Beruflich Dokumente
Kultur Dokumente
TSP MODEL
20/30/40/50/60
64 Catalyst Drive
Canton, NC 28716 USA
+1-828-646-9290
+1-828-646-9527
w w w.allteccorp.com
TerraStreamer TSP
ESE Terminal Installation Guide
Table of Contents
Warranty.......................................................................................................... 2
Supplied Items.............................................................................................. 3
TerraSteamer TSP Early Streamer Emission (ESE) Terminals....... 4
Features.................................................................................................................................4
Protection Performance.....................................................................................................5
Protection Radius - Additional Levels.............................................................................5
Positioning & Height................................................................................... 6
TerraSteamer ESE Terminal.............................................................................................6
Preferred Installation Points.............................................................................................6
Pre-Installation Checklist..................................................................................................7
Important Safety and Other Considerations................................................................7
Ground System Configurations.......................................................................................8
1. Installation of the Grounding System............................................. 8
Down Conductor Routing Guidelines............................................................................9
Number of Down Conductors and Grounds...............................................................10
Adaptor................................................................................................................................10
2. Down Conductor Installation........................................................... 11
3. Termination of the Down Conductor............................................ 12
Lower End............................................................................................................................12
Upper End............................................................................................................................13
4. TerraStreamer ESE Terminal Installation.................................... 14
Guyed FRP Masts...............................................................................................................14
Metallic Masts....................................................................................................................16
5. Lightning Strike Counter Installation............................................ 17
6. Final Installation Verification............................................................ 18
7. Inspection/Maintenance.................................................................... 18
Schedule..............................................................................................................................18
Checklist..............................................................................................................................18
Disclaimer..................................................................................................... 19
Warranty
The warranty is limited to the cost of replacement of equipment providing
it has been installed and/or certified by Alltec Corporation or its authorized
distributor. Alltec Corporation shall in no event be responsible for any loss of
business or profits, downtime or delay, labor, repair or material costs or any
similar or dissimilar consequential loss or damage incurred by the buyer. All
other costs such as: insurance premiums, freight charges, loss of profit, and re-
installation of equipment are not included. Also specifically excluded from the
warranty is any responsibility for other direct or indirect damages or death.
NOTE: Alltec Corporation shall in no event be responsible if the products
have not been stored or used in accordance with its specifications and
recommended procedures.
WARNING
THERE IS A SAFETY ADVISORY AGAINST
STANDING WITHIN A PROXIMITY OF 12 FEET
(4 METERS) OF THIS LIGHTNING PROTECTION
SYSTEM WHILE AN ELECTRIC STORM IS
DEVELOPING OR IN PROGRESS.
TerraStreamer TSP
Adaptor
ESE Terminal
64 Catalyst Drive
ve
Canton, NC 28716 USA
Tel: +1 828.646.9290
46.929
Fax: +1 828.646.9527
28.646.9
US Toll Free: +1 800.20
800.203.2658
w w w.allteccorp.com
info@allteccorp.com
W A R R A N T Y R E G I S T R AT I O N A N D S TAT E M E N T O F C O M P L I A N C E
TerraStreamer TSP System Project Informa
Information
Q U A L I T Y C E R T I F I C AT E
System Installed - Model Type: Name of Project:
Serial #s: Address:
Model:
M odel: TSP-20 Serial No: # of Terminals:
Triggering
Tr
riggering Tim
Time Advance (T) = 22s Type,
e, size and length of down conductor:
Type Type of Structure:
Installation Date:
This is to certify the above product is manufactured to a design achieving a triggering time (T) as stipulated
above in accordance with NF C 17-102 and UNE 21 186. Protective Radius Obtained: Installation Contractor:
NF C 17-102 Inspected by:
This document further certifies that this unit meets or exceeds all Quality Control parameters as established by
UNE 21 186 Inspection Date:
Alltec Corporation, and that Electrical Testing according to the above International Standards has independently
verified performance, as documented by a fully Accredited Laboratory. Ground Resistance Reading: Alltec Distributor:
Important Notice:
Quality Control Verification Parameters: Failure to perform installation and maintenance as per Alltecs recommendations automatically voids all warranty conditions.
Accredited High Voltage Testing: For Warranty registration, please complete the above and mail to Alltec Corporation within 30 days of installation (see reverse side)
3
TerraStreamer TSP
Early Streamer Emission (ESE) Terminals
The TerraStreamer ESE Lightning Terminal is an externally mounted, proactive,
structural lightning protection device and is designed to activate itself in the
moments directly preceding an imminent direct strike. The installation of a
TerraStreamer ESE Terminal combines the best advantages of two systems: the
direct path to ground of a conventional lightning protection system, and state-
of-the-art ESE technology employed in the TerraStreamers internal design.
