Beruflich Dokumente
Kultur Dokumente
............. Dated:
TECHNICAL NOTE
COMMENTS
1. Scope of work:
A. Rehabilitation and Upgradation of Pune - Mulshi - Mangaon - Mhalsa -Dighi Port and
Indapur (NH-66)-Tala - Mandad - Agardanda -Dighi Port (SH-96 & SH-92). This
section [Section-I(A) : Pune- Shende Patil Wada] starts from existing km 13+180 in
Pune (On Mumbai Banglore By Pass) & ends at existing km 43+420 in Shenda Patil
Wada in the state of Maharashtra. The project road starts at design km 1+275 and
ends at design km. 31+400 of Pune Shenda Patil Wada, NH-753F to two lane with
paved shoulder configuration in the state of Maharashtra through an Engineering,
Procurement and Construction (EPC) mode.
B. Following provisions have been allowed:
Total - 30.125 km
(c) Culverts
(f) Traffic Control Devices, Road Safety Work and Road Furniture as per
provision of manual have also been taken.
As there are Electricity poles are at some places and water supply line at few
point found in between ROW, a provision of Rs. 640.2 lakh is considered in
estimate for shifting of these utilities.
CE, MSRDC has confirmed that 93.46% of total land required for project
implementation is in possession of Department and status of remaining 6.54
% land acquisition is as under:
Total Land required = 60.25 Ha,
Total Land available =56.31 Ha
Total Land to be acquired= 3.94 Ha,
(i) Private Land= 3.94 Ha.
(ii) Forest Land= Nil
S. AMOUNT AMOUNT
ITEM OF WORKS
No. (Rs.) (Cr.)
1 ROAD WORKS
i BILL No. 1 - SITE CLEARANCE AND DISMANTLING 14050257.03 1.41
BILL No. 2 - EARTH WORK, EROSION CONTROL AND
ii 108047057.32 10.80
DRAINAGE
BILL No. 3 - SUB-BASES, BASES (NON- BITUMINOUS) AND
iii 145967362.99 14.60
SHOULDERS
iv BILL No. 4 - BITUMINOUS PAVEMENT 8896300.00 0.89
V BILL No. 5 - CEMENT CONCRETE ROAD 852583424.65 85.26
vi BILL No. 6 - NEW JERSEY TYPE MEDIAN 60212764.44 6.02
vii BILL No. 7 - C.C. DRAIN 206721561.37 20.67
viii BILL No. 8 - PAVER BLOCK 164036005.00 16.40
BILL No. 9 - TRAFFIC SIGNS, ROAD MARKINGS AND OTHER
ix 129088061.67 12.91
APPURTENANCES
BILL No.10 - JUNCTION IMPROVEMENT & APPROCHES
x 112554877.68 11.26
IMPROVEMENT
xi BILL No.11 - PLANTATION (HORTICULTURE) WORK 7809400.25 0.78
S. AMOUNT AMOUNT
ITEM OF WORKS
No. (Rs.) (Cr.)
xii BILL No.12 - PROTECTION WORK 103970347.80 10.40
xiii BILL No.13- BUS SHELTER 4599344.00 0.46
AMOUNT - I 1918536764.20 191.85
2 CD-STRUCTURES - BIIL No. 11
i RECONSTRUCTION OF CULVERT 52,754,760.25 5.28
ii WIDENING OF CULVERT 11,733,348.00 1.17
iv RECONSTRUCTION OF MINOR BRIDGE 71,570,138.90 7.16
v WIDENING & REPAIR OF MINOR BRIDGE 79,503,916.30 7.95
AMOUNT - II 215,562,163.45 21.56
(A) COST OF CIVIL WORKS (SUB TOTAL) BASE COST 2,134,098,927.65 213.41
MODIFICATIONS & DEVIATION , IF ANY
SUB TOTAL FOR CIVIL WORKS (A) 2,134,098,928 213.41
COST PER KM FOR CIVIL WORKS 70,841,458 7.08
3. Modifications:
Nil
4. Design specifications including deviations, if any:
All material, design and construction operations for the project are proposed
conforming to the IRC: SP: 73-2015 & deviations as mentioned in Schedule D
to the Manual are proposed to be followed. Manual of Specifications and
Standards for Two-laning of Highways, IRC-58-2011 and Ministry standard
specification Revision-V 2013.
5. Specifications
6. Contract Documents:
7.1 The time limit for awarding of this work is 6 months from the date of sanction
and should be strictly followed as per the instructions communicated to all
State PWD/ MSRDC vides this Ministry's letter no. RW/NH-15015/29
/2001-PL dated 05.07.2001 and compliance reported to the Ministry. If the
work is not awarded within the stipulated time, it may lead to de-sanction of
the work unless Ministry's prior approval to extension of the time limit is
obtained.
