Sie sind auf Seite 1von 287

1

1 BEFORE THE PUBLIC UTILITIES COMMISSION

2 STATE OF COLORADO

3 -------------------------------------------------------

4 DOCKET NO. 09A-324E VOLUME 9

5 -------------------------------------------------------

6 IN THE MATTER OF THE APPLICATION OF TRI-STATE


GENERATION AND TRANSMISSION ASSOCIATION, INC., (A) FOR
7 A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY FOR
THE SAN LUIS VALLEY-CALUMET-COMANCHE TRANSMISSION
8 PROJECT, (B) FOR SPECIFIC FINDINGS WITH RESPECT TO EMF
AND NOISE, AND (C) FOR APPROVAL OF OWNERSHIP INTEREST
9 TRANSFER AS NEEDED WHEN PROJECT IS COMPLETED.
-------------------------------------------------------
10 DOCKET NO. 09A-325E

11 -------------------------------------------------------

12 IN THE MATTER OF THE APPLICATION OF PUBLIC SERVICE


COMPANY OF COLORADO (A) FOR A CERTIFICATE OF PUBLIC
13 CONVENIENCE AND NECESSITY FOR THE SAN LUIS VALLEY TO
CALUMET TO COMANCHE TRANSMISSION PROJECT, (B) FOR
14 SPECIFIC FINDINGS WITH RESPECT TO EMF AND NOISE, AND
(C) FOR APPROVAL OF OWNERSHIP INTEREST TRANSFER AS
15 NEEDED WHEN PROJECT IS COMPLETED.
-------------------------------------------------------
16

17 PURSUANT TO NOTICE to all parties in

18 interest, the above-entitled matter came on for hearing

19 before MANA L. JENNINGS-FADER, Administrative Law Judge

20 of the Public Utilities Commission, on July 26, 2010;

21 said proceedings having been reported in shorthand by

22 James L. Midyett, Michele Koss, and Harriet S.

23 Weisenthal, Certified Shorthand Reporters.

24 WHEREUPON, the following proceedings were

25 had:
2
1 APPEARANCES

2 (AS NOTED OF RECORD.)

3 INDEX

4 WITNESS PAGE

5 KAREN T. HYDE 15
Direct Examination by Mr. McGann 15
6 Cross-examination by Mr. Douglas 42
Cross Examination by Ms. Mandell 179
7 Redirect Examination by Mr. McGann 181
JAMES R. DAUPHINAIS
8 Voir Dire Examination by Mr. Sopkin 210
Direct Examination Con't by Mr. Douglas 220
9 Cross Examination by Mr. Nelson 257
Cross Examination by Mr. Sopkin 262
10

11 EXHIBITS

12 NUMBER MARKED ADMITTED

13 Exhibit No. 132 3 16


Exhibit No. 133 3
14 Exhibit No. 134 3
Exhibit No. 135 3
15 Exhibit No. 135-A 3
Exhibit No. 136 3
16 Exhibit No. 137 54 68
Exhibit No. 138 68 73
17 Exhibit No. 139 91 92
Exhibit No. 140 91 101
18 Exhibit No. 141 120 121
Exhibit No. 142 157
19 Exhibit No. 143 275

20

21

22

23

24

25
3
1 PROCEEDINGS

2 (Whereupon, Exhibit Nos.

3 132 through 135, 135 A and 136 marked for

4 identification).

5 A.L.J. JENNINGS-FADER: Good morning,

6 everyone.

7 This is a continuation of the hearing in

8 Dockets No. 0A-324-E, and Docket No. 09A-325E -- I'm

9 not going to read the titles, they are previously read

10 numerous times into the record.

11 This is continuation of the hearing and a

12 reopened evidentiary hearing held pursuant to Decision

13 No. R10-0486-I.

14 My name is it Mana Jennings-Fader. I'm

15 the Administrative Law Judge assigned by the Commission

16 to hear this case.

17 And I would like to begin this morning by

18 taking appearances beginning with the applicants.

19 MR. DOUGHERTY: Good morning, Your Honor.

20 Tom Dougherty on behalf of Tri-State

21 Generation & Transmission Association.

22 A.L.J. JENNINGS-FADER: Good morning.

23 MR. SOPKIN: Good morning, Your Honor.

24 Greg Sopkin on behalf of Public Service

25 Company of Colorado.
4
1 A.L.J. JENNINGS-FADER: Good morning.

2 MR. McGANN: Good morning.

3 David McGann on behalf of Public Service

4 Company of Colorado.

5 A.L.J. JENNINGS-FADER: Thank you and

6 good morning.

7 MR. SANTISI: Good morning, Your Honor.

8 Michael Santisi, Assistant Attorney

9 General, appearing on behalf of staff of the PUC.

10 A.L.J. JENNINGS-FADER: Thank you and

11 good morning.

12 MR. SCHLESINGER: Good morning.

13 Assistant Attorney General Jake

14 Schlesinger, appearing on behalf of the Office of

15 Consumer Counsel. And with me today is First Assistant

16 Attorney General Stephen Southwick, as well.

17 A.L.J. JENNINGS-FADER: Good morning.

18 MR. FLANAGAN: Top of the morning to you

19 Your Honor.

20 A.L.J. JENNINGS-FADER: Top of the

21 morning to you.

22 MR. FLANAGAN: Tim Flanagan along with

23 Matt Douglas and Tim Macdonald for Trinchera.

24 A.L.J. JENNINGS-FADER: Thank you.

25 Any other counsel.


5
1 MR. NELSON: Thor Nelson, appearing on

2 behalf of Pole Canyon.

3 A.L.J. JENNINGS-FADER: Good morning.

4 MS. MANDELL: Good morning, Your Honor.

5 Victoria Mandell on behalf of Western

6 Resource Advocates. And I have with me today Kristin

7 Charipar -- and I'll get you that spelling in a second.

8 A.L.J. JENNINGS-FADER: Other counsel

9 present?

10 MS. HICKEY: Thank you, Your Honor.

11 A.L.J. JENNINGS-FADER: Good morning.

12 MS. HICKEY: Good morning.

13 Lisa Tormoen Hickey of the law firm

14 Alpern Meyer Stuart, representing Interwest Energy

15 Alliance.

16 A.L.J. JENNINGS-FADER: Thank you and

17 good morning.

18 Other counsel?

19 (No response.)

20 A.L.J. JENNINGS-FADER: I will not read

21 the folks who have not sent their counsel today as they

22 have not entered their appearance, I'll presume they

23 are not present.

24 I have a few preliminary matters before

25 we get started this morning. The first is, pursuant to


6
1 Commission policy and procedure, this proceeding is

2 being webcast. I ask whether any party present has an

3 objection.

4 (No response.)

5 A.L.J. JENNINGS-FADER: Seeing none, we

6 shall continue.

7 I would like to remind the parties about

8 the procedures that we have this morning -- or for

9 today and for Friday -- hopefully not for Saturday; and

10 that is that we'll take a ten-minute break this

11 morning, we'll take a 45-minute break for lunch, and

12 we'll take a 15-minute break this afternoon. If

13 necessary -- again, I hope not, we will continue until

14 7 this evening.

15 We have arranged for court reporters

16 through that time period.

17 I would like to remind the parties that

18 Public Service and Tri-State have a right if they wish

19 to do so to offer oral rebuttal at the conclusion of

20 the presentations today -- excuse me, this week.

21 I would like to direct -- request Public

22 Service and also to Tri-State, would you all -- either

23 or both of you be prepared to identify whether you

24 intend at least to offer oral rebuttal at the end of

25 Mr. Dauphinais's testimony -- with respect to his


7
1 testimony, obviously not with respect to

2 Dr. Shefferin -- Shefferin; is that correct?

3 MR. DOUGLAS: Yes, Your Honor.

4 A.L.J. JENNINGS-FADER: Thank you.

5 (Pause.)

6 A.L.J. JENNINGS-FADER: Principally this

7 is for planning purposes; so if you could put that in

8 the back of your mind and maybe tell us after lunch

9 that would be fine.

10 MR. SOPKIN: Thank you, Your Honor.

11 (Pause.)

12 MR. SOPKIN: Clarification, Your Honor

13 you are not suggesting that we would put on rebuttal

14 testimony to Mr. Dauphinais prior to Dr. Shefferin.

15 A.L.J. JENNINGS-FADER: No. I mean, if

16 you would be so kind, if you are inclined, only to

17 inform me and the parties whether or not you intend to

18 offer rebuttal to Mr. Dauphinais, then holding

19 Dr. Shefferin -- obviously no one can know about her

20 testimony until it's given.

21 MR. SOPKIN: Okay, we'll get back to you

22 on that.

23 A.L.J. JENNINGS-FADER: That's fine.

24 Thank you very much.

25 We have pending a motion filed by


8
1 Trinichera Ranch to take administrative notice which

2 we'll take up as a preliminary matter. I am aware of

3 no other pending motions.

4 Is a party aware of a pending motion of

5 another -- another pending motion as to which no ruling

6 has been made?

7 (No response.)

8 A.L.J. JENNINGS-FADER: Okay. Holding

9 the motion for administrative notice for oral argument

10 in a few moments, has any party any other preliminary

11 matters?

12 MR. NELSON: Yes, I have a short

13 preliminary matter.

14 I passed out to the parties a letter that

15 was submitted to the Commission by the Board of County

16 Commissioners of Heurfano County, sent on June 16,

17 2010. And I just wanted to confirm this morning, as a

18 preliminary matter, that Your Honor is aware of the

19 letter and that the letter is going to be considered as

20 public comment in this proceeding along with other

21 public comment that was made previously in the docket.

22 A.L.J. JENNINGS-FADER: Thank you,

23 Mr. Nelson.

24 Let me clarify for the party what's going

25 on with written public comment that has been filed in


9
1 this proceeding. Not only did Heurfano -- the County

2 Commissioners of Huerfano County file two separate

3 letters, I think one in March and one in June with

4 respect to this matter, there have been a number of

5 other written comments received by the Commission, some

6 by folks who also testified at the two public hearings

7 and also some by folks who did not.

8 It is the Commission's practice to

9 consider, to the extent the Commission considers it

10 prudent, those written public comments. They are

11 technically not in the evidentiary record in this

12 proceeding, unlike the formal statements which were

13 given under oath during the two public hearings to take

14 public comment that were held in this matter; but

15 nonetheless, the Commission does consider them and does

16 give them some weight. What that weight is will be at

17 the discretion of the Commission.

18 MR. NELSON: Thank you, Your Honor.

19 A.L.J. JENNINGS-FADER: Certainly.

20 Anything else?

21 (No response.)

22 A.L.J. JENNINGS-FADER: With that, I

23 would like to turn to and start this morning by taking

24 oral argument to the motion for administrative notice.

25 Public Service, insofar as -- and --


10
1 excuse me, and Tri-State, insofar as I'm aware have not

2 filed written responses; am I correct?

3 MR. SOPKIN: Yes, Your Honor. And if I

4 may, they did not see a request for shortened response

5 time so.

6 A.L.J. JENNINGS-FADER: Let me start by

7 saying, there was no request for shortened response

8 time. No one was required to file a written response.

9 I just wish to be sure that I have not somehow missed a

10 filing which was made. So did Public Service file a

11 written response?

12 MR. SOPKIN: No.

13 And if I may continue, we did intend on

14 filing a written response. It was our understanding

15 that since no shortened response time was requested

16 that Trinichera Ranch was not requesting to put in

17 evidence in this proceeding those matters for which it

18 seeks administrative notice; that I'm guessing they

19 probably want to put it in their closing statement of

20 position in this case. So we were intending on

21 responding in writing.

22 That said, if you do want to address it

23 this morning, we're prepared to do so. But our initial

24 inclination was to say that we are going to file a

25 written response opposing it.


11
1 A.L.J. JENNINGS-FADER: Mr. Dougherty?

2 MR. DOUGHERTY: That's consistent with

3 Tri-State's understanding as well.

4 A.L.J. JENNINGS-FADER: Well, I would

5 really rather get this resolved sooner rather than

6 later simply because I think it would confuse the

7 record immensely to have something come in after the

8 evidentiary hearing by way of administrative notice

9 which then is evidence to which the other parties have

10 not had an opportunity to respond, assuming the motion

11 is granted.

12 So I would like to proceed if you all are

13 prepared to do so. If not, I will -- I can hold the

14 oral argument until Friday and hear it on Friday, if --

15 I'm also amenable to that.

16 MR. SOPKIN: Your Honor, we would in fact

17 prefer discussing that on Friday.

18 A.L.J. JENNINGS-FADER: With the

19 understanding that if the motion is granted, then

20 you-all would present whatever response you have to

21 present orally; is that correct -- I mean, any evidence

22 in response you would present that orally?

23 MR. SOPKIN: Yes, Your Honor. I would

24 say that because we did not think this was going to be

25 an issue in this proceeding that we have not discussed


12
1 what witnesses we'll need available but we will

2 certainly take that up in the next couple of days.

3 A.L.J. JENNINGS-FADER: Ms. Mandell --

4 and because we're webcasting, I apologize, I'm going to

5 have to ask you to come to the front so the folks can

6 hear -- assuming our best listening audience would like

7 to hear your audience.

8 Yes, ma'am?

9 MS. MANDELL: Your Honor, WRA may also

10 have oral argument on Friday with regard to the motion.

11 A.L.J. JENNINGS-FADER: Okay, thank you.

12 MS. MANDELL: Thank you.

13 A.L.J. JENNINGS-FADER: So, folks, we

14 will hold over the motion for administrative notice

15 until Friday.

16 Mr. Flanagan, Mr. Douglas, Mr. Macdonald,

17 to whom am I to address my next question which was

18 whether you all intended to examine as to those

19 documents, the Public Service's witness?

20 MR. DOUGLAS: I can answer that, Your

21 Honor; and the answer is, no, I did not intend to

22 question Public Service's witness about those

23 documents.

24 A.L.J. JENNINGS-FADER: Okay, good. We

25 won't be facing that issue. Thank you very much for


13
1 that heads up.

2 All right, so that will be the first

3 order of business on Friday, will be the oral

4 argument -- or the option is you may file something in

5 writing if you wish to do so and I'll decide it on the

6 written pleadings. So --

7 MR. SOPKIN: Thank you.

8 A.L.J. JENNINGS-FADER: -- to me it's

9 not -- as long as it's not 5:00 on Thursday.

10 MR. SOPKIN: Right.

11 A.L.J. JENNINGS-FADER: Thank you.

12 I think that takes care of all of those.

13 We'll get the preliminary matters -- excuse me, I have

14 been getting over something and I will apologize in

15 advance for clearing my throat repeatedly during the

16 proceedings.

17 Public Service, are you prepared to

18 proceed?

19 MR. SOPKIN: Your Honor, we did have one

20 preliminary matter we wanted to address.

21 A.L.J. JENNINGS-FADER: Okay.

22 MR. SOPKIN: I'm sorry.

23 Just briefly, Your Honor, we did receive

24 your Decision No. R 10-046-I which ruled on Public

25 Service's two motions in limine with some other rulings


14
1 in that as well. And we just wanted to, sort of as a

2 heads up, it's our understanding that Public Service

3 can still object on a case-by-case basis in this

4 proceeding if it believes that the matters that are

5 being raised are more properly addressed in other

6 dockets, such as the -- such as resource planning or

7 RES compliance dockets or the application to amend 2007

8 Resource Plan Docket No. 10A-377E; also, if it's

9 otherwise outside the scope of the reopened record, and

10 also if Public Service did not raise the issue in its

11 direct case, for example, reliability issues.

12 So we just wanted to raise that as a

13 heads up because we're guessing there will be

14 objections during this proceeding and we do not wish to

15 try Your Honor's patience in that regard.

16 A.L.J. JENNINGS-FADER: As to each of the

17 three areas, one -- anyone may object as to any of

18 those areas --

19 MR. SOPKIN: Thank you.

20 A.L.J. JENNINGS-FADER: -- on a case --

21 question-by-question basis.

22 So counsel?

23 MR. McGANN: We are prepared, Your Honor.

24 We call Karen Hyde.

25 A.L.J. JENNINGS-FADER: Thank you.


15
1 (Discussion off the record.)

2 KAREN T. HYDE,

3 having been called as a witness, being first duly

4 sworn, testified as follows:

5 A.L.J. JENNINGS-FADER: Thank you very

6 much.

7 I would like you to have a seat,

8 Ms. Hyde; and if you could be sure the microphone is

9 on.

10 THE WITNESS: It is.

11 A.L.J. JENNINGS-FADER: Thank you.

12 And also, counsel, if you have anything

13 to say or objections or whatever, please be sure the

14 mike is on so it will be broadcast.

15 Thank you.

16 DIRECT EXAMINATION

17 BY MR. McGANN:

18 Q Good morning --

19 MR. McGANN: Your Honor, actually I had

20 one preliminary question. Ms. Hyde has already been a

21 witness in this case; may I dispense with preliminaries

22 in terms of her job duties, to move the proceedings

23 along as well?

24 A.L.J. JENNINGS-FADER: I think so, yes,

25 unless they have changed.


16
1 THE WITNESS: No.

2 MR. McGANN: I don't believe they have.

3 BY MR. McGANN:

4 Q Ms. Hyde, could you please take a look at

5 what has been marked for identification as Hearing

6 Exhibit 132 which should be in front of you.

7 A Yes, I have it.

8 Q And can you tell me what that document

9 is?

10 A It is House Bill 10-1001 from this last

11 legislative session.

12 Q Was that the bill that was signed by the

13 Governor?

14 A Yes.

15 MR. McGANN: Your Honor, I move for the

16 admission of Exhibit 132 into the record.

17 A.L.J. JENNINGS-FADER: Exhibit 132 for

18 identification has been offered. Voir dire or

19 objection?

20 MR. DOUGLAS: No objection, Your Honor.

21 A.L.J. JENNINGS-FADER: Thank you.

22 132 is admitted.

23 BY MR. McGANN:

24 Q Ms. Hyde, I would like to take the next

25 four exhibits together if I could. So if you could


17
1 take a look at what has been marked for identification

2 as Exhibits 133 through 135-A.

3 A I have them.

4 Q Okay. And can you please describe for

5 me, what is Exhibit 133?

6 A It's our application to amend the 2007

7 Resource Plan.

8 Q And what is Exhibit 134?

9 A It's direct testimony and exhibits of

10 Jim -- of James F. Hill.

11 Q Is that -- is it the testimony that

12 supports that application?

13 A It is.

14 Q And what is Exhibit 135?

15 A It is separately marked Exhibit JFH-1

16 that was also part of the application and one of the

17 exhibits to Hill's testimony.

18 Q And can you tell me what is Exhibit

19 135-A?

20 A It is the confidential version of that

21 exhibit.

22 Q Can you tell me, referring specifically

23 to page 6 of the application which was Exhibit 133 --

24 and when you are there, let me know.

25 A Yes, I'm there.


18
1 Q Can you tell me in general what relief

2 Public Service sought from -- is seeking from the

3 Commission in its application to amend the 2007

4 Resource Plan?

5 A We sought to have them amend their

6 decision for us to acquire approximately 355 megawatts

7 of solar to instead acquire either 60 megawatts, 90

8 megawatts or 185 megawatts. And we sought relief from

9 the 200 megawatts solar thermal with storage set-aside.

10 Q And referring back to now Exhibits 133

11 through 135-A, are those true and correct copies of the

12 documents Public Service filed with the Commission to

13 seek approval to an amendment to its 2007 Resource

14 Plan?

15 A Yes, they are.

16 MR. McGANN: Your Honor, I move for the

17 admission of Exhibits 133 through 135-A.

18 A.L.J. JENNINGS-FADER: I'm going to take

19 them seriatim: Exhibit 133 for identification, which

20 is the application which opened Docket 10A-377E, is

21 offered. Voir dire or objection?

22 MR. DOUGLAS: No objection.

23 A.L.J. JENNINGS-FADER: The application

24 is admitted -- Exhibit 133 is admitted.

25 MR. FLANAGAN: Your Honor, while we don't


19
1 object to that exhibit, we don't want it to constitute

2 a waiver of the position that that docket can't be

3 opened as long as there is judicial review of the

4 underlying case.

5 A.L.J. JENNINGS-FADER: And I appreciate

6 that. That is a matter which, to the best of my

7 knowledge is now pending, has been briefed and is

8 pending in front of the Commission in Docket 10A-377E;

9 and we will proceed here as if the Commission proceeds

10 with that application and we'll have to take up what

11 happens if that application does not go forward. We'll

12 act as if that issue is not in this docket because the

13 Commission will not have taken up amending the Phase 2

14 decision. Okay.

15 MR. FLANAGAN: I just --

16 A.L.J. JENNINGS-FADER: I just want that

17 to be clear to everybody.

18 MR. FLANAGAN: We didn't want to be in a

19 position of waiving that.

20 A.L.J. JENNINGS-FADER: Nothing done here

21 can or will constitute a waiver of anything in another

22 docket, insofar as I'm concerned.

23 Now, Exhibit 134 for identification is

24 the direct testimony and exhibits of Mr. Hill, prefiled

25 in Exhibit -- excuse me, in Docket 377E.


20
1 Objections or voir?

2 MR. DOUGLAS: No objection.

3 MR. McGANN: If I may, just one

4 clarification, Your Honor on Exhibit 134, it -- Exhibit

5 134 is actually Mr. Hill's testimony. His exhibit was

6 actually separately labeled as Exhibit 135.

7 A.L.J. JENNINGS-FADER: Thank you.

8 Counsel, I have a question --

9 MR. McGANN: Yes.

10 A.L.J. JENNINGS-FADER: -- about 134. My

11 ruling in this case I believe -- I hope was clear that

12 we are not getting into the underlying specifics of

13 what drove -- excuse me, the -- we are looking at

14 potentially the -- no, we're looking at the effects of

15 granting the application, but we are not examining in

16 this proceeding what drove the company to file the

17 application beyond the scope of what Ms. Hyde has

18 identified in her prefiled statement.

19 My concern about admitting Exhibit 134 is

20 that it opens the door for examination on precisely

21 those areas about which I have already said we will not

22 take testimony.

23 Can you help me out?

24 MR. McGANN: I appreciate your caution,

25 Your Honor. First of all -- and I agree with your


21
1 prior ruling. And our intent in introducing Mr. Hill's

2 testimony was not to somehow do anything to contradict

3 that ruling. To the extent that -- we simply are

4 referring the exhibit and Mr. Hill's testimony for

5 completeness sake. Quite frankly, if you wanted to

6 understand simply the relief we've sought, you could

7 get that from the application which is Exhibit 133 and

8 you do not need Exhibits 134, 135 or 135-A.

9 And to your point, Your Honor, we would

10 agree to simply introduce the application as Exhibit

11 133 because our intent is not to open up the hearing to

12 the issues you have identified.

13 A.L.J. JENNINGS-FADER: And if I could

14 complete the thought there, do you agree with me that

15 if this were to come in as evidence that potentially

16 opens the door to examination on the evidence -- on

17 that evidence?

18 MR. McGANN: I wouldn't, although I think

19 to avoid the issue we should not introduce Exhibit 134,

20 if that would be the -- if that would be Your Honor's

21 understanding of the result if we were to introduce

22 Exhibit 134.

23 I was actually -- when Mr. Sopkin

24 clarified what our position would be with respect to

25 objections during the course of this proceeding,


22
1 notwithstanding the introduction of these exhibits, we

2 fully intended to object to questions concerning the

3 very issues that you have pointed out.

4 Now, again, to avoid that issue entirely,

5 we have no -- absolutely no objection to and would

6 actually encourage, given your statements here this

7 morning, we would actually at this point proceed and

8 just admit Exhibit 133 and not Exhibits 134, 135 or

9 135-A if there is any suggestion that doing so

10 introduces or somehow opens this proceeding to examine

11 the issues that you have identified.

12 A.L.J. JENNINGS-FADER: I would like you

13 to take a moment and consider the question and tell me

14 whether you intend to withdraw the identified exhibits.

15 MR. McGANN: May I consult with my

16 co-counsel?

17 A.L.J. JENNINGS-FADER: You may.

18 (Discussion off the record.)

19 MR. McGANN: I believe we have an answer

20 and a further request.

21 A.L.J. JENNINGS-FADER: Well, the answer

22 first and then let's see about the request.

23 MR. McGANN: The answer would be we would

24 intend to withdraw at the very least Exhibits 134, 135

25 and 135-A.
23
1 My request then becomes, if the

2 application, which is Exhibit 133, if all we need to

3 know here is exactly the relief that we have sought in

4 the amended application and Ms. Hyde has already

5 testified to that orally; and if the introduction of

6 the application would get into the issues that Your

7 Honor has identified this morning, we would withdraw

8 Exhibit 133.

9 A.L.J. JENNINGS-FADER: Okay, let me

10 start by cleaning up the record.

11 Exhibit 134 for identification, Exhibit

12 135 for identification, and Exhibit 135-A for

13 identification are withdrawn.

14 Now, as to 133, which is the verified

15 application, I will admit -- I will proceed with 133 in

16 the record simply because it states quite succinctly

17 what the options are that are pending before the

18 Commission and lays the groundwork for the three -- the

19 185, 90, and 60 megawatts, which were the lower limit

20 of what we're talking about in this -- in the current

21 proceeding, and leave it to counsel to do a

22 question-by-question objection. But I can -- I think

23 the application is important to understand the issues

24 in the reopened proceeding.

25 MR. McGANN: Thank you, Your Honor.


24
1 A.L.J. JENNINGS-FADER: I think we're at

2 136.

3 MR. McGANN: Exactly.

4 BY MR. McGANN:

5 Q Now, Ms. Hyde, if you could, take a look

6 at what has been marked as Exhibit 136 for

7 identification.

8 A I have it.

9 MR. McGANN: May I have a moment, Your

10 Honor?

11 A.L.J. JENNINGS-FADER: You may.

12 MR. McGANN: Your Honor, because we have

13 not offered -- or we have withdrawn our request to

14 submit the testimony of Mr. Hill, I actually see no

15 reason to move forward with Exhibit 136.

16 A.L.J. JENNINGS-FADER: Thank you.

17 MR. McGANN: So I would proceed with my

18 examination of Ms. Hyde.

19 A.L.J. JENNINGS-FADER: Okay, let me

20 just -- excuse me while I try to figure out what I have

21 done with all my exhibits.

22 Thank you. You may proceed.

23 BY MR. McGANN:

24 Q Now Ms. Hyde, just so, frankly, I have it

25 straight what's in the record, could you place before


25
1 you Exhibit 132, which is House Bill 10-1001 as signed

2 by the Governor?

3 A Uh-huh.

4 Q Do you have that in front of you.

5 A I do.

6 Q And could you also place in front of you

7 Exhibit 133 which is the application to amend the

8 Resource Plan?

9 A I have it.

10 Q And can you tell me, does the Renewable

11 Energy Standard amendment enacted in House Bill 10-1001

12 or the application to amend the 2007 Resource Plan

13 impact Public Service's participation in the project?

14 A No. Our plans have not changed. We

15 still want to build the line.

16 Q Now, let's take the Renewable Energy

17 Standard amendment first that was enacted in House Bill

18 10-1001, which was Exhibit 132. Why do you say that

19 the amendment to the Renewable Energy Standard does not

20 change the company's plans?

21 A Well, because although it changes the

22 standard, it doesn't change the basis for the standard

23 and the important parts that were driving our plans in

24 this case. In other words, it did not change the

25 legislative declaration of wanting to increase


26
1 renewable energy to the maximum practicable extent; and

2 it also didn't change the drive to utilize the 2

3 percent retail rate proceeds to acquire renewable

4 energy.

5 Q Now, you mentioned the 2 percent rate cap

6 in your prior answer. Were there any changes in the

7 new legislation that affected that 2 percent retail

8 rate cap?

9 A Yes, there were a few. We're allowed now

10 to apply interest on the RESA balances and it's clear

11 that we can borrow forward the money that could be

12 acquired in future years. We also have the ability to

13 seek reduction to the 3 percent distributed generation

14 provision if we need to. We can also seek reduction in

15 the standard rebate offer if we need to to make it less

16 than $2 and we can continue to acquire from customers

17 who installed distributed generation, we can continue

18 to acquire money into the RESA on kind of a fair share

19 basis.

20 Q When you say that you can continue to

21 collect moneys from distributed generation customers,

22 how was money collected from distributed generation

23 customers prior to the enactment of this amendment?

24 A It was based on the total bill. So 2

25 percent of the total bill. So when a customer


27
1 installed solar generation, their bill became smaller

2 and they contributed less money to the RESA.

3 Q And what does the amendment allow the

4 company -- what does the amendment do in terms of

5 assessing that charge to those customers?

6 A It lets us collect money that would be

7 the fair share even if it's in excess of 2 percent of

8 their bill.

9 Q Now moving on to the amended Renewable

10 Energy Standard that's set forth in the amendment, does

11 the company need to construct the line in order to meet

12 the minimum standards set forth in the amended RES for

13 the year 2020?

14 A No.

15 Q Then why has the company asked for

16 permission to construct the line?

17 A Well, first of all, we consider this to

18 be a timing issue. We still want to acquire the

19 additional solar so we need the line in order to

20 acquire that solar in our next acquisition. And we

21 need to acquire additional solar both because it's the

22 public policy in Colorado and also to use the 2 percent

23 rate cap.

24 Q With respect to the construction of

25 transmission lines, is there anything unique about


28
1 transmitting energy from facilities that generate their

2 power from solar as opposed to other fuels that affect

3 the construction of those lines?

4 A Yes.

5 Q And what is that?

6 A Well, the solar energy falls on the

7 ground in certain places, so you have to build the

8 solar resources where those solar resources are -- you

9 have to build the solar generation where the solar

10 resources are; and in this case, the best resources in

11 the state are in the San Luis Valley. Other plants,

12 say a gas-fired plant or coal-fired plant, you have

13 more flexibility because you can bring the gas and

14 transmission to wherever you want so site those plants.

15 Q Why is the company specifically trying to

16 access solar resources in the San Luis Valley?

17 A Because it's the best solar resource for

18 both PV and solar thermal in Colorado. It's got the

19 best quality of resource. It has developers who are

20 willing to develop projects in that area. And the

21 company is willing to buy those -- to expand our

22 portfolio of solar resources.

23 MR. DOUGLAS: Your Honor, I want to

24 object and move to strike. I think we're being

25 cumulative now of the hearing and I don't believe that


29
1 last answer related in any way to the issues presented

2 in the reopened hearing.

3 MR. McGANN: I believe the testimony went

4 to my -- my question was -- this whole line of

5 questioning began with why is it the amendment doesn't

6 change our desire for the line? And I think what

7 Ms. Hyde has said and I think what Mr. Douglas has

8 identified is that our reasons haven't changed; the

9 same reasons that we had in the initial hearings are

10 the same reasons that we have today. So to

11 Mr. Douglas' point, is it going to be a reiteration of

12 what we had before, it absolutely will; but I think it

13 has to be stated for this reopened record.

14 A.L.J. JENNINGS-FADER: I will overrule

15 the objection.

16 Counsel, if you could be careful in

17 phrasing the question so we can be careful about, does

18 the amendment change whatever, you know, so that we're

19 focused on events which have occurred since the close

20 of the last record.

21 MR. McGANN: I will, Your Honor.

22 Thank you.

23 BY MR. McGANN:

24 Q Ms. Hyde, would you agree with me that as

25 a foundational matter that the company favors and the


30
1 company established in the first round of hearings that

2 the company favors concentrating solar power facilities

3 over other renewable resources?

4 A In the future, yes, we believe that those

5 will form a good part of our acquisitions.

6 Q Has anything in the amendment changed

7 that from the company's perspective?

8 A No.

9 Q Moving on to the application to amend the

10 Resource Plan, if the Commission were to amend the

11 Resource Plan and set the solar resource acquisition

12 level of 60, 90, or 185 megawatts, would that impact

13 Public Service's participation in the project?

14 A No.

15 Q Why not?

16 A Because none of the issues identified in

17 the reopening have changed our plans. We still want to

18 build the transmission line. We just had to delay the

19 acquisition of those solar resources because we

20 couldn't get the line approved in time; and so we

21 scaled back our acquisition right now, but it's just a

22 matter of timing. We still want to add additional

23 solar thermal and that's why we would continue to push

24 for the approval of the project.

25 Q Would you agree with me that there are a


31
1 number of things that are uncertain about the future?

2 A Yes.

3 Q Do you have an opinion as to what is

4 certain -- what is certain to occur if the certificate

5 for this transmission line is denied?

6 A If the CPCN is denied, we'll severely

7 curtail the amount of solar resources that we can add

8 in the San Luis Valley, in the future.

9 MR. McGANN: Your Honor, may have a

10 moment?

11 A.L.J. JENNINGS-FADER: You may.

12 MR. McGANN: I have nothing further, Your

13 Honor.

14 A.L.J. JENNINGS-FADER: Thank you,

15 counsel.

16 Let's do it an odd way, does anyone other

17 than Trinichera Ranch have any questions?

18 MS. MANDELL: No, thank you, Your Honor.

19 A.L.J. JENNINGS-FADER: Thank you all.

20 Mr. Douglas.

21 MR. DOUGLAS: Thank you, Your Honor.

22 (Pause.)

23 A.L.J. JENNINGS-FADER: And not to slight

24 Blanca Ranch, I'm including them -- or it in the

25 Trinichera Ranch reference.


32
1 MR. FLANAGAN: That's a conservation

2 easement.

3 MR. DOUGLAS: Your Honor, before I start

4 into the actual questioning of Ms. Hyde, we had some

5 discussion -- or you and Mr. McGann had some discussion

6 about the exhibits that Public Service had marked but

7 not offered.

8 A.L.J. JENNINGS-FADER: They were

9 withdrawn, yes.

10 MR. DOUGLAS: Some of them, yes, were

11 offered and then withdrawn.

12 And, Your Honor, I would like to at this

13 time offer those exhibits into the record. I do not

14 believe that we can have a complete record with respect

15 to the reopened hearing issue relating to the

16 application to amend without those exhibits. There is

17 a significant level of detail in the testimony of

18 Mr. Hill and in the -- and Exhibit 135 is the amendment

19 to 2007 Colorado Resource Plan, itself, that is not

20 contained in the application that I believe

21 specifically relates to some of the issues that in Your

22 Honor's ruling you have allowed questioning into.

23 And I agree with you that there is

24 overlap between -- in those exhibits between what

25 issues you have allowed and what issues you have


33
1 excluded from consideration in the reopened hearing.

2 And we -- as you may know, we respectfully disagree

3 with some of the -- with the issues that have been

4 excluded; however I believe that in order to explore

5 the issues that Your Honor has opened the record to, it

6 is important that these exhibits be admitted into the

7 record.

8 So with that I would offer -- I believe

9 the foundation was laid by Mr. McGann -- 133, 134, 135,

10 and Exhibit 136 into the record.

11 A.L.J. JENNINGS-FADER: Mr. McGann?

12 MR. McGANN: If I may respond, Your

13 Honor, we offered the exhibits -- well, actually let me

14 go back to Mr. Sopkin's preliminary statement which was

15 that based upon the rulings that have been made so far

16 on our motions in limine, to a certain extent we were

17 uncertain as to what the scope of the hearing would be.

18 We certainly agree with Your Honor's ruling that

19 matters that have to be addressed in the Resource Plan

20 or the amendment to address the Resource Plan, Resource

21 Planning dockets, as well as RES Compliance Plan

22 dockets have to be addressed in those particular

23 proceedings.

