Sie sind auf Seite 1von 1

Average cost of 16 '' pipeline construction

S.N. Description % $/KM SAR/KM REMARKS


Materials & Equip , Materials include
1 line pipe, pipe coating, and cathodic 14.0% 587,109.96 - SA SUPPLY
protection
2 labor 42.0% 1,761,329.89 6,622,600.39
3 Misc. 39.0% 1,635,520.61 6,149,557.51
4 Right-of-way (ROW)-& Damages 5.0% 209,682.13 788,404.81

total 100.00% 4,193,642.60 13,560,562.71

204.901 KM Total 2,778,572,860.13

Notes :
1
Miscellaneous" costs generally cover surveying, engineering, supervision, contingencies,
telecommunications equipment, freight, taxes, allowances for funds used during construction
(AFUDC), administration and overheads, and regulatory filing fees.

2 ROW costs include obtaining rights-of-way and allowing for damages.