Beruflich Dokumente
Kultur Dokumente
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
DOCUMENT
No. :
S - 0 0 0 - 5 3 1 4 - 0 0 1
Sohar
User: JGMA
1 - Reviewed No Comments
Date: 18/07/2014
Y.J. YOO /
J.Y. KWON /
A.MAGPALI
K.S. CHOI
PREPARED
CHECKED
APPROVED
APPROVED
Page 1 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
REVISION HISTORY
Revision
Total Number
List of Updated/ Modified
Purpose
Number of Sheets
Sections (if any)
OWNER
2 1 6.0
2 1 14.2
SRIP-QT-JH-OH-CV-0473.
HOLD LIST
Page 2 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
TABLE OF CONTENTS
2.0 DEFINITIONS............................................................................................................................................ 5
5.0 UNITS........................................................................................................................................................ 7
Page 3 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
14.3 EQUIPMENT................................................................................................................................. 19
Page 4 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
1.0 INTRODUCTION
1.1 SCOPE
This specification covers the minimum requirements for the design, material, fabrication and installation
2.0 DEFINITIONS
For the purpose of this specification, the following definitions shall hold:
Term Definition
CONSULTANT : Private or Public entity that provides the Services to the OWNER
this project.
3.1 The work covered in this specification shall comply with all relevant governmental and local laws,
3.2 For subjects not covered by regulations, codes and standards or specifications, the design, material,
fabrication and erection shall be based on good economical engineering practice, subject to approval
by OWNER.
4.0 REFERENCES
The following specifications, codes (including applicable addenda) and standards shall constitute the
minimum requirements for this specification. The latest edition of codes, standards, etc., shall be used.
4.1 SPECIFICATIONS
Page 5 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
S-000-5330-001
Erection)
(2001)
BS EN 1997-2 (2007)
Testing
BS 4449 (2005) Specification for Steel for the reinforcement of concrete, weldable
BS 5896 (1980) Specification for high tensile steel wire and strand for the pre-
stressing of concrete
BS EN 15630-1 (2010) Steel for the reinforcement and pre-stressing of concrete. Test
Provisions
nd
AWS D1.1/D1.1M (2010) Structural Welding Code Steel (22 Edition)
ANSI/ASCE 7 (2010) Minimum Design Loads for Buildings and Other Structures
th
AISC 325 (2005) Manual of Steel Construction (Allowable Stress Design) 13
Edition
ASTM A6/A6M (2011) Standard Specification for General Requirements for Rolled
ASTM A252 (2010) Standard Specification for Welded and Seamless Steel Pipe
Piles
ASTM A416/A416M (2006) Standard Specification for Steel Strand, Uncoated Seven- Wire
ASTM A615/615M (2006) Standard Specification for Deformed and Plain Carbon Steel
ASTM A775/775M (2006) Standard Specification for Epoxy-coated Reinforcing Steel Bars
ASTM A857/A857M (2007) Standard Specification for Steel Sheet Piling, Cold Formed,
Light Gage
Page 6 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
ASTM D1143/D1143M (2007) Standard Test Methods for Deep Foundations Under Static
ASTM D3966 (2007) Standard Test Methods for Deep Foundations Under Lateral
Load
ASTM D4945 (2008) Standard Test Methods for High-Strain Dynamic Testing of Piles
ASTM D5882 (2007) Standard Test Methods for Low Strain Impact Integrity Testing
of Deep Foundations
PIP STS02360 (2008) Driven Piles Specification (PIP = Process Industry Practices)
4.5 In case of conflict between above-mentioned codes and standards and this specification,
5.0 UNITS
5.2 Pipe size measurements shall be to the ANSI (American National Standards Institute).
5.3 For simplification purposes, one (1) kg weight may be taken as equal to 10 N (0.010 kN).
Page 7 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
7.1 GENERAL
7.1.1 The main function of bearing piles is to transfer the loads on a foundation to deeper (soil) strata which
The foundation settlement/deformation is less than the allowable values of the foundation and
7.1.2 The design and testing of piles shall take into account both short-term and long-term behavior of the
pile foundation.
7.2.1 The type of piles with regard to material (steel, cast-in-situ or precast concrete) and method of
installation shall be as called for on design drawings and as recommended by approved piling
specialist.