24 Our offering of the attachments to the

25 application to amend the 2007 Resource Plan was simply


34
1 for administrative convenience to the extent Your Honor

2 wanted those in the record.

3 For example, when we tendered the

4 disclosure from Ms. Hyde's testimony, we included the

5 entire filing in the tendering of the witness

6 disclosure.

7 Your Honor has pointed out -- and we

8 agree -- that by doing that we run the danger of

9 expanding the scope of this proceeding. And I

10 appreciate Your Honor's caution and we absolutely agree

11 with Your Honor's ruling. And it's pretty clear from

12 Mr. Dougla's offering of those exhibits that that's

13 exactly what Mr. Douglas wants to do.

14 I accepted your ruling, Your Honor, and

15 agree that the scope of this hearing is what is the

16 impact on the line, to the extent that the Commission

17 reduces the amount of solar that the company is ordered

18 to acquire pursuant to the 2007 Resource Plan?

19 That's all. And I agree with Your

20 Honor's ruling that to really tighten the hearing up

21 and make sure we didn't get into extraneous issues,

22 simply introducing the application which gives that

23 lower limit, is all that is needed in order to

24 sufficiently limit the scope of this hearing.

25 So I agree with Your Honor's ruling and


35
1 we oppose Mr. Douglas' motion to introduce these other

2 exhibits into the record.

3 I want to be clear that our offering was

4 not that we thought that these -- that we were going to

5 rely on these documents or that these documents were

6 relevant to this particular proceeding; it was simply

7 out for administrative convenience that we offered

8 those exhibits. Your Honor has made a ruling that they

9 are not to be admitted and we agree with that ruling.

10 MR. DOUGLAS: Your Honor.

11 A.L.J. JENNINGS-FADER: You may respond,

12 Mr. Douglas, and then I have a question.

13 MR. DOUGLAS: Okay, Your Honor, I'm not

14 intending to offer those exhibits to expand the issues

15 in the hearing as Mr. McGann argues or to say that

16 offering those exhibits -- or admitting those exhibits

17 into evidence would change your prior rulings on the

18 motion in limine which gave us direction on the topics

19 that you believe are on -- are within limits and off

20 limits.

21 I'm simply saying that there is relevant

22 and admissible information in those exhibits that

23 relates specifically to the areas of testimony that you

24 have allowed in your rulings in this proceeding and

25 that we cannot have a complete record without them.


36
1 And the fact that there may be other details in there

2 that relate to areas you consider off limits is not a

3 reason to refuse admission of the documents.

4 A.L.J. JENNINGS-FADER: In your opinion.

5 MR. DOUGLAS: In my opinion.

6 A.L.J. JENNINGS-FADER: Mr. Douglas, let

7 me ask you two questions: The first is, can you help

8 me to understand why you would need the -- what I'm

9 going to refer to as the reliance documents, that is

10 the testimony of Mr. Hill and the specifics of the

11 underlying information supporting the application to

12 amend the 2007 Colorado Resource Plan in order to --

13 why do you need that information in order to examine

14 Ms. Hyde on the following issue which is -- which is

15 the issue in this docket, quote -- excuse me, in this

16 proceeding with respect to the amendment and that issue

17 is the impact, if any, on the need for the project in

18 the event the Commission grants the application to

19 amend the 2007 Colorado Resource Plan and sets the

20 solar resource acquisition level at 185 megawatts, at

21 90 megawatts or at 60 megawatts period, unquote.

22 MR. DOUGLAS: Your Honor, the answer to

23 that is that Public Service in this case has discussed

24 or put forth as its stated need for the line both

25 short-term solar resource acquisitions which have now


37
1 dropped to either 60, 90, or 185 in their view and also

2 longer term solar resource acquisitions identified as

3 three solar thermal placeholders totaling 250 megawatts

4 in the years 2016 through 2018.

5 The portions of -- specific portions of

6 both the Hill testimony and the actual amendment,

7 Exhibit 135 to the 2007 Colorado Resource Plan,

8 specifically address issues that were discussed by

9 Ms. Hyde and other witnesses regarding those future

10 solar resource acquisitions which Public Service is

11 relying on at least in part for the need for the line

12 and whether the likelihood of acquisition of those

13 resources has changed in light of the information

14 contained in the amendment, specifically; and that's

15 relevant and that's something that Your Honor had ruled

16 is relevant. And those documents are needed to fully

17 explore that issue.

18 A.L.J. JENNINGS-FADER: Now I have yet

19 another question.

20 MR. DOUGLAS: All right.

21 A.L.J. JENNINGS-FADER: Where is the

22 reference in -- I assume you are talking about the most

23 recent ruling, the most recent decision.

24 MR. DOUGLAS: Uh-huh. Yes, Your Honor.

25 A.L.J. JENNINGS-FADER: R10-0746-I.


38
1 MR. DOUGLAS: Yes, Your Honor.

2 A.L.J. JENNINGS-FADER: So where did I

3 say that? I know I address it. I just want the

4 reference.

5 MR. DOUGLAS: Your Honor, in paragraphs

6 52 of that order and also --

7 A.L.J. JENNINGS-FADER: Right, discussing

8 Mr. Dauphinais' testimony.

9 MR. DOUGLAS: Right. Specifically, Mr.

10 Dauphinais' testimony specifically referred to the

11 three 250-megawatt solar thermal placeholder resources

12 and then the change of economic circumstances and the

13 amendment that relate to the likelihood of those being

14 developed.

15 A.L.J. JENNINGS-FADER: Thank you for

16 identifying that reference.

17 Now to my second question, can you

18 explain to me why you need the documents -- the

19 withdrawn exhibits for identification 134, 135, 135-A,

20 in order to cross-examine Ms. Hyde with respect to the

21 issue of the three solar thermal placeholders?

22 MR. DOUGLAS: Your Honor, specifically

23 those changed economic circumstances that are

24 referenced in Your Honor's ruling are detailed in those

25 specific documents. And what they are -- and then


39
1 taking those details and asking Ms. Hyde her opinion

2 about whether that affects the likelihood of those

3 resources is something that I can't do without the

4 documents.

5 A.L.J. JENNINGS-FADER: You can't do

6 without the documents? I'm unclear as to how you

7 can -- my question is this: Can you not refer to the

8 document or ask questions about the documents whether

9 or not they are in evidence?

10 MR. DOUGLAS: Your Honor, in questioning

11 Ms. Hyde, we could proceed with some of that. There is

12 a lot of detail in the exhibits; whether I cover it

13 all, there is also an opportunity in statements of

14 position to bring together the evidence and we may also

15 be asking Mr. Dauphinais or Dr. Shefferin to comment on

16 those.

17 It's my position that there is a lot of

18 information in those documents that is specifically

19 relevant to these issues and it's otherwise admissible

20 and should be in the record in order for us to not only

21 examine Ms. Hyde but also make the record complete with

22 that evidence that's relevant.

23 MR. McGANN: Your Honor, may I respond?

24 A.L.J. JENNINGS-FADER: I have a -- one

25 more question -- and one more question, Mr. Douglas,


40
1 did Mr. Dauphinais and/or Dr. Shefferin rely on any of

2 these documents in their summary of testimony?

3 MR. DOUGLAS: Yes, they did, Your Honor.

4 A.L.J. JENNINGS-FADER: Thank you.

5 Mr. McGann.

6 MR. McGANN: Your Honor, I think the way

7 you have explained the scope of this proceeding is

8 certainly our understanding of the scope and that is

9 very simply that we are to assume that the

10 Commission -- that the Commission will establish the

11 lower end of the company's solar acquisitions in the

12 amended Resource Plan docket; and the question here is

13 how does that impact the need for the line? And

14 that's, quite frankly, a very simple question. And we

15 have had actually Ms. Hyde answer that question without

16 reference to any of the documents that Mr. Douglas has

17 referred to.

18 I think the only reason Mr. Douglas would

19 want to get into those documents is to get behind the

20 reasoning that either Public Service had for seeking

21 the amendment or that the Commission might have for

22 reaching any one of those conclusions or perhaps

23 another conclusion. And I think Your Honor has already

24 stated that that is beyond the scope of this particular

25 proceeding so I see no need for Mr. Douglas to


41
1 introduce these exhibits for the cross-examination of

2 Ms. Hyde.

3 Now, it's another matter, to the extent

4 that Mr. Douglas, when he's examining Dr. Shefferin or

5 Mr. Dauphinais to try to get those exhibits into the

6 record through either of those witnesses. We'll take

7 that up by objection when those witnesses hit the

8 stand; but in terms of our case and Ms. Hyde's direct

9 testimony, I think Your Honor's ruling is well taken

10 and should stand. And Mr. Douglas's efforts to get

11 these exhibits into the record should be denied.

12 A.L.J. JENNINGS-FADER: You have the last

13 word if you wish to add anything. And this will be the

14 last word except of course for my ruling.

15 MR. DOUGLAS: Your Honor, if I asked

16 questions about these documents to go into an area that

17 has been ruled out, I'm sure Mr. McGann will object.

18 Also, Ms. Hyde answered a very broad

19 question at the end of her testimony about whether

20 anything in the amendment changes the plans of Public

21 Service. And I believe they have opened the door to

22 questions about looking at the specifics and saying,

23 so, wait, this doesn't change your plans, and exploring

24 those in detail. That's all fair game.

25 A.L.J. JENNINGS-FADER: And I agree with


42
1 you, counsel; but I think you can do that by

2 cross-examination and I do not believe you need the

3 documents in evidence in order to do that.

4 So to that extent, your motion to admit

5 Exhibits 134, 135, and 135-A, at least at this time and

6 through this witness is denied. And I appreciate that

7 that may lengthen the cross-examination.

8 MR. DOUGLAS: All right, may I proceed

9 Your Honor?

10 A.L.J. JENNINGS-FADER: You certainly

11 may.

12

13 CROSS-EXAMINATION

14 BY MR. DOUGLAS:

15 Q Good morning, Ms. Hyde.

16 A Good morning.

17 Q Ms. Hyde, you testified about House Bill

18 10-1001 and I want to go into a little more detail

19 about that statute and what it did, in your

20 understanding. So first of all, House Bill 10-1001

21 requires 30 percent of electric utility sales by 2020

22 to be supplied by renewable energy including banking of

23 credits and in-state bonuses and that sort of thing; is

24 that correct?

25 A It requires you to have Renewable Energy


43
1 Credits that are equal to 30 percent of your retail

2 sales.

3 Q And Renewable Energy Credits can be from

4 the generation of renewable energy from banked credits,

5 in-state bonuses, those things?

6 A Or purchased credits, yeah.

7 Q Okay. But the bottom line is 30 percent

8 by 2020?

9 A 30 percent Renewable Energy Credits.

10 Q And is it correct a banked Renewable

11 Energy Credit or REC is credit for renewable generation

12 that was generated in a previous year but not used in

13 that year to satisfy the RES requirements and therefore

14 carries over to a future year?

15 A Yes.

16 Q Okay. And the prior Renewable Energy

17 Standard or RES statute required 20 percent credits by

18 Renewable Energy Credits by 2020, including the similar

19 banking and in-state bonuses, correct?

20 A As a minimum, yes.

21 Q And that's a significant increase from 20

22 percent to 30 percent, correct?

23 A Um, our plans that we had in place with

24 the 20 percent satisfies the 30 percent; so the number

25 changed, but it really doesn't change our plans.


44
1 Q Okay. House Bill 10-1001 also requires 3

2 percent of electric utility sales in 2020 to be

3 supplied by distributed generation; that is correct?

4 A Yes.

5 Q And that 3 percent also -- the 30 percent

6 represent minimum requirements, correct?

7 A Yes.

8 Q You can exceed those if you can fit

9 additional resources that would exceed those minimums

10 within the 2 percent retail rate-impact cap.

11 A Yes.

12 Q Of that 3 percent requirement of

13 distributed generation, at least half must be generated

14 by retail distributed generation as defined in the

15 statute; that is correct?

16 MR. McGANN: I object to the form of the

17 question, Your Honor. Actually I also believe it

18 assumes facts not in evidence. The 3 percent standard

19 is subject to Commission change based on an application

20 by the utility. So I think when we are speaking about

21 that 3 percent, we shouldn't be talking about that as

22 an absolute number. It can be changed by the

23 Commission. I just simply believe that to the extent

24 Mr. Douglas is asking a hypothetical, it ought to be

25 asked in that context.


45
1 A.L.J. JENNINGS-FADER: Can I just --

2 before you respond, Mr. Douglas -- and you may -- give

3 me, please, the reference with respect to the change

4 that the Commission -- isn't that, for the record,

5 following December 31, 2014?

6 MR. McGANN: That is correct. And I

7 believe the context of Mr. Dougla's question was up to

8 2020.

9 A.L.J. JENNINGS-FADER: All right. So I

10 wish to be -- that is the provision to which you are

11 referring; is that correct?

12 MR. McGANN: Yes.

13 A.L.J. JENNINGS-FADER: Thank you. Then

14 in that context, the objection to the form of the

15 question is sustained; so if you could clarify the

16 question, sir.

17 MR. DOUGLAS: All right.

18 BY MR. DOUGLAS:

19 Q Ms. Hyde, as the statute is currently in

20 effect -- first of all, let me clarify, I'm asking you

21 right now about the statute as enacted. And you agree

22 there are certain provisions in the statute that may

23 result in changes in the future by the Commission to

24 some of these provisions; is that fair?

25 A Yes.
46
1 Q But the statute as written requires that

2 at least half of the 3 percent distributed generation

3 requirement be what is defined as retail distributed

4 generation; is that correct?

5 A Yes, by 2020, if it hasn't been changed

6 by the Commission.

7 Q Okay. And the prior statute required

8 that at least 2 percent of that prior 20 percent

9 requirement be met with on-site solar generation; is

10 that accurate?

11 A Yes, by 2020.

12 Q Okay. And you agree that there is no

13 requirement in House Bill 10-1001 that any of the

14 requirements of that statute be met by solar

15 generation, correct?

16 A Correct.

17 Q And you agree that essentially House Bill

18 10-1001 increases the amount of on-site distributed

19 generation from 0.4 percent of the total to 1.5 percent

20 now; is that accurate?

21 A By 2020, yes, it increased the minimum

22 standard, subject to all the caveats we've talked

23 about, from .4 percent to 1.5 percent.

24 Q Okay. And that prior renewable energy

25 statute allowed Public Service to count the on-site


47
1 solar distributed generation with that in-state bonus

2 of 1.25 times what was actually generated?

3 A Yes.

4 Q And House Bill 10-1001 removes that in-

5 state bonus for retail distributed generation, correct?

6 A Yes.

7 Q You agree that House Bill 10-1001

8 reflects a public policy goal in Colorado to increase

9 the amount of distributed generation?

10 A It dramatically changed the definition of

11 distributed generation from the original bill. So I

12 would need more clarification on what you are -- what

13 specifically you are asking about.

14 Q All right, let's take a look at your

15 deposition.

16 MR. DOUGLAS: Your Honor, may I approach?

17 A.L.J. JENNINGS-FADER: You may, thank

18 you.

19 BY MR. DOUGLAS:

20 Q Ms. Hyde, do you have in front of you a

21 copy of a deposition you gave in this matter on June

22 25th, 2010?

23 A Yes.

24 Q And if you would, please turn to page 25

25 of that deposition.
48
1 A.L.J. JENNINGS-FADER: Counsel, 25 of

2 the quarter pages --

3 MR. DOUGLAS: Yes, it's page 7 at the

4 very bottom, right; but it's deposition page 25.

5 A.L.J. JENNINGS-FADER: Thank you very

6 much.

7 MR. DOUGLAS: On the quarter pages.

8 A.L.J. JENNINGS-FADER: Thanks.

9 MR. DOUGLAS: You are welcome.

10 Q Are you with me, Ms. Hyde?

11 A Yes.

12 Q Starting on line 16, you were asked, You

13 mentioned public policy and it's clear from House Bill

14 10-1001, itself, that there is a public policy by the

15 Colorado legislature to increase the amount of

16 distributed generation, correct? And your answer was,

17 Yes. Yes, they want to increase distributed

18 generation. Do you see that?

19 A Yes.

20 Q And that was your testimony that day?

21 A Yes.

22 Q Do you agree that House Bill 10-1001

23 substantially increases the amount of retail renewable

24 distributed generation that Public Service must

25 acquire?
49
1 A It increases the minimum amount that we

2 need to acquire. It doesn't substantially increase the

3 amount we were planning to acquire.

4 Q Okay. But it does substantially increase

5 the minimum amount that you are required to acquire.

6 A Yes.

7 Q You agree that with banked renewable

8 energy credits and in-state bonuses, Public Service has

9 enough resources -- renewable resources with what is on

10 line today and what is planned in the 2007 Colorado

11 Resource Plan, as proposed to be amended by Public

12 Service to satisfy the House Bill 10-1001 minimum

13 requirements through 2029; is that correct?

14 MR. McGANN: Your Honor, I have an odd

15 objection. I have been letting this questioning go to

16 this point of time. I believe this is friendly cross.

17 We basically said we didn't need the line to meet the

18 minimum standards in the statute. And this entire line

19 of cross has been exploring that issue. We agree. We

20 do not need the line to meet the minimum requirements

21 of the statute. So I object to this as, quite frankly,

22 friendly cross.

23 A.L.J. JENNINGS-FADER: And I will say

24 that is an odd objection coming from the opposition in

25 this case.
50
1 Mr. Douglas?

2 MR. DOUGLAS: Your Honor, I'm exploring

3 the details of when or how long they will be able to

4 meet the statute.

5 She said we don't need the line to meet

6 the statute and I'm interested in details of when she

7 will need the line. And I think that's perfectly

8 relevant to the issues in this case.

9 A.L.J. JENNINGS-FADER: And I will allow

10 it to continue, provided we move to that topic, having

11 laid the foundation.

12 MR. DOUGLAS: Thank you, Your Honor.

13 A.L.J. JENNINGS-FADER: Objection

14 overruled.

15 BY MR. DOUGLAS:

16 Q So let me repeat the question: Do you

17 agree that with banked renewable credits and in-stated

18 bonuses Public Service has enough resources with what

19 it has on line today and what's planned in the 2007

20 Colorado Resource Plan as you proposed to amend it

21 downward to satisfy the minimum requirements of House

22 Bill 10-1001 through 2029?

23 A The full amount of the standard?

24 Q The minimum requirements of House Bill

25 10-1001.
51
1 A No, we're a little short on the retail

2 distributed.

3 Q All right, let's go to what I believe in

4 the documents you produced -- and we'll get there --

5 that Public Service describes as the non-DG

6 requirements, or non-distributed generation

7 requirements of House Bill 10-1001 which is essentially

8 27 percent as opposed to 30 percent; is that fair?

9 A Right. That's how -- the part that

10 doesn't have to be met by distributed.

11 Q Right. Okay, so as to that part does not

12 have to be met by distributed generation; you agree

13 that Public Service has enough resources, enough

14 renewable resources with what's on line today and

15 what's planned in the 2007 Colorado Resource Plan as

16 you proposed to amend it to satisfy the minimum

17 standard of House Bill 10-1001 through 2029?

18 A It meets the minimum REC standard. It

19 doesn't utilize the 2 percent.

20 Q As far as the 27 percent minimum

21 requirement, you can meet that through 2029 without

22 adding additional resources, right?

23 A Yes, it meets the minimum REC

24 requirements.

25 Q And you can only add resources beyond


52
1 those requirements if you can fit those resources

2 within the 2 percent retail rate-impact cap, correct?

3 A No, we could also add them if they were

4 Section 123 resources.

5 Q That's a good clarification. Let's try

6 that one again.

7 You could only add renewable resources

8 beyond that minimum requirements that you said you can

9 meet through 2029 if they are either Section 123

10 resources or you can fit them within the 2 percent

11 retail rate-impact cap, right?

12 A Yes.

13 Q And so you agree that Public Service can

14 meet that minimum requirement of 27 percent through

15 2029 without acquiring any of the three 250-megawatt

16 solar thermal placeholders that are described in the

17 2010 Public Service RES Compliance Plan, correct?

18 A Yes.

19 MR. McGANN: I object at this point in

20 time, Your Honor. The statute says we can meet a

21 standard through 2020. Mr. Douglas is now asking about

22 through 2029. I fail to see the relevance of this line

23 of questioning. I also think it's quite frankly

24 friendly cross.

25 A.L.J. JENNINGS-FADER: Well, as to the


53
1 friendly cross, I'll overrule the objection because

2 he's moving to the area of the three -- at least as I

3 heard the question, the three 250-megawatt placeholder

4 units that were discussed in the February hearing.

5 So -- but as to the other point with

6 respect to going past 2020 --

7 MR. DOUGLAS: Your Honor, I could ask

8 Ms. Hyde a clarification question but I don't believe

9 the requirements of the statute end in 2020. I believe

10 it's a continuing obligation at this point to have

11 those credits beyond 2020.

12 A.L.J. JENNINGS-FADER: I believe that

13 the statute specifically says for the years 2020 and

14 thereafter. So the objection on both grounds is

15 overruled. You may continue -- excuse me, Ms. Hyde,

16 you may answer the question.

17 THE WITNESS: I don't remember what it

18 was.

19 BY MR. DOUGLAS:

20 Q All right. Let me just repeat it rather

21 than have it read back because I think I have it.

22 Do you agree that Public Service can meet

23 the minimum REC requirements of House Bill 10-1001, the

24 non-DG, 27 percent, that we discussed through 2029

25 without acquiring any of the three 250-megawatt solar


54
1 thermal placeholders that were described in the 2010

2 RES Compliance Plan?

3 A Yes.

4 (Whereupon, Exhibit No. 137 marked for

5 identification.)

6 BY MR. DOUGLAS:

7 Q Ms. Hyde, do you have in front of you

8 what's been marked as Exhibit 137?

9 A Yes.

10 Q And have you seen this document before?

11 A Yes.

12 Q Is this a document that was prepared by

13 Public Service Company of Colorado?

14 A By -- yes, by Kari Clark.

15 Q Karen?

16 A Kari.

17 Q Kari Clark, thank you.

18 And is it correct that this document is

19 the -- what I would call the modeling or the

20 calculation of how Public Service will comply with

21 House Bill 10-1001 through 2030?

22 A I wouldn't say that. I would say that

23 this was a scenario that Kari ran to see what our

24 current plans would accomplish relative to House Bill

25 10-1001.
55
1 Q And by current plans, you mean what

2 Public Service currently has on line, plus the

3 resources in the 2007 Resource Plan as you propose to

4 amend it?

5 A Yes.

6 Q So, for example, it counts 125 megawatts

7 of solar thermal resources in the San Luis Valley and

8 nothing beyond that?

9 A You said 125 megawatts in the San Luis

10 Valley?

11 Q Yes.

12 A No, it has more than that of generation

13 in the San Luis Valley.

14 Q Well, I was hoping to avoid getting --

15 you are talking about page 2?

16 A Well, I'm trying to see page 2. I have a

17 lot of trouble with this spreadsheet.

18 Q I do have some bigger blow-ups if that

19 would help.

20 A I tried the magnifying glass, doesn't

21 work -- not enough.

22 Q Let me see if I can get us to agree

23 without getting into the details, it's the 125

24 megawatts of solar thermal, plus 60 of PV in the 2007

25 Resource Plan; is that correct?


56
1 A No, because it also has the Greater Sand

2 Hill and SunE Alamosa.

3 Q Okay, I think we are actually on the same

4 page, so let me just make sure we have this clear. In

5 Exhibit 137, Public Service has done a forecast of its

6 compliance with House Bill 10-1001 through 2030 that

7 includes the resources that are on line on today and

8 then specific to the San Luis Valley, the Alamosa and

9 Greater Sand Hill PV plants, plus the 185 megawatt

10 option that you proposed in the 2007 Resource Plan; is

11 that correct?

12 A I believe that's what's in here. I can't

13 actually see it to verify, but I believe that's in

14 here.

15 Q Well, we can get a magnifying glass or I

16 have a better copy if you want to take issue with it.

17 A A bigger copy, if you want me to verify

18 it; but if you can tell in here, I'm fine; because I

19 believe when I checked, that was what was in here.

20 Q Okay.

21 MR. DOUGLAS: Your Honor, I would offer

22 Exhibit 137 into evidence.

23 A.L.J. JENNINGS-FADER: Exhibit 137 for

24 identification has been offered. Voir dire objection?

25 MR. McGANN: Well, Your Honor, I suppose


57
1 I have an objection. First of all, this isn't a

2 document this witness prepared. Also, this witness was

3 having a difficult time reading the document.

4 Again, I still keep coming back to the

5 fact that this is cumulative of what has already been

6 testified to. So I'm not sure that the facts that Mr.

7 Douglas has elicited through this exhibit are in

8 controversy at this point.

9 So I object to the admission of the

10 document.

11 A.L.J. JENNINGS-FADER: Anyone else

12 before Mr. Douglas responds?

13 (No response.)

14 A.L.J. JENNINGS-FADER: Mr. Douglas?

15 MR. DOUGLAS: Your Honor, if I may

16 approach for the witness, I have a -- well --

17 A.L.J. JENNINGS-FADER: Well, perhaps you

18 can ask one question that starts with: Is this a

19 response to discovery; how did this come into the

20 possession of Trinichera Ranch? Start with that and

21 then show her the big picture.

22 MR. DOUGLAS: Thank you, Your Honor.

23 BY MR. DOUGLAS:

24 Q Ms Hyde, do you know whether this

25 document was produced to Trinichera Ranch in discovery


58
1 prior to the reopened hearing issues?

2 A Yes, it was.

3 Q And you said you are familiar with who

4 prepared this?

5 A Yes.

6 Q Who was that?

7 A Kari Clark.

8 Q And --

9 A K-a-r-i.

10 Q And did Ms. Clark prepare this as part of

11 her regular duties at Public Service Company of

12 Colorado?

13 A Yes -- she is not a Public Service

14 Company of Colorado employee.

15 Q By whom is she employed?

16 A Xcel Energy Services, Inc.

17 Q All right.

18 MR. DOUGLAS: If I may approach, Your

19 Honor?

20 A.L.J. JENNINGS-FADER: You may.

21 THE WITNESS: Oh, that's much more

22 promising.

23 A.L.J. JENNINGS-FADER: Counsel, if you

24 wish to look, you certainly may.

25 THE WITNESS: I don't have a printer this


59
1 big.

2 A.L.J. JENNINGS-FADER: Mr. Douglas, for

3 the record, could you identify -- you have handed her

4 one page of three pages. If you could, identify what's

5 been handed to the witness.

6 BY MR. DOUGLAS:

7 Q Yes, Ms. Hyde, does it appear that what I

8 have just handed you is a large blow-up of page 2 of

9 Exhibit 137?

10 A Yeah, you gave me page 2.

11 Q And I'll represent to you that pages 1

12 and 3 relate to the forecasts of Public Service's

13 compliance with the distributed generation requirements

14 of House Bill 10-1001, and the page about which I

15 intend to ask questions about at the this point is page

16 2, the one I just handed you.

17 A Okay.

18 MR. McGANN: May I have a moment, Your

19 Honor?

20 A.L.J. JENNINGS-FADER: You certainly

21 may.

22 (Pause.)

23 MR. McGANN: Your Honor, may I address

24 the exhibits -- actually with respect to

25 confidentiality, not with respect to --


60
1 A.L.J. JENNINGS-FADER: Why don't you

2 wait until Mr. Douglas has had an opportunity to

3 consult with his colleagues.

4 (Pause.)

5 A.L.J. JENNINGS-FADER: Are you back with

6 us?

7 MR. DOUGLAS: Yes, I am. I apologize,

8 Your Honor.

9 A.L.J. JENNINGS-FADER: No, that's fine.

10 I believe we now have an issue with

11 respect to confidentiality being raised with respect to

12 Exhibit 137 for identification.

13 Yes, Mr. McGann.

14 MR. McGANN: I believe that these

15 exhibits when expanded contain names of bidders and

16 therefore these are confidential. I don't believe we

17 introduced them to Trinichera Ranch as confidential

18 exhibits; however, I, having taken a look at the

19 exhibits and having consulted with Ms. Hyde, I believe

20 they are. So I would ask that these exhibits be marked

21 as confidential.

22 A.L.J. JENNINGS-FADER: I'm sorry, by

23 these exhibits, you are just referring to Exhibit 137

24 for identification?

25 MR. McGANN: That's correct.


61
1 A.L.J. JENNINGS-FADER: Okay, thank you.

2 I just wanted to be sure. Thanks.

3 In that event, yes, Exhibit 137, on the

4 representation of Public Service that it contains

5 confidential material, will now be Confidential Exhibit

6 137. We will not -- two things will happen, those who

7 have not signed confidentiality -- nondisclosure

8 agreements, please return whatever you may have

9 received; and secondly, the specifics with respect to

10 the exhibit will be discussed in a confidential session

11 of this proceeding.

12 However, I think for purposes of

13 identifying -- by admitting the document, we can

14 proceed.

15 Mr. Nelson?

16 MR. NELSON: Yes, I could make a request,

17 if I understood Mr. McGann's recommendation that the

18 information that is confidential is the names of the

19 individual parties, I was wondering if it would be

20 possible to request that at some point during this

21 process if this is ultimately admitted if Public

22 Service could produce a version of it that has the

23 confidential information redacted for those parties who

24 don't have -- or have not signed a nondisclosure

25 agreement.
62
1 A.L.J. JENNINGS-FADER: Mr. McGann,

2 perhaps -- Ms. Hyde?

3 THE WITNESS: Yes.

4 A.L.J. JENNINGS-FADER: Having looked at

5 what is now Confidential Exhibit 137 for

6 identification, you have identified at least page 2

7 some information which in your opinion is confidential

8 information, correct?

9 THE WITNESS: On page 2 and page 3.

10 A.L.J. JENNINGS-FADER: Okay. Could you

11 specifically identify for me and for the record what

12 the information is which in your opinion is

13 confidential?

14 THE WITNESS: Do you want me to point it

15 out to you?

16 A.L.J. JENNINGS-FADER: Well, is it in a

17 particular column; can you -- is there some way to

18 describe it or is it everything -- is it a particular

19 column or is it everything about particular entities

20 all the way across the document, if you understand my

21 question?

22 THE WITNESS: Yes, I understand.

23 No, it's very limited information. There

24 would be three pieces of information that would be --

25 that would have to be redacted. Very limited.


63
1 A.L.J. JENNINGS-FADER: And can you at

2 least identify where that information is found on each

3 page of the document, obviously without revealing the

4 information?

5 THE WITNESS: Right -- on page 2?

6 A.L.J. JENNINGS-FADER: Yes.

7 THE WITNESS: Right up here.

8 A.L.J. JENNINGS-FADER: So you are

9 looking at the upper left-hand corner of the document,

10 yes?

11 THE WITNESS: In the first column, under

12 the blue writing.

13 A.L.J. JENNINGS-FADER: Yes.

14 THE WITNESS: That next line.

15 A.L.J. JENNINGS-FADER: Yes.

16 THE WITNESS: That name --

17 A.L.J. JENNINGS-FADER: Okay.

18 THE WITNESS: -- is confidential.

19 A.L.J. JENNINGS-FADER: But not any

20 information which appears proceeding from left to right

21 about that -- about that entity; is that correct? Do

22 you understand my question?

23 THE WITNESS: Yes, I do.

24 We also haven't officially revealed for

25 that same line the exact number of megawatts. So that


64
1 very next one.

2 A.L.J. JENNINGS-FADER: Okay. And that

3 would be -- that's all the information on page 12?

4 THE WITNESS: Yes.

5 A.L.J. JENNINGS-FADER: Thank you.

6 And on page 3?

7 THE WITNESS: On page 3, similarly look

8 in the first column, about halfway down --

9 A.L.J. JENNINGS-FADER: Yes. I -- the

10 first column on the left, right?

11 THE WITNESS: The first column on the

12 left, about halfway down in the orange, there is the

13 names of two bidders.

14 A.L.J. JENNINGS-FADER: Okay. And that's

15 confidential.

16 And any information starting with that

17 name and moving right across the sheet, any other

18 information that would have to be removed as

19 confidential?

20 THE WITNESS: No.

21 A.L.J. JENNINGS-FADER: Okay, thank you.

22 That helps me to understand the scope of Mr. Nelson's

23 request. Thank you.

24 Public Service?

25 MR. McGANN: I believe we actually, if I


65
1 can consult for a moment, with my witness.

2 A.L.J. JENNINGS-FADER: You certainly

3 may.

4 (Discussion off the record.)

5 A.L.J. JENNINGS-FADER: Yes, sir?

6 MR. McGANN: Yes, Your Honor, we should

7 be able to provide a redacted copy of this exhibit.

8 A.L.J. JENNINGS-FADER: In which event,

9 the redacted version will be Exhibit 137 for

10 identification. The confidential version will be

11 Exhibit 138 for identification.

12 Mr. McGann, for the folks who don't have

13 access to the confidential version, when might Public

14 Service be able to provide that in that -- excuse me,

15 the public version?

16 MR. McGANN: Your question, Your Honor,

17 was when?

18 A.L.J. JENNINGS-FADER: When, yes.

19 MR. McGANN: May I consult?

20 A.L.J. JENNINGS-FADER: You may.

21 MR. McGANN: We believe we should be able

22 to provide it right after lunch.

23 A.L.J. JENNINGS-FADER: Excellent. Thank

24 you.

25 MR. NELSON: Thank you.


66
1 A.L.J. JENNINGS-FADER: Certainly.

2 We now have two exhibits about which we

3 are discussing, Mr. Douglas; we were trying to admit

4 these exhibits, I believe.

5 MR. DOUGLAS: Yes. And I would renew my

6 request at this time to offer Exhibit 137 and

7 Confidential Exhibit 137-A into the record.

8 A.L.J. JENNINGS-FADER: Okay. Now,

9 Mr. -- all counsel, Exhibit 137 and Exhibit 137-A have

10 been offered, voir dire or objection?

11 MR. McGANN: Your Honor, at this point in

12 time, I would just ask is there any reason to admit the

13 confidential version of the exhibit? Could we simply

14 just go with the public version once we provide it? Is

15 Mr. Douglas intending on going into confidential

16 information?

17 MR. DOUGLAS: Your Honor, I do not need

18 to go into confidential information, so it would be

19 fine with me to simply offer the public version of 137.

20 A.L.J. JENNINGS-FADER: Okay, fine. In

21 that event, that's what we shall do.

22 Exhibit 137 will be a-- or is admitted.

23 That puts some counsel at something of a

24 disadvantage at the moment since they don't have access

25 to the document about which we will be asking


67
1 questions.

2 We're going to go off the record for a

3 moment.

4 (Discussion off the record.)

5 A.L.J. JENNINGS-FADER: We will take a

6 few minutes -- unspecified few-minute break -- this is

7 not our morning break -- for the purpose of allowing

8 Public Service to redact the exhibit.

9 Mr. McGann, if you all would tell the

10 reporter when you are ready to go.

11 MR. McGANN: We will.

12 A.L.J. JENNINGS-FADER: And he'll come

13 get me.

14 MR. McGANN: We will, thank you.

15 (Recess.)

16 A.L.J. JENNINGS-FADER: We'll be back on

17 the record.

18 Mr. Douglas, how went the attempts with

19 this exhibit?

20 MR. DOUGLAS: It went well, Your Honor.

21 Ms. Hyde and Ms. Kittel redacted the

22 various versions and I think we're all on the same

23 page.

24 BY MR. DOUGLAS:

25 Q And correct me if I'm wrong, Ms. Hyde,


68
1 the version of Exhibit 137 you have in front of you is

2 now a public redacted version?

