Sie sind auf Seite 1von 10

ARTICLE IN PRESS

INTERNATIONAL JOURNAL OF

PROJECT
MANAGEMENT
International Journal of Project Management xxx (2007) xxxxxx
www.elsevier.com/locate/ijproman

Life cycle cost based procurement decisions


A case study of Norwegian Defence Procurement projects
Bernt E. Tysseland *

Royal Norwegian Naval Academy and Molde University College, P.O. Box 83, Haakonsvern, N-5886 Bergen, Norway

Received 25 June 2007; received in revised form 15 August 2007; accepted 4 September 2007

Abstract

A Norwegian Ministry of Defence publication states that when procurement decisions are made, systems that yield the lowest possible
life cycle cost (LCC) for the Norwegian Defence must be procured, even if this means that initial procurement cost becomes higher. How-
ever, several projects within the community are still carried out and reviewed based on initial procurement cost alone. This study inves-
tigates four hypotheses, based on agency theory and earlier LCC work, in order to help explain why this is happening. A questionnaire
was administered to all projects currently running in the defence community. Findings regarding project uncertainty, information sym-
metry, the project leaders attitude and knowledge about LCC, as well as control variables are discussed both towards theory and in
terms of managerial implications.
2007 Elsevier Ltd and IPMA. All rights reserved.

Keywords: Agency theory; Life cycle costing; Procurement decisions; Projects; Project leaders; Defence

1. Introduction and research question ally starts with the initial determination of its need,
continues through design and development, production,
In 1998 General Steinar Jssund, Head of the Norwe- deployment, operations and concludes with the systems
gian Army Material Command said: disposal. Life cycle cost may be categorized in many
The Norwegian Defences ongoing and future organiza- dierent ways, depending on the type of system and the
tional change, demands that the present focus on costs asso- sensitivities desired in cost-eectiveness measurement [2].
ciated with material system procurement is changed from However, the fundamental objective of LCC analysis is
only considering the initial procurement cost to looking at to identify the cost drivers that most signicantly contrib-
the material systems total life cycle cost.1 ute to LCC, since this allows for trade o considerations
Earlier research has presented cases where maintenance with respect to dierent courses of action [3]. Or as stated
and logistics support costs for a system can be cut with up by Ferrin and Plank [4]; the concept suggests that managers
to 50% by using integrated logistic support (ILS)2 and life adopt a long-term perspective, for the accurate valuation of
cycle cost (LCC) analysis [1]. The life cycle of a system usu- buying situations.
Since approximately 19933 the Norwegian Defence has
*
Tel.: +47 55505074; fax: +47 50505004. used ILS in some projects in order to minimize the total cost
E-mail address: btysseland@sksk.mil.no of material procurements accounted over the materials
1
From the intranet of the Army Material Command.
2
Integrated logistics support (ILS) is a disciplined management
3
approach, aecting both customer and industry, aimed at optimising Individuals within the Norwegian Defense has probably been working
equipment life cycle costs (LCC). It includes elements for inuencing with Integrated Logistic Support long before 1993, however according to
equipment design and determining support requirements to achieve an internal Navy Material Command report from 1995 the rst ILS
supportable and supported equipment (From the intranet of the Norwe- organization was establish around 1993 in the Air Force Material
gian Army Material Command, 2002). Command [18].

0263-7863/$30.00 2007 Elsevier Ltd and IPMA. All rights reserved.


