
entitled thereto because in refusing to pay rentals for the respective Consolidated Memoranda in the two cases, reiterating
remainder of the term of the Agreement, Globe only acted in their arguments in their respective petitions.
accordance with its rights.18 The Court is tasked to resolve the following issues: (1) whether
In G.R. No. 147334,19 Globe, the petitioner therein, contends the termination of the RP-US Military Bases Agreement, the
that the Court of Appeals erred in finding it liable for the amount nonratification of the Treaty of Friendship, Cooperation and
of US$92,238.00, representing rentals for December 1992, since Security, and the consequent withdrawal of US military forces and
tary Base Agreement, GMCR [now Globe] shall pay PHILCOMSAT personnel from Cubi Point constitute force majeure which would
the following rates exclusive of space segment charges: exempt Globe from complying with its obligation to pay rentals
under its Agreement with Philcomsat; (2) whether Globe is liable
1. a)First two (2) T-1 circuits at US$ 46,119 per circuit per to pay rentals under the Agreement for the month of December
month; 1992; and (3) whether Philcomsat is entitled to attorneys fees and
2. b)Third and fourth T-1 circuits at US$ 30,333.00 per circuit exemplary damages.
per month; No reversible error was committed by the Court of Appeals in
3. c)Extension of the first two (2) T-1 circuits in (a) above, issuing the assailed Decision; hence the petitions are denied.
starting on the 61st month, at US$ 40,406.00 per circuit There is no merit in Philcomsats argument that Section 8 of
per month; the Agreement cannot be given effect because the enumeration of
4. d)Extension of the third and fourth circuits in (b) above, events constituting force majeure therein unduly expands the
starting on the 61st month, at US$ 22,200.00 per circuit concept of a fortuitous event under Article 1174 of the Civil Code
per month; and is therefore invalid.
In support of its position, Philcomsat contends that under
Article 1174 of the Civil Code, an event must be unforeseen in order
to exempt a party to a contract from complying with its obligations
therein. It insists that since the expiration of the RP-US Military enumeration that runs contrary to, or expands, the concept of a
Bases Agreement, the non-ratification of the Treaty of Friendship, fortuitous event under Article 1174.
Cooperation and Security and the withdrawal of US military forces Furthermore, under Article 130626 of the Civil Code, parties to
and personnel from Cubi Point were not unforeseeable, but were a contract may establish such stipulations, clauses, terms and
possibilities known to it and Globe at the time they entered into conditions as they may deem fit, as long as the same do not run
the Agreement, such events cannot exempt Globe from performing counter to the law, morals, good customs, public order or public
its obligation of paying rentals for the entire five-year term thereof. policy.27
However, Article 1174, which exempts an obligor from liability Article 1159 of the Civil Code also provides that [o]bligations
on account of fortuitous events or force majeure, refers not only to arising from contracts have the force of law between the
events that are unforeseeable, but also to those which are contracting parties and should be complied with in good
foreseeable, but inevitable: faith.28 Courts cannot stipulate for the parties nor amend their
Art. 1174. Except in cases specified by the law, or when it is agreement where the same does not contravene law, morals, good
otherwise declared by stipulation, or when the nature of the customs, public order or public policy, for to do so would be to alter
obligation requires the assumption of risk, no person shall be the real intent of the parties, and would run contrary to the
responsible for those events which, could not be foreseen, or which, function of the courts to give force and effect thereto.29
though foreseen were inevitable. Not being contrary to law, morals, good customs, public order,
or public policy, Section 8 of the Agreement which Philcomsat and
A fortuitous event under Article 1174 may either be an act of God, Globe freely agreed upon has the force of law between them. 30
or natural occurrences such as floods or typhoons, 24 or an act of In order that Globe may be exempt from non-compliance with
man, such as riots, strikes or wars.25 its obligation to pay rentals under Section 8, the concurrence of the
Philcomsat and Globe agreed in Section 8 of the Agreement that following elements must be established: (1) the event must be
the following events shall be deemed events constituting force independent of the human will; (2) the occurrence must render it
majeure: impossible for the debtor to fulfill the obligation in a normal
manner; and (3) the obligor must be free of participation in, or
1. 1.Any law, order, regulation, direction or request of the aggravation of, the injury to the creditor.31
Philippine Government; The Court agrees with the Court of Appeals and the trial court
2. 2.Strikes or other labor difficulties; that the abovementioned requisites are present in the instant case.