3 A Yes.

4 A.L.J. JENNINGS-FADER: Super.

5 All right. Now, Mr. McGann, I think your

6 only question had to do with confidentiality. Are we

7 now good with Exhibit 137 for identification?

8 MR. McGANN: Yes, we are, Your Honor.

9 A.L.J. JENNINGS-FADER: Thank you.

10 Exhibit 137 for identification is

11 admitted.

12 MR. DOUGLAS: Thank you, Your Honor.

13 BY MR. DOUGLAS:

14 Q And, Ms. Hyde, before I ask you

15 questions -- I do have a couple questions about Exhibit

16 137 -- I want to mark Exhibit 138.

17 MR. DOUGLAS: I do not believe we have

18 any confidentiality issues with this one because if I

19 may speak to Mr. McGann, Mr. McGann, what I have done

20 is pulled only -- one page out of another one of the

21 documents you gave us that I don't believe has any

22 issues but you can verify.

23 A.L.J. JENNINGS-FADER: Thank you.

24 Exhibit 138 for identification.

25 (Whereupon, Exhibit No. 138 marked for


69
1 identification.)

2 (Pause.)

3 A.L.J. JENNINGS-FADER: Mr. Douglas?

4 MR. DOUGLAS: Thank you, Your Honor.

5 BY MR. DOUGLAS:

6 Q Ms. Hyde, do you have Exhibit 138 in

7 front of you?

8 A Yes, I do.

9 Q Was that a document that to your

10 understanding was introduced to Trinichera Ranch as

11 part of this reopened hearing?

12 A Yes, it was part of an answer to your --

13 one of your discovery questions.

14 BY MR. DOUGLAS:

15 Q And this was a document that was prepared

16 by Public Service?

17 A No, it was prepared by Kari Clark.

18 Q Xcel Energy?

19 A Xcel Energy.

20 Q And is it accurate to describe this as a

21 summary document relating to the forecast of Public

22 Service's compliance with House Bill 10-1001?

23 A I mean, it looks like a summary form. I

24 don't remember what scenario this was.

25 Q Well, if -- just so we make sure we're


70
1 all on the same page, you can compare some of the

2 numbers from Exhibit 138, the 2020 column, to page 2 of

3 Exhibit 137, and see that, for example, at the very top

4 the retail sales figure is the same; and at the very

5 bottom of page 2 of Exhibit 137, the number of

6 Renewable Energy Credits available to meet the

7 requirements of House Bill 10-1001 are identical. Do

8 you agree with that?

9 A I agreed with you on the retail sales.

10 What was the other one you wanted to compare?

11 Q The RECs available to meet the

12 requirements of House Bill 10-1001 which was the very

13 last line, just under the pink on Exhibit 137, page 2;

14 and you can see that in 2020 that number of a little

15 over 39 million matches up to the same number on

16 Exhibit 138, the total RECs available for compliance as

17 of 2020; is that accurate?

18 A I see that those numbers equal, yeah.

19 Q So as far as this document 138, is it a

20 summary -- the same scenario by -- what was the

21 person's name again?

22 A Kari Clark.

23 Q Kari Clark, the scenario run by Kari

24 Clark in Exhibit 137; is that correct?

25 A I'll have to accept your representation


71
1 because I don't know for sure that they are the same.

2 I know you just pointed out numbers that are the same.

3 Q Well, the bottom line, Credits Available

4 for Compliance in these two documents are the same,

5 correct, as of 2020?

6 A Through 2020. We only checked 2020.

7 Q Okay.

8 A But 2020 was the same.

9 Q And Exhibit 138 only goes through 2020,

10 correct?

11 A Right.

12 Q Okay. So do you have any reason to

13 disagree that Exhibit 138 which was prepared by the

14 same person appears to be a summary of the forecast

15 that is set forth in more detail in Exhibit 137?

16 A I can accept your representation. I have

17 no reason to know though whether it's the same. I know

18 she did multiple scenarios.

19 Q Okay.

20 A I don't know if this one is the same as

21 A-4.

22 Q Okay. So the bottom line number on

23 compliance with House Bill 10-1001 is the credits --

24 the total credits available for compliance in a given

25 year, correct?
72
1 A On 137?

2 Q Well, on both of them. The endgame is,

3 do you have enough credits to comply with the statute

4 or how do your total credits look as far as how they

5 compare to the requirements, right? That's the

6 endgame?

7 A Well, that's, I believe, what she was

8 analyzing under different scenarios.

9 Q Okay. And under -- at least as of 2020,

10 which is as far as 138 goes, and then 2020 on Exhibit

11 137, that bottom line number, Total Credits Available

12 for Compliance is identical, right?

13 A Through 2020, yes.

14 Q First of all, you can see --

15 MR. DOUGLAS: Let me stop at this point

16 and offer Exhibit 138 in evidence Your Honor?

17 A.L.J. JENNINGS-FADER: Exhibit 138 for

18 identification has been offered. Voir dire or

19 objection?

20 MR. McGANN: Your Honor, I -- two things:

21 I do object. Number one, I think the witness has said

22 she cannot vouch for the summary contained in Exhibit

23 138. Furthermore, during the questioning of Ms. Hyde,

24 I think Mr. Douglas was simply pointing out that 138

25 was a summary of what was in 137. 137 has been


73
1 admitted. Do we really need 138?

2 MR. DOUGLAS: Your Honor, I can answer

3 that question.

4 A.L.J. JENNINGS-FADER: Any other

5 response before any Mr. Douglas -- any other comment to

6 the -- with respect to the motion?

7 (No response.)

8 A.L.J. JENNINGS-FADER: Mr. Douglas.

9 MR. DOUGLAS: Your Honor, Exhibit 138

10 contains some information, specifically the nameplate

11 capacity of what was considered in that analysis that

12 Ms. Hyde and I talked a little bit about in her

13 deposition which clarified some of the options in 137

14 that is not actually contained in 137 in that form.

15 A.L.J. JENNINGS-FADER: I will admit 138

16 and the Commission will give to the exhibit the weight

17 that it deems appropriate.

18 MR. DOUGLAS: Thank you, Your Honor.

19 BY MR. DOUGLAS:

20 Q Ms. Hyde, if you would take a look at

21 Exhibit 138, and do you see for the portion of that

22 document talking about the non-DG or non-distributed

23 generation requirements of House Bill 10-1001, there is

24 a section that talks about the nameplate capacity of

25 the resources; do you see that?


74
1 A Yes.

2 Q Okay. And do you agree that this

3 analysis by Kari Clark, based on the information in

4 that nameplate capacity section, was forecasting solar

5 thermal generation in the San Luis Valley at the

6 125-megawatt level?

7 A Yes.

8 Q And you believe that's also the case in

9 Exhibit 137 that the forecast that was run in that

10 exhibit model, the solar thermal resources in the San

11 Luis Valley was at the 125-megawatt level?

12 A Yes.

13 Q And is it your understanding that the

14 generation level -- the total generation level for the

15 San Luis Valley that was modeled in the forecast that's

16 in Exhibit 137 includes that 125 megawatts of solar

17 thermal, 60 megawatts of additional solar PV, plus the

18 generation from the Greater Sand Hill and Alamosa PV

19 plants?

20 A Yes.

21 Q All right. Now, if you take a look at

22 page 2 of Exhibit 137, which I believe you have a large

23 version of it if you need to refer to that one, do you

24 agree that -- well, let me start over.

25 If you take a look at Exhibit 137, this


75
1 document is the support, if you will, for your

2 statement that no additional resources are needed until

3 after 2029 that you gave earlier; is that correct?

4 A To meet the minimum REC requirements,

5 yes, based on this analysis.

6 Q All right. And starting in 2030, the

7 very far right column, that's the first time there is a

8 deficit identified by Public Service in the available

9 credits to meet those requirements, right?

10 A To meet the non-DG portion, yes.

11 Q All right. And if you look at the top

12 part of that 2030 column, the first fifteen or so

13 entries as it goes orange, that's all relating to wind

14 generation by Public Service; is that correct?

15 A Yes.

16 Q And the deficit that is set forth in this

17 exhibit, starting in 2030, assumes that nine of those

18 wind contracts -- nine of those fifteen wind contracts

19 that are listed will have expired; is that correct?

20 A Yes.

21 Q And, in fact, starting in 2012, all

22 fifteen of those wind contracts listed there will be on

23 line and in service, correct?

24 A I would say it looks like they are all on

25 line from 2012, but it looks like that doesn't start


76
1 them all being on line because it looks like the next

2 year there is one that's not.

3 Q Yeah, it looks like one of them -- it's a

4 small one, right? It looks like five megawatts expires

5 in 2013, right?

6 A Yes.

7 Q Okay. So starting in 2012 and continuing

8 for a number of years after that -- you can refer to

9 Exhibit 138 if you need to, but Public Service will

10 have on line over 1950 megawatts of nameplate wind

11 generation, correct?

12 A Yes.

13 Q And the nine contracts that are assumed

14 to have expired as of this deficit in 2030 make up a

15 significant portion of that wind generation; do you

16 agree with that?

17 A Yes.

18 Q And do you believe that it's likely that

19 at least some of those nine wind contracts will be

20 renewed?

21 A I don't know.

22 Q That would be determined in a future

23 resource docket?

24 A Yeah, I think it will be determined in a

25 future resource docket and the age of the equipment at


77
1 that time.

2 Q All right. But some of them may well be

3 renewed and be generating in 2030 and beyond; correct?

4 A I don't know.

5 Q It's possible, isn't it?

6 A It is possible that they could do some

7 kind of life extension or bid those back in, yes.

8 Q If that would happen, that would reduce

9 the availability of energy resources credits starting

10 in 2030, correct?

11 MR. McGANN: I object, Your Honor. I

12 allowed a few questions. I think we're getting into

13 resource planning issues, In the future you might

14 acquire a certain resource mix; and I think that's

15 beyond the scope of the rehearing.

16 A.L.J. JENNINGS-FADER: Other response

17 before Mr. Douglas?

18 (No response.)

19 A.L.J. JENNINGS-FADER: Counsel?

20 MR. DOUGLAS: Your Honor, I'm not trying

21 to get into the details of resource mix, but Ms. Hyde

22 talked about a time frame after which they would start

23 to need additional renewables which they are talking

24 about as a future justification for this line. And I'm

25 exploring whether and the extent of deficit they say is


78
1 there -- and I'm pretty close to being done with this

2 area.

3 A.L.J. JENNINGS-FADER: I'll allow a

4 couple of more questions in this area, then please move

5 on.

6 MR. DOUGLAS: All right, thank you, Your

7 Honor.

8 BY MR. DOUGLAS:

9 Q Ms. Hyde, I believe the last question

10 was, if some of those nine contracts that are listed in

11 this Exhibit 137 as having expired as of 2030, if some

12 of those are renewed, that would reduce the deficit in

13 the Renewable Energy Credits that would be needed as of

14 2030 and beyond, correct?

15 A If we renewed -- if we picked some of

16 these and they produced energy in those years, would it

17 reduce the -- would it give us more RECs to comply?

18 Q Yes.

19 A Yes.

20 Q And Public Service is currently studying

21 the feasibility of adding an additional 1000 megawatts

22 of wind to its system on top of these 15 wind resources

23 that we have been discussing, correct?

24 A No. We're studying the cost to add a

25 thousand megawatts and we're studying the impact of


79
1 cycling on our larger units.

2 Q Okay, you are studying issues relating to

3 whether or not you would be able to add up to an

4 additional thousand megawatts of wind above the

5 resources we have been talking about, correct?

6 A Yes.

7 Q And that study is not yet completed?

8 A No, it's not -- and it's two studies.

9 Q Two studies?

10 A Right.

11 Q And you are not aware of any preliminary

12 results or findings from those studies?

13 A No, I'm not.

14 Q But you agree that at least some -- well,

15 strike that.

16 Is it correct that Exhibit 137 and the

17 Renewable Energy Credits that are forecast there do not

18 include any of that potentially up to a thousand

19 megawatts of wind?

20 A Yes.

21 Q And you agree that at least some of this

22 additional thousand megawatts of wind that's currently

23 being studied by Public Service will be added to the

24 system by 2020, correct?

25 A I think -- I don't know what the result


80
1 of the study will be. I know we would like to be able

2 to try to add more wind to the system. We're concerned

3 about the feasibility and viability of that. Plus we

4 haven't gotten to the level where we add the 700

5 megawatts.

6 Q Sure, but you think it is reasonable --

7 you think that Public Service will probably add some of

8 that additional thousand, right?

9 A Probably add something. I don't know

10 what -- that it's going to be very significant, but

11 some amount.

12 Q Some amount but less than the full

13 thousand?

14 A Much less than the full thousand.

15 Q All right, I want to talk a little bit

16 about the retail rate impact limitation in House Bill

17 10-1001. You mentioned that a little bit in your

18 direct examination. And the old RES statute that was

19 replaced by House Bill 10-1001 included a retail

20 rate-impact cap, right; is that correct?

21 A Yes.

22 Q It provided Public Service could add a

23 rider on to ratepayers' bills of up to 2 percent to put

24 money into an account called the RESA account that

25 would pay for the incremental cost of future renewable


81
1 acquisitions, correct?

2 A It doesn't really go into an account;

3 it's tracked as a separate mechanism, but you don't put

4 the money into an account.

5 Q But for accounting purposes, you have a

6 separate bucket that you have designated a RESA fund

7 that is used to -- that's collected from this 2 percent

8 rider that pays for the incremental cost of renewable

9 resource acquisitions.

10 A Yes.

11 Q And under the old statute that was capped

12 at 2 percent of the total electric bill annually for

13 each customer, right?

14 A Yes.

15 Q And the new statute maintains that retail

16 rate impact limit and a maximum of 2 percent of the

17 total electric bill annually for each customer,

18 correct?

19 A Not for each customer because it exempted

20 the 2 percent for customers who installed distributed

21 generation.

22 Q The old statute?

23 A The new statute.

24 Q Oh, I see what you are saying. The new

25 statute says the maximum impact of 2 percent of the


82
1 total electric bill annually for each customer except

2 those customers that install retail distributed

3 generation can -- you can get more than 2 percent from

4 those folks?

5 A Yes.

6 Q But you agree, when the legislature last

7 raised the rate impact -- well, strike that.

8 Do you agree that when the Colorado

9 legislature changed the RES requirements from 10

10 percent to 20 percent, they also doubled the retail

11 rate-impact cap from 1 percent to 2 percent?

12 A Yes.

13 Q And in this case, under House Bill

14 10-1001, it went from 20 percent to 30 percent, but the

15 retail rate impact stayed at 2 percent?

16 A Right. Yes.

17 Q The amended statute now allows Public

18 Service to advance funds from year to year to augment

19 the amounts collected from customers under the 2

20 percent retail rate-impact cap; is that correct?

21 A I think we always could advance funds.

22 It just let's us recover our interest rate at the

23 weighted average cost of capital.

24 Q I just want to make sure we all

25 understand what we're talking about.


83
1 So, first of all, before Public Service

2 can advance funds against future RESA collections, it

3 must have Commission approval for that; is that

4 correct?

5 A I need to look at the legislation.

6 Q We can look at that. That's Exhibit 132.

7 If you take a look at page 8.

8 A Yes, under the new rule, we need

9 Commission approval.

10 Q And so under this rule, Public Service

11 cannot collect more than 2 percent from ratepayers

12 other than distributed generation retail customers in

13 any given year, correct?

14 A Yes.

15 Q But you can spend more than 2 percent or

16 what you collected under that 2 percent in a given year

17 and pay yourself back from future 2 percent collections

18 from customers; is that accurate?

19 A Yes. For the amount that's above the

20 cost effective piece.

21 Q Okay, if you get Commission approval to

22 do so --

23 A To borrow the money forward.

24 Q Right.

25 MR. McGANN: I object, Your Honor.


84
1 Actually there is an existing Commission rule -- we're

2 arguing about rules and statutes. There is an existing

3 rule that provides for borrowing forward and carrying

4 balances up and down. I object to the question, it

5 mischaracterizes the law.

6 MR. DOUGLAS: I'm asking what the statute

7 requires, Your Honor. And I think that's what she

8 answered. I'm not sure what the objection refers to

9 because I think we actually moved on.

10 MR. McGANN: I understood the question to

11 basically ask whether Commission approval was needed to

12 carry forward balances or -- to carry balances or

13 borrow forward or balances. That's not the case.

14 That's not what this statute says. It says you need to

15 seek Commission approval to get the weighted -- my

16 understanding is to get the weighted after-tax cost

17 of -- let me -- let's refer to the part of the statute

18 that Mr. Douglas is referring to.

19 A.L.J. JENNINGS-FADER: Page 8?

20 MR. McGANN: I believe it's page 8,

21 right.

22 MR. DOUGLAS: Yeah, under (g)(1)(b), it

23 says, At the request of the qualifying retail utility

24 and upon the Commission's approval, the qualifying

25 retail utility may advance funds from year to year to


85
1 augment the amounts collected from retail customers

2 under this paragraph. And I believe Ms. Hyde confirmed

3 that that's the law.

4 MR. McGANN: And I'm simply suggesting

5 that that's the current Commission rule. The

6 difference is that the weighted after-tax cost of

7 capital can be added to those balances at an interest

8 rate.

9 A.L.J. JENNINGS-FADER: To the extent

10 that you think Ms. Hyde's testimony to date needs

11 clarification, you certainly may address that on

12 redirect.

13 MR. McGANN: Thank you, Your Honor.

14 MR. DOUGLAS: Thank you, Your Honor.

15 BY MR. DOUGLAS:

16 Q Now, what we're essentially talking

17 about, Ms. Hyde, is that the RESA account which is the

18 dollars available for future renewable resource

19 acquisitions can go into the negative if Public Service

20 spends more in a given year than it's collected under

21 the 2 percent rider; is that accurate?

22 A Yes.

23 Q And if it goes into the negative, Public

24 Service, as you discussed, earns interest on that

25 negative balance at its after-tax weighted average cost


86
1 of capital.

2 A Yes.

3 Q And currently that rate is 7.88 percent?

4 A I don't know what it is at the moment.

5 It changes with our capitalization structure and

6 interest rates.

7 Q Okay. And if that's in a Commission

8 decision, you would have no reason to disagree with

9 that?

10 A I would have no reason to disagree with

11 what was our weighted cost of capital when the decision

12 was rendered. I don't know if it's our weighted cost

13 of capital today.

14 Q If it's not 7.88 today, is it something

15 in that ballpark?

16 A Yes.

17 Q So in other words, Public Service gets a

18 return on a negative RESA balance, correct?

19 A We get interest at the weighted average

20 cost of capital, yes.

21 Q And that interest is passed on to the

22 ratepayers to pay, correct?

23 A I think it's added to the balance to be

24 paid by the ratepayers at some point.

25 Q Right, meaning that that interest on the


87
1 negative balance is additional revenue to Public

2 Service above the actual cost of their renewable

3 resources; is that accurate?

4 A It would be revenue to Public Service at

5 some point in the future when it starts to get repaid.

6 Q Right, revenue above the actual cost of

7 the resources, right?

8 A I guess I'm having trouble -- it's not

9 revenue today because we're negative. It's just an

10 accrual today.

11 Q It may be future revenue, but it's

12 additional revenue to Public Service above the actual

13 cost paid for those resources, right?

14 A Yes, at some point in time it is.

15 Q And you don't believe there is any legal

16 limit on how far into the negative under this statute

17 or any Commission rule that Public Service can go in

18 the RESA account, do you?

19 A That's correct.

20 Q But you do agree that Public Service

21 would not be willing to maintain a negative RESA

22 balance for a period of ten years, right?

23 A I think that ten years is probably too

24 long. I don't know exactly what -- how many years we

25 would be willing to do it.


88
1 Q And I believe you told me before that the

2 maximum time that Public Service would be willing to

3 maintain a negative RESA balance is somewhere between

4 five and ten years, right?

5 A I think I told you it becomes an

6 accounting determination whether that asset is still

7 recoverable, and preliminary discussions with the

8 accounting group said that ten years is probably too

9 long to be able to perfect the regulatory asset. So it

10 really becomes an accounting issue of what the

11 accountants are satisfied with and our auditors.

12 Q And what you told me is your accountants

13 would likely be -- feel it would be too long at ten

14 years, would be acceptable at five years, and the line

15 would be somewhere in between, right?

16 MR. McGANN: I object, Your Honor. I

17 have allowed it to go for a little while. These are

18 RES Compliance Plan issues. If we're going to go to

19 the issue and ask them what they should do with these

20 RESA balances, this is outside the scope of this

21 reopened record.

22 A.L.J. JENNINGS-FADER: Response, Mr.

23 Douglas?

24 MR. DOUGLAS: Your Honor, Ms. Hyde

25 testified on direct that they would have available for


89
1 RESA dollars to meet that plan to add more solar; and

2 part of the analysis of whether RESA dollars will be

3 available involves this concept of borrowing forward

4 and how far into the negative they are willing to go;

5 and I believe that's relevant to the likelihood of

6 acquisition of future resources. And we're almost

7 done.

8 A.L.J. JENNINGS-FADER: All right, I must

9 say I totally admire the way you always throw that in.

10 I just think that's -- you know, for completeness, I

11 certainly do.

12 I do think we're getting a little far

13 afield.

14 MR. DOUGLAS: Okay.

15 A.L.J. JENNINGS-FADER: So I'm going to

16 cut you off before you reach your last couple of

17 questions.

18 MR. DOUGLAS: I'll move on then.

19 BY MR. DOUGLAS:

20 Q Ms. Hyde, I believe you have indicated

21 that you believe that the 2010 Public Service RES

22 Compliance Plan continues to reasonably reflect the

23 solar resources that will be acquired over the next

24 several years.

25 MR. McGANN: I object, Your Honor. That


90
1 mischaracterizes her testimony. She did not testify to

2 that in this proceeding.

3 MR. DOUGLAS: Your Honor, I believe she

4 doesn't specify the 2010 RES Compliance Plan; however

5 she did, in her notice of witness testimony, which we

6 can get out to refresh her recollection. So she has

7 indicated that in the past.

8 A.L.J. JENNINGS-FADER: I will allow that

9 question because I believe Ms. Hyde's testimony was

10 that as to the amendment to the 2007 Colorado Resource

11 Plan, that nothing in that amendment or proposal has

12 changed Public Service's long-term plan.

13 MR. DOUGLAS: Are --

14 A.L.J. JENNINGS-FADER: Excuse me, and

15 then she described that as the short-term change but

16 not a long-term change.

17 Counsel?

18 MR. DOUGLAS: Thank you, Your Honor.

19 BY MR. DOUGLAS:

20 Q Let me rephrase this a little bit: You

21 believe, Ms. Hyde, that the 2010 Public Service RES

22 Compliance Plan is the best place to look for Public

23 Service's longer term acquisition of solar resources;

24 is that accurate?

25 A At this time, yes.


91
1 MR. DOUGLAS: If I may approach, Your

2 Honor?

3 A.L.J. JENNINGS-FADER: You may.

4 (Whereupon, Exhibit Nos. 139 and 140

5 marked for identification.)

6 BY MR. DOUGLAS:

7 Q Ms. Hyde, you have Exhibits 139 and 140

8 in front of you?

9 A I do.

10 Q And are those copies of -- well, is

11 Exhibit 139 a copy of Volume 1 of the Public Service

12 2010 Renewable Standard Compliance Plan?

13 A Yes.

14 Q And is Exhibit 140 a copy of Volume 2 of

15 Public Service 2010 Energy Standard Compliance Plan,

16 essentially the tables -- supporting tables to Volume

17 1?

18 A Yes.

19 Q And that's in fact the 2010 RES

20 Compliance Plan that you just referred to in your

21 testimony?

22 A Yes.

23 MR. DOUGLAS: Your Honor, I would offer

24 Exhibit 139 and 140 into evidence.

25 A.L.J. JENNINGS-FADER: Exhibit 139 for


92
1 identification has been offered. Voir dire or

2 objection?

3 MR. McGANN: Your Honor, given your prior

4 ruling, I have no objection to Exhibit 139.

5 Exhibit 140, I do know that the tables

6 that are reflected in this exhibit were changed during

7 the course of the proceeding which is actually still

8 ongoing. And I believe those hearing exhibits were

9 changed during the course of the proceeding when it was

10 reopened to actually consider changes to these tables.

11 So I do not believe the tables here are an accurate

12 reflection of the tables that were ultimately

13 introduced into the record in that case.

14 A.L.J. JENNINGS-FADER: Let's take

15 Exhibit 139. Seeing no objection, Exhibit 139 for

16 identification is admitted.

17 Now, Mr. McGann, your statements with

18 respect to revised or changed tables have to do with

19 Exhibit 140 for identification; is that correct?

20 MR. McGANN: That is correct, Your Honor.

21 A.L.J. JENNINGS-FADER: And do you happen

22 to know, sir -- well, one can inquire of the witness,

23 when it says on Exhibit 140 for identification revised

24 January 27, 2010, do you know whether that includes

25 then the amendments?


93
1 MR. McGANN: It does not. The tables

2 that were revised in the hearing were revised March 19,

3 2010.

4 A.L.J. JENNINGS-FADER: Thank you. So

5 the basis of the objection is that the exhibit does not

6 accurately represent the tables contained in the

7 exhibit?

8 MR. McGANN: That's correct.

9 A.L.J. JENNINGS-FADER: And ultimately

10 admitted into evidence?

11 MR. McGANN: That's correct. And I'm

12 specifically referring to tables 7-1 through 7-5.

13 A.L.J. JENNINGS-FADER: Thank you.

14 Counsel?

15 MR. DOUGLAS: Your Honor, we got this off

16 the Public Service website. It says it's revised

17 1/27/2010. If there were further additions after that

18 point, we had a discovery request in conjunction with

19 this particular proceeding for revised tables,

20 specifically 7-3 and 7-4 that we asked for. We haven't

21 been given those. I believe this is the best

22 information we have as far as what was produced to us

23 by Public Service. If there were substantial changes

24 to the tables -- and I'm specifically going to be

25 talking about Table 7-3 and 7-4 -- that I don't know


94
1 what the revisions he's talking about, whether they

2 substantially affect the numbers we're going to talk

3 about or not. If so, whether they can produce those to

4 us over lunch or we can talk about them it, if Ms. Hyde

5 is coming back for rebuttal -- there may be other

6 opportunities, but this is the information they gave us

7 and I believe I'm entitled to ask the witness about it.

8 A.L.J. JENNINGS-FADER: Mr. -- before I

9 ask Mr. McGann -- or give Mr. McGann the opportunity to

10 respond, Mr. Douglas, I understood you to say that

11 Public -- that Trinichera Ranch specifically requested

12 of Public Service in discovery what?

13 MR. DOUGLAS: We will to get -- we can

14 pull that to get the specific language, but we

15 specifically asked for revised tables. If you want

16 me --

17 A.L.J. JENNINGS-FADER: Revised table to

18 Volume 2 of the 2010 Renewable Energy Standard

19 Compliance Plan?

20 MR. DOUGLAS: Yes, Your Honor.

21 A.L.J. JENNINGS-FADER: And to date that

22 response to that has been?

23 MR. DOUGLAS: I believe they said they

24 had not redone the table.

25 A.L.J. JENNINGS-FADER: Counsel?


95
1 MR. McGANN: My understanding --

2 A.L.J. JENNINGS-FADER: I'm sorry,

3 Mr. McGann.

4 MR. McGANN: My understanding of the

5 discovery request was, Has the company modeled the

6 affected or revised assumptions described on JFH-1 in

7 the amended Resource Plan on the Renewable Energy

8 Standard adjustment balance in the 2010 RES Compliance

9 Plan? That we have not done.

10 What we did was in the course of the 2010

11 RES Compliance Plan, we amended or corrected these

12 tables. It had nothing to do with JFH-1 and the

13 results of that analysis.

14 So at least that's the discovery. What I

15 understand Mr. Douglas is referring to.

16 MR. DOUGLAS: Your Honor, the discovery

17 request reads --

18 A.L.J. JENNINGS-FADER: I'm sorry, could

19 you give me a reference, a number so that we all

20 understanding which --

21 MR. DOUGLAS: Yes.

22 A.L.J. JENNINGS-FADER: I haven't seen

23 them -- so we all understand what's being discussed?

24 MR. DOUGLAS: Yes. I apologize, because

25 it's a little confusing. The requests were renumbered,


96
1 so I'm looking at the renumbered request by Public

2 Service. It's listed Trinichera Ranch Discovery

3 Request 26-8. And it's: If the company has updated

4 the analysis in the 2000 RES Compliance Plan filed in

5 Docket 09A-772E, including but not limited to tables

6 4-1, 4-2, 4-3, 4-4, 7-1, 7-2, 7-3, 7-4 to reflect the

7 revised assumptions in the company's 2007 Colorado

8 Resource Plan, please fully describe the updated

9 analysis and provide the revised tables.

10 MR. McGANN: And again, Your Honor,

11 that's not what those revisions did.

12 A.L.J. JENNINGS-FADER: Okay, by which --

13 could you be more specific? Are you referring to the

14 specific language with respect to the -- that if you

15 have updated it with respect to this particular thing?

16 As I recall that's -- I don't have the language in

17 front of me; but is that your point?

18 MR. McGANN: That's correct. To reflect

19 the specific language in 26-8 is to reflect revised

20 assumptions in the amendments to the 2007 Colorado

21 Resource Plan. These tables were not amended to

22 reflect that amendment.

23 MR. DOUGLAS: Your Honor, I would also

24 add, I discussed these tables specifically and this

25 version of the document with Ms. Hyde at her


97
1 deposition. There was a question raised about -- Ms.

2 Hyde was unsure whether they were the most recent

3 tables or not; we went through all the numbers with

4 that understanding, she was not sure. Public Service

5 never, after that time, provided any information or

6 tables to indicate to Trinichera Ranch, prior to just

7 now, that in fact there had been further updates to

8 those tables.

9 MR. McGANN: I can respond, Your Honor,

10 or --

11 A.L.J. JENNINGS-FADER: Yes, thank you.

12 MR. McGANN: There was no obligation to

13 respond to any further requests, Your Honor. I mean,

14 we had a request on the table asking whether or not we

15 had updated these tables for the amended Resource Plan.

16 We had not. Ms. Hyde mentioned during her

17 deposition -- actually I think Mr. Sopkin mentioned he

18 thought the tables had been revised and there was no

19 follow-up from Trinichera Ranch after that point in

20 time.

21 Yes, it is true Mr. Douglas continued to

22 ask Ms. Hyde questions concerning those tables; but the

23 question at that point had already been raised. At

24 that point there was either an obligation to the

25 parties for Trinichera Ranch to ask for updated tables


98
1 or go on the website where they found these tables and

2 find the updated tables from the 2010 RES Compliance

3 Plan.

4 MR. DOUGLAS: Your Honor, I believe we

5 did go to the website and this was what -- this was the

6 most recent one that we found. And we did make an

7 attempt to do that and confirmed to our satisfaction

8 that at least that appeared to be the most recent one

9 available on the Public Service website.

10 A.L.J. JENNINGS-FADER: Well, this is

11 awkward in the following respect: First of all, let me

12 say that I agree with Public Service that the discovery

13 request as read into the record was limited to changes

14 made for a particular purpose, that is to reflect the

15 amendments on the 2007 Public Service Colorado Resource

16 Plan. Based on representations of counsel, which I

17 presume one can confirm with the witness, that appears

18 not to be the reason or the basis on which the changes

19 were made to the referenced Table 7-3 and -- 7-3 and

20 7-4 in Hearing Exhibit 140.

21 So I agree with Public Service that there

22 is no obligation, excuse me, to provide the updated

23 pages -- tables, as a discovery issue.

24 So my concern now has to do with

25 admitting Exhibit 140 for identification, knowing that


99
1 the information about which it appears Mr. Douglas

2 intends to inquire is incorrect in terms of the

3 evidence admitted in another proceeding, as the tables

4 admitted in another proceeding. So I -- at this

5 juncture, I will not allow Exhibit 140 for

6 identification to be admitted. And we'll see whether

7 this can be addressed after lunch or at some other

8 time; but at this juncture, there is sufficient

9 question with respect to the accuracy of this exhibit

10 to warrant -- to warrant -- to sustain the objection

11 and not admit the exhibit.

12 MR. DOUGLAS: Your Honor, I'll just

13 represent -- we'll come back to this in -- maybe after

14 lunch or at a break, but we've just checked again on

15 the website and this was the most recent version that

16 was available that we could find.

17 A.L.J. JENNINGS-FADER: Perhaps I could

18 ask this, do you know what website was being checked?

19 MR. DOUGLAS: That's the question I just

20 asked whether it was the Public Service website or the

21 Commission docket or both, and we're double-checking

22 that.

23 A.L.J. JENNINGS-FADER: Okay, thank you.

24 At this point I will sustain the

25 objection and not admit Exhibit 140 for identification


100
1 in its present form.

2 (Discussion off the record.)

3 A.L.J. JENNINGS-FADER: Mr. Douglas,

4 could we take the official ten-minute break at this

5 juncture to give the court reporter time to do the

6 paper and we'll be back at ten minutes to the hour --

7 ten minutes to the hour.

8 (Recess.)

9 (Discussion off the record.)

10 A.L.J. JENNINGS-FADER: We'll be back on

11 the record.

12 Mr. Douglas.

13 MR. DOUGLAS: Your Honor, we have

14 obtained what are essentially the errata sheets filed

15 in Docket -- I can't remember the number but in the

16 2010 RES compliance docket. In fact the exhibit in

17 that docket is still listed as the January 27, 2010

18 update; but if you click on the document itself, there

19 are some pages that are an errata to that which are the

20 tables to which Mr. McGann is referring. So -- but

21 there is not a completely revised exhibit. So what I

22 would propose is that Exhibit 140 be admitted as is

23 because there are portions of that that are not part of

24 this errata; and then we are still compiling all the

25 copies of what I would propose to mark as Exhibit 141


101
1 which are the revised tables that we have obtained that

2 relate to Exhibit 139.

3 A.L.J. JENNINGS-FADER: Mr. -- before --

4 just as a quick clarifying question, then you would

5 presumably not ask questions of Ms. Hyde with respect

6 to the revised variables 7-3 and 7-4 or any other of

7 the revised tables until 141 is admitted?

8 MR. DOUGLAS: That's correct.

9 A.L.J. JENNINGS-FADER: Okay, thank you.

10 With that clarification, I will take this

11 as a reoffer of Exhibit 140.

12 Mr. McGann or any other counsel?

13 MR. McGANN: May I have a moment, Your

14 Honor?

15 A.L.J. JENNINGS-FADER: Yes.

16 MR. McGANN: No objection, Your Honor.

17 A.L.J. JENNINGS-FADER: Thank you.

18 Exhibit 140 is admitted and we await

19 Exhibit 141.

20 A.L.J. JENNINGS-FADER: Thank you, Mr.

21 Douglas.

22 Thank you, counsel. We'll reserve 141.

23 MR. DOUGLAS: Thank you, Your Honor. And

24 I will proceed with some questions about 139 while

25 we're waiting for the full copies of 141.


102
1 A.L.J. JENNINGS-FADER: Thank you.

2 BY MR. DOUGLAS:

3 Q All right, Ms. Hyde, I have handed -- do

4 you have in front of you what's been marked Exhibit

5 139?

6 A Yes.

7 Q And just to orient us all, that's Volume

8 1 of Public Service's 2010 Renewable Energy Standard

9 Compliance Plan?

10 A Yes.

11 Q Okay. And this 2010 plan includes

12 projections through 2020; is that correct?

