Beruflich Dokumente
Kultur Dokumente
DESIGN
Hong Kongs new airport covers an area of 1248 ha, of which three quarters
Written discussion closes
has been reclaimed from the sea. This paper describes the civil engineering 15 November 1998
design for the HK$50 billion project including the reclamation, runways,
550 000 m2 passenger terminal building, ground transportation centre and
supporting infrastructure. It covers the early site selection and the factors
affecting the layout of the airport. It details the leading role taken by the
Authority in the prediction of reclamation settlement and how this was
accounted for in the design and construction of the works. It concludes with
a brief description of the wide-ranging environmental initiatives which were
applied at all stages of this massive project.
15
PLANTAND
OAKERVEE
Alternative sites for a replacement airport were looked at the development of an airport at Chek
considered as far back as 1946 (Fig. 1) .1 The two Lap Kok together with land development potential
sites examined at that time were rejected for aero on north Iantau with a coastal highway and a
nautical reasons and high cost. To meet the steadily fixed link crossing to Tsing Yi.
increasing demand at Kai Tak a new runway (2542 Master planning and financing studies complet-
m long), parallel taxiway and passenger terminal ed in 19823 established in some detail the feasibili-
were planned in the 1950s and opened in 1958. With ty of building the two-runway airport at Chek Lap
the introduction of heavier, wide-bodied aircraft the Kok within a seven-year period at a total cost of
runway was subsequently extended to 3392 m in HK$ 15.3 billion (mid-1982 prices). However, due
1975. Also in the 1970s it was realized that the single to a downturn in the global economy and uncer-
runway at Kai Tak together with constrained operat- tainties arising from concurrent Sine-British
ing hours (due to noise over Kowloon) would have a negotiations on Hong Kongs future, the project
tin&e capacity. A new airport was needed with dual was deferred.
runways, preferably aligned along an easterly axis However, while planning came to a standstill
into the prevailing winds; and good land access the growth of air traffic through Kai Tak contin-
would be essential. Thus the first serious search for ued unabated. Between 1980 and 1990 alone,
alternative sites was made between 1973 and 1975.2 annual passenger numbers rose from 8 million to
The study concluded that Chek Lap Kok (Fii. 2) 20 million and the volume of air cargo passing
would be the best choice at an estimated cost of through the airport trebled.
HK83.6 billion (1974 prices), including the cost of By 1989, the need for a new airport could no
road access on north Lantau. The principal reasons longer be ignored and once again planners
for its selection were that focused on Chek Lap Kok, but in a new context.
This time the airport was to be studied as part of
l all aeronautical criteria would be met for a 24- a combined port and airport development strate-
hour a day operation gy and included a review of alternative sites to
l the engineering feasibility for site formation Chek Lap Kok.
was established In October 1989, the Hong Kong government
l the programme for the works was less uncer- announced the adoption of a strategy based on a
tain than other sites new airport at Chek Lap Kok, and a network of
l the environmental impact during construction supporting road and rail infrastructure to be
and for operations was acceptable known as the Airport Core Programme.
l an airport at Chek Lap Kok was compatible Chek Lap Kok was chosen as the airport loca-
with other proposed developments on Lantau tion ahead of other site options because it met a
Island and also with port activities in the west- number of basic criteria. It offered greater eco
ern harbour. nomic benefits and could be built and made oper-
ational earlier than other considered sites. It also
In 1978 studies undertaken by the government provided greater scope for an integrated and
16
CML ENGINEERING
DESIGN
viable transport infrastructure network, the poten- Table 1. Air passenger and cargo demand forecasts
tial for urban development in the form of Hong
Kongs ninth new town and the ability to integrate Passengers Cargo: tonnes
future port and airport development. The govern-
Year 1991 forecest 1994 forecast 1991 forecast 1994 forecast
ment emphasized that the airport would develop
incrementally with expansion capacity for phased 1.2 million 1.7 million
1996 29.5 million 33.9 million
development well into the next century.