3. 3.Insurrection; Philcomsat and Globe had no control over the non-renewal of the
4. 4.Riots; term of the RP-US Military Bases Agreement when the same
5. 5.National emergencies; expired in 1991, because the prerogative to ratify the treaty
6. 6.War; extending the life thereof belonged to the Senate. Neither did the
7. 7.Acts of public enemies; parties have control over the subsequent withdrawal of the US
8. 8.Fire, floods, typhoons or other catastrophies or acts of military forces and personnel from Cubi Point in December 1992:
God; Obviously the non-ratification by the Senate of the RP-US Military
9. 9.Other circumstances beyond the control of the parties. Bases Agreement (and its Supplemental Agreements) under its
Resolution No. 141. (Exhibit 2) on September 16, 1991 is beyond
Clearly, the foregoing are either unforeseeable, or foreseeable but the control of the parties. This resolution was followed by the
beyond the control of the parties. There is nothing in the sending on December 31, 1991 o[f] a Note Verbale(Exhibit 3) by
the Philippine Government to the US Government notifying the The aforementioned events made impossible the continuation of
latter of the formers termination of the RP-US Military Bases the Agreement until the end of its five-year term without fault on
Agreement (as amended) on 31 December 1992 and that the part of either party. The Court of Appeals was thus correct in
accordingly, the withdrawal of all U.S. military forces from Subic ruling that the happening of such fortuitous events rendered Globe
Naval Base should be completed by said date. Subsequently, exempt from payment of rentals for the remainder of the term of
defendant [Globe] received a formal order from Cdr. Walter F. the Agreement.
Corliss II Commander USN dated July 31, 1992 and a notification Moreover, it would be unjust to require Globe to continue
from ATT dated July 29, 1992 to terminate the provision of T1s paying rentals even though Philcomsat cannot be compelled to
services (via an IBS Standard B Earth Station) effective November perform its corresponding obligation under the Agreement. As
08, 1992. Plaintiff [Philcomsat] was furnished with copies of the noted by the appellate court:
said order and letter by the defendant on August 06, 1992. We also point out the sheer inequity of PHILCOMSATs position.
Resolution No. 141 of the Philippine Senate and the Note PHILCOMSAT would like to charge GLOBE rentals for the
Verbale of the Philippine Government to the US Government are balance of the lease term without there being any corresponding
acts, direction or request of the Government of the Philippines and telecommunications service subject of the lease. It will be grossly
circumstances beyond the control of the defendant. The formal unfair and iniquitous to hold GLOBE liable for lease charges for a
order from Cdr. Walter Corliss of the USN, the letter notification service that was not and could not have been rendered due to an
from ATT and the complete withdrawal of all the military forces act of the government which was clearly beyond GLOBEs control.
and personnel from Cubi Point in the year-end 1992 are also acts The binding effect of a contract on both parties is based on the
and circumstances beyond the control of the defendant. principle that the obligations arising from contracts have the force
Considering the foregoing, the Court finds and so holds that the of law between the contracting parties, and there must be
afore-narrated circumstances constitute force majeure or mutuality between them based essentially on their equality under
fortuitous event(s) as defined under paragraph 8 of the Agreement. which it is repugnant to have one party bound by the contract while
leaving the other party free therefrom (Allied Banking Corporation
... v. Court of Appeals, 284 SCRA 357). . . .33
From the foregoing, the Court finds that the defendant is With respect to the issue of whether Globe is liable for payment of
exempted from paying the rentals for the facility for the remaining rentals for the month of December 1992, the Court likewise affirms
term of the contract. the appellate courts ruling that Globe should pay the same.
As a consequence of the termination of the RP-US Military Although Globe alleged that it terminated the Agreement with
Bases Agreement (as amended) the continued stay of all US Philcomsat effective 08 November 1992 pursuant to the formal
Military forces and personnel from Subic Naval Base would no order issued by Cdr. Corliss of the US Navy, the date when they
longer be allowed, hence, plaintiff would no longer be in any actually ceased using the earth station subject of the Agreement
position to render the service it was obligated under the was not established during the trial.34 However, the trial court
Agreement. To put it blantly (sic), since the US military forces and found that the US military forces and personnel completely
personnel left or withdrew from Cubi Point in the year end withdrew from Cubi Point only on 31 December 1992.35 Thus, until
December 1992, there was no longer any necessity for the plaintiff that date, the USDCA had control over the earth station and had
to continue maintaining the IBS facility. . . .32(Emphasis in the the option of using the same. Furthermore, Philcomsat could not
original.) have removed or rendered ineffective said communication facility
until after 31 December 1992 because Cubi Point was accessible
only to US naval personnel up to that time. Hence, the Court of
Appeals did not err when it affirmed the trial courts ruling that
Globe is liable for payment of rentals until December 1992.