doi:10.1016/j.ijproman.2007.09.005

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

2 B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx

total life cycle. In the summer of 2004 the importance of ILS Control
and LCC was highlighted by the Norwegian Ministry of Knowledge of variables
LCC
Defense (NoMoD) in their publication. Konsept for frems- H4
kaelse av materielle kapasiteter i forsvarssektoren (Nor- Information
wegian title). In this publication the NoMoD clearly states symmetry
H3 Use of LCC
that when investment decisions are made, solutions/systems
that yield the lowest possible life cycle cost, given equal sys- Attitude
tem eectiveness, must be preferred, even if this means that towards LCC H2
the initial investment cost becomes higher. Project
However, approximately at the same time Commodore uncertainty H1
Morten Jacobsen, Chief of Procurement in the Norwegian
Defence Logistic Organization (NoDLO), said in a speech Fig. 1. Research model.
that they are still experiencing that procurement in some
projects are carried out and reviewed based on initial pro- focused on the relationship found between rms, but
curement costs alone. Reports from the United Kingdom agency theory can also be used to evaluate relations within
are also concluding that the British experience is much the rm/organization, which is the case in this study [9].
the same [5]. According to agency theory two main problems can
Based on the information presented above the main occur in agency relationships; the rst problem is that of
question of this research is What can explain that some conicting goals between the principal and the agent, and
procurement projects are still carried out and reviewed the second problem is that of risk preferences.
based on initial procurement costs alone when the ocial The rst problem will arise when the goals of the princi-
policy is to apply the life cycle cost approach? pal and the agent conict, and it is dicult or expensive for
the principal to verify what the agent is actually doing [8].
2. Theory framework The second problem, concerning risk preference arises
when the principal and the agent have dierent risk prefer-
The concept of LCC, sometimes called Total Cost of ences and hence will prefer dierent actions due to this. The
Ownership (TCO) has been discussed, and examined empir- assumption is that the principal will be risk neutral while
ically but with limited scope [4]. Literature review has not the agent will be risk adverse.
revealed many studies that could help answer the main As mentioned before, agency theory describes the rela-
research question raised in this study. One study was found tion between the principal and the agent using the metaphor
where the authors looked into the adoption of total cost of of a contract; hence the unit of analysis will be the contract
ownership for sourcing decisions [6]. The main dierence governing the relationship between the two parties.
between that study and this study is that in our case it is
already decided by the mandate group that LCC should 3. Research model and hypothesis
be used. The fact that the mandate group has decided that
LCC should be used brings forward what is known as the The research model (Fig. 1) is based on the belief that
mandate problem [7]. Organizations, such as the procure- agency theory constructs along with the knowledge con-
ment projects of this study, are established by owners. It struct4 to a certain degree can explain why some procure-
is the owners (the mandate group) who decide which goals ment projects within the Norwegian Defence focus on life
and tasks the organization is going to have [7]. In order to cycle costs while others do not.
reach any preset goal, the mandate group must implement In the research model the dependent construct is there-
a governance system that makes sure that the leaders and fore the project leaders use of life cycle costing in procure-
employees of the organization implement actions to reach ment decisions. The independent constructs are project
the goal. According to Greve [7], one of the main theories uncertainty, information symmetry, attitude towards LCC
that regulates the relationship between the mandate group and knowledge about LCC. In addition to the independent
and the organization leaders, is agency theory. constructs, some control variables were examined and in the
The main theoretical perspective of this study is there- nal regression model independent dummy variables of the
fore agency theory, used in an exploratory fashion. In addi- control variable found to be signicant are included.
tion to agency theory, one of the propositions put forward
in a paper by Waak [1] where he discusses why LCC is not 3.1. Project uncertainty
more used, namely lack of knowledge, is also examined.
According to Eisenhardt [8], agency theory is directed at Uncertainty in the context of agency theory is connected
the ubiquitous agency relationship, in which one party del- to the basic risk assumptions of the theory. In agency the-
egates work to another, which performs that work. Agency ory the principal is assumed to be risk neutral, whereas the
theory will describe the relation between the parties (the
principal and the agent) with the metaphor of a contract
4
[8]. Most empirical work towards agency relations are From Waak [1].

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx 3

agents are assumed to be risk adverse [9]. The rationale jects are nished on time and within the original investment
behind this is that the principal most likely can spread budget, their attitude towards the use of LCC based invest-
his risk over several projects, whereas the agent will have ment decisions will most likely be negative. Project leaders
to succeed in the one project he has. Hence in the case acting in what they think are their self-interest at the
of defence projects the NoMoD will have a portfolio of expense of the principals interest is called adverse selection
projects to govern, and even if one project comes out with [8]. However it is hard to measure such behaviour by ques-
higher costs than expected, another project might experi- tions. Based on this, a substitute in terms of the project
ence lower costs than expected. The project leader (agent) leaders general attitude towards the use of LCC, is used
on the other hand, has only his one project, and he will as an indicator. Negative attitude is not necessarily a sign
therefore play safe in order to minimize potential failure. of bad will, but can be the eect of prior experiences, lack
Project uncertainty could be measured by a wide variety of information and so on. In any case, based on the new
of items, such as the number of tasks in the project, depen- concept from the NoMoD, project leaders should base
dency among tasks and so on. However, since the focus of their investment decisions on life cycle cost, and not to
this case study was on life cycle cost procurement decisions, do this is strictly speaking adverse selection.
especially connected to the calculation of operational cost The following hypothesis is proposed on attitude
(e.g. maintenance cost and spare part cost) it was decided towards the use of LCC:
to look upon uncertainty as whether the system procured
Hypothesis 2. Positive attitude towards the use of LCC by
can be acquired so called commercially o the shelf
the project leader will positively aect the use of LCC-
(COTS), or whether it has to be developed specically (high
based procurement decisions.
asset specicity). It is assumed that COTS systems indicate
lower risk for the project manager than asset specic sys-
tems. In the same direction, if a system is COTS, it is most 3.3. Information symmetry
likely already in use by others and it is therefore more likely
that operational data (e.g maintenance and reliability data) Information symmetry refers to the principal and agent
can be acquired by the project, and hence reduces the risk possessing the same information. In our case, the project
associated with the system in terms of calculating life cycle leaders will most likely possess detailed information about
cost. If the system is not in use by others, the risk of making the project that the NoMoD (represented by dierent pro-
incorrect calculations will increase. Based on the discussion ject boards) cannot access easily. With dierent informa-
of project uncertainty the following hypothesis is proposed: tion we have information asymmetry, and this can lead
to adverse selection.
Hypothesis 1. Project uncertainty will negatively aect the
According to Eisenhardt [8], information systems can
use of LCC-based procurement decisions.
curb adverse selection. The argument is that since informa-
tion systems can inform the principal about what the agent
3.2. Attitude towards LCC is actually doing, the agent will realize that he cannot
deceive the principal. We assume that alignment of infor-
According to Greve [7] it is the mandate group who mation is important regarding the use of LCC (making sure
decides which goals and tasks the organization is going that the agent knows and believes in the intent of the prin-
to have. In this research, we look upon the Norwegian cipal). In the case of Norwegian Defence projects the prin-
Ministry of Defence as the owner of the defence projects, cipals maybe most important information system should
and hence it is NoMoDs prerogative to decide that when be the project boards (or equivalent) that the dierent pro-
project leaders make investment decisions they should jects report to. If the project board clearly states that they
favour solutions that yield the lowest possible life cycle cost want information on how the project leader uses life cycle
for the system, even if this means that the initial investment cost when making investment decisions, the project leader
cost becomes higher.5 will realize that this is what the project really is governed
The problem arises when this goal of the principal con- by. In this case we have a situation where information sym-
icts with, or is not aligned with the preconception of the metry exists between principal and agent considering the
agents. Traditionally project success is measured on the tri- use of LCC. On the other hand, if the board is not
ple constraints; time, budget and overall quality [10]. How- informed about life cycle cost questions, and/or is not
ever the triple constraint has often only included the interested in this information, it is less likely that the pro-
research & development- and investment-phases of the pro- ject leader will focus on LCC, and hence information asym-
ject, not the operation & support and disposal-phases. If metry can be present.
the project leaders still think that their future (for example Based on the above, the following hypothesis on infor-
promotion) is based on the fact that the procurement pro- mation symmetry is proposed:
Hypothesis 3. Information symmetry between principal
5
(NoMOD) and agent (project leader) regarding the use of
Konsept for fremskaelse av materielle kapasiteter (Norwegian title), LCC will positively aect the project leaders use of LCC.
published on the Norwegian defense intranet site 15 July 2004.

