COMPRESSIVE STRENGTH
C1-161 C1 - Arena - G'stand, Wall W15Ma, W16M Rabban 10-May-07 17-May-07 39.5 39.5 07-Jun-07 52.5 50.5 51.5
4-days=47.0,44.0,53.5,
C1-171 C1 - Arena - West Buttress, Footing WB1-J/2 Rabban 22-May-07 29-May-07 47.5 47.5 19-Jun-07 61.5 62.0 61.8 40.0, 41.5
5-days=47.5,42.0,52.0
--- do --- Rabban 22-May-07 29-May-07 43.5 43.5 19-Jun-07 50.8 58.5 54.7 43.5,46.0
7 days=52.547.0
--- do --- Rabban 22-May-07 29-May-07 48.0 48.0 19-Jun-07 53.5 62.5 58.0 51.5,48.0,48.0
14 days=55.0,54.0,58.0,
--- do --- Rabban 22-May-07 29-May-07 41.0 41.0 19-Jun-07 58.5 58.0 58.3 72.0,59.5
--- do --- Rabban 22-May-07 29-May-07 38.0 38.0 19-Jun-07 56.5 61.0 58.8
C1-175 C1 - Arena - G'stand, Bearing Wall F-G/16 Rabban 27-May-07 03-Jun-07 46.5 46.5 24-Jun-07
C1-178 C1 - Arena - G'stand, Bearing Wall W16Ma, W16M Rabban 31-May-07 07-Jun-07 52.5 52.5 28-Jun-07
C1-180 C1 - Arena - G'stand, Bearing Wall F-G/15-16 Rabban 04-Jun-07 11-Jun-07 55.0 55.0 02-Jul-07
C1 - Arena - G'stand, Stair Bearing Wall, WISF Wall, 1st-2nd Flr, 2nd-3rd
C1-184 Bearing Wall Flr, 2nd-3rd Flr Rabban 12-Jun-07 19-Jun-07 51.0 51.0 10-Jul-07
COMPRESSIVE STRENGTH
CHECKED BY:
Page 2 of 2