Neither did the appellate court commit any error in holding
that Philcomsat is not entitled to attorneys fees and exemplary
damages.
The award of attorneys fees is the exception rather than the
rule, and must be supported by factual, legal and equitable
justifications.36 In previously decided cases, the Court awarded
attorneys fees where a party acted in gross and evident bad faith
in refusing to satisfy the other partys claims and compelled the
former to litigate to protect his rights;37 when the action filed is
clearly unfounded,38 or where moral or exemplary damages are
awarded.39 However, in cases where both parties have legitimate
claims against each other and no party actually prevailed, such as
in the present case where the claims of both parties were sustained
in part, an award of attorneys fees would not be warranted. 40
Exemplary damages may be awarded in cases involving
contracts or quasi-contracts, if the erring party acted in a wanton,
fraudulent, reckless, oppressive or malevolent manner. 41 In the
present case, it was not shown that Globe acted wantonly or
oppressively in not heeding Philcomsats demands for payment of
rentals. It was established during the trial of the case before the VOL. 262, SEPTEMBER 20, 1996 245
trial court that Globe had valid grounds for refusing to comply with
Development Bank of the Philippines vs. Court of Appeals
its contractual obligations after 1992.
WHEREFORE, the Petitions are DENIED for lack of merit. G.R. No. 118180. September 20, 1996.*
The assailed Decision of the Court of Appeals in CA-G.R. CV No. DEVELOPMENT BANK OF THE PHILIPPINES,
63619 is AFFIRMED. petitioner, vs. COURT OF APPEALS, Sps. NORMY D. CARPIO
SO ORDERED. and CARMEN ORQUISA; Sps. ROLANDO D. CARPIO and
Quisumbing (Actg. Chairman), Austria- RAFAELA VILLANUEVA; Sps. ELISEO D. CARPIO and
Martinez and Callejo, Sr., JJ., concur. ANUNCIACION del ROSARIO; LUZ C. REYES, MARIO C.
Puno (Chairman), J., On Official Leave. REYES, JULIET REYES-RUBIN, respondents.

Petition denied, assailed decision affirmed. Contracts; Obligations; In conditional obligations, the
acquisition of rights and the extinguishment or loss of those already
acquired depend upon the happening of the event which constitutes
the condition.In conditional obligations, the acquisition of
rights, as well as the extinguishment or loss of those already
acquired, shall depend upon the happening of the event which the decision. The text itself must expressly state the reason why
constitutes the condition. attorneys fees are being awarded. The court, after reading through
Same; Same; Agrarian Reform; Constitutional Law; Non- the text of the appealed decision, finds the same bereft of any
Impairment Clause; Neither Sec. 6 of the Comprehensive Agrarian findings of fact and law to justify the award of attorneys fees. The
Reform Law (R.A. 6657) nor Sec. 1 of E.O. 407 was intended to matter of such fees was touched but once and appears only in the
impair the obligation of contracts earlier concluded.We reject dispositive portion of the decision. Simply put, the text of the
petitioners contention as we ruleas the trial court and CA have decision did not state the reason why attorneys fees are being
correctly ruledthat neither Sec. 6 of Rep. Act 6657 nor Sec. 1 of awarded, and for this reason, the Court finds it necessary to
E.O. 407 was intended to impair the obligation of contract disallow the same for being conjectural.
petitioner had much earlier concluded with private respondents. Same; Egregious error in the interpretation of a provision of a
Same; Same; Same; Same; Same; Due Process; Statutory law is not equivalent to gross and evident bad faith.While DBP
Construction; The CARL and E.O. 407 were not intended to take committed egregious error in interpreting Sec. 6 of RA 6657, the
away property without due process of law nor were they intended to same is not equivalent to gross and evident bad faith when it
impair the obligation of contracts; Laws cannot have retroactive refused to execute the deed of sale in favor of private respondents.
effect unless there is an express provision in them to that effect.