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

4 B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx

3.4. Knowledge about life cycle costing jects were 252 with 98 project leaders.6 It was decided to
direct questions towards the dierent projects, and hence
There is no real consensus within science on what one person (the project leader) sometimes answered several
knowledge is, but in terms of this research we apply the fol- times due to the fact that several project leaders lead more
lowing denition: Knowledge is the condent understand- than one project. Since not all projects in the database are
ing of a subject, potentially with the ability to use it for a active, the initial number of 252 projects was reduced to
specic purpose [11]. Hence, knowledge about life cycle 150 at the time of data collection.
costing will refer to the common understanding of the con- The measuring instrument of choice is a questionnaire.
cept and how it should be applied within procurement pro- The main reason for choosing a questionnaire is to produce
jects in the Norwegian defence. statistics and be able to quantitatively accept or reject the
Even though knowledge as such, is not a common hypotheses put forward in the research model. The ques-
agency theory construct, knowledge of LCC is proposed tionnaire was sent to the 150 potential respondents by
to help align the interest of the principle with that of the including a link to the questionnaire database in an e-mail
agents. The proposition is that when the agent, either by from the person in charge of all procurement projects in the
himself or through members within his own project, has NoDLO. In the summer of 2006, after two reminders, 87
thorough knowledge about life cycle costing, he will be informants (58%) returned answers to the questions. Out
more likely to understand and accept the position of of the 87 answers, 9 responses had high levels of missing
the principle (NoMoD), and therefore use LCC. This data and therefore they were deleted. The remaining 78
is in line with Waak [1], when he proposes that LCC responses (52%) were all complete.
is not used because: In spite of considerable eort in
training, a deep lack of knowledge exists with regard to 4.2. Measures, validity and reliability
LCC. This is both true with regard to eectiveness of
the method and how it should be applied within the busi- Constructs are all measured by multi item ordinal scales.
ness at hand. All construct items use a ve point Likert-type scale with end
Hence the following hypothesis is proposed regarding points ts very badly and ts very well. The control
knowledge of LCC: variables were covered with nominal questions regarding
the main type of procurement the project is dealing with
Hypothesis 4. Better knowledge about life cycle costing will
(material, information technology or engineering), what
increase the use of LCC based procurement decisions.
NoDLO site the project works out of (Army, Navy or Air
Force) and the size of the project in terms of personnel work-
3.5. Control variables ing full time with LCC in the project (1, 24 or 5 or more).

In order to control for non hypothesised variables that 4.2.1. Content validity
could inuence the use of LCC based procurement deci- To minimize the possibility of the respondents not
sions, variables like what main type of procurement the understanding the terminology and layout of the questions,
project is dealing with, what NoDLO site the project works the questionnaire was tested out on three respondents
out from and the size of the project in terms of personnel within the Norwegian Navy and two respondents within
working with LCC were included in the study. the NoDLO. Based on their feedback some alternations
were done. Regarding the problem that respondents do
not want to reply, validity is tried increased through guar-
4. Method anties of anonymity.

4.1. Data collection and measuring instrument 4.2.2. Uni-dimensionality


An exploratory factor analysis in the form of principal
The unit of analysis in this study is the contract gov- component analysis (PCA) was conducted in SPSS.7 First
erning the relationship between the NoMOD (the principal) the dierent original items in the summed scales of the
and the project leaders (the agents) concerning life cycle study (TUseofLCC, TInfoSym, TKnowledge, TUncertain-
costing. The contract is a metaphor regarding the relation- ty and TAttitude), were assessed towards suitability for fac-
ship between the principal and the agent. The relationship tor analysis. In accordance with general recommendations,
data was collected from project leaders within the Norwe- the dependent scale (TUseofLCC) and the independent
gian Defence project community. Most projects delivering scales were measured separately. The assumption of mini-
to the Army are situated at a site in Kolsas outside Oslo,
Navy projects from a site in Bergen and Air Force projects 6
from a site at Kjeller outside Oslo. The total number of pro- The numbers are from The NoMoDs project investment database
called FID (Forsvarets investeringsdatabase).
jects and project leaders are shifting with the numbers of 7
SPSS is short for the Statistical Package for the Social Sciences. The
projects being started and/or terminated, but at the start system was rst developed in the 1960s, and has since gone through many
of the data collection (December 2005) the number of pro- updates [19]. The version used in this study is SPSS Release 13.

