QMS INITIAL ASSESSMENT

KAPCO Manufacturing, Inc.

Date: June 2, 2009

Program Objectives:

ISO 9001:2008 Certification, New application.


Enhance QMS to align with current organizational structure and business process
Work on possible application of management softwares

Program Commencement: June 2, 2009

Target Completion: Last Week of November 2009

Nature of Business: Surface treatment and plating process

Scope of Certification: Provision of Surface treatment and plating process

Previous Certification: June 2008 Validity under MOODY International

Number of Employees: 170

ISO 9001:2008 Assessment Result

ISO CLAUSE EXISTING SYSTEM CURRENT STATUS REQUIREMENTS REMARKS


4.0 Quality Management Business Process Map Not updated - Established, document, implement, Identify Business needs and organizational set-
System Quality Manual Not updated maintain and improve the QMS up.
4.1 General Requirements Procedures Updated effectiveness.
Work Instructions Not updated - Business Processes Description Design and Develop QMS based on the current
Quality Plans Updated - Control of Outsourced Process business process and organizational structure.
Records
Conduct Business Process Mapping Session.
4.2 Documentation Quality Manual based on Not updated - Documented Quality Policy and Needs updates and revision in compliance to
Requirements ISO 9001:2000 Objectives ISO 9001:2008
4.2.1 General - Quality Manual
4.2.2 Quality Manual - Procedures and records
- Extent of documentation depends on
the organization
4.2.3 Control of Documents Procedure: Control of Implementation on going, Documents and records required by the Alignment with current business operation and
Documents & Control of records are updated and QMS must be controlled. ISO 9001:2008.
Records maintained.
4.2.4 Control of Records In-charge: 2 DCC Documented procedure is required for Try Implementation of Document Control
personnel Archive room maintained documents and records control. Software.
- Access & Filing System not
implemented in some Orientation of staff and employees on
departments document and records control is
recommended.
5.0 Management President: Mr. Y. Kurosaka President: Active Required evidence of commitment for Recommend system or process for top
Responsibility VP: Mr. T. Kurosaka VP: Based in Japan QMS development, implementation and management involvement and participation.
5.1 Management GM: Mr. R. Naito GM: Based in Japan Improvement.
Commitment Check how this requirement is being met and
5.2 Customer Focus Ensure customer requirements are recommend a system or process in order to
determined and are met with the aim of comply
enhancing customer satisfaction.
5.3 Quality Policy Quality Policy The Same, currently used, Appropriate to the purpose of the A review of Quality Policy content is
documented and posted evidence of continuing review organization. recommended.
not available
Includes commitment to comply with Check if the Policy provides framework for
requirements & continually improve the establishing objectives, what does this really
QMS effectiveness. mean?

Provides a framework for establishing Check method of review and communication


objectives and how are these defined in the QMS

Is communicated and understood

Needs review for continuing suitability


5.4 Planning Department Goals, Not established for the Top management must ensure quality Review and develop guidelines for setting and
5.4.1 Quality Objectives targets, measurable previous years objectives including those needed to monitoring quality objectives.
objectives. meet requirements for the product are
established at relevant functions and
levels within the organization.

Must be measurable and consistent with


the quality policy

Must ensure planning of QMS is carried Develop guidelines for the Conduct of QMS and
5.4.2 QMS Planning QMS and Business Not performed since 2006 out. Ensure the integrity of QMS is Business Planning.
Planning maintained when changes are planned
and implemented.
5.5 Responsibility, Authority Organizational Stucture - Updated Must ensure responsibilities and Review of Manpower job assignments and
and Communication Job Descriptions - Not updated, some not authorities are defined and departmental functions is recommended.
5.5.1 Responsibility and Authority & Approval available communicated
Authority Matrix - Not updated Study the need for re-allocations of job, vs
Departmental/Functional hiring and transfer of employees.
Description - Not updated
Set appointment and schedule for organizing
activity.

Develop or revise documentation when


necessary.
5.5.2 Management Appointed QMR - Existing and employed MR must be appointed by top Review position and appointment of MR
Representative - Records not updated management and must be a member of
the management.

Shall have responsibility and authority: Check how the MR should meet the
- Ensure that the QMS is established, responsibility and authority requirements. Set
implemented and maintained guidelines or incorporate in the system when
- Reporting the performance of the QMS necessary.
- Ensuring the promotion of awareness
of customer requirements
5.5.3 Internal Communication - Meetings - Existing and regularly Check the need for allocating bulletin boards
- Memos conducted and other internal communication processes.
- Bulletin Boards - Memos still circulated
- Bulletin Boards are used
5.6 Management Review Management Review Last Management Review Shall review the QMS at planned Review System for the conduct of management
Meeting at least twice a Year 2006 intervals to ensure its continuing review. Set guidelines when necessary.
5.6.1 General year. suitability, adequacy and effectiveness.

5.6.2 Review Input Required Inputs


Required Outputs
5.6.3 Review Output
Records shall be maintained (1)

6 Resource Management PPC and Warehouse - Implemented and Shall determine and provide resources Review the existing system and align It with the
process 2 In charge maintained needed to: current organizational set-up and ISO
6.1 Provision of resources HR procedure 1 HR - Implemented and - Implement and maintain the QMS and 9001:2008 requirements.
personnel Maintained continually improve its effectiveness
Accounting procedure 2 - Implemented and - To enhance customer satisfaction by Identify available records to demonstrate
In charge maintained meeting customer requirements compliance.
6.2 Human resources Job Specifications - Existing not updated Personnel performing work affecting Review the existing system and align it with the
Competency Statement - Existing and not updated conformity to product requirements shall current business needs and requirements of
6.2.1 General Training Procedure - Partially implemented mostly be competent. ISO 9001:2008.
general orientation
6.2.2 Competence, training Training In-charge 1 HR Determine the necessary competence.
and awareness Officer
Where applicable provide training or
other actions to achieve the necessary
competence.