The CARL (Rep. Act 6657) was not intended to take away property PETITION for review on certiorari of a decision of the Court of
without due process of law. Nor is it intended to impair the Appeals.
obligation of contracts. In the same manner must E.O. 407 be
regarded. It was enacted two (2) months after private respondents The facts are stated in the opinion of the Court.
had legally fulfilled the condition in the contract of conditional sale Office of the Legal Counsel for petitioner.
by the payment of all installments on their due dates. These laws Restituto G. Cudiamat for private respondent.
cannot have retroactive effect unless there is an express provision
in them to that effect. PADILLA, J.:
Attorneys Fees; While judicial discretion in the award of
attorneys fees is not entirely left out, the same, as a rule, must have This is a petition for review on certiorari under Rule 45 of the Rules
a factual, legal or equitable justificationthe matter cannot and of Court which seeks to set aside the decision1 of the Court of
should not be left to speculation and conjecture.The award of Appeals (CA) dated 28 February 1994 in CA-G.R. CV No. 37158, as
attorneys fees under Article 2208 of the Civil Code is more of an well as the resolution dated 11 August 1994 denying petitioners
exception to the general rule that it is not sound policy to place a motion for reconsideration.
penalty on the right to litigate. While judicial discretion in the The facts are undisputed:
award of attorneys fees is not entirely left out, the same, as a rule, Private respondents were the original owners of a parcel of
must have a factual, legal or equitable justification. The matter agricultural land covered by TCT No. T-1432, situated in Barrio
cannot and should not be left to speculation and conjecture. Capucao, Ozamis City, with an area of 113,695 square meters,
Same; The matter of attorneys fees cannot be touched once and more or less.
only in the dispositive portion of the decisionthe text itself must
expressly state the reason why attorneys fees are being awarded.
As aptly stated in the Mirasol case: x x x The matter of attorneys 1Entitled Spouses Normy D. Carpio and Carmen Orquisa vs.
fees cannot be touched once and only in the dispositive portion of Development Bank of the Philippines penned by Justice Antonio
M. Martinez concurred in by Justices Cancio C. Garcia and Ramon Petitioner then informed private respondents that the
Mabutas, Jr. prestation to execute and deliver a deed of conveyance in their
favor had become legally impossible in view of Sec. 6 of Rep. Act
On 30 May 1977, private respondents mortgaged said land to 6657 (the Comprehensive Agrarian Reform Law or CARL)
petitioner. When private respondents defaulted on their obligation, approved 10 June 1988, and Sec. 1 of E.O. 407 issued 10 June 1990.
petitioner foreclosed the mortgage on the land and emerged as sole Aggrieved, private respondents filed a complaint for specific
bidder in the ensuing auction sale. Consequently, Transfer performance with damages against petitioner before the Regional
Certificate of Title No. T-10913 was eventually issued in Trial Court of Ozamis City, Branch XV. During the pre-trial, the
petitioners name. trial court narrowed down the issue to whether or not Sec. 6 of the
On 6 April 1984, petitioner and private respondents entered CARL (Rep. Act 6657) had rendered legally impossible compliance
into a Deed of Conditional Sale wherein petitioner agreed to by petitioner with its obligation to execute a deed of conveyance of
reconvey the foreclosed property to private respondents. the subject land in favor of private respondents. The trial court
The pertinent stipulations of the Deed provided that: ordered both parties to file their separate memorandum and
WHEREAS, the VENDOR acquired a parcel of land in an auction deemed the case submitted for decision thereafter.
sale by the City Sheriff of Ozamiz City, pursuant to Act 3135, as On 30 January 1992, the trial court rendered judgment, the
amended, and subject to the redemption period pursuant to CA dispositive part of which reads:
141, described as follows: WHEREFORE, judgment is rendered ordering defendant to
xxx xxx xxx execute and deliver unto plaintiffs a deed of final sale of the land
WHEREAS, the VENDEES offered to repurchase and the subject of their deed of conditional saleLot 5259-A, to pay
VENDOR agreed to sell the above-described property, subject to plaintiffs P10,000.00 as nominal damages, P5,000.00 as attorneys
the terms and stipulations as hereinafter stipulated, for the sum of fees, P3,000.00 as litis expenses and costs.3
SEVENTY THREE THOUSAND SEVEN HUNDRED ONLY
(P73,700.00), with a down payment of P8,900.00 and the balance The trial court held that petitioner interpreted the fourth
of P64,800.00 shall be payable in six (6) years on equal quarterly paragraph of Sec. 6, Rep. Act 6657 literally in conjunction with Sec.
amortization plan at 18% interest per annum. The first quarterly 1 of E.O. 407.
amortization of P4,470.36 shall be payable three months from the The fourth paragraph of Sec. 6, Rep. Act 6657 states that:
date of the execution of the documents and all subsequent Upon the effectivity of this Act, any sale, disposition, lease,
amortization shall be due and payable every quarter thereafter. management contract or transfer of possession of private lands
xxx xxx xxx executed by the original landowner in violation of this act shall be
That, upon completion of the payment herein stipulated and null and void; Provided, however, that those executed prior to this
agreed, the Vendor agrees to deliver to the Vendee/s(,) his heirs, act shall be valid only when registered with the Register of Deeds
administrators and assigns(,) a good and sufficient deed of after the effectivity of this Act. Thereafter, all Registers of Deeds
conveyance covering the property, subject matter of this deed of shall inform the DAR within 320 days of any transaction involving
conditional sale, in accordance with the provisions of law. (Exh. agricultural lands in excess of five hectares.