TerraStreamer ESE Terminals are designed to react to the rise in the ambient
electrical field which is present with approaching thunderstorms, and become
active only during storm activity.
The system operates without the need for external power supply or spare
parts for standard operation.
To keep the TerraStreamer ESE Lightning Protection System operating at
optimum levels it needs to be maintained and inspected regularly.
Features
NF C 17-102 and UNE 21 186 tested and certified
High level of protection radius
Lightweight and low wind loading
Reliable operation in any atmospheric condition
Suitable for corrosive environments
Simple to install
Five year replacement warranty
Available in five models for all applications
Patent Pending
4
Protection Performance
Protection Areas
TSP 20 TSP 30 TSP 40 TSP 50 TSP 60
H(m)
(Rp) (Rp) (Rp) (Rp) (Rp)
2 15 20 25 30 32
3 23 29 37 45 48
4 31 40 50 59 65
Level I 5 39 50 62 73 80
6 40 50 62 74 80
8 40 51 63 74 80
10 41 51 63 74 80
2 18 23 28 33 38
3 26 34 42 49 55
4 36 46 55 64 74
Level II 5 45 58 69 80 89
6 47 58 69 80 90
8 47 59 70 81 90
10 48 60 71 81 91
2 21 26 32 37 42
3 31 39 48 54 62
4 42 52 63 73 82
Level III 5 54 66 80 92 99
6 54 66 80 92 99
8 56 68 81 93 100
10 57 69 82 94 100
2 24 29 36 41 45
3 35 43 52 60 65
4 49 59 71 80 87
Level IV 5 61 74 88 101 108
6 62 74 89 102 108
8 63 76 90 103 109
10 65 77 91 104 110
Level 1++:
Structure with roof protected by
ESE level 1+ with protection radius
reduction by 40% and ensuring
a complete protection from the
materials on the roof against direct
lightning.
5
Positioning & Height
If the external installation for a given structure comprises several ESE Terminals
these are to be interconnected by a suitable conductor, unless it has to be
routed over a structural obstacle (cornice, parapet wall) with a positive or
negative level difference in excess of 1.50m (see Fig. A).
When ESE Terminals protect open areas such as playing fields, golf courses,
swimming pools, camping sites, etc., they should be installed on specific
supports such as lightning poles, pylons, or any other nearby structures which
enable the ESE Terminal to cover the area to be protected.
The ESE Terminal height may be increased by means of an elevation mast. If the
ESE Terminal is steadied by conductive guy lines, these should be connected
at the bottom attaching points to the down conductors by means of suitable
conductors.
2m 2m
6
Pre-Installation Checklist
Determine the best location for ESE Terminal(s), then the mounting
method (tower, mast, structure, etc.) and the optimum routing of down
conductor(s).
Locate area(s) for grounding system installation and determine where the
new system will be connected to any existing grounding system and metal
bodies of conductance, etc.
Verify that all parts and system components are compatible (dissimilar
metals not allowed) and in good condition.
Review installation plans, structural drawings, site drawings and mast
erection instructions.
Read this Installation Guide and familiarize yourself with all of the system
components and functions.
Be sure that all tools and equipment required for system installation are
available and in good working order.
Follow all industry guidelines and local/site requirements for safety and
safety equipment.
7
Ground System Configurations
A ground resistance of less than10 Ohms is required for successful operation of
the TerraStreamer ESE Terminal.If, due to space constraints or high soil resistivity,
it is not possible to readily install a grounding system as recommended, consult
Alltec Corporation for further advice.
B
P
P
B
Radial Delta
D: Down-conductor
B: Building foundation loop ground
P: Grounding system
8
The application of TerraFill ground enhancement backfill aids in the
reduction of soil resistivity to the recommended level of less than 10
Ohms.
A ground inspection/test well should be installed where the end of the
down conductor terminates to the grounding system. This gives an access
point for disconnection and future testing.
Each down conductor should be provided with a means of disconnect for
testing. These disconnect/test terminals may be located 2m above ground
level and should be marked Lightning Conductor and the symbol:
9
Number of Down Conductors and Grounds
The number of down conductors is dictated by the height and width of the
structure to be protected. Typically, structures of a height greater than 28
meters require two down conductors, as do structures where the height is less
than the distance from the roof edge to the center of the structure where the
terminal is to be located. See Figure C, below.
Adaptor
Down conductors should be attached to the TerraStreamer ESE Terminal using
the supplied adaptor as per Fig. D , and as recommended in sections following.
Fig. D - Adaptor
10
2. Down Conductor Installation
The Warning Labels (2) supplied with TerraStreamer ESE Terminals
should be installed in locations where personnel may be in close contact
to the down conductor(s).