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx 5

mum sample size in a PCA was met [12]. The initial corre- Table 1
lation matrix of the independent construct variables and Rotated component matrix for the independent constructs items
the dependent variable showed that from one to several Component
items on each construct had to be removed due to low item 1 2 3 4
to item correlation.8 The correlation matrixes for the Knowledge3 0.919 .035 .126 .074
dependent and independent ordinal constructs can be seen Knowledge4 0.892 .087 .190 .011
in Appendix 1. The coecient values for UseofLCC4 and Knowledge1 0.727 .079 .215 .171
UseofLCC5 were so close to 0.3 they were still kept in Uncertainty2 .066 0.900 .138 .001
Uncertainty1 .044 0.888 .151 .021
the analysis. Further it was found that sucient correla- Uncertainty3 .045 0.745 .113 .159
tions exist among the items with a Barletts test of spheric- Info symmetry2 .123 .165 0.830 .019
ity [12]. Finally the measure of sampling adequacy (MSA) Info symmetry3 .112 .075 0.796 .101
came out with 0.792 for the dependent construct and 0.605 Info symmetry4 .103 .164 0.712 .162
for the independent constructs [13]. Hence all tests justify Attitude LCC6 .167 .112 .004 0.858
Attitude LCC5 .071 .012 .022 0.850
that it is appropriate to apply factor analysis, and a Princi-
pal Component Analysis (PCA) was done in SPSS. It is Extraction method: principal component analysis.
Rotation method: Varimax with Kaiser normalization.
suggested that PCA should be done separately for the Rotation converged in ve iterations.
dependent and independent constructs. For the dependent
construct the PCA gave an eigenvalue of 2.710 for one fac- As mentioned before, the PCA assigned all ve items of
tor with a value of 0.729 for factor two (if two factors were the dependent construct to one factor. The correlation of
to be retained), hence below the recommended cut-o value each item to the summated scale score were; 0.67, 0.6,
of 1 for the eigenvalue [12]. This is in accordance with the 063, 0.45 and 0.47 (from item 1 to item 5). This result indi-
predetermined numbers of dependent factors. The percent- cates that each item is measuring the same as the summated
age of variance explained with a one factor dependent solu- scale [13]. Further a satisfactory internal consistency given
tion is a little low (with 55%), but acceptable, and the by a CA value of 0.780 was found.
factor loading of the ve items to the construct are all All independent items were, as shown in Table 1,
above 0.6 (item 1 is 0.829, item 2 is 0.760, item 3 is assigned to appropriate factors. The project uncertainty
0.802, item 4 is 0.621 and item 5 is 0.644). Based on this (TUncertainty) items had all item to total correlation
uni-dimensionallity for the dependent summed scale is met. above 0.5 and a Cronbachs Alpha of 0.82. This indicates
For the independent items a PCA with Varimax rotation a reliable scale.
was done in SPSS. The predicted numbers of factors should Attitude towards the use of LCC by the project leaders
be four. The rotated component matrix is shown in Table 1. (TAttitude) summed scale is made up of two items, both
As can be seen in Table 1, the items loaded against the showing correlation of each to the summated scale of 0.5, this
factors as predicted, and with factors that are signicant together with an alpha value of 0.67 indicate a reliable scale.
[12]. The total variance explained with the four factor solu- Information symmetry between the principle and the
tion is 73.1% which is considered indicative of a well agent regarding the use of LCC (TInfoSym) got a sum-
dened structure [12]. It can be concluded that it is statisti- mated scale that after the PCA was made up of three items.
cally highly signicant that uni-dimensionality is present in The items have an item to total correlation of 0.59, 0.54
the summed scales making up the dierent constructs. All and 0.5. Further the scale has a Cronbachs Alpha vale
items (dependent and independent) included in the nal of 0.72, and hence the scale should be reliable.
model can be seen in Appendix 2. The last independent construct is the project leaders (or
his/her teams) knowledge about LCC (TKnowledge). After
4.2.3. Reliability and scale validity the PCA only one item was removed and the nal scale has
Reliability on the collected data was checked through three items, with an item to total correlation of 0.72, 0.77
the use of item to total correlation and inter-item correla- and 0.48. This together with an alpha value of 0.8 indicates
tion on the items making up the scale and Cronbachs internal consistency.
Alpha for the constructs themselves. Item to item correla- Scale validity was assessed with the use of discriminant
tion is already presented in the last section, and found to validity. As can be seen in Table 1, the nal model demon-
be acceptable. strated good discriminant validity with no cross construct
Hair et al. [12] suggest that item-to-total correlation loadings above 0.5.
should exceed 0.50, however other researchers have advo-
cated a cut-o threshold of 0.4, [14]. Finally, since this 5. Test of hypotheses
research is of an exploratory nature the accepted lower
limit for Cronbachs Alpha (CA) is 0.60 [12]. In order to test the hypotheses of the study, a multiple
regression analysis was used. Before the regression equation
was set up a one-way analysis of variance (ANOVA) for each
8
Both Hair et al. [12] and Pallant [13] suggest that the cut of point for of the three control variables (type of project, project size and
the correlation coecient should be 0.3. project site) with use of LCC as factor was conducted in