A, p. 5, Records)2 while Sec. 1 of E.O. 407 states that:
Sec. 1. All government instrumentalities but not limited to x x x
On 6 April 1990, upon completing the payment of the full financial institutions such as the DBP x x x shall immediately
repurchase price, private respondents demanded from petitioner execute deeds of transfer in favor of the Republic of the Philippines
the execution of a Deed of Conveyance in their favor. as represented by the Department of Agrarian Reform and
surrender to the latter department all landholdings suitable for It is likewise interesting to note that despite the mandate of
agriculture. Sec. 1, R.A. 6657, appellant continued to accept the payments made
by the appellee until it was fully paid on April 6, 1990. All that the
The court a quo noted that Sec. 6 of Rep. Act 6657, taken in its appellant has to do now is to execute the final deed of sale in favor
entirety, is a provision dealing primarily with retention limits in of the appellee. To follow the line of argument of the appellant
agricultural land allowed the landowner and his family and that would only result in an unconscionable injury to the appellee.
the fourth paragraph, which nullifies any sale x x x by Obligations arising from contracts have the force of law between
the original landowner in violation of the Act, does not cover the the contracting parties and should be complied with in good faith
sale by petitioner (not the original land owner) to private (Flavio Macasaet & Associate, Inc. vs. Commission on Audit, 173
respondents. SCRA 352).
On the other hand, according to the trial court, E.O. 407 took Going now to E.O. 407, We hold that the same can neither affect
effect on 10 June 1990. But private respondents completed appellants obligation under the deed of conditional sale. Under the
payment of the price for the property, object of the conditional sale, said law, appellant is required to transfer to the Republic of the
as early as 6 April 1990. Hence, with the fulfillment of the condition Philippines all lands foreclosed effective June 10, 1990. Under the
for the sale, the land covered thereby, was detached from the mass facts obtaining, the subject property has ceased to belong to the
of foreclosed properties held by DBP, and, therefore, fell beyond the mass of foreclosed property falling within the reach of said law. As
ambit or reach of E.O. 407. earlier explained, the property has already been sold to herein
Dissatisfied, petitioner appealed to the Court of Appeals (CA), appellees even before the said E.O. has been enacted. On this same
still insisting that its obligation to execute a Deed of Sale in favor reason, We therefore need not delve on the applicability of DBP
of private respondents had become a legal impossibility and that Circular No. 11.4
the non-impairment clause of the Constitution must yield to the
demands of police power. In the present petition for review on certiorari, petitioner still
On 28 February 1994, the CA rendered judgment dismissing insists on its position that Rep. Act 6657, E.O. 407 and DBP
petitioners appeal on the basis of the following disquisitions: Circular No. 11 rendered its obligation to execute a Deed of Sale to
It is a rule that if the obligation depends upon a suspensive private respondents a legal impossibility.5 Petitioner also
condition, the demandability as well as the acquisition or questions the award of attorneys fees, nominal damages, and costs
effectivity of the rights arising from the obligation is suspended in favor of private respondents, as not in accord with law and the
pending the happening or fulfillment of the fact or event which evidence.6
constitutes the condition. Once the event which constitutes the We rule in favor of private respondents.
condition is fulfilled resulting in the effectivity of the obligation, its In conditional obligations, the acquisition of rights, as well as
effects retroact to the moment when the essential elements which the extinguishment or loss of those already acquired, shall depend
gave birth to the obligation have taken place (8 Manresa, 5th Ed. upon the happening of the event which constitutes the condition. 7
Bk. 1, pa. 33). Applying this precept to the case, the full payment The deed of conditional sale between petitioner and private
by the appellee on April 6, 1990 retroacts to the time the contract respondents was executed on 6 April 1984. Private respondents
of conditional sale was executed on April 6, 1984. From that time, had religiously paid the agreed installments on the property until
all elements of the contract of sale were present. Consequently, the they completed payment on 6 April 1990. Petitioner, in
contract of sale was perfected. As such, the said sale does not come fact, allowed private respondents to fulfill the condition of effecting
under the coverage of R.A. 6657. full payment, and invoked Section 6 of Rep. Act 6657
only after private respondents, having fully paid the repurchase As to petitioners contention, however, that the CA erred in
price, demanded the execution of a Deed of Sale in their favor. affirming the trial courts decision awarding nominal damages, and
It will be noted that Rep. Act 6657 was enacted on 10 June 1988. attorneys fees to private respondents, we rule in favor of
Following petitioners argument in this case, its prestation to petitioner.