7.2.2 The type of pile to be used is defined by type of loading, the soil conditions, such as drivability and
corrosivity of soil, possibility of tension stresses in the pile due to heave and also the site conditions,
7.2.3 The choice with regard to end bearing, friction, or partly friction and partly bearing type of piles shall be
determined in accordance with geotechnical data recommendations and shall be as specified by the
7.2.4 If more than one type of pile is suitable in any particular condition, then the choice shall be governed by
relative costs.
7.2.5 Whatever type of pile is used, it should have the necessary strength when installed to transfer the loads
7.2.6 Raked piles shall be avoided where possible and shall be provided to resist horizontal forces where the
7.2.7 Neutral earth resistance on pile caps, ground beams, etc., may be taken into account in assessing the
The minimum center-to-center spacing of piles shall be as follows, unless otherwise specified in the
For piles deriving their resistance from end bearing: not less than twice the least width or
Piles deriving their resistance from both end bearing and skin friction: Not less than three pile
diameters.
Page 8 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
8.1 GENERAL
All piling works shall be based on UBC Volume 2 (1997)-Structural Engineering Design Provisions or
8.2.2 The CONTRACTOR/SUB-CONTRACTOR is responsible for obtaining all information required for the
calculation of the pile reinforcement. Calculations shall incorporate the following load cases and
requirements:
Transport/fabrication of piles.
Additional load due to negative skin friction to be added to the design capacities for each pile.
Safety factor for pile capacity (including positive or negative skin friction) shall be:
Safety factor for lifting (in pile driving equipment) shall be 2.0 with pile tip on the ground and 1.4
All safety factors shall be in accordance with the latest applicable codes and regulations and
Page 9 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
8.3 MARKING
8.3.1 After a prefabricated concrete pile has been cast, the date of casting, reference number, sizes and
where appropriate, the pre-stressing force shall be clearly inscribed on a label near the top.
8.3.2 Lifting and support point shall be indicated on the shaft of the piles.
8.3.3 Each prefabricated concrete pile shall be marked at intervals of 200 mm along the top 5 m of its length
8.3.4 Test piles shall be marked at intervals of 200 mm over the full length.
8.3.5 Each prefabricated concrete pile shall receive a color marking on top. Piles with standard reinforcement
shall get a green mark, while piles with extra reinforcement shall be marked in purple.
8.4 HANDLING
8.4.1 The method and sequence of lifting, transporting from the factory to the construction site and storing of
piles shall be such that the piles are not damaged. Only the designed lifting and support points shall be
used.
During transport and storage, piles shall be stored on adequate supports located under the lifting points
of the piles.
8.4.2 CONTRACTOR has to prepare and submit handling procedures to OWNER or CONSULTANT for
8.4.3 OWNER or CONSULTANT shall inspect each pile when it is delivered on the construction site. Piles
which are damaged to such an extent that, in the opinion of OWNER or CONSULTANT, their structural
integrity is impaired or likely to be impaired during the driving, will be rejected by OWNER or
CONSULTANT.
8.5.1 Storage facilities for piles must be installed on site as a part of the pile works. Upon receipt, piles must
be inspected by OWNER or CONSULTANT, material receiving reports made and issued. In case of
8.5.2 Piles shall not be stacked in more than four layers, with wooden cribbing installed so lower pile is free
8.5.3 All piles within a stack shall be in groups of the same type. Packings of uniform thickness shall be
8.6.1 CONTRACTOR/SUB-CONTRACTOR must stake out the locations of the piles. Stakes shall be
numbered and color-coded in accordance with the numbering on the piling drawings.
Page 10 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
9.1 MATERIALS
9.1.1 All materials and work shall be in accordance with Specification for Structural Steelwork (Materials,
9.1.2 All structural pipes shall conform to ASTM 53 Gr. B, API 5L Gr. B or equivalent as per BS EN 10210.
Pipes shall be either seamless or mill welded. Spiral-welded pipe is not acceptable. Section sizes and
9.1.3 The grade of steel for splice plates, caps and driving points shall be the same as that of the steel
section. Connections should be all welded to the details shown on the drawings.
9.1.4 Protective coatings where required, shall be as indicated on the drawings. Length of coating shall be
Surfaces due to receive a protective coating shall be blast cleaned, prior to application of the coating,
which shall then be applied in accordance with the suppliers instructions. Areas modified within the
coated length, such as at cutoffs and at splices with plates welded, shall be recoated using materials
and methods compatible with the existing coating. Curing should be allowed to take place before pile
installation.