The most direct path to ground is recommended, avoiding sharp bends.
Down conductors should be installed around the outside walls of the
structure.
Any extended metal running vertically through the structure should be
bonded to the down conductor at the top and bottom of the structure.
Down Conductor
Mast
Fastener
Roof Edge
11
3. Termination of the Down Conductor
Lower End
Down conductor(s) should be directly connected to the grounding system
through the use of a suitable ground rod clamp or by using TerraWeld
exothermic welding.
Exterior Wall
Cable Splicers or
Exothermic Welds 1m Minimum
Fin
Three Radials ish
ed
2m - 10m long gra
de
50c
mM
in.
Ground Rod
Minimum 16mm Diameter x 3m length
12
Upper End
Each TerraStreamer ESE Terminal comes supplied with the adaptor (Fig. G).
This adaptor accepts either flat copper strip, or stranded copper wire.
Flat copper strip attaches to the external flat side of the adaptor.
Round/stranded copper wire is inserted into the hole in the base of the
adaptor and secured with the two screws provided.
TerraStreamer
ESE Terminal
Supplied Adaptor
Set Screws
Down Conductor
Adaptor Bolts
Mast
Fig. G - Down Conductor Upper End
13
4. TerraStreamer ESE Terminal Installation
14
Installation Examples Using FRP Masts:
TerraStreamer
Guy Ring ESE Terminal
FRP Mast
Guy Wire
Mast Base
Strike Counter
Inspection Well
Grounding System
TerraStreamer
Guy Ring ESE Terminal
FRP Mast
Guy Wire
Mast Base
Strike Counter
Inspection Well
Grounding System
15
Metallic Masts
Following installation of the TerraStreamer ESE Terminal to a metallic mast,
it will be necessary to connect the metallic mast to a down conductor in
order to convey the lightning energy to the grounding system.
The connection between the metallic mast and the appropriately sized
down conductor should be completed by approved mechanical means or
by exothermically welding (TerraWeld) the down conductor at a practical
point somewhere along the length of the mast.
Particular care should be taken to ensure that compatible metals are used
when connecting the down conductor to metallic masts (e.g. aluminum to
copper connections require an approved bimetallic connector).
It is important that a minimum of one third of the mast height be securely
fixed to the structure to which the mast is mounted.
TerraStreamer
ESE Terminal
Metallic Mast
Strike Counter
Inspection Well
16
TerraStreamer
ESE Terminal
Metallic Mast
Stainless Steel
Mounting Brackets
Strike Counter
Inspection Well
17
6. Final Installation Verification
The following should be checked for quality of workmanship and compliance
to recommended installation instructions and NF C 17-102 requirements:
Correct TerraStreamer ESE Terminal and placement for proper zone of
protection.
Correct mast and any associated brackets and fastenings have been used
for installation.
Guying, anchor points and fastenings.
Down conductor routing and attachment points
Connection of down conductor to grounding system
Grounding system
Labeling
7. Inspection/Maintenance
Alltec Corporation recommends inspection and any required maintenance to
be performed regularly and as listed below:
Schedule
After each known lightning strike to the terminal.
Once every twelve months minimum.
If changes have been made to the structure.
Checklist
Check for any damage to the TerraStreamer ESE system.
Check TerraStreamer ESE Terminal body and tip for excessive pitting or
other damage.
Inspect the TerraStreamer ESE Terminal and ensure that no dirt or
other matter is embedded in the air gap between the center tip and the
surrounding panel edges.
Verify that the structure to be protected has not been modified or expanded
since the last maintenance check.
Make sure that the electrical continuity of all visible conductors is correct,
and that no conductors or other parts have been weakened by corrosion.
Check that all rigging, mast mounts, and conductor fixings are secure and
tight.
Check that all down conductors and equipotential bonds remain correctly
positioned and that they are securely attached and no damage or theft
has occurred.
All warning labels must still be in place and visible.
Check the strike counter for secure installation and record the number of
strikes, if any.
18
Disclaimer
Neither the TerraStreamer ESE Terminal nor any other lightning protection
system to our knowledge can provide 100% protection from lightning.
In order to provide the most effective Early Streamer Emission (ESE) Air
Terminal technology available today, Alltec TerraStreamer ESE Terminals are
independently tested and certified to meet NF C 17-102 and UNE 21 186
standards. In addition, these modern standards have provided the applicable
information contained in this Installation Guide to correctly implement a
proper ESE system.
19
Installation Guide
TSP MODEL
20/30/40/50/60
64 Catalyst Drive
Canton, NC 28716 USA
+1-828-646-9290
+1-828-646-9527
w w w.allteccorp.com