execute the deed of sale was rendered legally impossible by Section It appears that the core issue in this case, being a pure question
6 of said law. In other words, the deed of conditional sale was of law, did not reach the trial stage as the case was submitted for
extinguished by a supervening event, giving rise to an impossibility decision after pre-trial.
of performance. The award of attorneys fees under Article 2208 of the Civil
We reject petitioners contention as we ruleas the trial court Code is more of an exception to the general rule that it is not sound
and CA have correctly ruledthat neither Sec. 6 of Rep. Act 6657 policy to place a penalty on the right to litigate. While judicial
nor Sec. 1 of E.O. 407 was intended to impair the obligation of discretion in the award of attorneys fees is not entirely left out, the
contract petitioner had much earlier concluded with private same, as a rule, must have a factual, legal or equitable justification.
respondents. The matter cannot and should not be left to speculation and
More specifically, petitioner cannot invoke the last paragraph conjecture.9 As aptly stated in the Mirasol case:
of Sec. 6 of Rep. Act 6657 to set aside its obligations already x x x The matter of attorneys fees cannot be touched once and only
existing prior to its enactment. In the first place, said last in the dispositive portion of the decision. The text itself must
paragraph clearly deals with any sale, lease, management expressly state the reason why attorneys fees are being awarded.
contract or transfer or possession of private lands executed by The court, after reading through the text of the appealed decision,
the original landowner. The original owner in this case is not the finds the same bereft of any findings of fact and law to justify the
petitioner but the private respondents. Petitioner acquired the award of attorneys fees. The matter of such fees was touched but
land through foreclosure proceedings but agreed thereafter to once and appears only in the dispositive portion of the decision.
reconvey it to private respondents, albeit conditionally. Simply put, the text of the decision did not state the reason why
As earlier stated, Sec. 6 of Rep. Act 6657 in its entirety deals attorneys fees are being awarded, and for this reason, the Court
with retention limits allowed by law to small landowners. Since the finds it necessary to disallow the same for being conjectural.10
property here involved is more or less ten (10) hectares, it is then
within the jurisdiction of the Department of Agrarian Reform While DBP committed egregious error in interpreting Sec. 6 of RA
(CAR) to determine whether or not the property can be subjected 6657, the same is not equivalent to gross and evident bad faith
to agrarian reform. But this necessitates an entirely different when it refused to execute the deed of sale in favor of private
proceeding. respondents.
The CARL (Rep. Act 6657) was not intended to take away For the same reasons stated above, the award of nominal
property without due process of law. Nor is it intended to impair damages in the amount of P10,000.00 should also be deleted. The
the obligation of contracts. In the same manner must E.O. 407 be amount of P3,000.00 as litigation expenses and costs against
regarded. It was enacted two (2) months after private respondents petitioner must remain.
had legally fulfilled the condition in the contract of conditional sale WHEREFORE, premises considered, the petition is hereby
by the payment of all installments on their due dates. These laws DENIED, and the decision of the CA is hereby AFFIRMED, for lack
cannot have retroactive effect unless there is an express provision of any reversible error, with the MODIFICATION that attorneys
in them to that effect.8 fees and nominal damages awarded to private respondents are
hereby DELETED.
SO ORDERED.
Bellosillo, Vitug, Kapunan and Hermosisima, Jr.,
JJ., concur.

Petition denied, judgment affirmed with modification.


Notes.There is no ambiguity in Section 16(e) of Republic Act
No. 6657 to warrant an expanded construction of the term
deposit. (Land Bank of the Philippines vs. Court of Appeals, 249
SCRA 149 [1995]) The matter of attorneys fees cannot be touched
upon only in the dispositive portion of the decisionthe text itself
must state the reasons why attorneys fees are being awarded.
(Valiant Machinery and Metal Corporation vs. National Labor
Relations Commission,252 SCRA 369 [1996])

o0o

Das könnte Ihnen auch gefallen