10.1 MATERIALS
10.1.1 All structural concrete shall be Grade 30, with a characteristic compressive strength of 30MPa (cylinder
10.1.2 Reinforcement steel shall be deformed high yield bars Grade 60 as ASTM A615/615M. Reinforcing
10.1.4 All materials and work shall be in accordance with engineering specification S-000-5320-001, Concrete
Page 11 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
10.2.1 The cover to reinforcement, including binding wire, shall not be less than 75 mm for fully embedded
10.2.2 The steel reinforcement shall be designed in such a way that the crack width of the concrete will remain
10.2.3 Local bars for resisting bending moments may be added but shall be so arranged as to avoid a sudden
discontinuity of the reinforcing steel which could lead to cracking during heavy driving.
10.2.4 Lateral reinforcement which is of particular importance in resisting driving stresses, shall be not less
than 6 mm diameter, securely fixed to the main reinforcement. Lateral reinforcement should be not less
than 0.6% of the gross volume, applied over a distance of three pile diameters from each end of the
pile.
10.2.5 Lateral reinforcement in the body of the pile shall be not less than 0.2%, spaced at not more than half
the diameter of the pile. The transition between the close spacing near the ends and the maximum
spacing should be made gradually over a length equal to about three times the diameter.
10.2.6 If joints to main longitudinal bars are required, they shall be staggered and preferably be made by full
penetration butt-welding.
10.3 FABRICATION
10.3.1 Forms shall be adequately supported to prevent settlement or sagging during fabrication.
10.3.2 Corners and driving head of square piles shall have 25 mm chamfers unless otherwise called for on
design drawings.
10.3.4 Main longitudinal bars shall extend to the head of the pile.
10.3.5 An electric control wire in each pile shall be installed in order to ensure that pile is undamaged after
10.3.6 Concrete shall be placed continuously for each pile to avoid cold joints.
10.3.7 Exposed, unformed concrete surfaces should be floated and lightly toweled.
10.3.9 The fabrication shall be executed in acc. with engineering specification S-000-5320-001, Concrete
10.4 TOLERANCES
The curvature along the axis of the pile shall not exceed 1 mm/m of length.
Page 12 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
11.1 MATERIALS
11.1.1 All structural concrete shall be Grade 30, with a characteristic compressive strength of 30MPa (cylinder
11.1.2 Reinforcement steel shall be deformed high yield bars Grade 60 as ASTM A615/615M. Reinforcing
11.1.3 Pre-stressing tendons shall be uncoated, stress-relieved steel strand with a minimum diameter of
strand of 12.5 mm (1/2 in) conforming to ASTM A 416 Grade 270. Grade 270 has minimum ultimate
2
strength of 1860 N/mm (270 ksi) based on the nominal area of the strand. Where relevant, BS EN
11.1.5 All materials and work shall be in accordance with engineering specification S-000-5320-001, Concrete
11.2.2 Sufficient pre-stressing steel shall be provided in the form of high-tensile wire, strand or bar so that the
11.2.3 Under normal loading conditions tensile strength of pre-stressed reinforcement shall be 50% of the
Pre-stressing strands should be enclosed in spirals minimum 5 mm diameter. Spiral pitch should
be a minimum of 150 mm in the middle part of the pile and 75 mm at the ends (over a length of
11.3 FABRICATION
11.4 TOLERANCES
12.1 GENERAL
The types of piles to be used shall be selected on the basis of the site and loading conditions.
Page 13 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
12.2 MATERIALS
12.4 TOLERANCES
13.0 INSTALLATION
13.1 PRE-DRILLING
13.1.1 In areas with underground obstacles of which the exact location is not known, predrilling should be
executed.
Drill diameter shall not exceed equivalent pile diameter. Diameter shall not exceed 400 mm.
The average drill depth shall be not deeper than 5 m above toe elevation of the pile.