The Provisional Airport Authority @AA) was 2001 33.2 million 40.7 million 1 ,4 million 2.1 million
established in April 1990 as a statutory organization 2010 : 44,7 million 65.9 million 2.3 million 3.4 million
to plan, design and construct the new airport. The
new airport master plan4 was also initiated in July
1990. In September 1991 a memorandum of under- l Opportunities for privatization would be maxi-
standing was signed by the governments of the UK mized.
and the Peoples Republic of China, contirming joint
support for the new airport and related core pro- There were three main workstreams undertak-
jects. The cost of the PAAs facilities at the airport en for the NAMP, namely planning, civil engineer-
in money-of-the-day or out-turn prices is HK849.8 ing and environmental impact assessment, which
billion. There followed almost four years of discus- were carried out in parallel.
sion between the two governments on the detailed
financing arrangements for the projects. During Air traffic demand
this time, the Hong Kong government sought to Air traffic studies carried out as part of the
maintain progress on the airport in accordance with NAMP determined the overall physical size of the
the requirements of the memorandum by, at vari- airport and the size of the facilities. The air traffic
ous stages, providing interest-free cash advances to forecasting process employed has been described
the PAA to enable critical works on the project to by 0akervee.s In essence, the predicted per capi-
proceed on a stepby-step basis. In July 1995 Hong ta gross domestic product was used as the prima-
Kongs legislative council passed the Airport ry variable to determine growth.
Authority Bill which enabled the PAA to be recon- Such has been the economic development in
stituted as the Airport Authority (AA), empowering the Asia-Pacific region that in 1994 a new air traf-
it to provide, develop, operate and maintain the new fic demand forecast covering passengers and
airport. On 29 November 1995 the airport commit- cargo was commissioned by the AA, as air traffic
tee of the Sino-British joint liaison group signed growth in the three years since completing the
agreed minutes on the membership of the AA and 1991 master plan had been significantly greater
this paved the way for establishment of the AA on 1 than forecast and reported previously.5 The 1991
December 1995. and 1994 forecast figures are given in Table 1.
The above were key events for the A4 and had Since 1987 annual passenger traffic has grown
a fundamental influence in the contracting of the by an average of 9.9% 6 and in 1996, despite its
design and construction of the airport. limitations, Kai Tak had an annual throughput of
30.2 million passengers, making it the third
Master plan busiest airport in the world in terms of interna-
The overall objective of the new airport master tional passengers.
plan (NAMP) study was defined as the prepara- Air cargo tonnage has grown by an average of
tion of a comprehensive and environmentally 11.0% since 1987. Based on preliminary figures
acceptable scheme for the planning and imple- from the Airports Council International, Kai Tak
mentation of an operationally safe and efficient was the worlds busiest in terms of international
new airport at Chek Lap Kok, covering progres- cargo in 1996 with a throughput of 1.56 Mt.
sive development into a two-runway airport oper- The forecast of passenger and cargo aircraft
ating 24 hours a day.4 movements was strongly influenced by the relative
The key assumptions made for the NAMP, com- ly high predominance of Boeing 747 and other wide
pleted in December 1991, which influenced the bodied aircraft. Both the 1991 and 1994 forecasts
planning of the airport facilities included the fol- for all aircraft movements are given in Table 2.
lowing.
The airport plan
l Kai Tak Airport would close when the new air- Air traffic demand and airspace constraints dic-
port opened. tated the layout of the airfield at Chek Lap Kok
* All passengers using the new airport would be which covers a total area of 1248 ha. The major
regarded as international, requiring them to planning recommendations in the NAMP were
be processed through immigration and cus- that runway centre-lines should be separated by
toms facilities. 1525 m which would allow independent runway
l The master plan would include a multi-modal operations in accordance with the recommenda-
surface transport system with a high priority tions of the International Civil Aviation
given to rail. Organization (ICAO); the airport would be
PLANTAND
OAKERVEE
Table 2. Forecasts of all aircraj movements of changing data and circumstances. The signifi-
cant changes (Fig. 3) were that: the southern run-
way was moved 360 m to the west to reduce recla-
mation costs and to preserve the eastern coast of
Chek lap Kok Island; the passenger terminal
building was moved 190 m westward so that more
1998 ,' ', id000 1 201000 ;
of the buildings foundation work was located on
2001 ,'177000,, 241 100 Chek Lap Kok Island to reduce construction costs;
,'
2010 229300 ,', 369 900 and the vehicular tunnels were re-aligned.