13 A Yes.

14 Q That's ten years out?

15 A It was filed in '9, so maybe 11 years.

16 Q From today it's looking out ten years?

17 A Right.

18 Q Where we are today.

19 And you agree Public Service only plans

20 its system for resource acquisitions within less than

21 ten years, correct?

22 A Correct -- up to ten years --

23 Q Yes.

24 A -- under the resource planning rules.

25 Q Okay. And the resources discussed in


103
1 this Exhibit 139, the 2010 Compliance Plan, that would

2 potentially be located in the San Luis Valley; other

3 than the resources that are part of the 2007 Resource

4 Plan, are three 250-megawatt solar thermal

5 placeholders, correct?

6 A That would specifically be in the San

7 Luis Valley, yes; there are three 250-megawatt solar

8 thermal with storage projects.

9 Q And in fact, the only solar resources

10 beyond the ones contained in the 2007 Resource Plan

11 that have been identified by Public Service through

12 2020 that would potentially be located in the San Luis

13 Valley are those three 250-megawatt facilities,

14 correct?

15 A As I'm sitting here, I don't think so

16 because I think that there's the potential for retail

17 DG in the San Luis Valley, but we didn't specifically

18 identify some segment of the DG that would be in the

19 San Luis Valley.

20 Q Okay. But as far as central solar

21 resources that could be potentially located in the San

22 Luis Valley through 2020, the only resources that have

23 been identified beyond the 2007 plan by Public Service

24 are these three 250-megawatt solar thermal facilities

25 that we've discussed, correct?


104
1 A Yes.

2 Q And you agree that the uncertainty that

3 you testified about previously in February in this case

4 as to how much RESA money will be available for the

5 acquisition of those three 250 solar thermal

6 placeholders that are discussed in the 2010 Compliance

7 Plan that that uncertainty still exists today, correct?

8 A Yes.

9 Q And you agree that this uncertainty

10 relates at least in part to the fact that the

11 assumptions that Public Service used in modeling what

12 resources could be acquired under the 2 percent cap in

13 this 2010 Compliance Plan, when those assumptions are

14 reevaluated, that could have a significant effect on

15 the amount of RESA dollars available for those

16 250-megawatt resources, correct?

17 A It could have an impact, yes.

18 Q And we know now, as we sit here today,

19 based on Public Service's filing of the application to

20 amend the 2007 Resource Plan that in fact a number of

21 modeling assumptions that were used in this 2010

22 Compliance Plan have changed significantly, correct?

23 A I guess I wouldn't look at it like that.

24 What we said in our amendment is that we have undated

25 some of the assumptions for the purpose of the


105
1 amendment to the Resource Plan and that there was some

2 change in some of the assumptions. We haven't gone

3 back to look at the 2010 Compliance Plan and whether

4 any of those assumptions changed. They are sort of

5 locked in.

6 Q Can you take a look at your deposition,

7 please. Do you still have that in front of you?

8 A Yes.

9 Q And if you look at small page 96 --

10 A Okay.

11 Q -- starting at line 7, I asked you this

12 question: And we know now, based on Public Service's

13 filing of the amendment to the 2007 Resource Plan, that

14 in fact a number of the modeling assumptions that were

15 used in the 2007 Resource Plan which carried over into

16 the 2010 Compliance Plan have as of today changed

17 significantly, correct? And your answer was, Yes. Is

18 that accurate?

19 A Yes, that they have changed as far as the

20 Resource Plan. We don't have them approved yet by the

21 Commission that they agree that they changed, but we've

22 proposed that they be changed.

23 Q But the testimony I just read is

24 accurate?

25 A Yes.
106
1 Q One assumption in the 2010 Compliance

2 Plan upon which the modeling was based was the

3 assumption as to the cost of carbon, correct?

4 A Carbon dioxide, yes.

5 MR. McGANN: Your Honor --

6 MR. DOUGLAS: And that --

7 MR. McGANN: -- I object to any further

8 questions concerning changed assumptions with respect

9 to the 2010 Resource Plan or what may happen in the

10 amended Resource Plan. Again, I think now we're

11 getting into the reasons behind the motivations behind

12 the requests for the amendment as well as what the

13 Commission might do with these changed assumptions.

14 There is nothing we can do in this docket except

15 present to you what we have presented to the

16 Commission. Only the Commission can decide what to do

17 with these various assumptions and we should not spend

18 the rest of the afternoon trying to explore what the

19 Commission might do with those assumptions. So I

20 object to any further questions along this line.

21 A.L.J. JENNINGS-FADER: Just so I'm clear

22 here, your concern is that we are getting into

23 questions about what the Commission might do in Docket

24 No. 010 -- excuse me, 10A-377E.

25 MR. McGANN: That's correct.


107
1 A.L.J. JENNINGS-FADER: Okay.

2 MR. McGANN: I believe that would be the

3 only purpose behind exploring these assumptions --

4 these economic assumptions and why they have changed.

5 That would be the only purpose in exploring this in

6 this particular proceeding.

7 A.L.J. JENNINGS-FADER: Thank you.

8 Mr. Douglas?

9 MR. DOUGLAS: Your Honor, I don't believe

10 the question went in any way to the motivation for the

11 amendment, why the carbon assumption changed. What I

12 asked and what I think is relevant specifically to Your

13 Honor's order is that Ms. Hyde gave testimony back in

14 February and reiterated it this morning that she

15 believes they will have money within the 2 percent cap

16 to carry out their plan. She says the plan is the 2010

17 compliance model; and, in fact -- or plan; and, in

18 fact, this modeling with these assumptions that were

19 made is her basis for saying they can fit it within the

20 2 percent cap.

21 The amendment provided information which

22 she has confirmed in her deposition and will confirm

23 shows that some of those assumptions would be different

24 if you were doing it today and that will potentially

25 affect the available RESA dollars for those same future


108
1 solar thermal resources that she has already testified

2 they will have the money for.

3 So I believe we're not getting into the

4 motivation of the amendment at all, we're getting into

5 what the amendment tells us that affects the likelihood

6 that these future resources will actually be able to be

7 acquired.

8 MR. McGANN: Your Honor, the limited

9 scope of this hearing is if the Commission sets the

10 lower end of the solar acquisition at 60, 90, or 185,

11 what effect does that have on the transmission line?

12 That's it. And what Mr. Douglas is getting into now is

13 again the motivations or the reasons behind why that

14 amendment was sought and what the Commission may do

15 with those assumptions, either in -- not only in this

16 amended Resource Plan but in a future Resource Plan.

17 And I believe that's beyond the scope of this reopened

18 hearing.

19 A.L.J. JENNINGS-FADER: Well, this is a

20 point of intersection which is uncomfortable but goes

21 like this. I will overrule the objection because in

22 the question in the deposition which Ms. Hyde just

23 affirmed as direct testimony, the question included

24 changes in the -- quote, A number of modeling

25 assumptions that were used in the 2007 Resource Plan,


109
1 which carried over into the 2010 Compliance Plan, has

2 as of today changed significantly, correct, unquote;

3 she said, Yes. She also affirmed that testimony just a

4 moment ago on the stand.

5 As I understand the question, it is not

6 directed to anything underlying the proposed amendment

7 to the 2007 Colorado Resource Plan; rather the question

8 explores whether changes which were -- which may have

9 surfaced as a result of the amendment to the 2007

10 Colorado Resource Plan, whether those changes

11 warrant -- excuse me, whether those changes change in

12 any way -- or presumably a significant way what Ms.

13 Hyde has already testified to that the 2007 -- the 2010

14 Compliance Plan remains the best available information

15 to Public Service with respect to its future resource

16 acquisitions. I think it is appropriate to examine

17 whether changed circumstances change her view with

18 respect to that point. I understand that's where the

19 question is going.

20 Proceed, Mr. Douglas.

21 MR. DOUGLAS: Thank you, Your Honor.

22 BY MR. DOUGLAS:

23 Q I can't remember which question I left

24 off at, but I was only about one question in so I'm

25 just going to start from the top if that's all right.


110
1 Ms. Hyde, one assumption in the 2010

2 Compliance Plan modeling was the assumption of -- well,

3 the assumption relating to the cost of carbon, right --

4 I think I did ask that one.

5 A Right, carbon dioxide.

6 A.L.J. JENNINGS-FADER: That's where you

7 were.

8 MR. DOUGLAS: All right, great.

9 BY MR. DOUGLAS:

10 Q The assumption in the base case of the

11 2010 Compliance Plan was that carbon legislation would

12 be passed and there would be an additional cost for

13 carbon starting in 2010, correct?

14 A Well, I think we had a carbon proxy cost

15 that started in 2010. And the Commission approved

16 that. I'm not sure that it was necessarily tied to an

17 assumption that legislation would pass in 2010.

18 Q Let's put that aside. The carbon cost

19 that was part of the assumptions in the 2010 Compliance

20 Plan was forecast in that modeling to start in 2010,

21 right?

22 A Yes.

23 Q And Public Service's assumption today,

24 based on the information contained in the application

25 to amend and the amendment -- proposed amendment to the


111
1 2007 Resource Plan is if that carbon cost start date

2 would be more accurate for modeling purposes to be a

3 2014 start date, correct?

4 MR. McGANN: If I may object, Your Honor,

5 and it's really to try to shorten things, if I may:

6 The reason I'm having an issue with this line of

7 questioning is that Mr. Douglas has now moved into the

8 amendment to the Resource Plan and he's now said, you

9 have presented certain numbers to the Commission in the

10 amended Resource Plan; does that change the result?

11 And I guess my only point now is that only the

12 Commission can decide whether it does.

13 A.L.J. JENNINGS-FADER: I --

14 Mr. McGann --

15 MR. McGANN: We can speculate --

16 A.L.J. JENNINGS-FADER: Mr. McGann, I

17 will allow you to finish your statement.

18 What I understand this questioning to be

19 doing is to say --

20 MR. McGANN: And I will object to the

21 form --

22 A.L.J. JENNINGS-FADER: I will sustain an

23 objection to the form of the question that was just

24 asked because that question in fact went to what is

25 going on in another proceeding.


112
1 But the assumption change may be asked as

2 a hypothetical or some other -- I don't know how, but

3 you may ask about an assumption; and if that assumption

4 proved to be true, would that change your opinion, Ms.

5 Hyde, with respect to the 2010 Compliance Plan being,

6 you know, continuing to be -- what's the word --

7 continuing to be an appropriate plan on which the

8 Commission ought to rely on; something along those

9 lines?

10 I understand your concern. The question,

11 Mr. Douglas asked went in fact precisely to that issue,

12 but he started to talk about what was going on in that

13 other proceeding.

14 What I want in this case is if anybody

15 wants to pursue this -- is assume a pre -- an

16 assumption is changed, what impact if any does that

17 have on the document on which Ms. Hyde has testified

18 she relies and she thinks continues to be a valid and

19 reliable document?

20 MR. McGANN: I understand your ruling,

21 Your Honor.

22 A.L.J. JENNINGS-FADER: Does that help

23 your -- you may certainly complete your thought, but I

24 just want to try to articulate -- Ms. Mandell, I do see

25 you in the back. So continue because I didn't mean to


113
1 interrupt you making your record and I apologize.

2 MR. McGANN: No, I appreciate your

3 explanation, Your Honor. I think it's -- it really --

4 just to summarize, it seems to me the only issue again

5 that's relevant in this reopened proceeding is where

6 does the Commission end up in terms of the lower of the

7 solar acquisitions; how they get there or what findings

8 they may make are not relevant. What Your Honor

9 suggested is as long as Mr. Douglas doesn't mention the

10 amended Resource Plan but talks about simply

11 generically the assumptions that went into the

12 amendment to the Resource Plan, he's allowed to bring

13 those into this proceeding.

14 At least that was the way I understand

15 your --

16 A.L.J. JENNINGS-FADER: As they pertain

17 to Ms. Hyde's testimony that the 2010 Public Service

18 Company Compliance Plan continues to be something on --

19 and particularly the three 250-megawatt placeholder

20 solar thermal facilities presumably to be located in

21 the San Luis Valley, I think that summarizes her prior

22 testimony on those three units -- as it pertains to

23 that, right. Yes, I do think that one may inquire into

24 that.

25 MR. McGANN: Thank you, Your Honor.


114
1 A.L.J. JENNINGS-FADER: Ms. Mandell --

2 and could you come forward again, sorry.

3 MS. MANDELL: Yes. I don't remember the

4 exact question now, but as to my recollection of the

5 question, I object to the form of the question for two

6 reasons: One is, as the question was phrased, it

7 didn't -- it sort of didn't accurately reflect that the

8 Commission is maybe considering that particular

9 assumption in another docket that's active and ongoing

10 right now; and then the second objection to the form of

11 the question is that the question also inferred that

12 the Commission can go back into the 2010 docket and

13 change the carbon assumption, which there is some

14 complexity to the way the RES -- the RESA is calculated

15 as to the lockdown of resources. So there is some

16 complexity there as to the changing of assumptions in

17 the 2010 plan that the question glossed over to the

18 point that it's not quite accurate.

19 So, thank you.

20 A.L.J. JENNINGS-FADER: Any other

21 objections as to this question -- pending question, if

22 anyone can remember the pending question?

23 Mr. -- of course we all can, that's a

24 joke.

25 Mr. Douglas?
115
1 MR. DOUGLAS: Thank you, Your Honor.

2 BY MR. DOUGLAS:

3 Q Ms. Hyde, I want --

4 A.L.J. JENNINGS-FADER: No, I need a

5 response to the objection -- now two pending

6 objections.

7 MR. DOUGLAS: Well, Your Honor, at this

8 point we're pretty far removed from that question. I

9 understand your position. I don't intend to get into

10 what the Commission might do in any other docket. I

11 intend to ask Ms. Hyde about the modeling that she said

12 supports her opinion that they will be able to

13 acquire -- to have RESA dollars to acquire these solar

14 thermal placeholders; how those have changed to be --

15 well, she has opinions about what's more accurate

16 today, and her opinions and Public Service's position

17 on inaccuracies or changes that would make that

18 modeling more accurate or relevant to the likelihood of

19 the acquisition of those resources; and what the

20 Commission will ultimately do is not part of the

21 question and not an area I intend to go into.

22 A.L.J. JENNINGS-FADER: I will sustain

23 the objection as to form and we can reask the question.

24 MR. DOUGLAS: All right.

25 BY MR. DOUGLAS:
116
1 Q Ms. Hyde, your position is that it would

2 be more accurate today to project the costs of the

3 resources and the RESA -- available RESA dollars using

4 a 2014 carbon assumption -- carbon start date as

5 opposed to the 2010 assumptions that were actually used

6 in the 2010 RES Compliance Plan modeling; is that

7 correct?

8 A No. We proposed that we would -- we

9 thought that that was probably a more realistic number

10 to use, but what we use from the RES Compliance Plan I

11 think is still up for grabs all over the place because

12 before we file the next plan, we won't have had --

13 likely not have any ruling in 377E; and we also will

14 still have the same 447E numbers. So I don't know that

15 it's correct to say that our position is that it's most

16 accurate to use that or best to use that in the 2011 --

17 in the next compliance plan.

18 Q Well, could I ask you to turn to your

19 deposition at page 99, please; starting on line 12, the

20 question I asked was, Right now I'm not asking you

21 about direction from the Commission, I'm asking what

22 your and Public Service's position is. Your position

23 is that it would be more accurate today to project

24 these costs out and the RESA dollars and how it all

25 works using a 2014 carbon assumption than the 2010


117
1 assumption that was actually used in the modeling,

2 right? And your answer was, Yes. Do you see that?

3 A Yes.

4 Q And we were talking then about the

5 modeling in the 2010 Compliance Plan.

6 A I'm not sure. We talked about it for

7 quite some time. I think there are several pages on

8 what it was we were talking about.

9 Q Well, do you believe --

10 A It starts somewhere around page 96.

11 Q But the question and answer I just read,

12 page 99, lines 12 through 19; is that accurate?

13 A Only when considered with the discussion

14 in the pages before it.

15 Q Well, let's look at the page before, page

16 98, starting at line 24; the question is, If you were

17 to take that modeling that was done in -- whenever it

18 was done for that 2010 plan, which used the 2010 carbon

19 assumption, and do that again today, it's your position

20 that it would be more accurate to use the 2014 start

21 for the carbon cost.

22 "ANSWER: It's our position that we think

23 that that's a more accurate representation, that that's

24 more accurate." And then you go on to say that you

25 don't know what the Commission is going to do with


118
1 that; correct?

2 A Right, because ultimately it's the

3 Commission's decision what number we use.

4 Q Right. But it's your position that the

5 2014 start date would be more accurate?

6 A It's our position -- yes, that that's a

7 better number right now; but, you know, the

8 Commission's entitled to use carbon in their

9 considerations and they can pick the number.

10 Q You also agreed that the recalculation of

11 the incremental cost of the renewable resources in the

12 2010 Compliance Plan can be dramatically affected as

13 far as the RESA funds available for the acquisition of

14 renewable resources based on the carbon cost, correct?

15 A Well, I don't think we recalculated 2010

16 Compliance Plan.

17 Q I don't know that that was my question.

18 You agree -- let me phrase it differently. You agree

19 that the recalculation of the incremental cost of

20 renewable resources -- strike that. Let me try again.

21 You agree that the recalculation of the

22 incremental increases, based on a change in the carbon

23 assumption, can dramatically affect the funds available

24 through the RESA for the acquisition of additional

25 renewable resources in later periods, right?


119
1 A I don't think that you recalculate 2010;

2 but obviously the carbon proxy costs has an impact on

3 how much goes through the RESA and how much goes

4 through the ECA.

5 Q And in fact, that can have a dramatic

6 effect, right?

7 A It can have a significant effect, yes.

8 Q Well, maybe -- in fact, in the 2010

9 Compliance Plan, Public Service modeled an alternative

10 case, a sensitivity analysis, that used this changed

11 assumption of a carbon cost start date from 2010 to

12 2014, correct?

13 A Yes.

14 MR. DOUGLAS: Your Honor, I believe

15 that's going to take us to the tables; and I now have,

16 timely -- I now have copies of Exhibit 141, if I may

17 approach.

18 A.L.J. JENNINGS-FADER: You may. Thank

19 you.)

20 (Discussion off the record.)

21 A.L.J. JENNINGS-FADER: Mr. Reporter and

22 the parties, on what has been offered -- or marked for

23 identification as Exhibit 141 in this proceeding is a

24 previously stamped "Exhibit 65, Docket No. 09A-772E,

25 March 19, 2010." Please strike through that exhibit


120
1 identification so that for purposes of our record all

2 will know that this is Exhibit 141 for identification

3 in the instant proceeding.

4 Does that help, Mr. Reporter?

5 (Whereupon, Exhibit No. 141 marked for

6 identification.)

7 A.L.J. JENNINGS-FADER: Mr. Douglas.

8 MR. DOUGLAS: Thank you, Your Honor.

9 BY MR. DOUGLAS:

10 Q Ms. Hyde, do you have Exhibit 141 in

11 front of you?

12 A I do.

13 Q And is that a copy of the revised tables

14 that supplement the 2010 Public Service RES Compliance

15 Plan tables that are Exhibit 140?

16 A Yes.

17 Q Okay.

18 MR. DOUGLAS: I would offer 141 into

19 evidence.

20 A.L.J. JENNINGS-FADER: Mr. -- before --

21 Ms. Hyde, what is your understanding, are the tables

22 that are shown in Exhibit 141 for identification, to

23 your understanding, to be substituted for the similarly

24 numbered tables that appear in Exhibit 140?

25 THE WITNESS: That's my understanding.


121
1 A.L.J. JENNINGS-FADER: Okay, thank you.

2 With that understanding, Exhibit 141 for identification

3 is offered.

4 Voir dire objection.

5 MR. SOPKIN: No objection.

6 A.L.J. JENNINGS-FADER: Exhibit 141 is

7 admitted.

8 MR. DOUGLAS: Thank you, Your Honor.

9 BY MR. DOUGLAS:

10 Q Ms. Hyde, if you will turn to the second

11 and third pages of Exhibit 141, I just want to get us

12 oriented on this. Is it correct that Table 7.3 models

13 what maybe we could call the base case for the 2010 RES

14 Compliance Plan and the available RESA dollars; and

15 Table 7-4 is this sensitivity analysis that changed the

16 modeling to reflect a carbon cost start date of 2014?

17 A Yes, it also changed the RESA -- the

18 calculation of the RESA.

19 Q The RESA revenue?

20 A Yes.

21 Q And we'll get into that; but just for

22 starters, Table 7.3 was what Public Service forecasted

23 would happen as far as the acquisition of the resources

24 listed in that plan and their effect on RESA dollars

25 and then the rolling balance of the RESA account going


122
1 forward through 2020, right?

2 A Yes.

3 Q And then Table 7-4 changed two things

4 from that forecast: One was it changed the carbon

5 start date; and the second thing was it increased the

6 collection of are RESA dollars from ratepayers to be a

7 full 2 percent through 2020; is that correct?

8 A Yes.

9 Q And in the base case, what you forecasted

10 when you filed this in Table 7-3, Public Service was

11 predicting that it would be able to reduce the 2

12 percent rider on ratepayers to 1 percent, starting in

13 2013; and to zero starting in 2016; is that correct?

14 A I don't know that we actually forecasted

15 that we could reduce the RESA, but our assumption was

16 that we didn't need the full 2 percent to fund the plan

17 that we had proposed.

18 Q Right. You were going to be back in the

19 positive in this RESA account as of 2012 under your

20 base case even though you reduced -- you modeled the

21 reduction of the rider to 1 percent in 2013 and -- or

22 starting in 2016, right?

23 A Yes.

24 Q Now, if you take a look at the difference

25 in 7-2, 7-3 and 7-4 on the rolling balance, do you see


123
1 that?

2 A Yes.

3 Q And we talked about this hypothetical

4 bucket of RESA dollars that from an accounting

5 standpoint Public Service maintains and draws against

6 when it purchases renewable resources and adds to from

7 these collections -- the 2 percent collection from

8 ratepayers, right?

9 A Yes.

10 Q And Column X is a rolling balance,

11 looking out until 2020, of where that hypothetical

12 account, that RESA account stands under your modeling,

13 right?

14 A A hypothetical, yes.

15 Q And so by changing the carbon

16 assumption -- the carbon cost start date from 2020

17 until -- on 7-3 to Table 14 on Table 7-4, that rolling

18 RESA balance, Column X, went from -- if you look at

19 2012, just in that year, it went from a forecasted

20 positive $27 million balance to a forecasted negative

21 $71 million balance, correct?

22 A Yes.

23 Q So that's a difference of essentially a

24 negative $98 million from this change in the carbon

25 assumption, just for that one single year, correct?


124
1 A Yes. In this hypothetical -- in this

2 kind of simple analysis, yes.

3 Q Well, the hypothetical is your prediction

4 of where these costs are going to come out changed to

5 reflect what you now believe is a more accurate

6 assumption, correct?

7 A I think that this was an exercise done,

8 kind of in the early years of this, saying why does

9 that assumption change those numbers? I don't know

10 that it really reflects where we are in 2010, you know,

11 as we're making our way through the year.

12 Q All right. But the purpose of Table 7-4

13 was to look at the impact of this changed carbon

14 assumption, correct?

15 A Yes, using this -- like I said, this

16 simple analysis.

17 Q Okay. You can call it simple if you

18 want, but the purpose of it was to look at what the

19 effect is, right, of the changed carbon assumption?

20 A Yes.

21 Q Okay. And that effect was $98 million

22 just for a -- a negative $98 million just for 2012,

23 right?

24 A Yes.

25 Q And that's a pretty big impact, right?


125
1 A Yes.

2 Q Although it's your position, that even

3 though that's big on the negative balance, it's small

4 on a bill, right?

5 A Yes.

6 Q Small on a customer's bill, we mean.

7 A Relatively, yes.

8 Q All right. Let's look at 2013. Now we

9 go on the base case, Table 7-3, from a positive 54

10 million predicted for 2013, to a negative 86 -- well,

11 really 87 million with that changed carbon assumption,

12 correct?

13 MR. McGANN: I object to the form of the

14 question. I believe in 2013 it also reduces the RESA

15 charge, if you take a look at the top right of 7-3; so

16 I think the hypothetical has to include both

17 assumptions.

18 MR. DOUGLAS: Well, he can flesh that

19 out. I think that actually exacerbates the negative

20 impact; but for starters, between -- let's start over.

21 Q 7-3 for 2013 predicted a positive $54

22 million balance in the RESA account, right?

23 A Yes.

24 Q And then in Table 7-4, you changed the

25 carbon assumption to 2014, and actually increased the


126
1 revenue you collected from ratepayers for 2013 and

2 still ended up with a negative $87 million balance,

3 correct?

4 MR. McGANN: I object to the form of the

5 question, Your Honor. That's not what these tables

6 show.

7 BY MR. DOUGLAS:

8 Q Is that accurate?

9 A.L.J. JENNINGS-FADER: I --

10 MR. DOUGLAS: I apologize, Your Honor.

11 A.L.J. JENNINGS-FADER: I was waiting for

12 the objection.

13 There is an objection -- well, you got

14 the objection. Is there a response to the objection?

15 MR. DOUGLAS: Your Honor, I thought I

16 stated it correctly. I believe the witness can correct

17 me if I -- if that's not accurate. My question is, is

18 that accurate? And she's free to answer yes or no.

19 A.L.J. JENNINGS-FADER: I'll overrule the

20 objection. You may answer whether the question -- you

21 can answer the question, Is it accurate -- is that

22 statement accurate?

23 THE WITNESS: Could you read it again for

24 me.

25 BY MR. DOUGLAS:
127
1 Q Sure. Table 7-3, the base case in the

2 2010 Compliance Plan model forecasted a $54 million

3 surplus in the RESA account as of 2013. And then in

4 7-4, the changed carbon assumption to 2014, coupled

5 with higher revenue collected from ratepayers in the

6 7-4 assumptions still resulted in a negative balance of

7 $87 million; correct?

8 A It's correct that in this projection

9 that's what the numbers are.

10 Q And that's about $140 million difference,

11 according to my calculations; is that accurate?

12 A The total from positive to negative,

13 those two numbers add up to somewhere around there.

14 But I don't think that it's accurate to say that that's

15 really where we expect the RESA balance to be.

16 Q Well, that's where you forecasted the

17 RESA balance to be under the assumptions you used for

18 the 2010 Compliance Plan modeling with the change in

19 the carbon assumption and the revenue that we talked

20 about; right?

21 A It was a simple assumption change, as you

22 said, but it also changes the balances in '10 for

23 example that we don't expect to change with that

24 assumption change. It won't affect the balances in

25 '10.
128
1 A.L.J. JENNINGS-FADER: When you say ten,

2 you mean 2010.

3 THE WITNESS: Column 2010.

4 A.L.J. JENNINGS-FADER: Thank you.

5 BY MR. DOUGLAS:

6 Q Right. 2010, we're starting out with a

7 $26 million negative balance, right?

8 A It looks like 29 --

9 Q Twenty-nine?

10 A -- to me.

11 Q Okay. So the changes in carbon

12 assumption doesn't affect the balance for 2010. That's

13 what you are saying, right?

14 A Right. But it does on 7-4. It doesn't

15 really change it though.

16 Q It's a negative $12 million for 2010,

17 right?

18 A Right. But the change in assumptions

19 won't really impact the 2010 balance.

20 Q You change -- you added a cost for carbon

21 as of 2010 when you modeled what the balance would be

22 in 2010. And now there is no cost for carbon; is that

23 accurate?

24 A No. As far as recovery goes, there is

25 still a cost of carbon, as far as how much dollars go


129
1 through the ECA and how much through the RESA.

2 Q Oh, because the Commission approved your

3 use of the 2010 assumption.

4 A Yes.

5 Q Okay, now I understand where you are

6 coming from. And I'm trying to get at questions that

7 don't assume or look into what the Commission might or

8 might not do. All I'm trying to get at here is when

9 you look at these forecasts that you did that looked at

10 the impact of this changed assumption in -- on future

11 available RESA dollars, according to your own modeling

12 we're looking at changes of -- well, really $141

13 million, just looking at 2013, right?

14 A Well, they build on each other. So the

15 change in 2010 in this scenario becomes part of that

16 negative in the future. But really 2010 doesn't

17 change.

18 Q All right, let's take the 12 million out

19 for 2010. We're still talking a $129 million dollar

20 change, right?

21 A Right, but the same thing happens to '11,

22 '12. I don't know where those will end up.

23 Q And when you look at 2011 to 2014

24 together that's about $129 million regular negative

25 impact on the RESA dollars, right?


130
1 A I don't know which numbers you are adding

2 now; but you are good at math, so --

3 Q Well, in any event we're talking about

4 over a hundred million dollars of impact according to

5 your own forecast on the future available RESA dollars

6 just from that one change to the carbon legislation,

7 correct?

8 A I would characterize these as scenarios,

9 not really a forecast, but we'll go in for additional

10 plans in between; but this sensitivity shows that sort

11 of level of difference between the two.

12 Q Now another assumption that Public

13 Service used in its modeling of the 2010 Compliance

14 Plan and available future RESA dollars is the cost of

15 natural gas, correct?

16 A Yes.

17 Q And you believe that a more accurate

18 forecast today versus what was used in the 2010

19 Compliance Plan would be about a 14 percent reduction

20 in those prices, correct?

21 A Well, I believe that both forecasts are

22 wrong and I don't know where the price of gas will go.

23 But according to the way the Commission has us estimate

24 natural gas prices, the estimate in the CRP amendment

25 is more updated than the other one.


131
1 Q All right. And you agree that when --

2 that if all the other modeling assumptions are kept the

3 same, when you lower the average price or the price

4 forecasted for natural gas, it raises the incremental

5 cost of the renewable resources, correct?

6 A Yes.

7 Q And if we wanted to accurately model,

8 today, the amount of RESA funds that would be available

9 for future renewable resource acquisition, that

10 modeling would need to use, in your opinion, revised

11 carbon assumptions, starting in 2015 and the revised

12 natural gas price forecast, correct?

13 A To redo the 2010?

14 Q Well, if you wanted to accurately model

15 that today, that's what you would need to do, right?

16 A I don't know about, "accurate." I just

17 said the forecasts were all wrong. Anyway, I don't

18 know where the price will go. But, I guess I would

19 answer, when we do the 2011 plan, we'll use different

20 assumptions, and we will go back and redo the '10 plan.

21 Q Okay. Let's take a look at your

22 deposition, turning to page 116, starting at line 16.

23 Are you there?

24 A Yes.

25 Q The question is -- there's a little


132
1 preamble, but Your Honor might appreciate it. "Right

2 now, we don't know what the Commission is going to do.

3 I am just trying to get what your position is. That

4 position could be contrary to the Commission rules, and

5 that's another uncertainty, I think. What I am just, I

6 guess, just trying to get, what your position would be.

7 That, if we wanted to accurately model, today, the

8 amount of RESA funds that would be available for future

9 resource acquisitions, we would take the 2010 modeling

10 you did, and we would need to use the revised carbon

11 forecast in the 2007 amendment, right?" "Answer: "In

12 part, yes." And the question: And a revised natural

13 gas assumption, right?" The answer is, "In part, yes."

14 Does that accurately set out the

15 testimony you gave in your deposition?

16 A Yes.

17 Q And using a revised lower natural gas

18 forecast would further move the RESA balance we just

19 looked at, in Table 7-4, into the negative, correct?

20 A In isolation, if you move those, yes.

21 Q And Public Service has not done any

22 modeling, as opposed to the carbon assumption we just

23 looked at, but not done any modeling of the impact of a

24 lower natural gas forecast on how that might affect the

25 predictions in the 2010 RES Compliance Plan; is that


133
1 correct?

2 A That's correct.

3 Q And it's your position, today, that both

4 the gas price forecasts and the carbon cost forecasts

5 have gone down, right?

6 A Yes. Our estimate of those numbers have

7 gone down, yes.

8 Q Okay. All right. Let's talk just a

9 little bit about demand and energy forecasts. You

10 agree that, for the last several years, the demand

11 forecasts by Public Service have been revised to

12 reflect reduced growth, correct?

13 A I think, for the last two years,

14 actually, year and a half.

15 Q Since March 2009?

16 A Yes.

17 Q And the growth rate and the energy

18 forecasts that were used in the modeling for the 2010

19 RES Compliance Plan have also gone down since that

20 modeling was done, correct?

21 A Estimates from the 2010 plan?

22 Q What you used for that model, the 2010

23 plan, to predict RESA dollars and collect the energy

24 forecasts, have gone down since that time, right?

25 A Our energy forecast has gone down.


134
1 Q Correct?

2 A Yes.

3 Q And that reduced energy forecast will

4 have an effect of reducing the available RESA dollars

5 in the future, all else being equal, correct?

6 A Well, it will reduce the RESA dollars and

7 it will also reduce the RES obligation. It will reduce

8 both.

9 Q That's true. Okay. Public Service

10 recently introduced a two-tier pricing structure; is

11 that correct?

12 A Recently, no. But it's in effect, yes.

13 Q Okay.

14 A We announced it -- well, we proposed it

15 in early 2009.

16 Q But it's now in effect?

17 A Yes.

18 Q And you expect that energy demand will go

19 down because of that new pricing structure?

20 A Slightly. And, ultimately, we think it

21 will go down a little bit.

22 Q Okay. I think you testified you're not

23 sure what period of time, but you estimated it would go

24 down by 75 gigawatt-hours?

25 A Right.
135
1 Q Do you recall -- do you agree that the

2 resource needs of Public Service are determined, among

3 other factors, by the growth in demand for electricity?

4 A Yes.

5 Q And do you agree that, if that growth is

6 stagnant, it would not be prudent for Public Service to

7 add resources earlier than necessary?

8 A No.

9 MR. DOUGLAS: Your Honor, if I may

10 approach, I don't believe it's necessary to admit this

11 into evidence. I simply want to show it to the

12 witness, if that's okay.

13 A.L.J. JENNINGS-FADER: You certainly

14 may.

15 BY MR. DOUGLAS:

16 Q Ms. Hyde, I have handed you a document.

17 Can you identify that as a copy of Decision No.

18 C09-0323, in the 07A-447E docket?

19 A Yes.

20 Q Is that something you have seen before?

21 A Not in a while but I'm sure I did.

22 Q Okay. If you turn to page 15 -- and I am

23 looking at paragraph 47. If you look at the second to

24 the last sentence, just for context, "The resource

25 needs of Public Service are determined, among other


136
1 factors, by the growth in demand for electricity." And

2 you agreed with that, right?

3 A Yes.

4 Q All right. Then, the next sentence, "If

5 that growth is stagnant, it would not be prudent for

6 Public Service to add resources earlier than

7 necessary." Do you see that?

8 A Yes.

9 Q Okay. But you disagree with the

10 Commission on that?

11 A Well, I think you're taking that sentence

12 out of context from an entire two-year docket. And I

13 believe what they were saying is that it doesn't make

14 sense for us to acquire resources to fill the

15 500-megawatt drop that we had in our load and resources

16 between the start of the docket and approximately this

17 time. But if you go to their end order, at the end,

18 they did order us to acquire some resources ahead of

19 time, in excess of our need. So, I think you have to

20 take it into context with the whole term -- the whole

21 context of that docket.

22 Q All right.

23 MR. DOUGLAS: One minute of indulgence,

24 Your Honor?

25 A.L.J. JENNINGS-FADER: You may, but only


137
1 a minute.

2 (Discussion off the record.)