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

6 B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx

SPSS. The analysis showed non-signicant dierence As explained in Section 3.1, uncertainty in this case
between the subgroups within project-type and project-size. study was chosen to be measured by so called COTS items.
Regarding project-site, however (whether the project is run The uncertainty construct used in this study correlated to
out of Kolsas (mostly Army), Bergen (mostly Navy) or Kjel- the use of LCC but only weakly, and with no statistical sig-
ler (mostly Air Force)), the ANOVA test showed, somewhat nicance. Based on this it was decided that the construct
surprisingly, that there was a statistically signicant dier- will not be included in the nal regression analysis. Hence
ence (0.003) somewhere among the mean scores on the use it must be concluded that in this case study no statistically
of LCC for the three sites. The descriptive data showed that signicant support was found towards Hypothesis 1: Pro-
projects lead out of Kjeller (N = 22) had a mean of 3.93, pro- ject uncertainty will negatively aect the use of LCC-based
jects based in Kolsas (N = 33) had a mean of 3.78 and pro- procurement decisions.
jects lead out of Bergen (N = 23) had a mean of only 3.33. The nal regression formula became:
Due to the non-metric data of the site variable two indica-
tor-coded dummy variables were made (ArmyCom and TUseofLCC b0 b1 TInfoSym b2 TKnowledge b4 TAttitude
NavyCom), with projects based in the earlier Air Force b5 ArmyCom b6 NavyCom e
Material Command as the comparison group. The initial
regression equation was set up as follows:
5.1. Regression analysis and results
TUseofLCC b0 b1 TInfoSym b2 TKnowledge b3 TUncertainty
b4 TAttitude b5 ArmyCom b6 NavyCom e The VIF values in Table 3 shows that multicollinearity is
not a problem. Hair et al. [12] estimate the minimum R
A normality plot and scatter plot of the standardized resid- square that can be found statistically signicant with a
uals against their predicted value as well as histogram of Power of 0.80 with 5 independent constructs and a sample
the error term distribution were produced and tests showed size of 78 to be approximately 17%. The total population in
acceptable results. this study is 150, and hence a sample size of 78 is fairly
The signicance level is set at the normal alpha level of large, it could therefore be argued that even a lower R
0.05. In the correlation and regression analysis one sided Square would be signicant. However, the nal model gave
tests are used. This can be done because prior to the tests a very acceptable result with an R square of 24.1%.
it was established through the hypothesis that the parame- The residuals of the regression were checked for linearity
ter will go in one particular direction. The correlation and homoscedasticity with the help of SPSS scatter plot,
matrix for the independent ordinal constructs (Table 2) and normality with the help of the Normal Probability Plot.
shows that multicollinearity initially is not a problem. The ndings did not indicate any nonlinear pattern to the
However, there is a statistical signicant bivariate correla- residuals. Further no pattern of decreasing or increasing
tion between the uncertainty construct and the information residuals can be seen, thus indicating homoscedasticity and
symmetry construct. This was expected, and the negative nally no substantial or systematic departure is observed
correlation indicates that the board is more informed about in the normal probability plot. Hence the regression variate
the use of LCC if the uncertainty for the project is high is found to meet the assumption of normality [12].
(more on this in the discussion section). Hypothesis 2 predicted that positive attitude towards
The correlation matrix further shows that TAttitude and the use of LCC by the project leader would positively aect
TInfoSym have statistically signicant correlation towards the use of LCC-based procurement decisions. This is sup-
the dependent construct (Use of LCC). The knowledge con- ported by the beta value for the standardized coecient
struct has not a correlation that is statistically signicant of the attitude construct (TAttitude = 0.215). The coe-
(signicance of 0.069) towards TUseofLCC but was still kept cient is as expected positive and it is statistically signicant
in the analysis because of the bivariate nature of the correla- with a one sided value of 0.0285 (P < 0.05), meaning that
tion matrix and the closeness to the 0.05 level of signicance. the attitude of the project leader towards the use of LCC

Table 2
Correlations and descriptive statistics
TUseofLCC TAttitude TUncertainty TKnowledge TInfoSym
TUseofLCC 1.0 0.284** 0.005 0.169 0.257*
TAttitude 1.0 0.121 0.095 0.043
TUncertainty 1.0 0.021 0.313**
TKnowledge 1.0 0.066
TInfoSym 1.0
Mean values 3.69 3.23 2.93 3.36 2.74
Standard deviation 0.64 0.95 1.31 0.73 0.81
* Correlation is signicant at the 0.05 level (1-tailed).
** Correlation is signicant at the 0.01 level (1-tailed).