Page 14 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
13.2.1 A pile driving procedure, which includes the minimum blow count, description of load tests when
13.2.2 Piles shall not be driven until the concrete has achieved the specified characteristic strength.
13.2.3 Before the start of pile driving, the required excavation work shall be done in acc. with Earthwork
Specification S-000-5312-002
13.2.4 The installation of piles and the sequence of driving shall be in accordance with the relevant design
13.2.5 Piles shall be driven vertically, except where noted on the design drawings.
13.2.6 Piles shall be driven within the tolerances set forth in Section 13.7 of this specification.
13.2.7 Piles damaged during driving shall be repaired or replaced as directed by OWNER or CONSULTANT.
13.3.1 Energy of the driving hammer shall be adjustable and set to the requirements for the pile type.
13.3.2 The CONTRACTOR or SUB-CONTRACTOR shall submit records of the type of rig and pile hammer he
intends to use, indicating weight, energy per blow, drop height, etc.
13.3.3 Pile driving and lifting equipment ensuring stability during handling, lifting and installing of the piles,
13.3.4 Driving of each pile shall start with new cushion material in the pile cap.
13.3.5 In hazardous areas, plastic dollies or other approved type shall be used for safety purposes.
13.4.1 The sequence of driving piles shall be as agreed with OWNER or CONSULTANT before
13.4.2 In general, the first pile shall be driven close to the location of a SPT (boring) or CPT (if available).
13.4.3 If pile driving has to be carried out on a sloping surface, driving shall start at the higher parts.
13.4.4 Piles in a large group should be either driven progressively from one side to the other or outward from
the center of the group. The final driving sequence shall be determined after detailed piling plan is
available.
13.5.1 Each pile shall be driven continuously until the specified or approved set and/or depth has been
reached and to the minimum specified blow count and, if applicable, when the pile tip has reached the
bearing zone.
Page 15 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
13.5.2 If refusal is encountered above the bearing zone, the pile driving system and/or installation procedure
13.5.3 If a pile does not meet the specified blow count, if applicable, within the bearing zone, driving shall
continue until the specified minimum blow count is achieved over a one meter interval. Alternatively,
these piles may be accepted if selective pile load tests do support that these piles have sufficient
13.5.4 During driving of piles to a specified toe elevation, the piling specialist shall carry out a continuous
check of the behavior of each pile and he will calculate, if necessary, by using HILEY or other approved
formula that each pile will reach the capacity required at the depth specified.
13.5.5 The penetration depth into the bearing soil layer, if applicable, shall be 3 x diameter of pile or 3 x the
13.5.6 At all stages during driving the piles shall be adequately supported and restrained by means of leaders,
trestles, temporary supports or other guide arrangements to maintain position and alignment and to
prevent buckling. These arrangements shall be such that damage to the pile does not occur.
13.5.7 To prevent damage to the pile during driving, the CONTRACTOR/SUB-CONTRACTOR shall ensure
that the pile hammer is properly centered over the pile, the steel cover (pile cap) over the pile head fits
properly (20 mm ply maximum), the wooden filling (two (2) layers of pinewood) has the proper
13.5.8 In case the pile drifts away during the driving, the pile hammer shall be re-centered over the pile to
13.5.9 Piles shall be driven only. Pulling, jetting, jacking of piles into the required position shall not be
permitted.
13.5.10 Where penetration of the pile is suddenly resisted by underground obstructions, such as buried rocks,
the pile CONTRACTOR/SUB-CONTRACTOR shall stop pile driving and bring this condition
13.5.11 Where piles are of the driven type and the spacing and ground conditions are such that ground heave
is likely, the resulting amount of uplift and lateral movement of the piles shall be recorded by means of
levels and positions taken on each pile each day, over a period agreed between CONTRACTOR and
OWNER or CONSULTANT. Piles which heave more than 25 mm shall be reseated to their original
elevation.
13.5.12 An elevation shall be taken on each pile as soon as it has been driven and elevations shall again be
13.6.1 Penetration and driving records shall be kept by the CONTRACTOR and shall be supplied (daily) to the
OWNER or CONSULTANT.
13.6.2 The pile installation log book records shall include, but not be limited to, the following information:
c. Type of pile.
d. Dimensions of pile.
Page 16 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
e. Date of manufacture.
j. Reference elevation.
l. Make, type and weight of hammer, and rated energy per blow if applicable.
m. Stroke of hammer.
o. For each pile nearest to a SPT (boring) or Cone Penetration Test (CPT) location, blow counts
shall be recorded over the total length of the pile, and these blow counts shall be presented in a
p. Special observations during pile driving, such as intervals in driving, crushing of the pile material,
13.6.3 If piles have to be extended, the driving record will also show:
Extended length.
Extended length.