,,, The key features of the airport site plan (Fig. 4)
are two parallel runways, each 3800 m long, and 35
designed for a configuration of two parallel run- km of associated taxiways; a passenger terminal
ways bearing 070/250 N each 3800 m long and buildiig comprising a Y-shaped concourse and pro-
60 m wide; the passenger terminal complex would cessing terminal connected by way of an under-
be located between the runways; and the rail and ground automated people mover and linked to the
primary road access would be along the eastern ground transportation centre (GTC); a high-speed
edge of the airport island. rail and road network serving the GTC; aircraft base
The airport is a phased development and as such maintenance facilities at the western end of the air-
has been planned to open with a design capacity of field; airport support facilities including air cargo,
35 million passengers and 3 Mt of cargo annually. catering and an aviation fuel tank farm located south
Initially, has a single runway, one passenger pro- of the runways; various government facilities includ-
cessing building, the major part of the Y-shaped ing the air traffic control tower and centre, fire sta-
concourse with 38 frontal gates (connected to the tions, sea rescue stations, airmail centre, a police
terminal by ah-bridges) and 27 remote aircraft station and a facility for the government flying ser-
stands. Within months of the airport opening, the vice. Commercial developments are also under con-
second runway will become operational, the struction, including a llO@room hotel, a 175@space
remainder of the Y-concourse will be constructed multi-storey car park, a freight forwarding centre,
and a further 10 frontal gates will be added. headquarters and crew accommodation for Cathay
Appendix 1 gives a comparison between facilities at Pacific and headquarters for Dragonair/CNAC.
the existing airport at Kai Tak and those at the
new airport at Chek Lap Kok. Ultimately the air- Design contracts
port will have a designed capacity of about 87 mil- The NAMP identified general requirements for
lion passengers and 9 Mt of cargo annually. all the airport facilities and included outline
Airport planning is a continuous process and fol- scheme designs for the passenger terminal build-
lowing completion of the NAMP the AA made fur- ing, the airfield, the infrastructure and utilities.
ther design refinements and revisions in the light The first major detailed design contract for the
Fire station ,
Northern runw
Future madfield
Ammal centre
Government /
Fire statlon
\
-%c.
Air cargo
\ - -
7 LA
/
flying service Business aviation
Freight forwarding
Telephone exchange
Aviation fuel tank farm
airport itself was awarded in March 1992 for the tally for co-ordination of all designs. The authors Fig. 4. Airport site
passenger terminal building. For the remainder of would like to acknowledge the cooperation of plan
the works a large number (30) of contracts were designers in dealing with the interfaces and
let between 1993 and 1996 to design consultants. assisting in the co-ordination process. The AA
A full list of the design contracts is given at also held quarterly review meetings with all
Appendix 2. The reasons for this strategy arose design firms to review progress at a strategic
from the limited funding available at the time level, which proved beneficial to all concerned.
which required all design work to be initiated on An example of the AAs initiatives with regard to
a stepby-step basis. Also, the AAs board wished co-ordination was with respect to the provisions
to have participation by a number of designers, necessary to account for settlement of the airport
each expert in specific areas-airfield pavements, platform and this is described later in this paper
ground lighting, stormwater drainage, utilities, under the heading Design and construction levels.