7.2 CE, M.S.R.D.C. will intimate this Ministry about award of
contract/commencement of work immediately as per instructions contained
in this Ministry's letter no. RW/NH-11060/1/98-(DO-I) dated 05.11.1998.
7.3 E procurement must be adhered to while inviting tender for the work.
7.4 The tenders for the work shall be invited on EPC mode as per guidelines
issued by this Ministry vide circular letter No.RW/NH-24035/4/2008-P &
M/PIC dated 21.05.2011 in addition to guidelines issued by this Ministry vide
circular Letter No. RW/NH-11024/3/99-US (D-1) DATED 9.3.2000, No.
RW/NH-24035/4/2008-P&M dtd. 21.05.2010 and No.NH-
12037/67/2010/LWE dated 2.8.2010. The work shall be awarded as per
guidelines issued by the Ministry vide letter No.NH-15015/29/2001-PL dated
05.07.01.
7.5 While accepting tenders that the overall cost of estimate at tender rates
including contingencies, work charge establishment and agency charges does
not exceed by more than 5% of sanctioned cost.
7.6 Excess in tender cost is caused only be routine factors such as increase in cost
of labour or material.
8. General
8.2 The estimates for carrying out the activities under the provision of
contingencies including change in scope of work will be approved by
Ministry on assurance/certification by Authority's Engineer/CE (NH), PWD
Department that the amount provided against contingencies is available and
the same has not been indirectly utilized by accepting higher tender rates.
Authority's Engineer/ENC/CE (NH), PWD Department shall also certify that
approval of estimates to be charged to contingencies will not cause revision of
the sanctioned estimate.
8.5 In order to ensure that there is no slippage in achieving the targets, the
progress may be closely monitored by ENC/CE (NH), R86B Departmental
quarterly status report be furnished to the Ministry in the prescribed
proforma.
8.6 During the course of execution, the traffic may be regulated in accordance
with guidelines laid down vide Ministry's letter no. NHIII-33 (126)/72 dated
20.03.1973 and letter No.RW/NH-11060/1/1998-D.O.1 dated 07.10.1987.
Smooth flow of the traffic may be ensured by providing adequate traffic
control devices in accordance with stipulation of IRC: SP: 55:2001 "Guidelines
on Safety in construction Zone".
8.8 The display boards on development activities of the work shall be made as
per guidelines issued vide Ministry's letter no. RW/NH-33044/ 10/2002-S&R
(R) dated 26th May, 2003. The cost of the same will be met out of the
provision of contingencies allowed in the estimate.
8.9 Provision for quality control @ 0.25% has been allowed. The work is to be
carried out in accordance with the "Hand Book of Quality control for
construction of Roads and Runways (Second Revision)-IRC SP:11-1988",
observing strict quality control instructions contained in the Ministry's letter
No.NH-III/P/I/83 dated 19 April 1984 and permanent records maintained
thereof.
8.10 The independent quality control tests of all items from any of the accredited
laboratories as per IRC: SP:94-2011 shall be carried out from the quality
control provision in estimate to ensure the quality of work.
8.11 Neither the work nor any item of work shall be split into small parts for
awarding the work to a number of contractors. In this regard, instructions
issued in this Ministry's letter No. NH-III/P/25/84 dated 4/8/1984 may be
referred
8.12 Guidelines for Road Safety vide Ministry's letter No. RW/ NH-
33072/04/2004-S86R(R) dated 27.04.2012 shall be followed wherever
applicable.
9. Cost of work:
9.1 The estimate is based on rates of SOR Pune Circle based on year 2016-17 and
applicable to 2016-17. It is presumed that CE, M.S.R.D.C. while forwarding
the proposal has satisfied himself about the adequacy and workability of the
rates of various items of work and that rates adopted in the estimate are latest
and no revision of the rates has occurred till date.
9.2 The lead for the carriage of different materials as proposed in the estimate has
been allowed for estimate purpose only. However, while calling tenders the
sources may not be indicated. The contractor shall be responsible to procure
the material conforming to specification of the work. No provision of extra lead
during execution of the work shall be allowed.
9.3 In view of the above comments, the cost of the estimate amounts to Rs. 268.21
Crores including 3% agency charges.
10. Targets:
Following physical and financial targets shall be strictly adhered to subject to the
availability of funds:
Cumulative progress
Financial (Rs. in Crores)
Year
Milestone
Physical Construction Maintenance Total
2016-17 Preliminary
2017-18 Milestone I 40% 105.15 0 105.15
2018-19 Milestone II 100% 262.87 0 262.87
2019-20 Milestone III 100% 0 0.53 263.40
2020-21 Maintenance 100% 0 1.07 264.47
2021-22 Maintenance 100% 0 1.60 266.07
2022-23 Maintenance 100% 0 2.13 268.21