3 BY MR. DOUGLAS:

4 Q Ms. Hyde, do you have Exhibit 136 in

5 front of you, or can you get that in front of you?

6 A Yes, I have it.

7 Q Okay. And is that a document you've seen

8 before?

9 A Actually, no, but I knew it was going to

10 be a document.

11 Q Okay.

12 A.L.J. JENNINGS-FADER: How prescient of

13 you.

14 THE WITNESS: Yes. Actually, I saw it

15 like an hour ago, when you showed it to me the first

16 time.

17 BY MR. DOUGLAS:

18 Q Okay. And this is, in fact, the notice

19 of filing of correction to the Direct Testimony of

20 Mr. James Hill?

21 A Yes.

22 Q And I want to talk about that just a

23 little bit. This is something that we received Friday

24 afternoon, and it included some revised figures, I

25 believe, from the proposed amendment to the 2007


138
1 Resource Plan.

2 A.L.J. JENNINGS-FADER: I'm sorry. Could

3 we stop for a moment. You're looking at Exhibit 136

4 for identification?

5 MR. DOUGLAS: Yes.

6 A.L.J. JENNINGS-FADER: The one that you

7 didn't offer?

8 MR. DOUGLAS: Yes.

9 A.L.J. JENNINGS-FADER: Okay. Just

10 checking.

11 MR. DOUGLAS: Your Honor, and I thought

12 your preface was for me to discuss it with the witness

13 instead of offering it.

14 A.L.J. JENNINGS-FADER: That's fine.

15 MR. DOUGLAS: I am happy to offer it.

16 A.L.J. JENNINGS-FADER: I just wanted to

17 be sure that's the one we're talking about.

18 MR. DOUGLAS: Right.

19 A.L.J. JENNINGS-FADER: And it is.

20 MR. DOUGLAS: I thought so.

21 A.L.J. JENNINGS-FADER: Yes.

22 MR. DOUGLAS: All right.

23 BY MR. DOUGLAS:

24 Q I am not sure if I got an answer to that

25 question.
139
1 A What was the question?

2 Q I don't know, but let's try it again.

3 A Okay.

4 Q This document, this correction to the

5 Direct Testimony of Mr. Hill, includes some revised

6 figures for the proposed amendment to the 2007 Resource

7 Plan?

8 A Yes.

9 Q And those figures relate to the analysis

10 by Public Service as to whether Public Service can meet

11 its demands or forecasted demands with the lower levels

12 of solar that are now being proposed for the San Luis

13 Valley in that amendment, correct?

14 A I think, actually, it's an analysis of

15 whether we need to invoke a contingency plan under the

16 resource planning rules.

17 Q Well, let's take a look. According to

18 the contingency plan --

19 A.L.J. JENNINGS-FADER: According to

20 Figure 4, in Exhibit 136?

21 BY MR. DOUGLAS:

22 Q According to Figure 4 in Exhibit 136, if

23 the Commission approved the 185-megawatt option, in

24 Public Service's application, to amend its 2007

25 Resource Plan, that would lead to a predicted 85


140
1 megawatts of surplus generation resources, as of 2015,

2 on the Public Service system; is that correct?

3 MR. McGANN: Object, Your Honor, to form.

4 I think, consistent with your prior explanation of the

5 scope of this proceeding, this is going beyond it. You

6 will he actually asking her specific questions about

7 the amendment to the Resource Plan, and attempting to

8 bring this into this particular docket. This is not a

9 hypothetical. This is not anything along the lines of

10 what has been suggested before was permissible, so, I

11 object.

12 MR. DOUGLAS: Your Honor, if I may

13 respond?

14 A.L.J. JENNINGS-FADER: Any other

15 objection? Thank you.

16 MR. DOUGLAS: I believe the scope of this

17 proceeding includes the implications of the 60-, 90-,

18 and 185-megawatt options, which have never been

19 discussed before, because they are new. And one brief

20 angle on that is, will Public Service need more

21 resources than this, or will they be able to meet their

22 demands, as they forecast them, at these reduced

23 levels, or will they need to add something more.

24 That's the road we're going down now.

25 A.L.J. JENNINGS-FADER: I am going to


141
1 sustain the objection. That will be determined by the

2 Commission in Docket No. 10A-337E, which is the docket

3 in which the Commission is considering the proposed

4 amendment to the 2007 Resource Plan.

5 The scope of this proceeding is, assuming

6 the Commission does reduce it to the proposed 185 or 90

7 or 60 megawatts, what if any impact. I think what

8 you're talking about gets us away from that, so, stay

9 focused on those proposed numbers.

10 MR. DOUGLAS: Well, I guess I would

11 wonder how -- if the -- I thought my question did

12 assume that the Commission did pick one of these

13 levels. And then, if so, do they expect that they are

14 going to need to add more resources, which could affect

15 whether those more resources could be in the San Luis

16 Valley. That's where I am going, and it would --

17 A.L.J. JENNINGS-FADER: Why don't you

18 just ask three questions: Assume 185, assume 90, and

19 assume 60, and see what falls out.

20 BY MR. DOUGLAS:

21 Q Ms. Hyde, if the Commission selects or

22 approves the 185-megawatt option proposed in Public

23 Service's application to amend the 2007 Resource Plan,

24 would Public Service, based on what you know or what's

25 been filed, require any additional resources through


142
1 2015, in order to meet its forecasted demand?

2 A No, we would not.

3 Q What about as to the 90-megawatt option

4 in the amendment to the 2007 Resource Plan?

5 A I just want to clarify one thing. In

6 answering that, I assumed that everything else worked

7 out the way, you know, the kinds of load and resources

8 that we got, we got the level of DSM that's included in

9 there, and that all of the other resources did come

10 on-line. Just for clarification,I was looking at that,

11 just that matter in isolation.

12 And, if we had just the 90? I got to

13 calculate that one. I believe, with just the 90, we

14 would be a few megawatts short, maybe around 10

15 megawatts.

16 A.L.J. JENNINGS-FADER: Again, Ms. Hyde,

17 through 2015.

18 THE WITNESS: Through 2015 only.

19 BY MR. DOUGLAS:

20 Q And I believe it's accurate that any

21 shortage of that nature could be met by a number of

22 things, including additional available generation

23 capacity at Comanche?

24 A Yeah. We indicated that we didn't need

25 to invoke the contingency plan, because we did have


143
1 some options, if we end up being short by those 10s of

2 megawatts.

3 Q And do those -- well, strike that. Let's

4 go to the 60-megawatt option. Is there a shortage

5 associated with that option, if the Commission selects

6 it?

7 A We would be about 15 -- I mean 40

8 megawatts short, in our projections, by 2015.

9 Q Okay. That's what was revised in this

10 testimony; it went from 50 to 40?

11 A Yes.

12 Q Okay. And that 40-megawatt shortage,

13 again, is something that Public Service believes it has

14 various options to meet?

15 A Right. Because we're sitting pretty far

16 away from that in time.

17 Q In fact, are you aware if those forecasts

18 that you've just talked about include the expected

19 retirement of the Arapahoe 4 plant?

20 A They would show it retiring, I believe,

21 by 2015 by -- by the end of 2015, I think.

22 Q And do you know whether or not all of the

23 scenarios that are being modeled in the Clean Air -

24 Clean Jobs docket include the Arapahoe 4 plan as not

25 being retired?
144
1 MR. McGANN: Objection. Scope.

2 MR. DOUGLAS: Your Honor, Ms. Hyde

3 identified small shortages, and we're talking about

4 some of the options, besides more generation in the

5 San Luis Valley, that could be used to meet those

6 shortages.

7 A.L.J. JENNINGS-FADER: I'll allow it.

8 THE WITNESS: Most, but not all of the

9 plans for Clean Air - Clean Jobs show Arapahoe, well,

10 retiring on coal and continuing to be available on gas,

11 but not all.

12 BY MR. DOUGLAS:

13 Q All right. So, the bottom line is Public

14 Service has various options available, aside from new

15 generation that could potentially be located in the

16 San Luis Valley, to meet these shortages that you have

17 discussed with the 60- and the 90-megawatt options?

18 A Through 2015 only.

19 Q Okay. All right. I want to get back,

20 briefly, to the changes in the assumptions from the

21 2010 Compliance Plan modeling. You agree that those

22 three assumptions that we talked about, carbon cost,

23 natural gas forecasts and energy growth forecast, have

24 all moved in the direction, since that modeling was

25 done, of making it less RESA dollars available for the


145
1 acquisition of future solar thermal resources such as

2 those 250-megawatt placeholders?

3 A In isolation those three make less RESA

4 dollars available. They also make the RESA -- the

5 obligation under the RES lower.

6 Q So, less need to add more renewables and

7 less RESA dollars available?

8 A Yes. Just for those three in isolation.

9 Q And another change in the assumptions,

10 from the 2010 Compliance Plan modeling, would be that

11 the price of the solar thermal resources, or the

12 forecasted price, has gone up, since that was

13 originally bid as part of the RFP process for the 2010

14 Colorado Resource Plan; is that correct?

15 A The one solar project that we have been

16 talking about, the price has gone up. I don't know

17 that I would translate that into the price of solar

18 thermal going up.

19 Q All right. But generally, the modeling

20 that was done in the 2010 Compliance Plan, about the

21 cost of those three placeholder resources, was based on

22 the information that Public Service had from that

23 original 250-megawatt bid, right?

24 A Yes.

25 Q Okay. And the price of that 250-megawatt


146
1 bid has gone up, right?

2 A No. Because there's no longer a

3 250-megawatt bid.

4 Q Okay. All right. The price of the solar

5 thermal bid, on a levelized cost basis, a dollar per

6 megawatt-hour, has increased from the original

7 250-megawatt bid to the now 125-megawatt bid, correct?

8 A Yes.

9 Q And that has gone up, in part, due to the

10 down-sizing of the bid from 250 megawatts to 125

11 megawatts, correct?

12 A Yes.

13 Q And I don't want you to get into the

14 highly confidential information that we discussed at

15 your deposition, because I don't see need a for it.

16 So, assume that my next question does not call for any

17 of that detail.

18 A Okay.

19 Q All right. You agree that the solar

20 thermal bid price, that original 250-megawatt bid

21 price, also increased on a levelized cost basis, when

22 it went to 125 megawatts, because of two additional

23 factors unrelated to the down-sizing of the project,

24 correct?

25 A Yes.
147
1 Q Okay. Now, the original 250-megawatt

2 solar thermal resource, in the approved 2007 Resource

3 Plan, was approved as a Section 123 resource, correct?

4 A Yes. Could I just clarify my last yes?

5 Those two reasons -- actually we did get clearance to

6 say them, and they are somewhat related to down-sizing,

7 because it changed some of the way that they financed

8 the project, the -- other changes.

9 Q Okay.

10 A So, while the two reasons are not

11 directly tied, I think they are still indirectly --

12 Q Well --

13 A -- tied a little bit.

14 Q Well, is it your position that that

15 document that we looked at, at your deposition itself,

16 is no longer highly confidential?

17 A No. The document is still highly

18 confidential, but the bidder did say that we could say

19 the three reasons.

20 Q Okay. Well, while we're on the subject

21 let's take a look at it.

22 (Discussion off the record.)

23 MR. DOUGLAS: I'm trying to remember the

24 procedures for the highly confidential documents.

25 A.L.J. JENNINGS-FADER: You may show it


148
1 to the witness, if you wish to do so. If you wish to

2 offer it as an exhibit, it will be a highly

3 confidential exhibit, in which event it will need to be

4 encased in some sort of a closed envelope. But, right

5 now, you're fine.

6 MR. DOUGLAS: The decision incorporates,

7 in part, what Ms. Hyde says.

8 BY MR. DOUGLAS:

9 Q Is it your testimony that you are

10 comfortable reading into the record the three reasons

11 that were identified by the bidder as to why the price

12 went up?

13 A Yes.

14 Q Okay. Then I will just hand you a copy

15 of this. Ms. Hyde, just to orient us, we're looking at

16 a May 10th, 2010 letter, from a bidder to -- from the

17 original bidder of the 250-megawatt solar thermal

18 facility to Xcel Energy, correct?

19 A Yes.

20 Q Okay. And what it says, in the second

21 paragraph, is that, subsequent to the bid, the

22 250-megawatt bid, the following events occurred that

23 impacted the original offer, right?

24 A Yes.

25 Q Okay. No. 1, transmission out of the


149
1 solar resource area, in the San Luis Valley, was likely

2 to remain constrained at 125 megawatts, right?

3 A Yes.

4 Q We are talking about -- that's the

5 down-sizing we talked about, that you had mentioned?

6 A Yes.

7 Q Then, No. 2: The terms and conditions of

8 the DOE Federal loan guaranty became less favorable

9 than originally assumed, right?

10 A Yes.

11 Q And, No. 3, the rate of return required

12 by tax equity investors increased, right?

13 A Yes.

14 Q Okay. All right. I can take that back.

15 A That would be great.

16 Q So, we can keep it secret.

17 A Yes.

18 Q Okay. Now, we were just moving onto the

19 issue of this original bid, for this 250-megawatt solar

20 thermal facility. The original approval was that it

21 would be considered a Section 123 resource, correct?

22 A Yes.

23 Q All right. And that means that the costs

24 of that resource would not be counted against the 2%

25 retail rate impact cap, right?


150
1 A That the portion above the non -- the

2 cost-effective piece wouldn't count against the RESA,

3 yes.

4 Q Right. The incremental cost over --

5 well, let's back up. The way RESA dollars are used to

6 purchase renewable resources is that the incremental

7 cost of the renewable resource, over natural gas

8 generation, is what changes the RESA account; is that

9 right?

10 A I don't -- I am trying to think whether

11 it's resource by resource. I think it's just the pool

12 of resources, compared to a nonrenewable portfolio,

13 forms the split between the ECA and the RES.

14 Q You are right. But the renewable

15 portfolio includes the cost of the renewables. And

16 then the no-RES that it's compared to replaces the

17 renewable resources with natural gas generation,

18 correct?

19 A Right.

20 Q Okay. And, so, your testimony is that,

21 for the Section 123 resource, that original

22 250-megawatt solar thermal plant, the incremental cost

23 of that resource would not have been charged against

24 the RESA account?

25 A Right.
151
1 Q Okay. Will you agree that the increased

2 price for the solar thermal with storage bid, coupled

3 with falling gas prices and the expectation of the

4 carbon legislation won't be enacted for several years,

5 act in concert to erode the economics of solar thermal

6 with storage, relative to combined cycle natural gas

7 generation, correct?

8 A Yes, based on those assumptions.

9 Q And Public Service, during the 447E

10 docket, Resource Plan docket proceedings, represented

11 to the Commission, and the Commission adopted the

12 characterization of Public Service, that the cost of

13 that solar thermal bid was slightly higher than the

14 combined cycle natural gas bids, right?

15 A Yes. I believe the Commissioners asked

16 Mr. Hill that question and that was his answer.

17 Q And you agree that the solar thermal bid

18 price is no longer slightly higher than natural gas,

19 right?

20 A If you adopt the change in assumption, it

21 is more expensive than it was before.

22 Q And, in fact, it's more expensive to the

23 point that Public Service is no longer asserting that

24 that solar thermal bid that's now been changed to the

25 125-megawatt bid is in a reasonable cost range in


152
1 comparison to other combined cycle gas bids, right?

2 A Correct.

3 Q And because of that, Public Service has

4 asked the Commission, in the new docket, to determine

5 whether the 125-megawatt solar thermal plant remains in

6 the public interest, right?

7 A We asked them to see if that changed

8 their Section 123 determination, which considered,

9 among other things, that comparison between the bids

10 and the combined cycle, but it had a lot of other

11 components to it.

12 Q Okay. But you're asking for a

13 determination, by the Commission, as to whether that

14 resource is in the public interest as a Section 123,

15 right?

16 A Right. We are asking if they can affirm

17 their Section 123 determination.

18 Q Okay. And Public Service has no position

19 on whether the costs of the 125-megawatt solar thermal

20 bid that's set forth in that 2007 amendment, whether

21 those costs are reasonable; is that right?

22 A Correct.

23 Q Okay. And you agree that the changed

24 circumstances, regarding the economics of that original

25 bid, that formed the basis for the Commission's


153
1 decision approving that as a Section 123 resource,

2 warrants reconsideration, right?

3 A Because the Commission based, in part,

4 their decision on Jim Hill's testimony, we felt that we

5 should bring it to their attention that he would not

6 testify in the same way, based on the changed

7 economics.

8 Q Okay. But, if there had been no issue of

9 a delay with the transmission line, you personally

10 think that Public Service would have gone forward with

11 the acquisition of the original 250-megawatt solar

12 thermal resource, despite the fact that you can no

13 longer assert that it's in a reasonable cost range?

14 A I think that if we had not had to reduce

15 the overall amounts that we took, we would have been

16 continuing in compliance with the Commission's Phase 2

17 final order, to acquire the resources that they told us

18 to acquire.

19 Q Okay. I'm not sure that answered the

20 question. The question is, do you think you would have

21 gone forward with it, with that original resource, if

22 there had been no issue with delaying the transmission

23 line?

24 A It's hard for me to extract the two,

25 because of part -- you know, the delay in the


154
1 transmission line that made us -- had to -- go down to

2 the 125, but if conditions had not changed, and we were

3 still expecting a line to come in-service in advance of

4 those projects coming in-service, I believe we would

5 have continued along and entered into the contracts

6 that were part of the Commission order.

7 Q And charged all of that to ratepayers,

8 despite the increase in costs you talked about?

9 A Well, I think that we would have -- the

10 contracts would have been entered into in the same --

11 at the same prices, essentially, that the Commission

12 approved. So, the Commission had already determined

13 whether it was prudent to enter into those contracts.

14 So, we would have charged the amount of those

15 contracts.

16 Q Right. But you agree that the changed

17 economics significantly affected the incremental costs

18 of the resource, right?

19 A But we wouldn't change the way we would

20 project to recover those between the different clauses,

21 and the facilities, then, wouldn't have changed the

22 costs. So, we would be doing what the Commission had

23 deemed was prudent.

24 Q Okay. But as we sit here today, Public

25 Service can't assert that the solar thermal resource


155
1 currently proposed for the valley is even in a

2 reasonable cost range, correct?

3 A Well, I think we never said it was a

4 reasonable cost for solar thermal. We just said that

5 we think that the basis of the Commission's decision

6 may have changed, based on the updated assumptions, and

7 we're seeing if they can still make that determination.

8 Q Okay. But the company can no longer

9 assert, as of today, that the solar thermal with

10 storage bid price is reasonable relative to the

11 combined cycle gas bids, right?

12 A That is true. But we didn't say that

13 it's not unreasonable for solar thermal with energy

14 storage. I believe it is still a reasonable price for

15 solar thermal with energy storage.

16 Q Okay. You just can't say that it's

17 reasonable, given all the alternatives, like natural

18 gas, that are available?

19 A I wouldn't directly compare it to those,

20 but, because of the way that the Commission relied on

21 Mr. Hill's testimony, we wanted to update them on that.

22 Q Okay. So, the Commission did compare it

23 to those.

24 A Yes.

25 Q Okay. Do you agree that the incremental


156
1 cost of wind only minimally impacts the cost of

2 resource portfolios and may lead to RESA savings?

3 A Well, the same things that change the

4 cost for solar thermal will similarly impact the

5 cost-effectiveness of wind going-forward. So, I can't

6 assert that that's true, going-forward.

7 Q Okay. But I didn't ask about -- I'm just

8 asking, generally, if you agree that the incremental

9 cost of wind only minimally impacts the cost of

10 resource portfolios and may actually lead to RESA

11 savings?

12 MR. McGANN: Your Honor, I think we're

13 getting into a resource mix/resource planning issue. I

14 think the witness has already given an answer, and, I

15 think, we would should move on. I really do. I think

16 resource planning issues, or the resource mix the

17 company should either recommend or the Commission

18 should approve, are not the subject of this reopened

19 hearing.

20 A.L.J. JENNINGS-FADER: Other statements

21 with respect to the question? Mr. Douglas.

22 MR. DOUGLAS: Your Honor, if there are

23 limited RESA dollars available, and no one knows

24 exactly what those are going to be in the future, but

25 they are changing, and we're taking a look at how that


157
1 impacts future resource acquisition that might be

2 located in the San Luis Valley, it's relevant that

3 other resources that may be available generally,

4 without getting into the details of future resource

5 planning and specifically what they want to add or not,

6 but it's relevant that some have less impact on RESA

7 dollars than others.

8 A.L.J. JENNINGS-FADER: I will sustain

9 the objection. I do think that's getting too far

10 afield.

11 BY MR. DOUGLAS:

12 Q All right. Ms. Hyde, you agree that the

13 majority of the money that's paid out of the RESA

14 account, today, and has been for the last couple of

15 years, has gone to pay for the distributed generation

16 rebate; is that accurate?

17 A Through the Solar Rewards Program?

18 Q Yes.

19 A Yes.

20 Q All right.

21 (Discussion off the record.)

22 (Whereupon Exhibit No. 142 was marked for

23 identification.)

24 BY MR. DOUGLAS:

25 Q Ms. Hyde, you have been handed what has


158
1 been marked as Exhibit 142. Are you familiar with that

2 document?

3 A I don't remember having seen it, but,

4 yes, I am familiar with the -- that we filed such a

5 report.

6 Q Okay. This is actually the first filing

7 of such a report, in the 2008 Renewable Energy Standard

8 Compliance Report; is that correct?

9 A Yes.

10 Q And the purpose of this report -- correct

11 me if I am wrong -- is to take a look at -- well, the

12 2010 Compliance Plan was a forward-looking forecast,

13 where you think RESA dollars are going to go and how

14 it's all going to play out, right? That's the

15 Compliance Plan?

16 A Yes.

17 Q Okay. And this is a compliance report

18 which looks back at the previous year to see how actual

19 RESA dollars were collected and spent and how that

20 compares to the forecast made, right?

21 A I don't remember if it compares to the

22 forecast, but it definitely shows how we actually

23 performed in the compliance year.

24 Q Okay. Well, if you look at Attachment 6,

25 which is towards the end of that document, does that


159
1 compare what you have forecast, as far as the

2 expenditures and revenues for RESA for 2008 versus

3 actual?

4 A Yes.

5 Q Okay.

6 MR. DOUGLAS: Your Honor, I would offer

7 142 in evidence.

8 A.L.J. JENNINGS-FADER: Exhibit 142 for

9 identification has been offered. Voir dire or

10 objection?

11 MR. McGANN: Your Honor, I object --

12 actually, I'm not sure I see the relevance of the

13 document at this point. I certainly understand it's

14 Public Service's Compliance Plan report. But I'm not

15 sure I understand the relevance of this particular

16 document to this proceeding, since we are talking about

17 the need for this transmission line with respect to

18 Public Service's future resource needs. I'm not sure

19 what to say at this point, other than I fail to see the

20 relevance of this document to this proceeding.

21 A.L.J. JENNINGS-FADER: Other objections

22 or voir dire with respect to the document?

23 Mr. Douglas.

24 MR. DOUGLAS: Your Honor, this gets back,

25 again, to Ms. Hyde's testimony, and at the last


160
1 hearing, at this hearing, about the fact that she

2 believes there will be plenty of RESA money to acquire

3 these solar thermal placeholder resources. And looking

4 back at the RESA expenditures, and, in particular, the

5 ones relating to distributed generation, in light of

6 the increased distributed generation required by House

7 Bill 10-1001, is relevant as to when those dollars are

8 really going to be available and therefore the need for

9 the line.

10 A.L.J. JENNINGS-FADER: Mr. McGann.

11 MR. McGANN: Well, given that

12 explanation, I do have to say I don't think it's

13 relevant at all. We've got an amended statute that

14 actually gives -- has set forth in it several relief

15 valves in terms of the 2% RESA. So we have got a RESA

16 collection mechanism as well as the costs that hit that

17 RESA, that also can vary greatly, based upon this new

18 legislation.

19 So, I don't think it makes any sense to

20 now go back a couple of years and measure the

21 performance of the RESA account in a 2008 plan and try

22 to somehow suggest that that performance isn't related

23 at all to the performance of the Renewable Energy

24 Standard Adjustment in the future, given the new

25 statute and the relief valves that are set forth in the
161
1 statute. So, given that explanation, I really don't

2 see the relevance.

3 MR. DOUGLAS: Your Honor, the relief

4 valves were mentioned by Ms. Hyde, and they will be

5 the -- we'll get there in a minute. But, those are

6 things that the Commission has discretion to

7 potentially do.

8 The way things were calculated in '08 and

9 '09 is actually the ways things are still calculated

10 today, and unless the Commission acts. So, at this

11 point, looking back at what has happened over the last

12 couple of years, and then discussing these relief

13 valves, are all part of the discussion of what impact

14 House Bill 10-1001 has on these future RESA dollars.

15 A.L.J. JENNINGS-FADER: I am going to not

16 admit Exhibit 142. I think it considers too much, if

17 you will, too much information on too many extraneous

18 topics, given the explanation that counsel has given as

19 to the relevance of the document.

20 I think Mr. Douglas, or any counsel, can

21 achieve the stated purpose by simply asking the witness

22 how the RESA is currently calculated, and use that as a

23 foundation to start the discussion of what the

24 amendment will change.

25 MR. DOUGLAS: Okay.


162
1 A.L.J. JENNINGS-FADER: So, Exhibit 142

2 is not admitted.

3 BY MR. DOUGLAS:

4 Q Ms. Hyde, you, I believe, you agreed that

5 the majority of the money under RESA, over the last

6 several years, has gone to pay for rebates to customers

7 who install retail distributed generation, correct?

8 A Yes. The amounts under the Solar Rewards

9 Program.

10 Q Okay. And as the law stands today, the

11 way those rebates, and the costs pertaining to retail

12 distributed generation are calculated, is the same as

13 it was in those years when it was the majority of the

14 RESA dollars, correct?

15 A The way the -- the way that what you've

16 actually spent is calculated or what you're planning to

17 spend?

18 Q The way you actually pay out money

19 relating to the installation of the retail distributed

20 generation, which resulted in these RESA dollars, over

21 the last couple of years, being paid out, that you

22 discuss, the way that is calculated for someone who

23 installed retail distributed generation today is the

24 same, right?

25 A I don't think so. The way you pay out --


163
1 are you saying between 2008 and 2010 that it's the

2 same?

3 Q Well, let's start there, sure.

4 A I don't think so, because there's been

5 changes to the potential ownership of on-site solar,

6 and that has changed how the money gets paid out. And

7 we've also proposed a transparent, long-term reduction

8 to the REC payments, that changes how you pay out the

9 money under the RESA. They all go to spread the money

10 further than they did before.

11 Q Okay. Well, you agree that, prior to the

12 passage of House Bill 10-1001, and that was still a

13 bill that was being proposed and discussed, that Public

14 Service expressed concerns to the Commission that the

15 increased distributed generation requirement in House

16 Bill 10-1001 could potentially require most, if not

17 all, RESA dollars, correct?

18 A Yes.

19 Q And the reason you had that concern was

20 that, as you've said, the majority of RESA dollars

21 spent had been going to retail distributed generation,

22 right?

23 A I don't think we were concerned that they

24 had -- I mean, that's just the fact, that they had. I

25 think we were concerned that if all of the RESA dollars


164
1 went to the distributed program, that we would miss

2 some opportunities for some other renewable resources.

3 Q Okay. And you were concerned that a

4 significant increase in the required amount of the

5 retail distributed generation could potentially use up

6 all or most of the RESA dollars?

7 A I think we were concerned with several

8 things when the bill was first introduced, that being

9 among them.

10 Q Okay. So that -- I'm sorry. That was

11 one of your concerns?

12 A That was one of our concerns; that the

13 megawatts might be too high.

14 Q All right. And then you mentioned, on

15 your direct exam, that, I believe, two specific

16 provisions in House Bill 10-1001 mitigate the effect of

17 this increased distribution generation requirement, in

18 the sense that you are going to have to pay out or

19 you're hoping to pay out less money to these

20 distributed generation customers; is that accurate?

21 A I think that I said that it gave us

22 additional tools to help manage the RESA balance.

23 Q Okay. And that's why -- I believe you

24 referred to the, what we can call, "the fair-share

25 provision"; is that one of them?


165
1 A Yes.

2 Q And that is something that, if the

3 Commission approves, or depending on how the Commission

4 implements it, will allow you to collect RESA dollars

5 from these retail distributed generation customers,

6 despite the fact that their bill has gone down at about

7 the same level, right?

8 A Yes.

9 Q And then the second provision is that the

10 Commission has discretion to lower the standard rebate

11 from $2 a watt, to something less, if it determines

12 that that's appropriate, right?

13 A Yes.

14 Q Okay. And it's your opinion that these

15 changed -- let me start over. It's your opinion that

16 these changes in House Bill 10-1001, when implemented,

17 may change the way retail distributed generation costs

18 are incurred by Public Service, and could offset some

19 of the reduction in RESA dollars that we discussed from

20 the changed assumptions; is that accurate?

21 A Subject -- I think that requires me to

22 assume that the RESA -- that the Commission accepts our

23 proposed changes in assumptions.

24 Q Well, let's assume that you re-do the

25 modeling from the 2010 Compliance Plan, using the


166
1 assumptions that we talked about, that you believe

2 today are more accurate, and that the Commission says

3 that's a good way to do it. Let's assume that?

4 MS. MANDELL: I'm sorry. I have to

5 object to the form of the question again.

6 A.L.J. JENNINGS-FADER: Sorry,

7 Ms. Mandell. Well, perhaps all of us can hear you.

8 Again, you have to be sensitive to the microphone.

9 MS. MANDELL: I'm sorry to interrupt, but

10 I have to object to the form of the question, as to

11 going back and redoing the assumptions in the 2010

12 docket. That's so unlikely, given the Commission's

13 orders with regard to lockdown of the assumptions, with

14 regard to resource acquisition in these dockets. So, I

15 object to the form of the question.

16 A.L.J. JENNINGS-FADER: Thank you. Any

17 other objection to the question before Mr. Douglas

18 responds? Mr. Douglas.

19 MR. DOUGLAS: Your Honor, I believe I

20 asked it in the hypothetical, not speaking to what the

21 Commission will do, but if the Commission does approve

22 what Public Service says is, as of today, is more

23 accurate, what effect that might have.

24 A.L.J. JENNINGS-FADER: I would overrule

25 the objection, understanding the basis of the


167
1 objection.

2 BY MR. DOUGLAS:

3 Q So, Ms. Hyde, let's just orient ourselves

4 again. Assume, hypothetically, that the 2010

5 Compliance Plan modeling, we have resources that you

6 discussed in that plan, including these 250-megawatt

7 solar thermal placeholders, assume that you revise the

8 modeling to reflect the changed assumptions that we

9 discussed today that you believe are now more accurate,

10 all right?

11 A Okay.

12 Q You believe that these changes in House

13 Bill 10-1001, that could result in change to how the

14 distributed generation expenses are calculated for

15 Public Service, could offset the negative move in RESA

16 dollars that we discussed from those changed

17 assumptions, to some extent; is that accurate?

18 A Yes. In the hypothetical, knowing that

19 they won't re-do the 2010. But I think that we have a

20 whole suite of tools in order to manage those RESA

21 dollars.

22 Q Well, and Public Service has not studied

23 or modeled or tried to quantify the potential positive

24 effect on RESA dollars from these two provisions, the

25 fair-share provision and the potential reduction in


168
1 rebate, have they?

2 A No.

3 Q And, in fact, let's take a look at those,

4 if you would. Look at Exhibit 132, please.

5 A Got it.

6 Q If you look at page 9, what's here as --

7 I guess it's Roman 4B on this page, is that the

8 fair-share provision we've been discussing?

9 A Yeah.

10 Q And that's says, "Notwithstanding

11 subparagraph 1" -- or "i" -- "of this paragraph g, the

12 Commission may ensure that customers who install

13 distributed generation continue to contribute, in a

14 nondiscriminatory fashion, their fair share to their

15 utility's renewable energy program fund or equivalent

16 renewable energy support mechanism, even if such

17 contribution results in a charge that exceeds 2% of

18 such customer's annual electric bills." Did I read

19 that correctly?

20 A Yes.

21 Q So, it's the Commission's determination,

22 within their discretion, to determine how to implement

23 this collection of a fair share from retail distributed

24 generation customers, correct?

25 A Yes.
169
1 Q And is that currently the subject of a

2 rulemaking?

3 A I believe it is.

4 Q So, sitting here today, you don't know

5 what effect that might have, in the future, on RESA

6 dollars? You can't quantify it?

7 A I don't know. I don't think we have

8 gotten a final rule.

9 Q Okay. And we also talked about the

10 potential reduction in the standard rebate. If you

11 look at House Bill10-1001, page 6 -- actually, it

12 starts at the very bottom of page 6. Is that the

13 provision you are talking about, that carries over to

14 page 7?

15 A Yes.

16 Q Okay. And it says, "The amount of

17 standard rebate," and we're talking about standard

18 rebate to customers who install retail distributed

19 generation?

20 A Yes.

21 Q "The amount of standard rebate offer

22 shall be $2 per watt, except that the Commission may

23 set the rebate at a lower amount if the Commission

24 determines, based upon a Qualifying Retail Utility's

25 renewable resource plan or application, that market


170
1 changes support the change." Did I read that

2 accurately?

3 A Yes.

4 Q So, before any change to the rebate could

5 occur, Public Service is required to -- would be

6 required to request or file an application, with the

7 Commission, requesting that a market change supported

8 such a lowering of the rebate, right?

9 A Before you could change that part of the

10 amount that we pay to customers, we would have to file

11 an application, but we've already been reducing the REC

12 payment portion of what we pay to customers.

13 Q But that's on top of the $2 per watt?

14 A Yes.

15 Q So, as far as the reduction in the $2 per

16 watt, the Commission has the discretion to lower it or

17 not lower it, right?

18 A Correct.

19 Q And they will make that decision, at some

20 point, if Public Service files an application

21 requesting a change, right?

22 A Correct.

23 Q And Public Service has not yet filed an

24 application requesting a change, right?

25 A Not for this piece. We have already,


171
1 like I said, reduced the REC payment, yes, REC payment.

2 Q How much is the REC payment?

3 A I don't remember. It started out at, I

4 think, like $2.50 and it's been moving down since then.

5 And we did -- did the last proposal in September of

6 2009, to show it essentially reducing down towards

7 zero, over time. And we did that in cooperation with

8 CoSEIA, which is the solar installers trade industry --

9 trade group, and with the Governor's Energy Office.

10 Q Okay. But as far as this provision of

11 House Bill 10-1001, about reducing the standard rebate,

12 Public Service has not filed an application requesting

13 such a change, correct?

14 A That's true. But I think the resetting

15 of -- the other proposal gives you some indication that

16 the industry is interested in having that money spread

17 around more, to more installations.

18 Q Well, but you're speculating about what

19 the Commission might do, right?

20 A Yes.

21 Q Okay.

22 A Actually, I was speculating on how

23 industry would receive it.

24 Q Okay. But whether the Commission reduces

25 the standard rebate, under this provision, to something


172
1 less than $2 per watt, whether they do it at all, and

2 if so, how much, depends on the Commission's finding as

3 to whether market changes would support such a change,

4 correct?

5 A Yes.

6 MR. DOUGLAS: If I could have a minute,

7 Your Honor?

8 A.L.J. JENNINGS-FADER: Certainly.

9 (Discussion off the record.)

10 MR. DOUGLAS: Your Honor, I am noticing

11 the time. I wonder if this would be a good time for a

12 lunch break, and, then, I can see if I have significant

13 additional questions.