electrical and mechanical works, roads, bridges,
ancillary buildings and landscaping. The airport platform
The allocation of funds on a step-by-step basis To accommodate all the facilities and allow for
led to interface problems such as the stormwater phased development of the airport required the
design being awarded before the airfield pave- creation of 1248 ha of land (Fig. 5). Twenty-five
ments package and the utilities design before the per cent of the airport platform is made up of the
roads package. This inevitably created complica- former islands of Chek Lap Kok and Lam Chau,
tions and led to an iterative design process. The which have been excavated to a level of about +6
consequences of a large number of design inter- m PD (principal datum). The remainder of the
faces and design work being undertaken out of platform is land which has been reclaimed from
sequence were felt throughout the design and the sea as part of a major site preparation contract
construction phases. In addition, the fluid nature which began in December 1992, the construction
of the contracting strategy for the construction details of which are briefly described in a related
works which arose from the uncertainty over paper.7 A full description of the design, construc-
future funding meant that the completed designs tion and performance of the site preparation
from several designers had to be split and recon- works is given in reference 1.
solidated to suit each works contract.
Design co-ordination meetings, chaired by the Design and performance
AA and attended by all design managers and rep Chek Lap Kok and Lam Chau Islands are
resentatives from all designers, were held periodi- formed predominantly of granite. Completely
19
PLANTAND
OAKERVEE
Fig. 7. Grading
envelopes forjill types
A, B, A/B and C
Fill type B
Fdl t y p e C
rying Chek Lap Kok Island and subsequently An integral part of the reclamation design was
crushed for aggregates, was designed to acceler- the installation and monitoring of surface and
ate primary consolidation of the alluvial clays and subsurface geotechnical instruments to assess
also to improve the creep characteristics of the the performance of the reclamation and to allow
rockfills. Vibrocompaction of 11 Mm3 of the sand- predictions of future settlement to be refined. The
fill was carried out over some 60 ha of land being sub-surface instruments comprised clusters of
developed under the current construction phase. piezometers installed around a central extensome-
The treatment was required to reduce creep set- ter at approximately 500 m centres. A grid of sur-
tlement of the sandfill and to reduce the potential face survey markers was constructed across the
for vibration induced settlement during follow-on reclamation at approximately 200 m centres to
piling and other construction activities. The provide a fuller picture of the surface settlement
acceptance criterion for the vibrocompaction of the reclamation.
works was a minimum CPT value of either 8 MPa Early predictions of settlement were made using
or 15 MPa, depending on the intended land use. the results of in situ and laboratory tests. As more
PLANTAND
OAKJIRVEE
q Surcharge
7 Drainage culverts
6 Avration fuel tank farm 1 1 -?-?/-I
q Vibrocompaction
9 Test embankment
10 Road and rail emb
q Dynamic compaction 11 Rail embankment
1 2 Northern runway
Vibrocompactron:
1 Cross field taxiway
2 Maintenance base
Scale: km
monitoring data have become available, the predic- ment assessment it soon became clear that the
tion method has changed to an observational AA were in the best position to address this issue
approach making full use of the monitoring data. ti-om their overall knowledge of the platform
Fuller details of the performance of the reclamation behaviour. It was also known that contractors
are given in a companion paper. 10 In summary, the were reluctant to take on risk associated with the
remaining or residual settlement from January 1997 settlement of the platform. The AA therefore took
to 2040 is typically in the range 200 mm to 500 mm. on responsibility for settlement during construc-
At the present time (August 1997) the primary con- tion of the follow-on works and established the
solidation of the alluvial clay is typically 90% com- concept of installation levels.