13.7.1 Piles shall be driven to the specified positions within the following tolerances:
The maximum deviation from the specified slope shall not exceed 1% (10 mm/m) of the pile
length or any section of the length measured when the pile is aboveground in the leads.
On completion of the driving the horizontal tolerances of pile location shall be within the
following deviations:
Page 17 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
13.7.2 The CONTRACTOR shall prepare a table showing the deviation of every pile from its exact required
13.8.1 In case the location of a pile is outside the allowable tolerances, OWNER or CONSULTANT will decide
whether the pile location is acceptable or if additional pile(s) have to be driven or structural
13.8.2 If a pile is damaged during pile driving activities, OWNER or CONSULTANT will decide whether the
pile can be repaired or if the pile shall be cut off and abandoned. The decision of OWNER or
13.8.3 Damaged driven concrete piles shall be tested (when required) with the "Acoustic Wave Method",
A lap shall be formed by stripping reinforcement of surrounding concrete for a distance of forty times the
diameter of the longitudinal bars. They shall be thoroughly cleaned and all lateral reinforcement removed.
Additional reinforcement shall be placed in position, securely fixed or welded to main bars and the pile
Pre-stressed concrete piles may only be lengthened using approved steel couplings.
14.1 GENERAL
14.1.1 A number of piles may be selected by the OWNER or CONSULTANT for testing.
14.1.2 The results of the integrity tests shall be used as basis to decide on additional pile load tests or
14.1.3 Tests shall be made both, before and during the schedule pile installation.
Page 18 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
Ultimate load tests should all be carried out on preliminary piles. Proof load tension tests should also
be carried out on preliminary piles. Other proof load tests should be carried out on working piles. The
locations of preliminary piles should be shown on the drawings. These should be finally cut off a
Pile capacities, i.e. allowable working loads should be confirmed by the ultimate load tests as follows:
When determined or confirmed by a loading test, the allowable pile capacity should be 50% of the
ultimate load, but should in no case exceed the load which produces a net movement of 0.3 mm
When determined or confirmed by a loading test, the allowable pile capacity should be 50% of the
ultimate load, but should in no case exceed the load which produces a net movement of 0.3 mm
Piles should be tested for lateral design capacity in accordance with IBC 2012 par. 1810.3.3.2.
The resulting allowable load shall not be more than one-half of the load that produces a gross
lateral movement of 1 inch (25mm) at the lower of the top of foundation element and the ground
surface.
14.3 EQUIPMENT
CONTRACTOR is responsible for the design, procurement and construction of all structural details
A steel test plate of appropriate thickness for the loads should be set on the pile so as to
obtain full bearing. The size of the test plate should be not less than the width of the pile,
nor less than the area covered by the force-applying apparatus. The test plate should be
Piles should be capped with a concrete head of suitable size, reinforced to distribute the
Vertical compression or tension loads should be applied axially to the test piles, with care taken to
minimize eccentric loadings. A sufficiently strong test beam should be centered over the test pile to
Reaction System
a. Vertical compression or tension loads should be applied axially to the test piles, with care
taken to minimize eccentric loadings. A sufficiently strong test beam should be centered
over the test pile to achieve this, together with hydraulic jack.
Page 19 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
b. For vertical tension loads the beams can be reacted against either preliminary or
working piles.
c. For horizontal loads reaction may be achieved by jacking against kentledge. With
OWNERS or CONSULTANTs approval two (2) piles may be jacked apart to achieve
14.4 INSTRUMENTATION
The main objective of the load tests is to derive load-displacement curves from the results. Therefore
during testing measurements should be taken for load, displacement and time.
Loads
Loads applied to the pile head can be monitored by one (1) of the following instruments:
Displacement
Variations in temperature should be monitored throughout the test, to ascertain the influence upon test
Instrumentation should be arranged in such a manner that it can be conveniently observed from a single
position.
Before the start of testing, calibration certification for instrumentation should be submitted to OWNER or
CONSULTANT.