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx 7

Table 3
Regression model, dependant variable: Use of LCC
Independent variable Unstandardized coecient Standard error Standardized coecient beta t-value VIF
Constant 2.522 0.482 5.232**
TInfoSym (b1) 0.108 0.087 0.137 1.241 1.150
Knowledge (b2) 0.182 0.090 0.209 2.013* 1.025
TAttitude (b4) 0.144 0.075 0.215 1.936* 1.170
ArmyCom (b5) 0.157 0.162 0.123 0.967 1.537
NavyCom (b6) 0.470 0.188 0.340 2.502* 1.752
N = 78; F = 4.578 (p < 0.001); R2 = 0.241; Standard error of the estimate = 0.572.
* Correlation is signicant at the 0.05 level (1-tailed).
** Correlation is signicant at the 0.005 level (1-tailed).

makes a signicant unique contribution to the prediction of (see Table 2). This correlation indicates that the project
the use of LCC based procurement decisions. board is more informed about the use of LCC if the uncer-
In Hypothesis 3, the prediction was that information sym- tainty for the project is high (non COTS). Information sys-
metry between principal (Ministry of Defense) and agent tems can curb adverse selection [8], and hence it can be
(project leader) regarding the use of LCC would positively argued that NoMoD through the project boards has made
aect the project leaders use of LCC. The empirical nding sure that less information asymmetry can occur when pro-
is that the relationship is as expected with a coecient of ject uncertainty is high (non COTS) in order to reduce the
0.137 (TInfoSym). However, this construct is not statisti- possibility of adverse selection. It looks like the Norwegian
cally signicant (signicance value of 0.11). There is in other Defence already uses the agency theory concept of informa-
words 11% probability that the result is due to chance, and tion alignment in order to reduce the possibility of adverse
thus the hypothesis is not statistically supported. selection more in projects with high uncertainty than in pro-
The last hypothesis (Hypothesis 4) is supported empiri- jects with low uncertainty, and due to this we could not sta-
cally. It was initially hypothesized that better knowledge tistically conclude that project uncertainty negatively aects
about life cycle costing would increase the use of LCC the use of LCC-based procurement decisions.
based procurement decisions. The ndings indicate statisti- As stated above the rst problem in agency relationships
cal signicance with the one tail test of 0.024 (P < 0.05) and is that of conicting goals between the principal and the
a coecient of 0.209 (TKnowledge). agent [8]. The research questions tried to captured the atti-
Finally, the negative beta coecients for the two tude of the project leaders towards the use of LCC, in order
dummy variables (ArmyCom and NavyCom) indicate that to answer Hypothesis 2. The hypothesis was supported by
the intercepts for these two groups are lower than for the the empirical data, and from a theoretical standpoint this
reference group (Air Force site). However the lower inter- means that less goal conict exists between projects leaders
cept of the Army site (ArmyCom) is not statistically signif- with a positive attitude towards LCC and the principle,
icant, in comparison to the intercept of the Navy site than between the principle and project leaders with a less
(NavyCom), which is statistically signicant (see Table 3). positive attitude towards LCC.
According to agency theory one of the most eective
6. Discussion and conclusions ways to avoid goal conicts is to align the information
between the principle and the agent [8]. Statistically signi-
As stated in the theory section, Eisenhardt [8] claims cant support, based on the 0.05 signicant level, was not
that two main problems occur in agency relationships, found towards the hypothesis regarding information sym-
the rst problem is that of conicting goals between the metry between the principal and the agent (Hypothesis 3).
principal and the agent, and the second problem is that However, there is no more than 11% chance that the positive
of risk preferences. beta coecient found in the empirical data (which supports
It was assumed that the NoMOD would be risk neutral the hypothesis), is due to chance. Further, since the sample
when it comes to evaluating projects based on life cycle cost, size in the case of this research consists of more than 50% of
while the project leader was assumed to be risk adverse, the total population, it is very likely that information sym-
especially if the project in question had high project uncer- metry between the principal and the agent really makes a
tainty. The rst hypothesis therefore stated that Project unique contribution to the use of LCC based procurement
uncertainty will negatively aect the use of LCC-based pro- decisions. Hence, even if not statistically supported, the data
curement decisions. The data analysis showed that uncer- is in line with the agency theory proposition.
tainty correlated to the use of LCC, and in the direction Regarding the proposition that when the agent, either
that theory assumed (negative correlation). However, the by himself or through members within his own project,
correlation was weak and not statistically signicant, and has thorough knowledge about life cycle costing, he will
hence the hypothesis had to be rejected. It is however inter- be more likely to understand and accept the position of
esting to notice that there is a statistical signicant bivariate the principle (NoMoD), and therefore use LCC (expressed
correlation between uncertainty and information symmetry in Hypothesis 4) is supported by the data. This means that