plete and creep of the reclamation fills now typically The designers were required to design their
comprises about 50% of the residual settlement. works such that the facilities would remain opera-
The airport platform was substantially complet- tional throughout the airports life and to stan-
ed in 37 months and involved the movement of dardize their designs for a fixed date of January
about 360 Mm3 of material. The rapid pace of con- 1997. The AA then provided contractors with
struction was assisted by a practical application of rates of settlement for various zones of the recla-
engineering requirements and a carefully pro- mation. This information was derived from
grammed fill allocation plan taking best advantage time-settlement curves prepared for many points
of the various fill types available. This minimized on the platform. The construction period for the
the requirements for fill processing and ensured works represented a small window within the
that the fill placed in a particular area met the overall time-settlement curve (Fig. 9) and was
specific engineering needs of the future planned therefore approximated to a straight line. The AA
construction. This approach also minimized the issued settlement rates expressed as mm per
requirement for ground improvement thereby month and the contractor then determined his
reducing both cost and time. installation levels from this information and from
his own programme for the works by taking the
Design and construction levels linear rate of settlement multiplied by the number
The effect of the platform settlement coupled of months prior to January 1997 and adding this
with the different times at which works were due amount to the design levels.
to be constructed influenced the amount of over-
build necessary to achieve design levels in the Airfield pavements
long term. Air traffic forecasts and airspace considerations
Although each designer made his own settle- had determined that the Civil Aviation
CML ENGINEERING
DESIGN
Rlin& oendnd (CL) to taxiway CL 182.5 192 120 ,.180 1, : ,,,, 192
:
R u n w a y width 45 60 45 60 50 : I
Taxiway/taxilane width 23 29 23 30 - 2 9
23
PLANTAND
OAKERVEE
ment design it was assumed that the runway uti- Transverse sawn grooves (6 mm x 6 mm at 32
lization could be 70% departures from 07L/07R and mm centres) were specified in the runway wear-
45% from 25R/25L. A detailed traffic analysis was ing course to provide the required frictional char-
undertaken based on information from CAD acteristics.
regarding aircraft fleet mix and planned taxiing The total area of both runway/taxiway systems is
operations on the ground to establish cover-ages by 2 600 000 m2 and they have a design life of 20 years.
the design aircraft over the pavements. Within this period overlays will be placed because
The principal factors which affected the choice of the oxidation and weathering of the asphalt
of pavement were settlement, ride quality, fuel which occur in tropical climates and also, in limited
resistance, duration of loading and cost. Based on areas, for shape correction. Fig. 11 (a) shows a
these design considerations, asphalt surfaced cross-section of a typical asphalt pavement.
flexible pavements were selected for the run-
way/taxiway system on the reclamation, rigid Concrete pavements
pavement quality concrete for aprons and taxi- For the aprons, concrete paving is preferred
lanes on the original island and interlocking con- because of its ability to resist high loads from sta-
crete blocks for apron areas subject to significant tionary aircraft and its resistance to fuel and oil
differential settlements. spillage from aircraft or ground support vehicles.
The pavements have been designed using both Thus conventional rigid concrete pavements have
the 1989 UK PSAA Guide To Airfield Pavement generally been adopted for the aprons. During the
Design And Evaluation~o and the US LEDFAA early phase of design both continuously rein-
method following its release in 1995 by the US forced and unreinforced jointed concrete pave-
FAA.12 The first is a semi-empirical method in line ments were considered, and the latter were
with those recognized by ICAO and is based on selected on the basis of lower capital costs.
many decades of experience gained from evaluat- The rigid concrete pavements which cover an
ing the performance of existing pavements. The area of 700 000 m2 have a design lie of 45 years. 10
second is based on a linear elastic design The majority of these pavements are on the origi-
approach which calculates stresses and strains in nal island; elsewhere in situ plate tests using a 762
each pavement layer. It uses these stresses and mm dia. plate gave values of sub-grade reaction
strains to determine pavement thickness by an for the compacted fill of between 100 and 150
iterative process using established fatigue equa- kPa/mm. A conservative value of 40 kPa/mm was
tions. Both of these design approaches yielded selected for design purposes. The unreinforced
similar pavement structures. pavement is typically 450 mm thick on a 175 mm
After applying the various traffic scenarios, dry lean concrete base (Fig. 11 (b)). The specified
expected loading and settlement criteria many dii- 28day characteristic flexural strength was 4.5
ferent pavement sections were developed across MPa. Typical bay sizes are 6 m x 6 m. Mesh rein-
the airport. These were then rationalized into just forcement and trimmer bars were specified for
16 types to ease the construction process as many irregular bays and around penetrations.