14 A.L.J. JENNINGS-FADER: I am fine with

15 that. Before we break for lunch, do any parties have

16 any matter we need to address over lunch, except to

17 remind the parties -- excuse me -- Public Service and

18 Tri-State that you were going to consider whether or

19 not -- you would let us know after Mr. Dauphinais'

20 testimony, whether you are going to be offering oral

21 rebuttal, at least to his testimony. But that's, you

22 know, a speak-quietly-among-yourselves kind of

23 discussion. Yes, ma'am. Ms. Mandell.

24 MS. MANDELL: After the break, sorry.

25 Right after the break, you asked me whether or not I


173
1 had any questions for Ms. Hyde. And I answered no.

2 But, based on what has transpired since then, I have

3 very limited cross examination for her, once I have an

4 opportunity.

5 A.L.J. JENNINGS-FADER: I need to ask

6 you, Ms. Mandell, is this elicited as a result of her

7 Direct Testimony or as a result of the cross

8 examination -- testimony given in response to cross

9 examination?

10 MS. MANDELL: Testimony in response to

11 cross examination.

12 A.L.J. JENNINGS-FADER: I'll have to

13 think about it. Thank you. OCC, are you --

14 MR. SCHLESINGER: Still no questions.

15 A.L.J. JENNINGS-FADER: We'll take the

16 lunch break and I am going to give everyone 50 minutes

17 for lunch. So, we'll be back at 1:30.

18 (Recess.)

19 A.L.J. JENNINGS-FADER: We'll be back on

20 the record in the continuation of the hearing,

21 following the lunch break. Mr. Sopkin, I had a note

22 from the reporter. I wish to confirm, on the record,

23 that the confidential version of Exhibit 135 was

24 returned to you.

25 MR. SOPKIN: It was, yes.


174
1 A.L.J. JENNINGS-FADER: Okay. Thank you

2 very much. So, in theory, at least, all we have left

3 is the nonconfidential version.

4 MR. McGANN: Right.

5 A.L.J. JENNINGS-FADER: All right. I may

6 have misunderstood the note. Is, Mr. Sopkin, is 135

7 the filing of the amendment, the application

8 amendment -- I'm sorry, or Mr. McGann. My apologies --

9 amendment application?

10 MR. SOPKIN: It is a confidential version

11 of the exhibits to Mr. Hill's testimony.

12 A.L.J. JENNINGS-FADER: Okay. Right,

13 which was not admitted, so they just gave me the wrong

14 number. It should have been 136 was returned to you,

15 right?

16 MR. SOPKIN: I am showing 135A.

17 MR. McGANN: And 136 was, I believe, the

18 correction to Mr. Hill's testimony that was filed.

19 A.L.J. JENNINGS-FADER: It certainly was.

20 Thank you. It certainly was. Thanks. That was the

21 corrected testimony, right. Okay. Excellent. So we

22 are still correct and that confidential information has

23 been returned to you?

24 MR. SOPKIN: Yes.

25 A.L.J. JENNINGS-FADER: All right. Thank


175
1 you. We'll be off the record for a minute.

2 (Discussion off the record.)

3 A.L.J. JENNINGS-FADER: Thank you. We'll

4 be back on the record. Mr. Douglas.

5 MR. DOUGLAS: Thank you, Your Honor.

6 A.L.J. JENNINGS-FADER: Stand at the

7 podium. This won't take but a second. Ms. Mandell, I

8 have not forgotten you. I would address your request

9 after the conclusion of the cross examination.

10 And Tri-State/Public Service, not this

11 minute, I don't want to know absolutely, but will you

12 be in a position to tell us whether or not you will

13 offer a rebuttal witness after Mr. Dauphinais

14 testifies?

15 MR. SOPKIN: Your Honor, I think we think

16 we'll ask for the opportunity to confirm among

17 ourselves to decide.

18 A.L.J. JENNINGS-FADER: Sure. I

19 appreciate that courtesy. Thank you very much.

20 Mr. Douglas.

21 MR. DOUGLAS: Thank you, Your Honor.

22 BY MR. DOUGLAS:

23 Q Ms. Hyde, before we broke for lunch, you

24 and I, I believe, were still discussing the standard

25 rebate payment for retail distributed generation. Do


176
1 you recall that discussion?

2 A Yes.

3 Q And do you agree that the costs to Public

4 Service Company incurred in making those standard

5 rebate payments are charged against the RESA account?

6 A Yes.

7 Q Yes. All right. And, then, if you

8 would, please, look at Exhibit 134, and, in particular,

9 page 3 of 134. And I'll identify that, Your Honor. Do

10 you have that in front of you, Ms. Hyde?

11 A Yes.

12 Q Okay. And this is the Direct Testimony

13 and Exhibits -- well, strike that. Exhibit 134 is the

14 Direct Testimony of James F. Hill, correct?

15 A Yes.

16 Q All right. If you look at page 3, lines

17 7 through 11, Mr. Hill testifies that, "In addition,

18 the company is seeking guidance from the Commission

19 regarding their Phase 2 decision to have the company

20 pursue bids for solar thermal with storage." Do you

21 see that?

22 A Yes.

23 Q And do you agree with that?

24 A Yes.

25 Q Mr. Hill, then, testifies that the


177
1 company believes that changed circumstances, regarding

2 the underlying economic factors that form the basis for

3 that original decision, warrant reconsideration." Do

4 you see that?

5 A Yes.

6 Q And do you agree with that?

7 A Yes.

8 Q You mentioned, on direct examination,

9 that the reason you filed the application was for -- or

10 due to delays in the proposed transmission line that's

11 the subject of this docket. Another reason was because

12 of these changed circumstances that Mr. Hill discusses,

13 correct?

14 A No. We filed it because of the

15 reduction -- we had to reduce the amount of solar to

16 the level -- or below the level that we had available

17 in transmission capacity. And, as part of that

18 analysis, we saw that we had some changed economic

19 circumstances, that changed the testimony of Mr. Hill,

20 that was relied upon by the Commission.

21 So, that's kind of the byproduct. It's

22 not really the second reason we filed it. It's just

23 because we were filing the amendment, we needed to file

24 the other piece because of the Commission's reliance.

25 Q Okay. So, even though the company


178
1 believes these changed economic circumstances warrant

2 reconsideration, that was not one of the reasons for

3 your filing the amendment?

4 A Right.

5 Q Okay.

6 MR. DOUGLAS: Your Honor, that's all I

7 have.

8 A.L.J. JENNINGS-FADER: Ms. Mandell?

9 MS. MANDELL: Yes, Your Honor.

10 A.L.J. JENNINGS-FADER: I would like to

11 address some questions to you, if I may, before I rule

12 on your request. If I understood you before the break,

13 in response to a question, you said that these would be

14 questions that you have now based on information

15 elicited during the cross examination by -- of Ms. Hyde

16 by Mr. Douglas.

17 MS. MANDELL: That is correct, Your

18 Honor.

19 A.L.J. JENNINGS-FADER: Could you tell

20 me, please, what subject matter areas are involved?

21 MS. MANDELL: Yes. The model of the

22 proxy carbon cost. I had just a few questions there.

23 And one question with regard to the concept in the HB

24 10-1001 statute, with regard to the, as Public Service

25 calls it, "the fair share." We don't agree with that


179
1 particular designation.

2 A.L.J. JENNINGS-FADER: Are these, by way

3 of clarification, answers given by Ms. Hyde in

4 responses to questioning by Mr. Douglas?

5 MS. MANDELL: I would have to say, yes.

6 A.L.J. JENNINGS-FADER: We'll take -- I

7 would allow you to question. We'll take it one

8 question at a time.

9 MS. MANDELL: Thank you, Your Honor. I

10 will need to ask a couple of foundation questions.

11 CROSS EXAMINATION

12 BY MS. MANDELL:

13 Q Ms. Hyde, are you familiar with the Clean

14 Air - Clean Jobs Act docket now pending before the

15 Commission?

16 A Yes.

17 Q And that docket has to do with reducing

18 emissions from 900 megawatts of coal plants in the

19 metro area; is that right?

20 A A minimum of 900 megawatts, yes.

21 Q Thank you. And even though the Public

22 Service Company plan is not due until August 13th,

23 Public Service has given some preliminary indications

24 of the model analysis and some of the inputs they will

25 be using; is that right?


180
1 A Yes.

2 Q And what year has Public Service, on a

3 preliminary basis, indicated it will be using as the

4 initial year for the carbon proxy cost?

5 A 2014.

6 Q And, Ms. Hyde, with regard to the

7 rulemaking having to do with implementation of House

8 Bill 10-1001, would you agree with me there's

9 considerable dispute about how the Commission should or

10 should not implement the provision having to do with

11 what you call, "the fair-share provision"?

12 A Yes.

13 MS. MANDELL: That's all I had. Thank

14 you.

15 A.L.J. JENNINGS-FADER: Thank you.

16 Ms. Hyde. If you know, could you tell me the docket

17 number that's the Clean Air - Clean Jobs proceeding

18 or --

19 (Discussion off the record.)

20 A.L.J. JENNINGS-FADER: Sorry. If any

21 counsel knows the answer, that would be fine. I just

22 need -- I just want to know what the reference was.

23 MR. McGANN: I believe it's 10M-245E.

24 It's a miscellaneous docket.

25 A.L.J. JENNINGS-FADER: And I believe


181
1 that's correct but just double-checking. Thank you.

2 Redirect.

3 MR. McGANN: Thank you, Your Honor.

4 REDIRECT EXAMINATION

5 BY MR. McGANN:

6 Q All right, Ms. Hyde. I would like to

7 start out -- do you recall being asked a series of

8 questions by Mr. Douglas concerning assumptions

9 regarding carbon and gas prices and other assumptions.

10 Do you recall that line of questions?

11 A Yes.

12 Q I would like to take a step back for a

13 moment, and just have you describe for me, and for the

14 record, and for the Judge, how is it that the company

15 goes about, essentially, doing its resource planning

16 and its compliance with the RES, and what the

17 Commission requires the company to do in terms of those

18 assumptions, like gas and like carbon?

19 A To date, what we have had is actual

20 numbers for carbon, where we present a number, other

21 parties present their alternatives, and the Commission

22 comes up with a number to use for carbon.

23 And, then, right now, we have a

24 methodology for gas prices. It's an average of four

25 forecasts, plus a gas price volatility mitigation


182
1 estimate.

2 Q And do the Commission's rules speak to

3 where those assumptions and methodologies are derived

4 and, then, how they are to be used?

5 A Well, generally, they are derived in the

6 Resource Plan, and then they would be used in the RES

7 Compliance Plan.

8 Q And you mentioned -- or I mentioned, in

9 my questions, assumptions and then methodologies. And

10 am I correct that there are certain hard assumptions

11 the company is required to make like, for example, the

12 cost of carbon; is that correct?

13 A Yes.

14 Q And, then, there are certain

15 methodologies the Commission develops in a Resource

16 Plan, and that would apply, for example, to gas prices;

17 is that correct?

18 A Correct.

19 Q Well, let me ask you, then, when it comes

20 to those assumptions and methodologies, which prevails?

21 Is it the company's estimate of those numbers or is it

22 the Commission's decision on those numbers?

23 A The Commission decision.

24 Q And you would agree with me that those

25 numbers change over time?


183
1 A They do.

2 Q With specific reference to -- let's go

3 through each one of these. Let's start with the cost

4 of carbon. Do you believe that there has to be carbon

5 legislation that essentially assesses a cost for

6 carbon? For the Commission to determine a cost of

7 carbon?

8 MR. DOUGLAS: Your Honor, I would object.

9 This examination is entirely leading at this point.

10 MR. McGANN: It's a foundational

11 question; that I am going to ask her how the Commission

12 derives the carbon cost. I'm just trying to switch to

13 carbon.

14 A.L.J. JENNINGS-FADER: You may certainly

15 go ahead on that question.

16 THE WITNESS: I can't remember what it

17 was. Sorry.

18 BY MR. McGANN:

19 Q Well, how did --

20 A There doesn't have to be legislation in

21 order for the Commission to decide a carbon cost,

22 because they were given separate instructions in the

23 actual Colorado legislation to consider a carbon cost.

24 Q And let me ask you, when it comes to the

25 cost of carbon, does the cost of carbon affect only the


184
1 cost of solar resources?

2 A No. It affects the whole outcome of a

3 number of dockets. It affects how much demand-side

4 management we take, how much demand response we take,

5 how much -- it affects all of the renewable and

6 nonrenewable resources in a plan. It's widespread.

7 Q And for how long has the company

8 essentially considered the cost of carbon in terms of

9 its resource acquisition decisions?

10 A We had sensitivities around carbon as far

11 back as our first Resource Plan in 1993. And we have

12 been using a numerical estimate in our basecase since

13 the 2003 Resource Plan.

14 Q And I believe that you were asked a

15 series of questions that basically focused on the fact

16 that the company, in the amended Resource Plan, has

17 suggested the carbon legislation would begin in the

18 year -- or carbon costs would begin in the year 2014.

19 Do you recall that line of questioning?

20 A Yes, I do.

21 Q If carbon legislation were passed in

22 2014, what effect, if any, would that have on the

23 company's resource acquisition choices?

24 A I think it would depend on the form of

25 the legislation. But, in general, what really impacts


185
1 our resource decisions is the, right now, the carbon

2 proxy cost that the Commission approves, and that may

3 or may not reflect the number in legislation.

4 Q Let's move onto gas prices. I believe

5 you were asked a series of questions that established

6 the fact that, in the amendment to the Resource Plan,

7 the company was estimating a lower gas price; is that

8 correct?

9 A Yes.

10 Q What has been your experience with

11 respect to the price of gas over time?

12 A Every time we estimate it, using the

13 methodology from the Commission, it's different than

14 the time before. It's gone up and it's gone down in

15 the long term, and by a lot over the last few years.

16 Q I would like to move onto, I think it was

17 Exhibit 141, which was the Tables 7-3 and 7-4, from the

18 2010 RES Compliance Plan docket. Do you have that in

19 front of you?

20 A I do.

21 Q Well, let me just start, actually, with

22 just a preliminary question. I think -- do you

23 remember being asked by Mr. Douglas whether the 2010

24 RES Compliance Plan was the company's best -- and I am

25 paraphrasing here -- the best estimate of the company's


186
1 plans? Do you recall that question?

2 A Yes.

3 Q And I recall that your answer to that

4 question was, yes?

5 A Yes.

6 Q And I would just like you to explain that

7 answer, if you could. Why do you believe that that's

8 probably -- that that is the best estimate of the

9 company's plans, at least at this point in time?

10 A Because it's the only projection that we

11 have done, of those resource acquisitions, out into

12 that time frame at this point. We're just embarking on

13 another set of dockets that will consider what to do in

14 those years, and, so -- as we file the Clean Air -

15 Clean Jobs, and then the RES Compliance Plan, and then

16 the 2011 Resource Plan.

17 So, right now, it's the only plan that's

18 out there. But, in addition, we have significant

19 capacity needs, starting in 2016 and we need to add

20 something to the system in '16, '17, '18. So, I still

21 believe that it's reasonable to, since we have to add

22 something, to add solar thermal, both for its benefits

23 on the Renewable Energy Standard and the 2%, but also

24 because it will be used to serve actual capacity needs.

25 Q Well, moving onto --


187
1 MR. DOUGLAS: Your Honor, excuse me. I

2 need to object and move to strike that last answer. We

3 repeatedly asked Public Service for those load and

4 resource forecasts beyond 2015. The ones they produced

5 go through 2015 and not beyond. And now Ms. Hyde is

6 telling us, for the first time, that in 2016 they are

7 going to start having a deficit. It's not something

8 that we have information that we can respond to, and I

9 believe that should be stricken from the record.

10 A.L.J. JENNINGS-FADER: So, you have --

11 Mr. Douglas, can you add to your objection? The

12 testimony goes through, at least in response to

13 questioning on Exhibit 136, goes through 2015, and the

14 load and resources, with respect to that, at a 185

15 megawatt, 90 megawatt and 60 megawatt. You asked those

16 questions through 2015, correct?

17 MR. DOUGLAS: That's correct.

18 A.L.J. JENNINGS-FADER: So, your

19 objection now is going anything past what year?

20 MR. DOUGLAS: 2015, Your Honor.

21 A.L.J. JENNINGS-FADER: Anything past

22 2015?

23 MR. DOUGLAS: Yes.

24 A.L.J. JENNINGS-FADER: And this question

25 involved?
188
1 MR. DOUGLAS: She said, starting in 2016,

2 they would have additional needs.

3 A.L.J. JENNINGS-FADER: Okay. Thank you.

4 Now, one last little issue before I let other folks

5 chime in. Could you read the discovery request that

6 requested information to which you do not believe you

7 received a response that would allow this question?

8 MR. DOUGLAS: Yes. Your Honor, I will

9 find it. And if it might also help the Court, there is

10 a specific load and resources forecast that was

11 provided in response to discovery, which I have, which

12 goes to 2015, which I could hand the Court.

13 A.L.J. JENNINGS-FADER: That's okay. I

14 would take your representations. Thank you.

15 MR. DOUGLAS: Okay.

16 MR. McGANN: Your Honor, while

17 Mr. Douglas is looking, may I consult with my

18 co-counsel?

19 A.L.J. JENNINGS-FADER: You certainly

20 may. Absolutely. I just want to get the full scope of

21 the objection flushed out here.

22 (Discussion off the record.)

23 MR. DOUGLAS: Your Honor.

24 A.L.J. JENNINGS-FADER: Uh-hum.

25 MR. DOUGLAS: There's a lot to this one,


189
1 but this is the one. So, I will just read it into the

2 record. This is Trinchera Ranch -- what was numbered

3 by Public Service as Trinchera Ranch Discovery Request

4 26-12. And this is the load and resource forecasts

5 that I mentioned was produced in response to -- it

6 says, "Please provide a copy, in electronic form only,

7 of all financial reports, studies, analyses, work

8 papers, data assumptions, and other documents the

9 company has created, Commission conducted or relied

10 upon, in connection with the company's amendment to the

11 2007 Colorado Resource Plan filed on June 4th, 2010,

12 including but not limited to documents related to the

13 costs of the proposed concentrating solar with storage

14 facilities, as compared to combined gas facilities,

15 load and resource forecast, demand forecast, including

16 the most recent demand forecast completed in March

17 2010, described on page 12 of Exhibit JFH-1, rates,

18 models, gas prices, carbon legislation, frequency and

19 costs of curtailment payments before the effect of the

20 amendment on the 2% retail rate impact set forth in the

21 study."

22 A.L.J. JENNINGS-FADER: And in response

23 to that, you received the load and resources Tables

24 through the year 2015?

25 MR. DOUGLAS: That's correct.


190
1 A.L.J. JENNINGS-FADER: Thank you.

2 MR. McGANN: Your Honor, I believe -- I

3 am actually reading this at my computer screen. I am

4 back at counsel table, if I may.

5 A.L.J. JENNINGS-FADER: You certainly

6 may.

7 MR. McGANN: I believe the response to

8 26-12, which basically says, give us the financial

9 reports and studies you have created in connection with

10 the company's amendment to the Colorado Resource Plan,

11 including but not limited to.

12 And, so, I think again, we're back to the

13 fact that it was limited by that phrase, which was --

14 as it should have been, quite frankly. I mean, that's

15 the scope of the reopened docket. So, it makes perfect

16 sense that they would ask a discovery question along

17 those lines.

18 My understanding -- I don't think -- I

19 thought it was established, so, I don't think we were

20 required to produce the information Mr. Douglas

21 suggests by this Data Request, No. 1.

22 No. 2, I didn't think it was a secret

23 that we had load and -- that we had resource needs

24 beyond 2015. I thought that was established in the

25 first part of this case. It's also been established in


191
1 Clean Air - Clean Jobs, where Trinchera Ranch is a

2 party. It's also been established in the Resource Plan

3 docket, where they are a party as well. So, I'm not

4 sure that this is any particular secret for Trinchera

5 Ranch at this point in time.

6 A.L.J. JENNINGS-FADER: But your initial

7 response is that this is beyond the scope of the

8 discovery request?

9 MR. McGANN: Absolutely.

10 A.L.J. JENNINGS-FADER: Anything further,

11 Mr. Douglas?

12 MR. DOUGLAS: Your Honor, this was a

13 subject of negotiation. They actually produced to us,

14 first, the load and resources forecast for 2012. We

15 have requested it to go further out. And they -- I

16 believe we asked for 2020.

17 I don't have the e-mails with me, but

18 there was an e-mail response in response to this very

19 document, which then produced to 2015. The amendment

20 itself says we're fine through 2015, though, if you

21 will look at a couple of options, we'll have a small

22 deficit. I explored that with Mrs. Hyde.

23 And now, to the extent Public Service

24 wants to present testimony at this hearing that, in

25 fact, even though they are fine through 2015, they have
192
1 more needs starting in 2016, the deciding factor isn't

2 whether it's a secret in other dockets, or whether it

3 was established at the last hearing. It was -- we're

4 not asking to strike that testimony, but as to the

5 subject in this reopened hearing, for Ms. Hyde to

6 discuss this, in light of their production to us,

7 solely, of the information through 2015, isn't proper.

8 A.L.J. JENNINGS-FADER: I agree, unless

9 you are prepared to produce load and resources tables

10 beyond the year 2015, then 2015 it is.

11 And the testimony is stricken, Harriet.

12 The response of Ms. Hyde, that began with her

13 discussion of a need for resources beginning in the

14 year 2016, and that the solar thermal resources in the

15 San Luis Valley is intended, in part, at least to meet

16 that need, is stricken, to be clear. Thank you.

17 MR. DOUGLAS: Thank you, Your Honor.

18 BY MR. McGANN:

19 Q Ms. Hyde, if we could move onto -- I

20 think I had begun to ask you a series of questions on

21 Exhibit 141, so, if you could turn to that exhibit.

22 A I have it.

23 Q And I would like you to specifically look

24 at Tables 7-3 and 7-4.

25 A I have them.
193
1 Q And I believe you -- Mr. Douglas asked

2 you a series of questions regarding the rolling

3 deferred balance for the RESA account, which is, I

4 think, Column X in both of those tables; is that

5 correct?

6 A Yes.

7 Q Can you tell me whether or not that

8 rolling deferred balance includes the three solar

9 thermal placeholder plants that were set forth in the

10 2010 RES Compliance Plan?

11 A Yes. The rolling balance is after we

12 have already paid for those three 250-megawatt plants.

13 Q And if you could take a look at those two

14 tables, 7-3 and 7-4, can you tell me, of those tables

15 showing the wind, when the rolling deferred balance

16 becomes positive, and what the difference is between

17 those two tables?

18 A Yes. It shows that our estimate, with a

19 carbon proxy price starting in 2010, was that it would

20 turn negative in '12. And when we had the carbon proxy

21 price deferred to 2014, it would go positive in 2015.

22 A.L.J. JENNINGS-FADER: I'm sorry. Could

23 you help me out. Is that information on two different

24 tables or on the same table?

25 THE WITNESS: Two different tables.


194
1 A.L.J. JENNINGS-FADER: Could you tell me

2 which piece of information is on which table?

3 THE WITNESS: Sure.

4 A.L.J. JENNINGS-FADER: Thank you.

5 THE WITNESS: Table 7-3, Column X, on the

6 lower set of numbers, shows that the -- this one had

7 carbon proxy costs starting in 2010, and it shows that,

8 by 2012, we have a RESA excess. We had positive money

9 left over after paying for all of our resources.

10 And then Table 7-4, again, Column X, this

11 is a case in which, instead of having a carbon proxy

12 price in 2010, we have it in 2014, but we show, in

13 Column X, that we start to have a RESA excess in 2015.

14 A.L.J. JENNINGS-FADER: Thank you very

15 much. Thank you, Counsel.

16 MR. McGANN: Thank you.

17 BY MR. McGANN:

18 Q And, Ms. Hyde, just as a foundational

19 matter, am I correct that the RESA balance numbers that

20 are reflected in Exhibit 141, in Table 7-3 and 7-4,

21 those, essentially -- that modeling was done prior to

22 the enactment of new House Bill 10-1001?

23 A Yes, it was.

24 Q Now, what I would like to do now is, with

25 respect to the RESA balance, I would like to kind of


195
1 discuss with you some of the issues that Mr. Douglas

2 raised with respect to some of the provisions in the

3 statute that address how much money may be in that RESA

4 account. And, so, if you could -- let me just ask you

5 a general question. What are the amendments that were

6 enacted by the legislature in new House Bill 10-1001

7 that affect or that could potentially affect the amount

8 of money in the RESA account?

9 A There's at least four. One is the

10 provision for the positive or negative balance, and the

11 recovery, the interest on that, because it makes the

12 company neutral for spending the money ahead of time.

13 There's also the provision that allows us to seek a

14 reduction in the 3% distributed generation amount from

15 the Commission. There's also a reduction in the

16 standard rebate offer that we can seek from the

17 Commission. And there's the provision to allow us to

18 charge customers who have installed distributed

19 generation a higher amount than we would right now.

20 And I would say, also, that these

21 implement the series of tools that we already had in

22 order to try to manage the RESA. And that included

23 reductions in the REC payment and the payments, over

24 time, that are provided under the third-party ownership

25 or third-party financing model.


196
1 Q Well, let's start from that last answer,

2 then, and talk about the REC payments, then.

3 Do you know -- I believe you testified

4 already that the payments for the REC started at -- was

5 it 2,50?

6 A Right around 2.50.

7 Q And do you know where those REC payments

8 are now?

9 A On an equivalent basis, they are about 50

10 cents, just under 50 cents.

11 Q And does the company need to seek

12 permission to change or alter or lower those REC

13 payments?

14 A No.

15 Q Now, when it came to -- I believe you

16 mentioned this before, in your answer with respect to

17 those REC payments, that there had been an agreement

18 struck with the industry and with the Governor's Energy

19 Office to reduce those REC payments. Do you recall

20 that testimony?

21 A Yes.

22 Q I just would like you to actually expound

23 on that a little bit. Why do you believe that the

24 industry -- or, let me ask you this: Do you believe

25 that the industry supports the reduction or supported


197
1 the reduction of those REC payments?

2 A They did.

3 MR. DOUGLAS: Your Honor, I object.

4 Lacks foundation. Calls for hearsay.

5 A.L.J. JENNINGS-FADER: Other objections?

6 Mr. McGann.

7 MR. McGANN: I'm not used to getting

8 hearsay objections in Commission proceedings, that's,

9 probably, No. 1. But, No. 2, I believe I can establish

10 a foundation. Ms. Hyde is familiar with those

11 negotiations and is familiar with the reason why those

12 stakeholders essentially came to the agreement that

13 they did with the company, in terms of those reduced

14 REC payments.

15 A.L.J. JENNINGS-FADER: I actually have

16 absolutely a different question. What is the

17 purpose -- aside from the fact that it was discussed

18 during the cross examination, what is it that you're

19 trying to elicit from this witness?

20 MR. McGANN: Essentially, Mr. Douglas

21 raised the spectre of the fact that we would need to

22 seek Commission approval for reduction of, for example,

23 the $2 standard offer rebate.

24 A.L.J. JENNINGS-FADER: Correct.

25 MR. McGANN: So, what I would like to do


198
1 is establish with Ms. Hyde whether or not the industry

2 would be receptive to such a reduction, if the company

3 were to seek that from the Commission. I am trying to

4 get -- it's going to the likelihood that such a

5 reduction may be obtained. Mr. Douglas has thrown some

6 doubt on whether or not we would be able to obtain such

7 reduction. And I would like to address that through my

8 redirect of Ms. Hyde.

9 A.L.J. JENNINGS-FADER: I am still having

10 a difficult time, since you established that REC

11 payments can be reduced without any action by the

12 Commission, how delving into a discussion or an

13 agreement with respect to the REC payments advances

14 what you're discussing?

15 MR. McGANN: Simply, it would be the same

16 industry stakeholders that would be involved in the

17 reduction of the standard rebate offer. So, that was

18 the bridge that I was trying to create to get there.

19 A.L.J. JENNINGS-FADER: All right. The

20 objection is sustained, but on relevance grounds. She

21 answered the question that you don't need a Commission

22 order to reduce REC payments, and, as to the rest of

23 it, that's too speculative.

24 MR. McGANN: Let me move on, then.

25 BY MR. McGANN:
199
1 Q And, I believe, in part of your

2 testimony, when you had discussed reduction of the

3 standard rebate offer, you said that the company could

4 seek such a reduction through an application process.

5 Do you recall that testimony?

6 A Yes.

7 Q Is there any other way the company can

8 seek a reduction of the standard rebate payment?

9 A We could put it into our RES Compliance

10 Plan in addition to separate application.

11 Q Do you recall being asked a series of

12 questions about the fact that there's a new section of

13 the statute regarding obtaining an interest rate equal

14 to the weighted after-tax cost of capital on RESA

15 balances? Do you recall that series of questions?

16 A Yes.

17 Q And do you recall also being asked

18 that -- whether or not it was true that if customers

19 had to pay interest, that less money would be available

20 for renewable resources?

21 A Yes.

22 MR. DOUGLAS: Your Honor, I object. I

23 think that mischaracterizes the testimony.

24 THE WITNESS: Yes.

25 A.L.J. JENNINGS-FADER: There's an


200
1 objection. The answer is stricken until I rule on the

2 objection.

3 Mr. McGann.

4 MR. McGANN: I actually, at this point in

5 time, I believe that was certainly the answer that was

6 elicited from the witness. That was what I -- that was

7 my recollection. Well, and I can ask it in a different

8 way, too.

9 A.L.J. JENNINGS-FADER: I would

10 appreciate if you could avoid that particular issue.

11 Reask it. Thank you.

12 BY MR. McGANN:

13 Q To the extent the weighted after-tax cost

14 of capital is added to the RESA balance, some of the

15 RESA payments will go to the payment of that interest;

16 is that correct?

17 A Correct.

18 Q Do ratepayers or customers get any

19 benefit in the payment of that interest?

20 A Yes. They got to receive the renewable

21 energy earlier. They got, essentially, the time value

22 of the emission reductions.

23 Q And sticking with the new legislation, I

24 believe, do you recall being asked, I think at the

25 beginning of your cross examination, by Mr. Douglas,


201
1 whether or not there was a public policy in favor of

2 distributed generation?

3 A Yes.

4 Q And let me just give you the opportunity,

5 now, to explain that answer, if I could.

6 A Yes. I think that it's clear, when the

7 legislature was actually pushing a policy in favor of

8 retail distributed generation, or distributed

9 generation, in general, that the majority of the

10 standard still can be met by utility-scale resources.

11 And the way that they defined, "distributed

12 generation," we now can count things that we couldn't

13 count before to that standard, like our 100-year-old

14 hydros and existing solar resources.

15 So, while the numbers show that the

16 percentage of our load that has to be met by

17 distributed generation has increased, I don't think

18 that it actually shows a large shift in the state's

19 commitment to have retail distributed generation. I

20 also think that, because we only need a small increase

21 in our acquisitions to fill that amount, like another

22 32 megawatts over our previous plan; and that people

23 knew that we could do that reasonably, and could do it

24 within the rate impact, based on our testimony before

25 the legislature; that, I think, that you can't make a


202
1 sweeping judgement that that resulted in a public

2 policy that's significantly increased the state's

3 consideration of what's now referred to as, "retail

4 distributed generation."

5 Q Okay. And I would like to just now pose

6 to you the hypothetical that I think, perhaps,

7 Mr. Douglas was driving for during his cross

8 examination. I would like you to assume that the

9 company finds that the 2% -- the money that's under the

10 2% retail rate cap will not allow the company to

11 acquire the large utility-scale solar it desires to

12 acquire over the next 10 to 15 years. Do you have that

13 hypothetical in mind?

14 A Yes.

15 Q What would the company do?

16 A Well, we have a lot of ways to try to

17 deal with that. We could file to reduce the standard

18 rebate offer. We could file for the charges that are

19 allowed to the existing customers. We could continue

20 to drive down the REC payment. We could advocate other

21 changes at the legislature, as we have in years past.

22 I think we have a lot of tools that we could use. And

23 we could also ask the Commission to reduce the 3%

24 distributed generation standard.

25 So, we have a lot of tools, a whole suite


203
1 that we could use to manage how we spend that 2% over

2 time.

3 Q I would like you to now take a look at

4 Exhibit, I believe it's 137, which was the large

5 spreadsheet.

6 A Yeah.

7 A.L.J. JENNINGS-FADER: I'm sorry.

8 Three-page one or the --

9 MR. McGANN: The three-page.

10 A.L.J. JENNINGS-FADER: The colored

11 three-page?

12 MR. McGANN: That colored three-page one.

13 That's right.

14 A.L.J. JENNINGS-FADER: Okay. Thank you.

15 BY MR. McGANN:

16 Q And, specifically, well, let's start at

17 page 2 of 3.

18 A Okay. I am there.

19 Q Can you tell me whether or not this table

20 takes into account -- or also, actually, let me just

21 ask this question of the entire exhibit, all three

22 pages. Can you tell me whether or not this exhibit

23 takes into account the company's resource needs?

24 A No, it doesn't.

25 Q Can you tell me whether or not the table


204
1 takes into account the company's desire or plans to add

2 renewable resources?

3 A No. This is just one scenario that

4 looked at, basically, the plans that were approved at

5 the time, essentially, and the contracts that were in

6 place, and how that might allow us to meet the minimum

7 standards under the legislation.

8 It doesn't take into account how we would

9 meet future load growth or future resource needs. It

10 doesn't take into account the plans that we may bring

11 forth in Clean Air - Clean Jobs, or in the RES in

12 September of 2010, or the 2011 Resource Plan. It's

13 just one snapshot of what was in place at the time,

14 relative to the new standard.

15 Q And with respect to Exhibit -- if you

16 could turn now to Exhibit 138. I would like to ask you

17 the same questions with respect to that exhibit, so let

18 me ask you the first question: Does that exhibit take

19 into account the company's resource needs?

20 A No. When I'm looking at the nameplate

21 capacity with open net, in fact, in the second

22 rectangular box that Mr. Douglas talked with me about,

23 those numbers don't take into effect any resource needs

24 going-forward, or anything that we might put forth in

25 those other dockets.


205
1 Q And does Exhibit 138 take into account

2 the company's desire to add renewable resources or plan

3 to add renewable resources?

4 A No.

5 Q And if you know -- I am skipping around a

6 bit. Let's go back to the standard rebate. Do you

7 know how much or what percent of the RESA is absorbed

8 by the standard rebate payments?

9 A Well, in the beginning, when our payments

10 were about $2 on the standard rebate and $2.50 and/or

11 2.25 on the REC payment it was almost half that was

12 going to that. Now, because the REC payment is lower,

13 it should be a higher percentage that's going to that

14 standard rebate.

15 A.L.J. JENNINGS-FADER: I'm sorry,

16 Counsel. Ms. Hyde, just so that I am clear, meaning

17 that, at present, more than 50%? The standard rebate

18 payments consume more than 50%?

19 THE WITNESS: Right.

20 A.L.J. JENNINGS-FADER: I had a hard time

21 trying to understand what you were saying.

22 THE WITNESS: Because I was thinking out

23 loud. Okay. So we make, to the average residential

24 customer, a payment that involves two pieces, a REC

25 payment and a standard rebate. So, when we first


206
1 started the program, we were making a $2 standard

2 rebate offer, and, then, about a $2.25 or 2.50 REC

3 payment, both made upfront. And, so, a little bit less

4 than half, $2, of that 4.50, was the standard rebate.