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

8 B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx

Waaks [1] theory about lack of knowledge, with regard to tom line is that NoMoD must use every opportunity, to
LCC, leading to less use is empirically supported. ensure the project community that they really mean what
At the start of the research, control variables regard- they are stating in the concept.
ing what main type of procurement the project is dealing NoMoD together with the Norwegian Defence Material
with (project-type), what NoDLO site the project works Agency and the Norwegian Defence College started a pro-
out (project-site) of and the size of the project in terms ject leader certication program some years ago. The rst
of personnel working with LCC (project-size) were fully certied project leaders graduated in the spring of
included in the research model. The project leaders were 2005.9 In this program, use of LCC based procurement
asked to mark what subgroup within each of the tree decisions is a part of the education. The data of this anal-
variables they belonged to. No hypotheses were made ysis clearly show that project leaders with good knowledge
before the collection of data, and it was really not of LCC are more likely to use LCC in procurement deci-
expected to be a statistically signicant dierence between sions than those with less knowledge. It is therefore essen-
the subgroups within each variables. This was also the tial for the NoMoD to continue this program (and other
case regarding project-type and project-size. Somewhat programs/courses where LCC concepts can be learned), if
surprisingly though, the data clearly show that project they want the use of LCC to grow.
leaders working in Bergen (the Navy site) are on average Finally, since the data show that project leaders working
less likely to use LCC based procurement decisions than out of the old Navy Material Command site are less likely
their colleagues working in the Air Force site and the to use LCC based procurement decisions than their Army-
Army site. The data collected cannot verify why this is and Air Force-site colleagues, NoMoD should probably
the case. It is however a fact that the Navy site (Bergen) focus rst on this group of project leaders.
is much further in physical distance from the NoMoD The managerial implications discussed in this paper are
(the principal) situated in Oslo, than the Army site (Kol- all based on the data collected through the questionnaire
sas, just outside Oslo) and Air Force site (Kjeller, also issued to the project leaders under research. The question-
just outside Oslo). Other explanations could be connected naire was developed with the purpose of being able to
to organizational cultural dierences between Navy, accept or reject the hypotheses put forward in the research
Army and Air Force regarding how closely the goals model. Limited data is therefore available toward for
and tasks of the mandate group (the principal), are fol- example issues of organizational behaviour. However the
lowed. These are however only speculations. implications suggested above, are all in line with latest
research regarding the importance of managing relation-
6.1. Managerial implications ships for project success [15]. Due to space limitations fur-
ther discussions of general organizational issues will not be
The data show that high uncertainty in terms of projects addressed in this paper but can for example be explored in
with non COTS procurement, have better information the 2005 dissertation by Bourne [15].
alignment than projects that are less uncertain. Hence we
see that uncertainty already is closely connected to infor- 7. Limitations and future research
mation symmetry. In order for NoMoD to make sure that
project leaders do use LCC in procurement decisions it Since this is a case study from the Norwegian Defence,
becomes important that all projects are followed up by a the ndings can not be automatically transferred to other
project board. Further, this board must make sure that organizations considering the use of LCC based procure-
they and the project leader have the same information ment decisions. We do however believe that our ndings
about how LCC is used. Our data suggest that projects that could be benecial to most organizations.
have information symmetry regarding LCC decisions with We have in this study chosen to measure uncertainty by
the principal are more likely to use LCC than projects that the use of so called COTS items. Hence the focus has not
do not. been on the uncertainty based on for example task depen-
Further the empirical data clearly show that NoMoD dency, and thus such data were not collected. We accept
should do what they can to get a positive attitude from that this might be a limitation of the study, and that it
the project leaders towards the use of LCC, because this could on one hand be argued that if uncertainty was mea-
will assure more use of LCC based decisions. Answers to sured by a wide variety of items in addition to the COTS
the items of the attitude construct, indicate that not all pro- items (e.g. task complexity and task duration), we could
ject leaders believe that NoMoD really mean what they are have ended up with statistical acceptance of the uncertainty
stating in the LCC concept. In this concept NoMOD hypothesis. On the other hand we did, as shown earlier,
clearly state that when investment decisions are made, they collect data on project-type and project-size and found
must favour solutions that yield the lowest possible life only non-signicant dierence between the subgroups.
cycle cost, even if this means that the initial investment cost
becomes higher. Project leaders that do not believe in the
concept have a more negative attitude, and use LCC less 9
See, http://www.prinsix.no/prinsix/nyheter/krav_til_sertisering_
than those that believe what NoMOD is saying. The bot- av_prosjektlederkompetanse.

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx 9

A further limitation to the study is that the three ordi- this research, it is suggested that a more in depth qualita-
nal constructs and the dummy variables that ended up in tive case study of the use of LCC in Norwegian Defence
the nal analysis do not explain fully why some procure- Procurement projects could be conducted. According to
ment projects are still carried out and reviewed based on Yin [16], the most important application of a qualitative
initial procurement costs alone when the ocial policy is case study is to explain causal links in real-life interven-
to apply the life cycle cost approach. Other variables, tions that might be too complex for a quantitative survey
together with the ones already included in this study, to fully comprehend. Hence a possible future research
must be examined in order to fully answer the question. into the main question of this study could utilize Yins
Further the empirical data does not tell us why the pro- qualitative case study methodology. Finally, other theo-
jects leaders working out of the Navy site are less likely retical perspectives, like for example the administrative,
to use LCC than their project leader colleagues in the political and actor-network perspective used in earlier
Army- and Air Force-site. In order to examine this nd- studies of complex implementation processes [17], as well
ing, and other variables besides the ones hypothesised in as stakeholder theory [15] could also be addressed.

Appendix 1.

Correlation matrix for the dependent construct items


Use of LCC1 Use of LCC2 Use of LCC3 Use of LCC4 Use of LCC5
Use of LCC1 1
Use of LCC2 .528 1
Use of LCC3 .668 .468 1
Use of LCC4 .382 .381 .337 1
Use of LCC5 .376 .388 .393 .288 1

Correlation matrix for the independent constructs items

Uncer- Uncer- Uncer- Attitude Attitude Info Info Info Knowl- Knowl- Knowl-
tainty1 tainty2 tainty3 LCC5 LCC6 symmetry2 symmetry3 symmetry4 edge1 edge3 edge4
Uncertainty1 1
Uncertainty2 .792 1
Uncertainty3 .495 .532 1
Attitude .021 .052 .099 1
LCC5
Attitude .085 .094 .188 .503 1
LCC6
Info .258 .238 .239 .037 .007 1
symmetry2
Info .187 .196 .137 .005 .075 .521 1
symmetry3
Info .251 .222 .202 .066 .154 .459 .392 1
symmetry4
Knowledge1 .046 .051 .033 .040 .233 .208 .001 .012 1
Knowledge3 .085 .004 .097 .080 .071 .043 .136 .149 .492 1
Knowledge4 .017 .081 .016 .015 .155 .008 .217 .164 .416 .845 1

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005
ARTICLE IN PRESS

10 B.E. Tysseland / International Journal of Project Management xxx (2007) xxxxxx

Appendix 2.