of the scenarios gave rise to similar thickness Transverse joints were saw cut at approximately
requirements. In all, the airfield pavement works 10 to 15 h after concrete placement and steel dow-
cover 3 700 000 m2. els were provided at longitudinal joints. Load
transfer across the transverse joints is by aggre-
Asphalt pavements gate interlock at the sawn joint. All joints were
The initial structural design of the asphalt sur- sealed with a fuel-resistant sealant. Surface texture
faced pavements considered the use of a bound of the finished concrete was specified as a mini-
(cement or bitumen) base in accordance with the mum of O-7 mm using the sand patch test method.
PSA design guide. However, unbound bases with
relatively thin asphalt surfaces have provided the Concrete blocks
desired performance at many airports. These In apron areas where a rigid concrete pavement
pavements require very high quality aggregates could not tolerate the estimated differential move
with strict grading requirements with a consistent ments, interlocking shaped concrete blocks 80 mm
level of compaction to prevent premature rutting. thick have been adopted (Fig. 11 (c)) . The blocks
Following the identification of suitable high are nominally 225 mm by 112.5 mm and have a
quality aggregates, a pavement using crushed characteristic compressive cube strength of 60
rock base and sub-base courses was selected on MPa. The joint spacing was specified as 2-4 mm to
economic grounds, being signiicantly less costly ensure interlock via the jointing sand. To achieve
than a pavement with a bound base. Crushed rock this the contractor monitored mould wear and
aggregates of the specified quality for the subbase replaced the mould when the block plan diien-
course were available on site, retained from quar- sions increased by 1.25 mm which occurred at
rying Chek Lap Kok. For the base course and the about 80 000 cycles.13 Some 16 million blocks were
Marshall asphalt layers, crushed rock with a mini- required to cover 400 000 m2 of apron.
mum specified 10% fines value of 180 kN was Beneath the southern runway the eastern tun-
imported from nearby provinces in China. nel has been designed to carry vehicles from the
CML ENGINEERING
DESIGN
(a)
(W
-
300 mm subgrade-98% MMDD
(d
airport support facilities in the south to the pas- side to airside without affecting operations of the
senger terminal aprons, and the western tunnel is southern runway The eastern tunnel has been
for future access to the midfield. Both tunnels are commissioned but the western is for utilities only
each about 700 m long and have a utilities cell at present and will be fitted out when the mid-field
and dual carriageways to allow traffic from land- area is developed (Fig. 10).
25
PUNTAND
OAKERVEE
Scale. km
0 0.5 1
1
nage is also provided. The AA has implemented a vehicles and taxis; the latter incorporates a 24-taxi
comprehensive traffic control and surveillance sys- simultaneous pick up system. Private car pick-up
tem incorporating variable message signage to facilities for arriving passengers are provided in
minimize disruption to passenger movements in the multi-storey and at grade car parks.
the event of an incident on the approach roads. The highest level of the centre is occupied by
the road departures traffic. A departures fore-
Ground transportation centre court and median strip provide a total kerb length
The focal point of the landside road network is of 650 m along the face of the processing terminal
the ground transportation centre located between at airport opening. This allows taxis, public buses,
the passenger terminal building and the proposed hotel vehicles and private cars to drop off their
second terminal (Fig. 13)) which facilitates pas- passengers at this level.