Evaluate the effectiveness of the action


taken.
Ensure personnel awareness
Records shall be maintained (2)
6.3 Infrastructure Facilities and maintenance -Partially implemented, some Shall determine, provide and maintain Review the existing system and align it with the
Procedure records not updated the infrastructure needed to achieve current business needs and requirements of
-Some improvements in product conformity. ISO 9001:2008.
1 Staff facilities -Buildings, workplace and associated
utilities
-Process equipment (both hardware and
software)
-Supporting services (such as transport,
communication or information systems)
6.4 Work environment Clean room procedure -Implemented and Determine and manage the work Review the existing system and align it with the
Health and Safety maintained environment needed to achieve current business needs and requirements of
program -Not established conformity to product requirements. ISO 9001:2008.
7.0 Product Realization Product Planning and -Not fully implemented. Review the existing system and align it with the
realization. -Not fully implemented current business needs and requirements of
7.1 Planning of Product -Implemented, records not ISO 9001:2008.
realization Sales Marketing Flow available

Test Run

Quality Plan
7.2 Customer-related Sales and Marketing Flow - Sales and Marketing section Review the existing system and align it with the
processes removed in current current business needs and requirements of
organizational chart. ISO 9001:2008.
7.2.1 Determination of - Sales marketing are mostly
requirements related to the performed by mother
product company or the Japanese
management
7.2.2 Review of requirements - Former System is currently
related to the product not implemented.

7.2.3 Customer
Communication

7.4 Purchasing Purchasing procedure - System is partially Review the existing system and align it with the
implemented current business needs and requirements of
7.4.1 Purchasing process 1 Purchasing Staff ISO 9001:2008.

7.4.2 Purchasing Information

7.4.3 Verification of purchased


product Inspection & Testing - Implemented but records are
receiving inspection. not maintained.
- Performed by purchasing
- Warehouse staff
7.5 Production and service Production Schedule (PPC -Implemented but records are Clarify guidelines when should be a WIS be
provision Flow) not available. provided.

7.5.1 Control of production - 2 Staff Review the need for establishing SOP or
and service provision Operations Manual.
SOP not established -WIS Complete and posted
WIS available -Production Records
Production Reports maintenance Partially
implemented
7.5.2 Validation of processes QC-Engg Process - System not fully Review the existing system and align it with the
for production and service Test Run implemented current business needs and requirements of
provision Inspection and Testing - Records not available ISO 9001:2008.
- Performed under supervision
of Production Manager
7.5.3 Identification and Identification and - Not fully implemented, Review the existing system and align it with the
traceability Traceability records not maintained. current business needs and requirements of
ISO 9001:2008.

7.5.4 Customer Property Control of Customer - Not fully implemented and Review the existing system and align it with the
Property maintained. current business needs and requirements of
ISO 9001:2008.
7.5.5 Preservation of product Preservation of Product - Implemented but not in Review the existing system and align it with the
Inventory Management accordance with designated current business needs and requirements of
function. ISO 9001:2008.
- Under
Warehouse
7.5.6 Control of monitoring Control of Monitoring and - Implemented but some Review the existing system and align it with the
and measuring equipment Measuring device. lapses is assumed. current business needs and requirements of
ISO 9001:2008.
Performed under
maintenance section
8.0 Measurement Analysis Statistical Techniques - Not fully implemented Identify the need for the application of
and Improvement statistical techniques and other measurement
analysis and improvement activities.
8.1 General
Identify training needs and provide the
training.
8.2 Monitoring and Sales & Marketing - Not fully implemented Review the existing system and align it with the
Measurement current business needs and requirements of
ISO 9001:2008.
8.2.1 Customer Satisfaction

8.2.2 Internal Audit Internal Audit Procedure - Not fully implemented Review the existing system and align it with the
current business needs and requirements of
ISO 9001:2008.
Identify training needs and provide the training
8.2.3 Monitoring and Inspection and Testing - Implemented and records Review the existing system and align it with the
measurement of processes maintained. current business needs and requirements of
ISO 9001:2008.
8.2.4 Monitoring and Inspection and Testing - Implemented and records Review the existing system and align it with the
measurement of product maintained. current business needs and requirements of
ISO 9001:2008.
8.3 Control of Nonconforming Control of Nonconformity - Not fully implemented Review the existing system and align it with the
Product current business needs and requirements of
ISO 9001:2008.
8.4 Analysis of Data Quality Manual - Not fully implemented Identify and Classify data needed for gathering
and analysis.

8.5 Improvement Quality Manual - Not fully implemented Identify continual improvement programs
- More on facility suited for the company.
8.5.1 Continual Improvement Continual Improvement Improvement
programs
8.5.2 Corrective Action Corrective Action - Only external concerns with Review the existing system and align it with the
Procedure issued corrective action current business needs and requirements of
records ISO 9001:2008.

8.5.3 Preventive Action Preventive Action - Preventive action not fully Review the existing system and align it with the
Procedure implemented. current business needs and requirements of
ISO 9001:2008.

Conducted by:

Norlito M. Suelo

MST Consulting & Training Services

Noted by:

Aprilyn Armintia

KAPCO Manufacturing Inc.