Test piles should be of the same type and installed with the same equipment as working piles. Tests
should be carried out during the normal piling contract and with OWNERs or CONSULTANT present and
Method A
In principle the pile should be loaded to 1.5 to 2.0 times the working load in equal loading steps. Unloading
should take place after every load step, to gather information on load-displacement behavior in general
Page 20 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
The following steps are proposed for loading to 1.5 working load:
0.25 - 0.50 - 0 -
0.50 - 0.75 - 0 -
0.75 - 1.00 - 0 -
1.00 - 1.25 - 0 -
It might be necessary to unload to, for example, 0.1 times the working load instead of 0.0 to prevent
Working load is defined as the allowable load according to pile design plus negative friction on
Piles can be loaded up "regularly and reasonably fast". We recommend that the shortest of the
b. Constant until pile head movement is smaller than 0.1 mm/20 minutes.
Method B
The load should be maintained at each stage for the period indicated or until movement under the specific
Movement may be considered as ceased when it is continuing at no more than the following rates:
Rate of Loading
25 1 hour
50 1 hour
75 1 hour
100 6 hours
75 10 minutes
50 10 minutes
25 10 minutes
0 10 minutes
100 6 hours
125 1 hour
150 24 hours
175 1 hour *
200 6 hours *
175 10 minutes *
150 10 minutes *
125 10 minutes
100 10 minutes
75 10 minutes
50 10 minutes
25 10 minutes
Page 21 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
Procedure should be similar to the previous test but with the following applicable:
Rate of Loading
50 1 hour
100 1 hour
150 6 hours
100 10 minutes
50 10 minutes
0 -
Procedure should be similar to previous test but with the following applicable:
Rate of Loading
50 1 hour
100 1 hour
150 48 hours
100 10 minutes
50 10 minutes
0 -
14.6 RESULTS
The settlement or movement of piles under test loads shall be measured and recorded on completion of
each loading stage and every three (3) hours where the load period exceeds one (1) hour, but does not
Any necessary interpretation of test results will be made by OWNER or CONSULTANT. Should test results
warrant, OWNER or CONSULTANT may modify installation procedures and criteria, or the design load
capacities of piles.
15.1 GENERAL
15.1.1 Quality of the work in respect of both workmanship and materials shall be ensured throughout the
project. There shall be an element of self-certification by means of a quality assurance and control
procedure.
The quality assurance and control procedure shall be agreed between OWNER or CONSULTANT and
Page 22 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
The quality assurance and control procedure shall clearly identify Hold and Witness points for OWNER
As a minimum the quality assurance and control procedure shall include procedures and standards for:
Repair.
Acceptance.
Method Statements.
a. Pile installation.
b. Pile testing.
Workmanship.
15.1.2 CONTRACTOR/SUB-CONTRACTOR shall submit certificates, before work starts, for all materials to be
15.1.3 For steel piles certified mill tests reports shall be kept on file by the CONTRACTOR/SUB-
CONTRACTOR for inspection by the OWNER or CONSULTANT.
15.1.4 For concrete piles (prefabricated and cast-in situ) material certificates shall be submitted for:
Cement.
Reinforcing steel.
Page 23 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
what the design has been based and make the required tests as per the requirements stipulated in the
applicable code. The detailed record of the tests shall show the results that the specified concrete
strength has been reached. Copies of this record shall be submitted to the OWNER or CONSULTANT
15.1.6 If any test specimen fails to meet the specified concrete strength, CONSTRUCTION SUB-
CONTRACTOR shall carry out new tests for the already cast piles of the related batch. If the new tests
fail again, CONTRACTOR/SUB-CONTRACTOR shall bring this condition immediately to the attention
15.1.7 In the case of proprietary products, full catalogue details should be forwarded. For steel fabrication,
laboratory. A testing program shall be agreed at the start of the contract. Test reports demonstrating
compliance with the specification shall be submitted to OWNER or CONSULTANT upon completion of
piling work. The test reports shall be the property of the OWNER or CONSULTANT.
Page 24 of 25
Company LLC.
S-000-5314-001
Sultanate of Oman
Job No : 120476/ JI-2022
15.2 DOCUMENTS
Quality of the works shall be documented by means of certificates and test, inspection and acceptance
reports.
A complete set of all documents related to the works shall be handed over by CONSTRUCTION SUB-
CONTRACTOR to CONTRACTOR upon completion for handover to the OWNER or CONSULTANT.
Pile Logs.
As-built Drawings.
15.3 INSPECTION
15.3.1 CONTRACTOR and OWNER or CONSULTANT reserves the right of inspection of the work by the
15.3.2 CONTRACTOR shall keep a competent representative at the work fully authorized to act for him and
receive such orders as may given for proper continuation of the work.
Page 25 of 25