senger interchange between aircraft and the vari-
ous ground transportation modes. These include Passenger terminal building
the airport express railway, public buses and air- Whether travellers enter the check-in area of
buses, tour coaches, hotel buses and limousines, the passenger terminal building from the fore-
baggage vans, taxis and private cars. court or from the station platform, they find them-
Segregated provisions have been made for each selves within a breathtaking interior space. The
transport mode with emphasis placed on speed dominant feature is the roof, comprising 18 ha of
and efficiency of transfer, convenience, comfort steel barrel vaults (Fig. 15). The 36 m spans cre-
and safety for all passengers, well-wishers and air- ate a feeling of light and space and the geometry
port employees. At the core of the centre is the is aligned to lead passengers naturally through
rail station14 with direct air-conditioned links to check-in, immigration and security towards their
the terminal. Departing air passengers travel departure gate. The roof is high over the process-
along ramps with moving walkways to the check- ing terminal, cantilevering 27 m over the fore-
in area within the terminal. Arriving air passen- court, reducing in height over the east hall and
gers have a similar ease of access from the termi- along the central concourse before rising again
nal to their choice of ground transport, the rail over the west hall. Each 36 m x 36 m vaulted roof
departure platform being on the same level as air panel is formed of a lattice of straight 6 m long
passenger arrivals (Fig. 14). The station is I-beams, 406 mm deep for the majority of the
expandable to serve the future second terminal building and 457 mm deep members for the diag-
while maintaining the same level of service. onal concourses. The architectural requirement
Beyond 2010, up to 50% of air passengers and for constant depth and flange width required
well-wishers are expected to enter and leave the varying forces within the members to be accom-
airport through this station. modated by changes in flange thickness. The roof
The ground level of the centre is occupied by geometry is revealed by exposing the bottom
the road arrivals traffic. Separate pick-up areas flange of all diagonal elements and within the tri-
are provided for public buses, tour coaches, hotel angles so formed are soffit lining panels (perforat-
27
PLANTAND
OAKERVEE
Scale: m
0 IO 20
/
ed metal panels with acoustic insulation) posi- tied to reduce the impact of thrusts on the can- Fig. 13. (top). Plan of
tioned flush with the flanges. tilever concrete columns. terminal building and
Critical wind pressures were determined from Three important connection details emerged ground transportation
wind tunnel tests which indicated that the Hong from the design. First, that of a typical node centre
Kong code for wind loading was not conservative15 where six elements are joined: the solution adopt-
for low-level structures in such exposed conditions. ed was a node plate as depicted in Fig. 16. The Fig. 14. (above).
Seismic design was based on the New York code in second was the column head connections (Fig. Section through pro-
the absence (at the time of design) of guidance for 17) where within the confines of a 1200 mm dia. cessing hall and
Hong Kong. The design required the impact of the reinforced concrete column top, two 100-150 t, 36 ground transportation
sequence of roof module erection on the flexible m span roof modules had to be located together ten tre
concrete columns to be assessed to ensure that the with a 150 mm dia. downpipe and conduits for
tinal structure was within tolerance. Some vaults, electrical services. The third was the connection
primarily those over the processing terminal, are detail to link the undulating roof with the
CML ENGINEERING
DESIGN
Node plate
cladding: the solution was a cast stainless-steel I 1 I
Fig. 15. 3-D study
armature connection or wishbone (Fig. 18). internal view of roof
The roof covering comprises a waterproof
membrane, a vapour barrier and thermal and
sound insulation layers on a steel deck. Internally,
the soffit lining panels reflect light from luminar-
ies mounted on the roof gantry and from daylight
which enters the building through the skylights.
The contract for the design of the passenger ter-
minal building was awarded to the Mott
Consortium in March 1992. The consortium com-
prised Mott Connell, the Hong Kong practice of
Mott MacDonald (UK) and Connell Wagner
(Australia), which was responsible for engineering Fig. 16. Node plate
design and consortium management, and Foster detail
and Partners which undertook the architectural
design, in association with BAA, which carried out ensure that people are able to move through the
operational planning and systems design. As sub- building quickly and comfortably.
consultant, Ove Arup and Partners designed the Building services have been integrated within
roof and architectural steelwork, W. T. Partnership the structure to minimize obstructions to the pas-
was the quantity surveyor and OBrien Kreitzberg senger processing facilities and within the roof.