Measure of constructs
UseofLCC1 In the project we evaluate how dierent system solutions will aect the operations- and maintenance-
costs.
UseofLCC2 In my project we evaluate which technical solution will give the lowest operator training costs in the
operational phase of the equipment/system.
UseofLCC3 In my project we evaluate which systems will give the lowest maintenance costs in the operation and
support phase.
UseofLCC4 In a situation where two alternative systems yield the same benet, I would recommend the system
that gives the lowest possible life cycle cost, even if this means that the initial investment cost becomes
higher.
UseofLCC5 In my project we recommend/choose the system solution that gives the lowest initial procurement
(reversed) cost.
Knowledge1 All members of the project have knowledge about integrated logistic support and life cycle costing.
Knowledge3 I have good knowledge regarding integrated logistic support.
Knowledge4 I have good knowledge regarding life cycle costing.
Uncertainty1 In my project everything we procure is commercially available (commercially of the shelf).
Uncertainty2 In my project the main part of the procurement is commercially available.
Uncertainty3 In my project very little or nothing of what we procure is commercially available.
(reversed)
Info symmetry2 My project board (or the one I report to) has the same information regarding operations- and
support-cost for the alternative solutions/systems as I have.
Info symmetry3 My project board (or the one I report to) understands the concepts of life cycle costing.
Info symmetry4 Operations- and support-costs for the system I am procuring are on the agenda of the board
meetings.
Attitude5 There is no purpose in doing life cycle cost analysis, because the initial procurement cost will be the
(reversed) decisive factor anyway.
Attitude6 Operating costs, support costs and disposal costs for the system/material my project is procuring are
(reversed) less important than initial procurement cost.

References [11] Wikipedia, The Free Encyclopedia. <http://en.wikipidia.org>.


[12] Hair Jr Joseph F, Black William C, Babin Barry J, Anderson Rolph
[1] Waak Olof. Cut Maintenance and Logistics Support Cost with 50%, a E, Tatham Ronald L. Multivariate data analysis. 6th ed. Upper
fantasy or a feasibility. <http://www.systecon.se>. 2004. Saddle River, New Jersey: Pearson Prentice Hall; 2006.
[2] Fabrycky WJ, Blanchard BS. Life cycle cost and economic analysis. [13] Pallant Julie. SPSS Survival Manual. 2nd ed. Shoppenhangers Road,
Upper Saddle River, New Jersey: Prentice Hall; 1991. Maidenhead, Berkshire, United Kingdom: Open University Press,
[3] Masiello Gregory L. Reliability the life cycle driver: an exam- McGraw-Hill Education; 2005.
ination of reliability management, culture and practices, Master [14] Xiao Li, Dasgupta Subhasish. Measurement of User Satisfaction with
of Science Thesis, US Naval Postgraduate School, Monterey, Web-based Information Systems: an Empirical Study, Eighth Amer-
California. 2002. icas Conference on Information Systems. 2002.
[4] Ferrin Bruce G, Plank Richard E. Total cost of ownership models: an [15] Bourne Lynda. Project relationship management and the stakeholder
exploratory study. J Supply Chain Manage 2002;38:1829. Circle. A dissertation submitted in partial fullment of the
[5] Kirkpatrick David. The cost eectiveness of smart acquisition. RUSI requirement for the degree of Doctor of Project Management,
Def Syst 2004;6(3):936. Graduate School of Business, RMIT University, Australia 2005.
[6] Wouters Marc, Anderson James C, Wynstra Finn. The adoption of [16] Yin RK. Case study research design and methods. California:
total cost of ownership for sourcing decisions a structural equations SAGE Publications Thousands Oaks; 1994.
analysis. Account Org Soc 2005;30:16791. [17] Borum Finn, Christiansen John K. Revisiting the implementation
[7] Greve A. Organisasjonsteori nyere perspektiver. Universitetsforla- metaphor a comment on Actors and structure in IS Projects: what
get AS, Oslo. 1995. makes implementation happen?. Scandinavian J Manage 2006;22:
[8] Eisenhardt KM. Agency theory: an assessment and review. Acad 23842.
Manage Rev 1989;14(1):5774. [18] Rdseth Aage, Langeland Arne, Lilletvedt Tom Egil, Irgens Chris-
[9] Bergen M, Shantanu D, Orville Jr CW. Agency relationships in tian, Nysteen Klaus-Anders. Integrert logistikksttte i SFK, Haak-
marketing: a review of the implications and applications of agency onsvern, Bergen.1995.
and related theories. J Market 1992;56:124. [19] Bryman Alan, Cramer Duncan. Quantitative data analysis with SPSS
[10] Gemunden G, Salomo S, Krieger A. The inuence of project Release 10 for Windows, Routledge, 27 Church Road, Hove, East
autonomy on project success. Int J Project Manage 2005;23:36673. Sussex. 2001.

Please cite this article in press as: Tysseland BE, Life cycle cost based procurement decisions, Int J Project Manage (2007),
doi:10.1016/j.ijproman.2007.09.005

Das könnte Ihnen auch gefallen