SITE WORK
Staking out of building, establishment of lines grades and benchmarks.
All excavation work including all necessary shoring bracing, and drainage of
storm water from site. All backfilling and grading, removal of excess material
from site. Protection of property, work and structures, workmen, and other
people from damage and injury.
EXCAVATION
Structural Excavations-Excavations shall be depths Structural
Excavations-Excavations shall be depths shall be filled in concrete, and
bottom of such shall be level. All structural excavations shall extend as
sufficient distance from the wall and footings to allow for proper erection and
dismantling of forms, for installation of service and for inspection. All
excavations shall be inspected and approved before pouring any concrete,
laying underground services for placing select fill materials. The contractor
shall control the grading in the vicinity of all excavated areas to prevent
surface drainage running into excavations. Water which accumulates in
excavated areas shall be removed by pumping before fill or concrete is
placed therein.
Forms should not be removed until the concrete has attained sufficient
strength to support its own weight and any loads that may be placed on it.
Side forms of girders and beams may be removed earlier than the bottom
forms but additional post or shoring must be placed under the girders or
beams until they attained their strength.
GENERAL
Unless otherwise specified herein, concrete work shall conform to the
requirements or the ACI Building Code. Full cooperation shall be given other
trades to install embedded items. Provisions shall be made for setting items
not to be placed in the forms. Before concrete is placed embedded items
shall have been inspected and tested for aggregates and other materials
shall have been done.
MATERIALS
Cement for the concrete shall conform to the requirements of
specifications for Portland Cement (ASTM C-150).
Water used in mixing concrete shall be clean and free from other
injurious amount of oils, acids, alkaline, organic materials or other
substances that may be deleterious to concrete or steel.
The following proportions of concrete mixtures shall be used for the various parts of
the building:
All steel reinforcing bars shall be accurately placed and secured against
displacement by tying them together in each bar intersection with #16 GI Tie wire.
No reinforcing Bars shall be welded for tying which can impair the strength and
durability of steel. The steel reinforcing bars indicated for footings, columns, slabs,
beams, girders and other concrete members shall all conform to the number, size
and spacing as indicated in the drawings or schedule of steel reinforcements.
No steel reinforcements shall be installed in place unless it is free from rust,
scale or other coatings which will destroy or reduce the bond with concrete.
All exposed surfaces of the concrete hollow block walls shall be cement
plaster finish as indicated in the plans. The mixture of cement plaster for concrete
hollow block wall finishes shall be 1 part cement, 1 part lime, and 3 parts sand.
FLOOR FINISHES
The materials to be use as floor finishes for the building shall be as follows:
Living Area - Ceramic Floor Tiles (Unglazed)
Dining Area - Ceramic Floor Tiles (Unglazed)
Kitchen - Ceramic Floor Tiles (Unglazed)
Bedrooms - Ceramic Floor Tiles (Unglazed)
Toilet & Bath - Ceramic Floor Tiles (Unglazed)
All tiles for floor, walls and mouldings shall be free from separated edges,
chipped off corners and other defects which would adversely affect their
appearance and strength. All joints between tiles and mouldings shall be filled with
tile grout and carefully wiped.
Before tiles and mouldings are laid in place, they shall be thoroughly soaked
in water. Mortar to be used in setting the tiles shall be a mixture of 1 part of cement
only.
ROOFING
The roof to be used shall be GA#26 Pre-painted Galvanized Aluminum Long
Span Sheets of any desired design, color and brand type. The material to be used
for installation of roofing shall be 2 to 3 long self drilling screw for every
Corrugation, Rib and Wave.
For Bended sheets like Gutters, ridge rolls. Valley rolls and flashings joinery
shall be correctly fitted with 5/32 diameter blind rivets and all connections shall be
protected with silicone rubber sealant for water proofing.
All surfaces and parts of the roofing sheets that has been scratched and
damaged during the installation shall also be painted with on the spot aerosol spray
paint. The entire roofing shall be cleaned after the installation is finished.