provided design project scheduling. Thus, from a double-height basement containing
The first phase of the building is designed to the chiller plant which draws in seawater for cool-
handle 35 million passengers per annum. The pro- ing, conditioned air is fed vertically to the various
jected one-way standard busy rate (SBR: defined levels of the building by way of binnacles. Also,
as the projected activity during the 30th busiest within the basement is the heart of the baggage
hour in the year; this is a more reliable measure handling system capable of handling 19 200 bags
of an airports busy periods than a peak rate per hour at saturation. It incorporates a machine-
which will experience large fluctuations from year automated explosive detection system which sim-
to year) for this annual throughput is 5500 pas- plifies check-in as it enables all X-raying for hold
sengers/h. The gross floor area of the building in baggage to be carried out within the baggage
the first phase is 515 000 ma and is over 1.3 km handling system.
long, making it one of the largest single terminal Due to the large footprint of the building which
buildings in the world. The concourses provide straddles both the original island of Chek Lap
direct access through fixed link bridges and Kok and reclaimed land, many different types of
apron drive loading bridges to 38 aircraft stands, foundation have been employed including pad-
at airport opening, rising to 48 on completion of and-strip footings, rafts, bored and H-piles. Below
the north-west concourse (Fig. 13). An automat- ground level, the basement and tunnels are
ed people mover and moving walkways will designed as water-retaining structures and to
PLANTAND
OAKERVEE
Tie member
Departure concourse
FFL + 16.150
.
Arrival concourse
F F L +;2.150
Tunnel for
future
Scale: m baxww
0 2.5 5 system OO.OO$ datum
I
u1
Services tunnel
31
PLANTAND
OAKERVEE
32
i
Concluding remarks Columbia, 10-13 May, 1998.
14. Design and construction of the airport railway.
Hong Kong is used to accepting the challenges
Proceedings of the Institution of Civil Engineers, Civil Appendix 1. Hong /
presented by major engineering projects. This brief Engineering, Hong Kong International Airport, Part
paper has attempted to summarize the key planning Kongs airport facili-
2: Road and Rail Links, 126,1998.
and design tasks involved with the new airport 15. Scott, D M et al. The design of the passenger termi- ties-comparative
which has dwarfed previous Hong Kong efforts nal roof at Chek Lap Kok. In preparation. statistics
and perhaps ranks as one of the most significant of
engineering projects anywhere in recent times.
To achieve the objectives within a time scale of f3WW akpMf New &port et Cbk
at Kai Tak Lap Kok Phasa l(a)
less than eight years is a tribute to the massive
human endeavour which has had to be undertaken. Total airport site 333.6 ha 1 248 ha
33
PLANTAND
OAKERVEE
110 Airport expressway, rail link and roads design Halcrow Asia Partnership Ltd Sept. 1993
1llA Ground transportation centre and approach roads design Ove Amp and Partners (HK) Ltd Oct. 1993
1118 Airport railway design (GTC) Ove Arup and Partners (HK) Ltd Oct. 1993
140 Software quality management Engineerfng Centre for Software Dac. 1995
141 Communications systems design Parsons Brinkerhoff (Asia) Ltd Oct. 1993
142 Security systems design Parsons Brinkerhoff (Asia) Ltd Oct. 1993
170 Landscaping design Scott Wilson Kirkpatrick (HK) Ltd Apr. 1994
190 190 New airport transport study Wilbur Smith Associates J u l y 1992
193 Urban design guidelines and study Urbis Travers Morgan Ltd Dec. 1993
19QG Marine geology of Chek-lap Kok Brltieh Gceologllal survay Aug. 1QQ3
255 Site investigation and laboratory testing (land) Intrusion-Prepakt Foundation Ltd Sept. 1993
256 Manne site investigation and laboratory testing Lam Geotechnical Ltd Oct. 1993