5 Now, since, on an equivalent basis, the

6 REC payment is down to just under 55 cents and the

7 standard rebate is still at $2, $2 is a higher

8 percentage of 2.55, that $2 was at 4.50 -- I was trying

9 to get to a customer -- to a customer, right now, the

10 standard rebate is the bulk of the money that they are

11 getting.

12 A.L.J. JENNINGS-FADER: And, Mr. McGann.

13 I am unclear whether that answered your question. But

14 that's okay. Was the question in terms of payments

15 made to retail customers?

16 MR. McGANN: Yes.

17 A.L.J. JENNINGS-FADER: Thank you.

18 MR. McGANN: Your Honor, may I have a

19 moment?

20 A.L.J. JENNINGS-FADER: (Nodding head in

21 the affirmative.)

22 (Discussion off the record.)

23 MR. McGANN: Nothing further, Your Honor.

24 A.L.J. JENNINGS-FADER: First, just a

25 housekeeping matter, please. Ms. Hyde, be sure that


207
1 you leave all marked exhibits up at the front. Thank

2 you. But that aside, ma'am, I would like to thank you

3 very much for your testimony. And it's been extremely

4 helpful. Thank you so much.

5 THE WITNESS: Thank you.

6 A.L.J. JENNINGS-FADER: And you are

7 excused, at least for the moment. You may be subject

8 to recall, depending on your attorneys. Public Service

9 have anything further?

10 MR. DOUGHERTY: Nothing further.

11 A.L.J. JENNINGS-FADER: I am going to ask

12 this, because I just want to have the record clear,

13 Tri-State, I understand that you are offering no

14 witnesses with respect to this reopened proceeding; is

15 that correct.

16 MR. DOUGHERTY: We are not presenting any

17 affirmative witnesses, but we reserve our right to

18 present a rebuttal witness, Your Honor.

19 A.L.J. JENNINGS-FADER: In that event, I

20 believe that Trinchera Ranch is the only other party to

21 indicate an interest in presenting a witness.

22 Mr. Flanagan and Mr. Douglas or Mr. McDonald, how do we

23 proceed?

24 MR. DOUGLAS: Your Honor, Trinchera Ranch

25 would call Mr. James Dauphinais at this time.


208
1 A.L.J. JENNINGS-FADER: Thank you. Good

2 afternoon.

3 (Whereupon James R. Dauphinais was

4 sworn.)

5 A.L.J. JENNINGS-FADER: Thank you, sir.

6 Please have a seat. Move what was marked -- those

7 marked exhibits off to the side, if that would be more

8 convenient for you. And, Mr. Dauphinais, since you

9 have testified earlier in this proceeding, I will not

10 ask for the spelling of your name, but rather turn it

11 over to your counsel.

12 THE WITNESS: Mr. Douglas.

13 MR. DOUGLAS: Thank you, Your Honor.

14 DIRECT EXAMINATION

15 BY MR. DOUGLAS:

16 Q Mr. Dauphinais, could you please state

17 your name for the record and spell your name?

18 A James R. Dauphinais, D-a-u-p-h-i-n-a-i-s.

19 Q And Mr. Dauphinais, you have previously

20 testified in this docket; is that correct?

21 A That is correct.

22 Q Okay. And given that I am not going to

23 go back through all of the qualifications and things

24 that were presented previously, I will just get right

25 to it.
209
1 Mr. Dauphinais, one of the issues that we

2 have been discussing today, and is the subject of this

3 re-opened hearing, is a new statute, House Bill

4 10-1001, I would like to start by asking you first, are

5 you familiar with that statute?

6 A Yes, I am.

7 Q Okay. And what -- and Ms. Hyde talked

8 about some of the provisions in that statute. So, I am

9 not going to ask you to reiterate what we have already

10 heard about. But how does, in your opinion, based on

11 your understanding, how does House Bill 10-1001 differ,

12 in any significant respect to this docket, from the

13 previous Renewable Energy Standard statute?

14 A It enlarges the minimum amount of RECs

15 that are necessary in total, and the minimum amount of

16 RECs necessary for distributed generation and also for

17 retail distributed generation versus the previous act.

18 And it also does -- it also reduces the

19 amount of in-state bonus that should be applicable to

20 on-site solar, that is eliminated. And lastly, it

21 doesn't change the 2% retail rate cap.

22 Q Okay. And in your opinion, do those

23 changes -- those areas you have identified, in House

24 Bill 10-1001, impact Public Service's future resource

25 acquisitions in the San Luis Valley?


210
1 MR. SOPKIN: Your Honor, I object. I

2 know Mr. Douglas began with, we are not going to go

3 over your qualifications again, but, as I understand

4 Mr. Dauphinais' qualifications, it's in relation to

5 being a transmission engineer. So, I do not believe

6 that his qualifications have been established as to

7 resource planning issues. And if you would like, I can

8 conduct voir dire on that matter.

9 A.L.J. JENNINGS-FADER: I would.

10 MR. SOPKIN: Thank you.

11 VOIR DIRE EXAMINATION

12 BY MR. SOPKIN:

13 Q Good afternoon, Mr. Dauphinais. Nice to

14 see you again.

15 A Good afternoon.

16 Q Mr. Dauphinais, you submitted an Appendix

17 A to your original Answer Testimony in this case way

18 back when. And, Your Honor, if I may, I believe this

19 is part of Exhibit 33, which is what Mr. Dauphinais'

20 Answer Testimony was. So, we can either try to dig for

21 that, or I happen to have a copy here of the Appendix A

22 that I could just hand to the witness.

23 A.L.J. JENNINGS-FADER: That would be

24 easier, I believe. And that was Exhibit 33?

25 MR. SOPKIN: May I approach, Your Honor?


211
1 A.L.J. JENNINGS-FADER: You certainly

2 may. Thank you.

3 MR. SOPKIN: Does it need to be marked?

4 A.L.J. JENNINGS-FADER: That's all right.

5 It's already in the record.

6 BY MR. SOPKIN:

7 Q Mr. Dauphinais, do you have what is

8 marked as "Appendix A", "Qualifications of James R.

9 Dauphinais"?

10 A That is correct.

11 Q And am I correct that these are the

12 qualifications that you submitted as part of your

13 Answer Testimony in this matter?

14 A This is not all of the qualifications

15 that were provided in my Answer Testimony.

16 Q Okay. And am I correct that this is the

17 complete Appendix A to your Answer Testimony?

18 A Which is an extension of other discussion

19 of my qualifications, which was in the body of my

20 Answer Testimony.

21 Q Okay. Fair enough. Let's go over this

22 document. If I'm reading this correctly, you have an

23 associate's degree in electrical engineering technology

24 from Hartford State Technical College in 1983, correct?

25 A That is correct.
212
1 Q And, then, you were employed by the

2 Transmission Planning Department of Northeast Utilities

3 Company as an engineering technician for some time, and

4 then you went on to graduate, in 1990, at the

5 University of Hartford, with a bachelor's degree in

6 electrical engineering; is that correct?

7 A That is correct.

8 Q And while you worked at the, I believe

9 the same place, the Northeast Utilities Service

10 Company, you were an associate engineer, then you

11 became a senior engineer?

12 A That is correct.

13 Q And then, during your tenure there, you

14 worked on thermage voltage and stability analyses. And

15 I am turning to page 2 now. You worked from 1990 to

16 1997, representing Northeast Utilities on the New

17 England Power Pool Stability Task Force. And, then,

18 you also, turning to the next paragraph, you were

19 responsible for oversight of the day-to-day

20 administration of Northeast Utilities Open Access

21 Transmission Tariff; is that correct?

22 A That's correct.

23 Q Okay. And, then, in 1997, you joined the

24 firm of Brubaker & Associates, and there you've

25 testified on a number of matters, correct?


213
1 A That is correct.

2 Q Okay. In terms of resource planning

3 matters, you identity -- correct me if I am wrong --

4 during your deposition, that you testified before three

5 state commissions on resource planning issues in

6 adjudicatory type of cases like this one; is that

7 correct?

8 A That is correct.

9 Q Okay. And I believe, in fact, it was

10 identified in a filing here, those three cases -- in a

11 filing by Trinchera Ranch -- that you testified to.

12 One case was -- you filed February 29th, 2008, Direct

13 Testimony on behalf of NIPSCO Industrial Group before

14 the Indiana Utility Regulatory Commission. On March

15 24th, 2008, you filed Direct Testimony, again, on

16 behalf of the NIPSCO Industrial Group, at the State of

17 Indiana Utility Regulatory Commission.

18 And, then, I guess it was, previous to

19 that, September 14th, 2007, you also filed testimony in

20 the fall of -- excuse me -- in the fall of 2007, you

21 filed some testimonies before the Louisiana Public

22 Service Commission; is that correct?

23 A That is correct.

24 Q Okay. And I don't know that I need to

25 introduce your testimonies. I certainly have a copy of


214
1 your direct testimonies, and in each of these, if you

2 want to refresh your recollection. But let me just ask

3 you, starting with your Indiana -- the testimony you

4 filed with the State of Indiana Utility Regulatory

5 Commission, on March 24, 2008, you testified on behalf

6 of a industrial group that a utility did not show that

7 its proposed wind PPAs represent the least-cost option;

8 that there was a transmission congestion cost risk to

9 the wind power; wind generation would have a net

10 present value cost rather than benefit to the utility;

11 and the wind PPAs did not reasonably provide the option

12 for the utility to require the wind facilities to seek

13 network resource interconnection service from the

14 Midwest Independent Transmission System Operator. Is

15 that the gist of your testimony in that case?

16 A That's generally correct.

17 Q And, then, the second testimony we refer

18 to, again, before the Indiana Utility Regulatory

19 Commission, February 29th, 2008, you testified on

20 behalf of an industrial group to present its concerns

21 concerning the utility's request for a CPCN for a

22 535-megawatt gas combined cycle unit. Specifically,

23 you testified that the utility justified the economics

24 of that gas facility on the basis of using natural gas

25 as a fuel, but the utility indicated it might use


215
1 synthetic natural gas as a fuel, and the utility did

2 not show how it would hold ratepayers harmless from the

3 fact that capacity and energy from the combined cycle

4 unit was committed to PGN through May 31, 2010. Is

5 that the gist of your testimony in the case?

6 A That's correct.

7 Q And, then, before the Louisiana Public

8 Service Commission, in 2007, you testified on behalf of

9 an energy user's group to present its concerns --

10 excuse me -- its concerns regarding a utility CPCN

11 application to power the Little Gypsy Unit 3 plant with

12 Petroco. You opined that the net present value benefit

13 of the proposed Little Gypsy Unit 3 plant was

14 overstated versus a gas combined cycle unit, in part,

15 because you thought the utility's analysis downplayed

16 the risk of future carbon emission costs. Is that

17 accurate?

18 A Yes. There was no carbon emission cost

19 in their analysis.

20 Q Okay. But I believe there was a

21 sensitivity analysis performed with regard to carbon,

22 correct, in that case?

23 A Yes. But they didn't rely on that for

24 their cost/benefit analysis in their initial direct

25 case.
216
1 Q Okay. And in all three of those cases,

2 no party challenged your qualifications to testify on

3 the matters you testified to?

4 A That is correct.

5 Q And you have never testified to a utility

6 commission regarding a utility's compliance with a

7 Renewable Energy Standard or Renewable Portfolio

8 Standard, correct?

9 A I have not testified. I have other

10 involvement with those issues, but I have not

11 testified.

12 Q Okay. You are not an economist, correct?

13 A Beyond the application of economics to

14 regulatory matters, that's in rate matters and rate

15 design, I have experience in that, but I am not an

16 economist.

17 Q You have no degree in economics?

18 A That is correct.

19 Q And you have never personally used the

20 Strategist utility plan model that Public Service has

21 used in its resource planning cases before the Colorado

22 Public Utilities Commission?

23 A Not the Strategist model. The Strategist

24 is not the only model used out there and not all

25 utilities use models of that sophistication for the


217
1 resource plan.

2 Q You do acknowledge that the Strategist

3 model is somewhat different from those other production

4 sim models?

5 A Beyond the production cost simulator,

6 yes.

7 Q Okay.

8 MR. SOPKIN: Your Honor, that completes

9 my voir dire. If you like, I can state our objection

10 at this point.

11 A.L.J. JENNINGS-FADER: You may.

12 MR. SOPKIN: Public Service had not

13 contested Mr. Dauphinais' qualifications to testify to

14 transmission line engineering and planning matters in

15 this case. Public Service has no objection to

16 Mr. Dauphinais testifying to matters within his

17 expertise, such as the existing transmission system,

18 and in the San Luis Valley, with some tweaks, can

19 accommodate up to 185 megawatts of export capacity. I

20 believe that was, in fact, listed in his expected

21 testimony.

22 Public Service does not object to

23 Mr. Dauphinais' proposed testimony in the first notice

24 of witness testimony, because it was understood to be

25 within his expertise. And in that first notice of


218
1 witness testimony, there's just one sentence listed

2 there for Mr. Dauphinais' testimony with regard to the

3 impact of the House Bill 10-1001. I am referring to

4 page 3 of that document, paragraph 6.

5 "Mr. Dauphinais will testify regarding

6 the impact of the 30% Renewable Energy Standard on

7 resource acquisition in the Colorado Energy Resource

8 Zones, and the effect of such acquisitions on the

9 ability and appropriateness of the project and various

10 alternatives to meet the needs identified for the

11 project as effected by House Bill 10-1001."

12 Based on the testimony that

13 Mr. Dauphinais had given previously, based on his CV,

14 based on his testimonies, we did not believe that

15 Mr. Dauphinais had expertise with regard to energy

16 resource planning matters. And, so, we did not object.

17 We believe that the fact that he did not

18 identify, in the first notice of witness testimony, in

19 that paragraph 6, anything about RESA dollars, the 2%

20 cap, the 3% DG requirement, we thought that it was

21 going to be high level testimony simply about how the

22 30% RES affects the need for the transmission line

23 project, and not get into these various resource

24 planning issues.

25 His testimony in former cases, in other


219
1 states, do not compare different kinds of renewable

2 resources, which is what he wants to do in this case.

3 In any case, no one challenged his expertise in those

4 cases, so the question was never reached. He's not an

5 economist. His expertise in this case on resource

6 planning matters consists of reading pleadings in this

7 case and the resource planning cases which his

8 expertise might bootstrap.

9 Public Service requests that

10 Mr. Dauphinais not be permitted to testify regarding,

11 No. 1, the comparison of the economics and future

12 economics of different types of renewable resources;

13 and, No. 2, whether Public Service can comply with the

14 2% retail rate impact cap in the future, given the 3%

15 DG set-aside and the increased RES to 30%.

16 A.L.J. JENNINGS-FADER: Let's state the

17 second issue again, please.

18 MR. SOPKIN: Yes.

19 A.L.J. JENNINGS-FADER: The second.

20 MR. SOPKIN: The second matter to which

21 we object.

22 A.L.J. JENNINGS-FADER: Yes.

23 MR. SOPKIN: Whether Public Service can

24 comply with the 2% retail rate impact cap in the

25 future, given the 3% DG set-aside at this point in


220
1 time, and increased renewable energy standard to 30%.

2 This is based on the law that if a person doesn't have

3 the requisite expertise, then they do not assist the

4 trier-of-fact with regard to the issues.

5 A.L.J. JENNINGS-FADER: Thank you.

6 MR. SOPKIN: May I sit down, Your Honor?

7 A.L.J. JENNINGS-FADER: You may. If I

8 have any further questions, I will be happy to speak to

9 you from the counsel table. Mr. Douglas.

10 MR. DOUGLAS: Thank you, Your Honor.

11 Your Honor, I do have a, with Your Honor's indulgence,

12 a few follow-up questions to Mr. Sopkin's voir dire,

13 but I will save argument to after we do that. How

14 about that?

15 A.L.J. JENNINGS-FADER: You certainly may

16 ask your questions, and then present the argument.

17 MR. DOUGLAS: Thank you, Your Honor.

18 DIRECT EXAMINATION (CON'T)

19 BY MR. DOUGLAS:

20 Q Mr. Dauphinais, you mentioned that, in

21 addition to Appendix A, in your previously filed

22 written testimony, in this case, which is Exhibit 33,

23 that there was additional information about your

24 educational background and experience in that exhibit;

25 is that correct?
221
1 A Yes.

2 Q Okay. Do you have Exhibit 33 in front of

3 you?

4 A I don't have a copy in front of me.

5 A.L.J. JENNINGS-FADER: Unless you have a

6 copy, Counsel, Mr. Dauphinais, excuse me -- Dauphinais,

7 I will try to get that straight. Behind you, I think,

8 there are all of the exhibits. And I think they are

9 numerical. You should be able to find it close to the

10 number 33. Thank you, sir.

11 All right, Mr. Douglas.

12 MR. DOUGLAS: Thank you, Your Honor.

13 BY MR. DOUGLAS:

14 Q Mr. Dauphinais, do you now have Exhibit

15 33 in front of you?

16 A Yes, I do.

17 Q All right. If you would turn to -- I

18 said it's the fourth page of the exhibit, but it's

19 listed as page 2. Do you see that?

20 A Yes, yes, I do.

21 Q Does that include the information that

22 you were referring to?

23 A Yes, it does.

24 Q Okay. And can you tell me what

25 additional information about your background and


222
1 experience was contained in that Direct Testimony in

2 this case?

3 A It indicated that I have testified in the

4 past in regard to resource planning, among many other

5 issues.

6 Q Okay. And just so we can get oriented on

7 the record with those areas, I am just going to read

8 from line 13: "Since my employment with BAI, I have

9 testified before the Federal Energy Regulatory

10 Commission, FERC, and many state commissions on a wide

11 variety of issues, including but not limited to avoided

12 cost calculations, certification of public convenience

13 and necessity, fuel adjustment clauses, interruptible

14 rates, market power, market structure, prudency,

15 resource planning, standby rates, transmission losses

16 and transmission planning." Is that an accurate

17 statement?

18 A Yes.

19 Q And you were asked by Mr. Sopkin about

20 three specific proceedings in which you provided

21 written testimony that he was referring to, relating to

22 resource planning issues. Do you recall talking to him

23 about that?

24 A Yes.

25 Q All right. And did you present anything


223
1 other than written testimony in those cases?

2 A I presented oral testimony. I was

3 subject to cross examination.

4 Q Okay. And, Mr. Sopkin briefly summarized

5 your testimony in those cases. But is it correct that

6 all three of those proceedings, the subject of your

7 testimony related to resource planning issues?

8 A Yes. Those specific proposals, yes.

9 Q And in addition to providing testimony in

10 those three cases, about resource planning issues, have

11 you been involved in any other cases with resource

12 planning issues?

13 A Yes, I have.

14 Q Okay. Can you tell me about that?

15 A Yes. On behalf of the Louisiana Energy

16 Users group, I participated in a stakeholder group that

17 oversaw a study of retirement -- investigating the

18 retirement of Entenergy's older units. Entenergy is a

19 proper name. It's spelled, E-n-t-e-n-e-r-g-y.

20 Entenergy is a multi-state utility in the middle south

21 portion of the country. The study was done pursuant to

22 a settlement agreement before the Louisiana Public

23 Service Commission.

24 The stakeholder group basically worked

25 with the commission staff, with representatives from


224
1 Entenergy, representatives from independent generators

2 and representatives from large industrial users, which

3 was the role I served. In that stakeholder group, we

4 went through, in detail, all of the assumptions that

5 would be utilized for that study. We reviewed the

6 initial results of that study. We provided input on

7 those results. We provided input on the report for

8 that study, and I filed comments on behalf of the

9 Louisiana Energy Users Group before the Louisiana

10 Commission in regard to that study.

11 I have also been involved in another

12 stakeholder group, involving resource planning

13 analysis. Also, I'm sorry. This involved a utility in

14 Missouri, called Ameren UE. That's spelled

15 A-m-e-r-e-n, capital U, capital E, one word. It

16 involved another study, a resource planning study that

17 was part of a Settlement Agreement, this time before

18 the Missouri Public Service Commission. It involved

19 doing an analysis to compare the benefits to Ameren UE

20 for participation in the midwest ISO, the Southwest

21 Power Pool, or nonparticipation in the regional

22 transmission organization. Once again, very detailed

23 study. We had a -- we worked through assumptions as a

24 group. That, in the group there was a -- the Missouri

25 commission staff, the Office of Public Counsel of


225
1 Missouri, Entenergy and Ameren UE representatives. And

2 we basically went through, picked an independent

3 consultant to do the study, went through all of the

4 detailed assumptions, which included going through cost

5 assumptions, and identifying possible sensitivities on

6 different resource portfolios that Ameren UE might

7 utilize going-forward. And basically, once again, I

8 was involved in the preliminary results, providing

9 comments on that, providing comments on the draft

10 report.

11 In that case, we ultimately ended up with

12 a settlement, so there was no need to present

13 testimony. There was agreement on the outcome of the

14 results of that study.

15 Q Do you consider yourself an expert in

16 resource planning?

17 A Yes, I do.

18 Q And you mentioned -- or Mr. Sopkin asked

19 you about the Strategist model that's used by Public

20 Service, and I think you mentioned that there are --

21 that's one of a number of models used in the industry.

22 Do you have familiarity with any of the other models?

23 A I am familiar with the PacifiCorp --

24 that's spelled P-a-c-i-f-i, capital C-o-r-p. It's a

25 utility with service territory in several states in the


226
1 west, including Wyoming, Oregon, California, Idaho, and

2 Utah. I may have missed a state there.

3 They have a proprietary software package

4 where they look at optimization of different

5 portfolios, and trying to pick out what portfolio works

6 best and what is the pros and cons for each of the

7 portfolios.

8 Q And were you familiar with the Strategist

9 model used by Public Service prior to your work on this

10 case?

11 A I was aware it was used by a few other

12 utilities.

13 Q Had you ever any reason to review any

14 resource plans that had used that model prior to this

15 case?

16 A I reviewed the resource plans -- well,

17 not using Strategist in particular, no. I reviewed

18 PacifiCorp's integrated resource plan on behalf of the

19 client group -- or a specific client, actually a large

20 end-use customer in the State of Utah. And I have, in

21 other work in Louisiana, have reviewed the strategic

22 resource plan of Entenergy, which they didn't use

23 Strategist. They used another method to, basically,

24 weigh the pros and cons of different resource portfolio

25 approaches.
227
1 Q And another issue that Mr. Sopkin asked

2 you about is implementation of a renewable energy

3 portfolio or Renewable Energy Standard statute. Do you

4 have experience as an expert in other matters relating

5 to that issue?

6 A Yes. While I haven't testified in regard

7 to that issue, I provided assistance to the Missouri

8 Industrial Consumers Group in the State of Missouri.

9 Many them are customers of Ameren UE, and the questions

10 are with regard to the controversy that has arisen over

11 the implementation of the rate cap that was associated

12 with the renewable portfolio standard that was passed

13 through a ballot initiative in the State of Missouri.

14 Q And when you say the "rate cap," that was

15 part of the Missouri renewable energy portfolio

16 statute. Is that something -- is that a similar

17 concept to the retail rate impact cap that we've been

18 discussing here today?

19 A Broadly, yes.

20 Q Okay. Do you have any experience in the

21 area of renewable energy technology?

22 A Only in regard to being able -- in regard

23 to understanding how to apply the cost information and

24 the capacity information, the time-of-delivery type of

25 information, very similar information to what's needed


228
1 for the transmission planning, the difference being

2 cost also comes into play.

3 Q As far as the cost of the renewable

4 energy technology, have you testified in any proceeding

5 that involved the analysis of the cost of those

6 technologies?

7 A Only in regard to -- in the Indiana case,

8 I examined the cost of the facility that was proposed

9 versus possibly other alternative sites for wind farms.

10 Q Okay. Cost in relation to resource

11 planning?

12 A Correct.

13 MR. DOUGLAS: Your Honor, I don't have

14 any other voir dire questions. I would point out that,

15 well, first of all, I believe, in the areas that

16 Mr. Sopkin identified, that Mr. Dauphinais has

17 significant experience with resource planning, as it

18 relates to -- and I should also say, that the extent to

19 which we're going into resource planning is somewhat

20 limited, and Mr. Dauphinais has far more than enough

21 experience to testify and give opinions about the

22 issues that we've been discussing all day today that

23 are the subject of this reopened hearing. He's

24 provided expert testimony in multiple proceedings

25 involving resource planning, involving renewable


229
1 technologies, and the costs of those technologies.

2 He's been involved in stakeholder proceedings involving

3 those same issues by his clients, and in implementing

4 the interpretation of renewable energy statutes. And

5 he did, in fact, in his original testimony in this

6 case, list resource planning as an area of expertise

7 and something that -- about which he provided testimony

8 in other proceedings.

9 In addition, I'm at a loss as to why

10 Mr. Sopkin is focusing on the first notice of

11 Mr. Dauphinais' written testimony. There are two, and

12 in the second notice of witness testimony, there was

13 detail about the amended RES and the 2% retail rate

14 impact cap, and all of the things that we've been

15 talking about today. And Public Service did not raise

16 any issue in its motion in limine directed at that

17 second notice, with regard to the expertise of

18 Mr. Dauphinais. But I think it's pretty clear, from

19 the testimony Mr. Dauphinais has given today, that he's

20 qualified in these areas.

21 A.L.J. JENNINGS-FADER: Mr. Sopkin,

22 anything further?

23 MR. SOPKIN: Only, Your Honor, that I

24 specifically asked, in discovery, for all testimonies

25 Mr. Dauphinais has given, at any regulatory proceeding,


230
1 with regard to his expected witness testimony. And

2 there was listed five proceedings, two in Texas, two in

3 Indiana, and one in Louisiana. And the only cases

4 identified, I believe, during his deposition, related

5 to resource planning, were the two Indiana and

6 Louisiana.

7 Now we suddenly hear about a Missouri

8 case that I never heard of, and I think it's unfair to

9 talk about that now, when I didn't get a chance to ask

10 him about it during the deposition or in previous

11 witness testimony. That's the only case in which he's

12 alleged there is any testimony about some type of

13 renewable energy standard. I don't believe any of

14 that, of the other experience he's talked about, gets

15 into such nitty-gritty as how a RESA works, how a

16 resource plan works, how a DG set-aside works.

17 The reason I mentioned the first notice

18 of witness testimony is, as I understand Your Honor's

19 ruling, it appears to indicate that Mr. Dauphinais'

20 expected testimony, as listed in his second notice of

21 witness testimony, is somehow encompassed with the

22 description in the first notice of witness testimony.

23 While we don't believe that's the case, first of all,

24 because it did not list 3% or 2%, and, second, that's

25 the reason why we did not object, is we did not believe


231
1 he had the requisite expertise to go into the

2 nitty-gritty of renewable energy matters.

3 A.L.J. JENNINGS-FADER: Mr. Sopkin, to

4 that last point, why, then, was this issue not raised

5 in greater detail in your second motion in limine,

6 where you did have an opportunity to examine this

7 issue, and, in fact, filed a motion in limine

8 addressing some of these issues, but not raising a

9 question with respect to his expertise?

10 MR. SOPKIN: Because we were going -- I

11 wanted to ask him what his expertise was during his

12 deposition, to find out exactly what it was. And we

13 have since done that, last Wednesday. And I don't

14 believe he's qualified, based on that deposition.

15 MR. DOUGLAS: Your Honor, if I could

16 potentially clear up one point of apparent confusion.

17 A.L.J. JENNINGS-FADER: About the

18 discovery requests or about something else?

19 MR. DOUGLAS: About the Missouri question

20 that Mr. Sopkin raised.

21 A.L.J. JENNINGS-FADER: Yes. Thank you.

22 MR. DOUGLAS: My understanding, based on

23 the testimony today, and since he was exploring the

24 deposition, but maybe there is just some confusion on

25 Mr. Sopkin's part, but I don't believe Mr. Dauphinais


232
1 said there was any testimony involving that renewable

2 energy statute. That was, he provided expert advice to

3 an industrial group about implementation of that

4 statute. So, there's no unfair surprise. There is no

5 testimony, and that was clear. And I don't think we

6 need that, to read it, but that issue, that's exactly

7 what Mr. Dauphinais said in his deposition; that he had

8 advised his client there was no testimony and that was

9 I believe what he testified to today.

10 A.L.J. JENNINGS-FADER: And I think so as

11 well.

12 MR. SOPKIN: I believe, in his

13 deposition, he mentioned Louisiana, but not Missouri,

14 but I could be wrong.

15 A.L.J. JENNINGS-FADER: I believe that


16 Mr. Dauphinais through his testimony with respect to
17 the voir dire this morning or this afternoon has
18 evidence of sufficient background and work in the area
19 of resource planning to testify in the limited areas
20 about which he has been offered in this proceeding. So
21 the objection is overruled, and Mr. Dauphinais may
22 testify with respect to those areas.
23 MR. DOUGLAS: Thank you, Your Honor.
24 BY MR. DOUGLAS:

25 Q All right. Mr. Dauphinais, you had just


233
1 expressed some opinions that are your understanding of
2 how the requirements of House Bill 10-1001 differ from
3 the previous renewable energy standard statute.
4 Do you recall our discussion on that
5 point?
6 A Yes, I do.
7 Q And in your opinion do those changes in
8 House Bill 10-1001 that you discussed impact Public
9 Service's future resource acquisitions in the San Luis
10 Valley?
11 A I believe they make those acquisitions
12 less likely.
13 Q Okay. And why do you believe that?
14 A A couple of reasons. One is that the
15 minimum requirements have been raised for renewable
16 energy for RECs for Public Service have been raised to
17 30 percent of retail electric sales in general, but,
18 more importantly, in the area of retail distributed
19 generation requirements they have effectively gone up
20 five times.
21 Before you had a solar on-site
22 requirement that was basically half of four percent of
23 20 or .4 percent of retail electric sales, and that is
24 going up to 1 1/2 percent of retail electric sales.
25 Moreover, previously the 25 percent
234
1 in-state bonus could apply to the solar in state. The
2 5 percent in-state bonus cannot apply under the new Act
3 to retail distributed generation. So effectively we
4 get almost a five time increase in the amount of RECs
5 that are needed from retail distributed generation.
6 You have those two things that have
7 increased. You have no increase in the retail rate
8 cap. So that puts down -- that puts pressure on the
9 amount of dollars that are available for renewable
10 resources.
11 And you combine that with the fact that
12 solar thermal generation with storage is an expensive
13 renewable resource, it makes it, in my opinion,
14 unlikely that we will see, for example, the three
15 250-megawatt placeholders.
16 Q And how does that affect, in your
17 opinion, how do those changes, in your opinion, affect
18 the stated need for the proposed project by Public
19 Service?
20 A One of the stated needs for the proposed
21 project was to accommodate future, I think they termed
22 it renewable resources, not just solar resources, but
23 out of the San Luis Valley area. That was at least
24 part of the basis of need.
25 As far as the San Luis Valley side, one
235
1 of the justifications and needs was to support exports
2 of renewable resources from the San Luis Valley area.
3 Q All right. You were present in the
4 courtroom when Ms. Hyde testified that, in fact, Public
5 Service can meet the minimum REC requirements of House
6 Bill 10-1001, the nondistributed generation
7 requirements, without adding any central solar
8 resources beyond the ones that are discussed in the
9 2007 resource plan as proposed to be amended through
10 2029.
11 You heard that testimony, correct?
12 A Yes, I did.
13 Q Okay. Have you reviewed the documents
14 produced by Public Service that go through its modeling
15 or forecasting of that compliance with House Bill
16 10-1001 through 2030?
17 A Yes, I have.
18 Q Do you agree with Ms. Hyde that Public
19 Service will be able to comply with the requirements of
20 that House Bill through 2029 without any additional
21 solar resources in the San Luis Valley beyond the ones
22 in the 2007 resource plan as proposed to be amended?
23 A Yes, I think she indicated there was a
24 small gap in distributed generation. So we might see a
25 little distributed generation happen, but otherwise it
236
1 is fully complied with.
2 Q Okay. Through 2029; you agree with that?
3 A Yes.
4 Q And does that, in your opinion, have any
5 impact on the likely future acquisition of additional
6 generation resources in the San Luis Valley in the
7 future?
8 A There is no pressing need for the
9 addition of renewable resources in the San Luis Valley
10 if the economics support it with the money that comes
11 from the RES under the retail rate cap, it is in line.
12 Q So taken together what is your opinion
13 about the likelihood that the three solar thermal
14 placeholder resources that have been discussed in light
15 of House Bill 10-1001 and those projections and all of
16 this information whether that likelihood has changed
17 since your prior testimony in this case in February of
18 this year?
19 A I think that likely -- that it has become
20 less likely that those resources will be pursued.
21 Q Now, you also, you mentioned some of the
22 changes in the distributed generation requirements.
23 And do you have a specific opinion about
24 whether those changes in and of themselves may affect
25 future valuable RESA dollars for other renewable
237
1 resources?
2 A Yes.
3 Q What is that opinion?
4 A The opinion is that it could adversely
5 affect. As I indicated earlier, it was a four-time,
6 over four-time increase in the amount that is needed or
7 the minimum requirement.
8 While there are some provisions in the
9 Act that provide some potential safety valves on that,
10 we have no idea at this time whether if, for example,
11 Public Service pursued those, whether those would be
12 granted into and to what degree they would be granted.
13 Q Okay. And you heard Ms. Hyde testify
14 today about those provisions, and her belief that at
15 least to some extent those provisions may reduce the
16 additional cost of the distributed generation from the
17 new statute.
18 Do you recall that testimony?
19 A Yes, I do.
20 Q Okay. Do you agree with Ms. Hyde on that
21 issue?
22 A I am sorry. I lost my focus for a
23 minute. Can you repeat the question?
24 Q On the issue of whether or not those
25 changes in the new House Bill in the way I believe she
238
1 specifically mentioned that the fair share provision
2 collection and the reduction of standard rebate may
3 affect future RESA dollars, it is her opinion that
4 those changes may increase available RES dollars in the
5 future.
6 Do you have an opinion about that?
7 A I don't. It is not clear to me how that
8 can happen since all of those mitigation measures are
9 designed to really mitigate the cost from the
10 distributed generation.
11 Q Okay. I think my question was a little
12 unclear.
13 Do you agree or disagree with Ms. Hyde's
14 testimony on that point?
15 A I disagree.
16 Q And can you explain why you disagree?
17 A The provisions that exist, those safety
18 valve provisions or tools as the way Ms. Hyde referred
19 to them, are designed, appeared to be designed
20 primarily to mitigate the cost for the RECs provided
21 through distributed generation, specifically retail
22 distributed generation. I don't see how they can be
23 used to provide additional dollars beyond just
24 neutralizing maybe the cost of retail distributed
25 generation.
239
1 Q Okay. So your opinion is that at best
2 those expenses are countered against RES relating to
3 retail distributed generation will stay the same based
4 on the implementation or potential implementation of
5 those safety valves?
6 A They would help neutralize the cost for
7 retail distributed generation.
8 Q Okay. But not provide additional RES
9 dollars in the future?
10 A That's correct.
11 Q Okay. Have you done any modeling or
12 quantification of the potential impact of the changes
13 to the way retail distributed generation dollars are to
14 be collected by Public Service to look at that impact
15 in the future?
16 A No, I have not performed any quantitative
17 analysis.
18 Q All right. I want to change gears now
19 and talk about the verified application to amend the
20 2007 Resource Plan that is the other subject of this
21 reopen hearing.
22 Do you have an opinion about the impact
23 on the need for new transmission out of the San Luis
24 Valley if the Commission approves any one of the 60, 90
25 or 185 megawatt, the options set out in Public
240
1 Service's application to amend that resource plan?
2 A Yes, I do.
3 Q Okay. What are those opinions?
4 A The 60, 90, 185 megawatt generation
5 resource options represented in that application can
6 all be supported with the up-rate of the 115 KB line
7 that Public Service has proposed. It would not need to
8 be a second 230 KB transmission line into the valley to
9 support the export of those level of power from the San
10 Luis Valley.
11 Q And when you mention the up-rate to the
12 115 line, you are referring specifically to the minor
13 upgrade that is discussed by Public Service in the
14 amendment itself?
15 A Yes, the raising of towers, the number of
16 towers.
17 Q Okay. And how much additional transfer
18 capability would that provide?
19 A The company estimates 25 to 35 megawatts
20 and based on my review of the material provided in
21 discovery that appears to be reasonable.
22 Q Okay. So you agree then with Public
23 Service, and I believe Ms. Hyde testified about this
24 today, that no new transmission line is needed out of
25 the San Luis Valley to accommodate any of those three
241
1 options set forth in Public Service's application to
2 amend?
3 A That's correct.
4 MR. SOPKIN: Objection. Leading.
5 A.L.J. JENNINGS-FADER: Could you
6 rephrase? Thank you.
7 Q You were present in the courtroom when
8 Ms. Hyde testified about whether a new line would be
9 needed to accommodate any of the three options that are
10 discussed in Public Service's application to amend its
11 2007 resource plan?
12 A Yes, I was.
13 Q Okay. And do you agree with Ms. Hyde's
14 testimony on that subject?
15 A Yes, I do.
16 Q And what is your recollection of that
17 testimony?
18 A My recollection is she indicated that the
19 60, 90, 185 megawatt levels could be supported without
20 the addition of a new transmission line out of the San
21 Luis Valley.
22 Q Okay. All right. Now, what about Public
23 Service's testimony about future resources beyond the
24 2007 Resource Plan as amended, do you have an opinion
25 about whether the proposed project is needed to
242
1 accommodate those resources or any such resources?
2 A I don't believe it is necessary to
3 accommodate the three 250-megawatt placeholders, but I
4 believe the likelihood of them has decreased based on
5 the application that was filed and other information
6 that has been discussed today in regard to the 2010
7 compliance filing assumptions and the changes to some
8 of those economic considerations that were behind those
9 assumptions.
10 Q Okay. What information leads you to that
11 opinion?
12 A There is four areas. One is in the solar
13 thermal generation facility with storage that Public
14 Service is currently pursuing there has been an
15 increase on a levelized energy cost per basis or per
16 megawatt hour basis of that project enough so that the
17 company itself has presented that to the Commission for
18 consideration on whether the 125 megawatts, never mind
19 the 2,550 megawatt original size of that project,
20 should be pursued.
21 Some of that cost increase has been
22 attributed to a loss of economy of sales, but we have
23 heard two other reasons today which I don't see how
24 could be tied to that. There are three other areas.
25 One is that natural gas price assumptions
243
1 have fallen. We have heard about that in regard to the
2 forecasts for those natural gas prices today versus
3 what was assumed for the 2010 compliance filing.
4 There has been delay in carbon
5 legislation and that has been reflected in the changes
6 to assumptions that Public Service is using. They are
7 now assuming that carbon prices do not kick in until
8 2014 rather than 2010.
9 And, lastly, the demand forecast and also
10 the energy sales forecast of Public Service have
11 continued to fall and have fallen since the 2010
12 compliance filing was put together.
13 Q All right. And we will get into some of
14 the details, but overall how do those four changed
15 circumstances affect the future acquisition of solar
16 resources in the San Luis Valley in your opinion?
17 A I believe they make them much less likely
18 than before, and they were not likely before. They are
19 more speculative than they were before. The premium
20 that needs to be paid for solar thermal generation with
21 storage over a combined cycle gas turbine generation,
22 which is what the company compared it to in the past,
23 that premium has enlarged significantly. It can no
24 longer can be characterized, in my opinion, as being
25 slightly higher.
244
1 There is also other information that I
2 have seen that suggests that the cost for wind
3 generation and for PV generation has fallen, where
4 there is not similar information suggesting the same
5 thing is happening for solar thermal generation for
6 storage.
7 MR. SOPKIN: Objection. I move to strike
8 that answer. That has nothing to do with what this
9 docket has been reopened for. He is talking about the
10 cost of the wind and the cost of PV versus the cost of
11 solar. That is totally outside of Public Service's
12 application to amend its 2007 Resource Plan.
13 The question in this case is, how does
14 that application affect the need for the project? Now
15 Mr. Dauphinais is trying to testify to his own
16 reference perhaps of other sources outside that
17 application to try to cast doubt on solar thermal.
18 If we are going to get into that, I have
19 plenty of evidence. Otherwise, that is a resource
20 planning case, Your Honor.
21 A.L.J. JENNINGS-FADER: Mr. Douglas.
22 MR. DOUGLAS: Your Honor, Mr. Dauphinais'
23 notice of witness testimony included a mention of this
24 and in Your Honor's order there was one -- I can sight
25 to the order if I need to. I have it written down.
245
1 A.L.J. JENNINGS-FADER: Let us look at
2 paragraph 52 --
3 MR. DOUGLAS: Okay. Let us do that.
4 A.L.J. JENNINGS-FADER: -- which
5 requires, specifically identify the subject matter
6 areas about which Mr. Dauphinais may testify other than
7 reliability, which is in paragraph 53.
8 MR. DOUGLAS: All right. I believe it is
9 also paragraph 54. Wait. I am sorry. Hang on just a
10 second. Hang on just one second.
11 Your Honor, this gets a little
12 convoluted, but in paragraph 48 this is, which I kept
13 looking at your ruling on 54, but that is with respect
14 to the testimony specific to the amendment, but
15 paragraph 48 deny the second motion in limine with
16 respect to the supplemented testimony of Mr. Dauphinais
17 and then that supplemented testimony specifically --
18 A.L.J. JENNINGS-FADER: I thought this
19 questioning was going to the second issue.
20 MR. DOUGLAS: Well, there is overlap,
21 Your Honor. And the economic -- I believe the
22 question, I can get back to it, went to comparative
23 cost of different technologies, and that is something
24 that was in the first motion.
25 A.L.J. JENNINGS-FADER: Do you want to
246
1 look at footnote 13 on page 13 of decision number
2 R10-0746-I where we are quoting the specific subject
3 matters identified in the supplement.
4 MR. DOUGLAS: All right. Well, what I am
5 looking at, Your Honor, is page 3 of the notice of
6 witness testimony, the second notice.
7 A.L.J. JENNINGS-FADER: Just a minute.
8 Filed 18th of June. What page?
9 MR. DOUGLAS: Page 3. Paragraph 5(a),
10 about two-thirds of the way down, the sentence starts,
11 He will testify that all of these new RES requirements
12 coupled with the higher cost of solar thermal in
13 comparison to other renewable technologies demonstrate
14 that the three thermal placeholders that were used in
15 large part to justify the need of the project are even
16 more speculative than already established in the prior
17 hearing.
18 A.L.J. JENNINGS-FADER: That addresses
19 part of Mr. Sopkin's objection.
20 The other portion of the objection is,
21 excuse me, the information about which at least as I
22 heard it and about which Mr. Dauphinais is testifying
23 has not to do with Public Service Company but is
24 related to some other unspecified information.
25 Mr. Sopkin, is that correct?
247
1 MR. SOPKIN: Yes, that is correct. And I
2 don't know if it is my time to respond yet.
3 A.L.J. JENNINGS-FADER: I want to be sure
4 that I was clear. There are two pieces to the
5 objection, right?
6 MR. SOPKIN: Yes. It comes from
7 information outside of the application of amendment.
8 A.L.J. JENNINGS-FADER: Thank you.
9 MR. DOUGLAS: Your Honor, I can ask
10 Mr. Dauphinais more foundational questions. I believe
11 it comes from a combination of information from Public
12 Service but then also information from reasonable,
13 relied upon experts in Mr. Dauphinais' field, which
14 would be a proper subject for examination in my
15 opinion.
16 A.L.J. JENNINGS-FADER: Yet another
17 unfortunate intersection.
18 Mr. Sopkin.
19 MR. SOPKIN: Your Honor, look at your
20 Decision Number R10-0746-I at page 12. You reiterated
21 what you stated in the June 14, 2010 e-mail you sent to
22 the parties. Specifically the second paragraph of that
23 the issue to be explored in the instant docket is the
24 impact, if any, on the need for the project in the
25 event the Commission grants the application to amend
248
1 the 2007 Colorado Resource Plan and sets the solar
2 resource acquisition level at 185 megawatts, 90
3 megawatts or at 60 megawatts. The parties may present
4 testimony on the impact on the need for the project of
5 a Commission decision that sets the amount of solar
6 resources to be acquired at one of the stated levels.
7 It was my understanding that the confines
8 of this proceeding in terms of the amendment, the
9 effect of the amended 2007 resource plan is just that
10 the effect of the application to amend the 2007
11 resource plan, not what Mr. Dauphinais has done in the
12 last couple of months about the differences between the
13 cost of different types of renewable resources. That
14 is exactly a resource planning and respondent
15 compliance plan issue that the Commission will decide
16 in future cases in which there will be lot of the
17 stakeholders arguing which renewable resources are
18 better than others.
19 Certainly in a CPC transmission line case
20 we cannot make decisions as to what resources are more
21 cost effective than other resources based on whatever
22 research Mr. Dauphinais has dug up.
23 Honestly, if he goes into this, we will
24 be required to put on a rebuttal expert to go into all
25 of the various forecasts between the cost of solar
249
1 thermal versus the cost of combined cycle gas, versus
2 the cost of the wind, et cetera, et cetera. If we want
3 to do that, that is fine. It is going to make for a
4 long couple of days.
5 A.L.J. JENNINGS-FADER: Mr. Douglas, I
6 noted that your colleague was pointing something out to
7 you.
8 MR. DOUGLAS: Your Honor, brief
9 underscore that the second notice with respect, the
10 supplement of Mr. Dauphinasi's testimony about which
11 there was a motion in limine that was denied was
12 summarized by Your Honor in Footnote 13 of the order to
13 include the likely impact of the amended RES would be a
14 changed focus away from high cost utilities solar
15 thermal resources to lower cost renewable resources.
16 So, again, he is putting it in general
17 context on this. We are not going to be asking for
18 specific findings from the Commission on the cost of
19 different bids and specific technologies, but in
20 general there has been a lot of testimony in this case
21 about these speculative future solar thermal resources,
22 and Mr. Dauphinais believes that things have changed.
23 And this is one of the factors that plays into that and
24 he should be allowed to give that opinion.
25 A.L.J. JENNINGS-FADER: When I read the
250
1 supplement to the supplemental statement of proposed
2 testimony for this witness in the second notice of
3 testimony filed by Cuchara Ranch, I read D which I
4 believe is the portion to which you are referring as
5 stated in Footnote 13 on page 13 of the decision
6 R10-0746-I to be not an investigation of all of the
7 underlying factors which are the province to be more
8 appropriately addressed in resource planning dockets,
9 but rather a general statement as to his opinion that
10 the shift from higher cost, relatively higher cost to
11 relatively lower cost resources reduces the likelihood
12 of additional transfer capability needed out of the San
13 Luis Valley.
14 So the degree to which, Mr. Douglas, you
15 are investigating that question is beyond what I
16 understood would happen in this proceeding.
17 So to that extent I will sustain the
18 objection because it is delving into areas that are
19 more appropriately addressed in other proceedings.
20 MR. SOPKIN: Thank you, Your Honor.
21 MR. DOUGLAS: Your Honor, I don't believe
22 that I asked him the question that you just posed, and
23 if it is permissible, I would be happy to move there.
24 A.L.J. JENNINGS-FADER: I think that
25 would be an excellent question, although ill-framed on
251
1 my part.
2 Q Mr. Dauphinais, I believe you testified
3 about, in general, these economic changes and amended
4 RES and how they will, in your opinion, lead to a shift
5 from higher cost resources to lower cost renewable
6 resources in the future.
7 And my question to you is, how does your
8 opinion about that shift to lower cost resources affect
9 the need to build a transmission line to accommodate
10 additional generation in the San Luis Valley?
11 A It is a lower likelihood that solar
12 thermal generation with storage would be pursued, and
13 the San Luis Valley it is not the only place where that
14 can be, where it has been cited it might be placed as
15 generation. There is certainly the three 250-megawatt
16 placeholders the company has cited there.
17 So with even less, even lower likelihood
18 of those being pursued the need for a second
19 transmission line out of the San Luis Valley has
20 diminished for purposes of supporting exports.
21 Q And you mentioned in your prior answer
22 that the premium, I believe it was your word, in the
23 cost of solar thermal resources over natural gas
24 combined cycle resources, which is how Public Service
25 compared them, how that affects the likelihood of the
252
1 acquisition of these three 250-megawatt solar thermal
2 placeholders that we have been discussing.
3 Can you explain what you mean by that?
4 A Yes, lower natural gas prices create a
5 lower variable cost for producing energy for combined
6 cycle gas turbine generators.
7 Delayed carbon prices or lower carbon
8 prices lead to also lower variable cost for production
9 energy from combined cycle gas turbine generation.
10 So what that does is creates a greater
11 premium in that there is less cost savings provided in
12 terms of energy savings, energy production savings from
13 solar thermal generation with storage versus combined
14 cycle gas turbine generation as natural gas prices and
15 carbon prices assumptions become lower.
16 Q And how does that higher premium, as you
17 say, affect the likelihood that additional transmission
18 will be needed in the San Luis Valley to accommodate
19 future generation?
20 A It decreases the likelihood that solar
21 thermal generation with storage should be pursued
22 similar to the three 250-megawatt placeholders the
23 company has discussed previously, and that decreases
24 the likelihood that there is a need for additional
25 export capability out of San Luis Valley above that
253
1 necessary to support either the 60, 90 or 185 megawatt
2 levels and generation additions that are proposed in
3 Public Service's application to amend its 2007 Resource
4 Plan.
5 Q And you mentioned -- one of the things
6 that you mentioned specifically was the change in the
7 carbon cost assumption.
8 Have you done any quantification of the
9 effect of that change in carbon assumption on available
10 future RES dollars for renewable acquisitions?
11 A No, I have not done my own quantification
12 of that.
13 Q Do you know if Public Service did any
14 quantification on that?
15 A They did in their 2010 compliance, RES
16 compliance plan filing. They performed a sensitivity
17 study and I believe it was discussed this morning by
18 Ms. Hyde.
19 Q And have you reviewed that quantification
20 by Public Service?
21 A Yes, I have.
22 Q And do you have an opinion about what
23 that shows?
24 A That shows that even if they decide after
25 2016 to continue to draw two percent a year through the
254
1 RES, that there will be a negative balance through 2020
2 in terms of the RES balance, the rolling balance.
3 Q And have you done any quantification or
4 modeling of the impact of the change of natural gas
5 forecast that you discussed on future available RES
6 dollars?
7 A No, I have not.
8 Q Mr. Dauphinais, you have given some
9 opinions now about the effect of some changes and you
10 identified House Bill 10-1001, and then also the effect
11 of some economic changes reflected in Public Service's
12 amendment application to amend the 2007 Resource Plan,
13 and also the reduction levels that they are proposing.
14 Do you have an opinion about how overall
15 the need for additional transmission out of the San
16 Luis Valley has been affected by the combination of
17 those effects from House Bill 10-1001 proposed
18 amendment?
19 A The two changes act in concert to make it
20 less likely that there would be a need for additional
21 export capability above the 60, 90 or 185 megawatt
22 levels proposed in the application to amend the
23 resource plan.
24 Specifically, as I discussed, the change
25 to the amendment to the renewable energy standard put
255
1 pressure on such that there is likely to be fewer RES
2 dollars available, and that puts pressure on the
3 company to be even more cost effective than they are
4 right now in regard to applying those dollars, but it
5 may mean there is not enough dollars to pursue
6 additional renewable resources to some degree, and they
7 may count on higher cost resources like solar thermal
8 generation with storage.
9 You have that going on and then we know
10 on the other side from the application to amend the
11 2007 Resource Plan that you basically have a much
12 larger premium showing up for solar thermal generation
13 with storage versus combined cycle gas turbine
14 generation, much larger than originally envisioned.
15 So the combination of the two make it
16 much more unlikely that the three 250-megawatt
17 placeholders for solar thermal generation with storage
18 for San Luis Valley will actually come to be.
19 Q I am sorry. You said makes those three
20 250-megawatt placeholders far less likely?
21 A Less likely, yes.
22 Q Less likely than what?
23 A Less likely than they were before. They
24 were not likely before.
25 Q Okay. And in light of these effects that
256
1 you discussed from both House Bill 10-1001 and the
2 application to amend the 2007 Resource Plan, do you
3 have an opinion about whether constructing the proposed
4 San Luis Valley to Calumet double-circuit 30KB segment
5 of the proposed project would be prudent?
6 A My opinion is that it would not be
7 prudent to pursue that.
8 Q Why not?
9 A There is not a justification of need for
10 that level of export capability that is provided by the
11 project. There are other alternatives available that
12 provide a more phased-in approach to providing any
13 additional export capability that may become necessary
14 in the future to support exports of generation over 60,
15 90 or 185 megawatts.
16 MR. DOUGLAS: If I can have a moment,
17 Your Honor.
18 A.L.J. JENNINGS-FADER: Certainly.
19 MR. DOUGLAS: Your Honor, I have nothing
20 further.
21 A.L.J. JENNINGS-FADER: Mr. Douglas,
22 before you sit down, I believe that the motion that
23 Mr. Sopkin made was a motion to strike the response.
24 And while I granted the motion, I do not believe I was
25 as clear as I should have been that the motion to
257
1 strike is granted and the response to which the
2 objection was made is granted -- I am sorry -- the
3 testimony is stricken. I just wanted to, while you are
4 still there, I just wanted to deliver that
5 pronouncement.
6 MR. DOUGLAS: I appreciate that, Your
7 Honor.
8 A.L.J. JENNINGS-FADER: Okay. Thank you.
9 Now, in the identification of parties
10 that may have cross-examination for this witness the
11 Office of Consumer Counsel indicated that it might have
12 questions.
13 MR. SCHLESINGER: No questions, Your
14 Honor.
15 A.L.J. JENNINGS-FADER: Mr. Nelson, you
16 indicated that you might have some questions.
17 MR. NELSON: Yes, Your Honor.
18 CROSS EXAMINATION

19 BY MR. NELSON:
20 Q Good afternoon, Mr. Dauphinais.
21 A Good afternoon, Mr. Nelson.
22 Q In your testimony, if I understood it
23 correctly, it is your opinion that the passage of House
24 Bill 10-1001 makes the likelihood of solar thermal
25 resources decreased, the likelihood of new solar
258
1 thermal resources; and then, if I understood also
2 correctly, increases the need for resources that are
3 renewable but are not solar thermal, for example, wind.
4 Do I understand your testimony correctly?
5 A I don't think that is quite correct.
6 Q Okay. Let me try to unpack this a little
7 bit.
8 Your testimony was that with House Bill
9 10-1001 there is a higher renewable energy portfolio
10 standard than there was under the previous law.
11 Is that fair?
12 A That is correct.
13 Q Okay. You also testified that because
14 there was a higher requirement but the cost cap was not
15 changed, your opinion was that there would be a
16 systematic shift away from what you described as higher
17 cost resources towards what you described as lower cost
18 resources.
19 Did I understand you correctly?
20 A There was a greater emphasis on being
21 cost effective.
22 Q Would you agree with me that as you
23 understand it and as you have testified today that a
24 wind resource is one of those lower cost resources as
25 you see it?
259
1 A That is a lower cost resource.
2 Q I wanted to talk to you about in a couple
3 of places in your testimony you refer to the proposed
4 project in sort of a generic sense.
5 I would like to talk to you about it in a
6 more specific sense. You recall, do you not, there are
7 three different portions of this proposed project, the
8 transmission line from the San Luis, the Calumet
9 substation -- the Calumet substation and the
10 transmission line from the Calumet substation to the
11 Comanche power plant?
12 A Yes, I recall that.
13 Q Okay. And am I correct that with respect
14 to the Calumet substation and the transmission line
15 from the Calumet substation to Comanche, would you
16 agree that the purpose of that in large part is to
17 increase the transfer capability for wind resources on
18 to the PSCo system and to meet the resource needs of
19 the Front Range in general?
20 A I think that it is a combination of wind
21 and there is possibility of solar there. It is an area
22 that has been identified that is fairly good for solar
23 as well.
24 Q Okay. Focusing on the wind part of the
25 Calumet substation and the transmission line to get
260
1 from the Calumet substation to Comanche, I would then
2 be correct that if it becomes necessary to increase the
3 wind resources on the PSCo system because of the
4 passage of House Bill 10-1001, that that makes that
5 segment even more important than it was before that new
6 law was passed?
7 A I would say that the need for export
8 capability would be a bit higher since that is
9 identified as an area where wind might be cited, yes.
10 Q Okay. So could I take it from that that
11 from a transmission planning perspective, would you
12 agree it is reasonable for the Commission to approve
13 the Calumet substation and the transmission line from
14 Calumet to Comanche to focus only on that portion of
15 that, and would you agree that it is reasonable for the
16 Commission to approve that in part in light of the
17 expanded need for wind resources due to the passage of
18 House Bill 10-1001 that we have just been talking
19 about?
20 A It may be, yes. I have not taken a
21 position on that today, but it may be.
22 Q Okay. Then I will try it this way: At
23 least you have no objections on behalf of Cuchara Ranch
24 for the construction of the Calumet substation and the
25 transmission line from that to Comanche?
261
1 A That is correct.
2 MR. DOUGLAS: Your Honor, I just want to
3 put an objection on the record. I believe that is
4 beyond the scope. I don't believe Mr. Dauphinais has
5 been asked to look at this issue, which means there is
6 no foundation for it either.
7 A.L.J. JENNINGS-FADER: That's correct,
8 since his testimony was expressed to be limited only to
9 the San Luis Valley to Calumet substation.
10 MR. NELSON: The purpose for the question,
11 Your Honor, was that a couple of times during the
12 course of the presentation by Mr. Douglas he referred
13 to the "proposed project."
14 A.L.J. JENNINGS-FADER: I understand.
15 MR. NELSON: I am trying to clarify the
16 position as it relates to that. That was my last
17 question.
18 A.L.J. JENNINGS-FADER: In that event, I
19 will let you take the last answer, and thank you.
20 MR. NELSON: Thank you.
21 A.L.J. JENNINGS-FADER: Thank you,
22 Mr. Dauphinais.
23 A.L.J. JENNINGS-FADER: Ms. Mandel?
24 MS. MANDEL: No questions, Your Honor.
25 A.L.J. JENNINGS-FADER: Thank you. Does
262
1 any other party have questions of this witness before
2 the applicants?
3 In that event, we will take an afternoon
4 break, fortuitously about ten minutes. We will be in
5 recess until four o'clock at which time someone, I
6 don't know if it was Tri-State or Public Service, but
7 whoever may cross-examine this witness.
8 (Recess taken.)
9 A.L.J. JENNINGS-FADER: Back on the
10 record after the afternoon break.
11 Mr. Dougherty.
12 MR. DOUGHERTY: Your Honor, Tri-State
13 anticipates that Public Service will most likely cover
14 any issues that we would have done with Mr. Dauphinais.
15 So we will reserve our cross-examination time until
16 after Mr. Sopkin is done, but I expect that we will
17 have few to no questions.
18 A.L.J. JENNINGS-FADER: Thank you, sir.
19 Mr. Sopkin.
20 CROSS EXAMINATION

21 BY MR.SOPKIN:
22 Q Good afternoon again, Mr. Dauphinais?
23 A Good afternoon.
24 Q Mr. Dauphinais, as I understand it, you
25 have the opinion that the amended renewable energy
263
1 standard, and here we are talking about House Bill
2 10-1001 requires more emphasis on efficient and cost
3 effective acquisition of renewable resources as
4 compared to the previous RES because the amended RES
5 increased the percentage of required renewable
6 resources to 30 percent, removes any solar requirement,
7 increases the percentage of required distributed
8 generation to three percent and retains the 2 percent
9 retail rate impact cap; is that correct?
10 A It is. I would add it is also the
11 enlargement of the retail distributed generation
12 minimum requirement as well.
13 Q Okay. I thought that I said that. That
14 is okay.
15 Okay. You would agree that if the
16 Commission implements the former RES, the 20 percent,
17 RES did not disregard the issues of efficiency and cost
18 effectiveness when choosing renewable resources as part
19 of Public Service Company's resource portfolio?
20 A No, I am just saying there could be
21 increased emphasis on that.
22 Q In terms of the removal of the solar
23 requirement, would you agree that up to half of the
24 three percent distributed generation set aside can be
25 met by on-site solar facilities up to 30 megawatts,
264
1 correct?
2 A I am not so -- you described it as
3 on-site solar facilities, and so I am a little
4 confused. The Act discusses wholesale distributed
5 generation and retail distributed generation.
6 Q Okay. Why don't we do it this way: I
7 will tell you what, if you can look at Exhibit 132.
8 A Okay. That I have.
9 Q If you would turn to page 4 of that
10 document.
11 A I am there.
12 Q And on page 4 I will just skip down to
13 the capital E there. You see it says, 30 percent of
14 its retail electricity sales in Colorado for the years
15 2020 and thereafter with distributed generation
16 equaling at least 3 percent of its retail electricity
17 sales.
18 You do see that, correct?
19 A Yes, I do.
20 Q That is the new standard for, the new RES
21 standard for the year 2020, and thereafter 30 percent
22 RES standard with DG set aside at three percent of its
23 retail electricity sales, correct?
24 A Yes, with the caveat that there are other
25 provisions that better define how that distributed
265
1 generation can be made up.
2 Q Right. That.is what we are getting to.
3 A Okay.
4 Q Going down from there you see directly
5 below what we just read is Roman Numeral II A?
6 A Yes.
7 Q And it states, Of the amounts of
8 distributed generation in subparagraph C, D and E of
9 subparagraph Roman I of this paragraph C at least
10 one-half shall be derived from retail distributed
11 generation, correct?
12 A Yes.
13 Q All right. And turning back to page 2 of
14 this document, at the very bottom do you see that
15 distributed renewable electric energy or distributed
16 generation means, turning to the next page, A, retail
17 distributed generation and, B, wholesale distributed
18 generation? Do you see that?
19 A Yes.
20 Q Okay. And going down from there, there
21 is a definition of retail distributed generation, and I
22 am not going to ask you to read that.
23 Going down there is also a definition of
24 wholesale distributed generation which says, Means a
25 renewable energy resource in Colorado with a name plate
266
1 rating of 30 megawatts or less and that does not
2 qualify as retail distributed generation.
3 A Yes.
4 Q Do you see that?
5 A Yes.
6 Q Okay. And going back to the definition
7 of retail distributed generation directly above that in
8 Roman V, it starts out that it means a renewable energy
9 resource that is located on the site of a customer's
10 facilities, correct?
11 A Yes.
12 Q So now I am going to go back to my
13 original question.
14 Would you agree that up to half of the
15 three percent distributed generation set aside can be
16 met by on site -- excuse me -- let me remove the word
17 on site -- by wholesale distributed generation solar
18 facilities up to 30 megawatts?
19 A Yes.
20 Q Okay. And even though there is a
21 30-megawatt limit, to your knowledge, there is no
22 prohibition as to how many solar 30-megawatt
23 installations can be used to meet up to half of that
24 three percent DG set aside?
25 A There is no explicit prohibition, but if
267
1 they were very, very close to one another that might
2 get some scrutiny.
3 Q But there is no prohibition to it to your
4 knowledge, correct?
5 A Correct.
6 Q Okay. And in terms of where a
7 30-megawatt solar PV plant might be located, do you
8 have knowledge that some of the best solar resources in
9 the state of Colorado are in the San Luis Valley?
10 A Some of the best, not the only, but some
11 of the best.
12 Q And so, to your knowledge, nothing would
13 prevent Public Service, for example, from proposing in
14 the future multiple 30-megawatt PV solar plants in the
15 San Luis Valley, correct?
16 A If the economics supported it.
17 Q In terms of obtaining solar thermal --
18 moving on to solar thermal now -- obtaining solar
19 thermal within the two percent retail rate impact cap,
20 first off, you have seen Public Service's crunching of
21 numbers with regard to RES dollars available for that,
22 correct?
23 A Yes, I have.
24 Q And you have no reason to disagree with
25 those figures, correct?
268
1 A I have no reason to disagree with them.
2 Q And you have not done your own
3 quantitative analysis regarding those RES dollars,
4 correct?
5 A That's correct.
6 Q Now, your opinion as to how much solar
7 resources can be acquired under the 2 percent retail
8 rate impact cap of course assumes that that 2 percent
9 cap applies?
10 In other words, it is not a Section 123
11 resource, correct?
12 A That is correct.
13 Q All right. And in terms of what types of
14 solar resources might qualify to be Section 123
15 resources in future, that would be up to the Commission
16 to decide, correct?
17 A Yes.
18 Q And even aside from future parabolic
19 trough solar thermal installations, do you acknowledge
20 that there are other solar technologies that might be
21 developed in the future that could qualify to be
22 Section 123 resources, correct?
23 A That is possible, yes.
24 Q Now, let us move on to the effect of the
25 three percent distributed generation requirement.
269
1 You do acknowledge that House Bill
2 10-1001 allows a utility such as Public Service to
3 request that the Commission lower the three percent DG
4 requirement in the future, correct?
5 A Yes.
6 Q And so if Public Service believes that
7 the three percent DG requirement is consuming too many
8 RES dollars and thereby preventing the acquisition of
9 beneficial energy resources in the state of Colorado,
10 it can seek an order from the Commission to lower that
11 DG amount, correct?
12 A Yes, if it chooses to do that.
13 Q If that application were granted, RES
14 dollars would be freed up for that purpose?
15 A RES dollars would be freed up versus what
16 would have been consumed if that relief had not been
17 granted.
18 Q Okay. The same question with regard to
19 the standard rebate offer. You also agree that House
20 Bill 10-1001 allows a utility such as Public Service to
21 request that the Commission lower the $2 per watt
22 standard rebate offer for on-site solar DG in the
23 future, correct?
24 A Yes.
25 Q And the same thing if Public Service
270
1 believes that the standard rebate offer is consuming
2 too many RES dollars and that is somehow preventing the
3 acquisition of beneficial solar resources in the
4 future, it could seek an order from the Commission
5 lowering the standard rebate offer amount?
6 A Yes.
7 Q If the Commission granted that
8 application, RES dollars would be freed up?
9 A Again, relative to relief not being
10 granted.
11 Q Right. Now, you have an opinion that the
12 likely impact of the amended RES would be a changed
13 focus away from high cost utility scale solar thermal
14 resources to lower cost renewable resources such as
15 wind and solar PV, including distributed generation,
16 correct?
17 A Generally that will be the outcome of the
18 changes, yes.
19 Q And you would agree that wind, solar and
20 solar DG -- excuse me, wind, solar PV and solar DG
21 generation of resources without storage are
22 intermittent resources?
23 A Did you qualify the DG?
24 Q I said solar DG.
25 A Okay. Yes, they may be intermittent.
271
1 Q And you are aware that Public Service is
2 studying the cost of integrating intermittent resources
3 into its system, correct?
4 A It has performed some studies, and I
5 believe there is an additional wind integration study
6 underway.
7 Q Okay. Would you agree that conducting
8 such a study is a good idea?
9 A Yes, it is prudent.
10 Q And you also agree that at some point a
11 utility can reach a breaking point where it is cost
12 prohibitive to integrate more intermittent resources?
13 A It is possible to hit that point, yes.
14 Q In order to find that point you would
15 have to conduct a study of the transmission system and
16 generation resources on a or within a utility system,
17 correct?
18 A Yes.
19 Q And you have not conducted such a study,
20 correct?
21 A I have not conducted such a study, no.
22 Q And would you agree that the cost of
23 generation is highest during peak load times, correct?
24 A I guess. I need to make a clarification.
25 Are you talking about the incremental cost for power
272
1 for utility during high load conditions?
2 Q Yes.
3 A Yes, it is higher typically during peak
4 load conditions.
5 Q So would you also agree that a resource
6 that can be dispatched during peak load times has more
7 value to a utility than one that cannot be dispatched?
8 A That is true.
9 Q Would you agree that Public Service can
10 have summer peaking needs as late as 6 p.m. in the
11 evening or later?
12 A I believe that I have seen a figure from
13 a solar integration study that Public Service performed
14 that I think suggested from 2 to 5 p.m. would be the
15 peak period.
16 Q Okay. We will come back to that.
17 Would you agree that a solar thermal plan
18 with four-hour storage could be dispatched during peak
19 times?
20 A A solar thermal, yes, it could be
21 dispatched during peak times.
22 Q Let us move into changed economic
23 circumstances.
24 You discussed a number of economic
25 circumstances that you believe make the acquisition of
273
1 solar thermal resources in the future less likely.
2 Do you recall that discussion?
3 A Yes, I do.
4 Q Now, in terms -- one of those changed
5 economic circumstances you mentioned is the decrease to
6 the natural gas price forecast.
7 Do you recall that?
8 A Yes.
9 Q And would you agree that to the extent
10 gas prices have gone down, the relative cost
11 differential on all renewable resources including wind,
12 solar, PV and solar DG go up?
13 A They all go up, yes.
14 Q Would you agree that gas prices have been
15 characterized by volatility over the last ten to twenty
16 years?
17 A Yes.
18 Q Mr. Dauphinais, moving on to the issue of
19 the delay in expected carbon legislation from 2010 to
20 2014, would you refer to Exhibit 141, please?
21 A I have it.
22 Q I believe you were asked by Mr. Douglas
23 questions about when the rolling balance turns negative
24 with regard to delayed carbon legislation.
25 So I would ask you to turn to Table 7-4.
274
1 Are you there?
2 A I am on page 7-4, yes.
3 Q And looking at column X, that has the
4 rolling balance of RES dollars under a delayed carbon
5 legislation assumption, correct?
6 A That's correct.
7 Q If you look at that column it shows the
8 balance turning positive in the year 2015, correct?
9 A Yes. I don't believe my testimony was on
10 the balance last time.
11 Q But the balance increases there through
12 2020 to the amount of $285 million, correct?
13 A Yes.
14 Q Positive balance, correct?
15 A Correct.
16 Q Thank you. One of the issues you
17 discussed with regard to solar thermal is how the cost
18 of solar thermal relates to a combined cycle natural
19 gas unit.
20 Do you recall that?
21 A Yes, I do.
22 Q Do combined cycle natural gas units omit
23 carbon?
24 A Yes.
25 Q Thanks.
275
1 You do believe that some kind of carbon
2 legislation cap and trade or some type of carbon types
3 is more likely than not to occur in the next ten years;
4 isn't that true?
5 A Yes, I agree with that.
6 MR. SOPKIN: Your Honor, may I approach.
7 A.L.J. JENNINGS-FADER: You may.
8 MR. SOPKIN: I have one question on this
9 document. It is Colorado Statute Section 40-2-123. I
10 would ask that administrative notice be taken of it.
11 A.L.J. JENNINGS-FADER: That will be
12 done. Exhibit 143 is admitted.
13 (Whereupon Exhibit No. 143 admitted.)

14 Q Mr. Dauphinais, if you turn your


15 attention to Exhibit 143.
16 A Yes, I have it.
17 Q And would you please read the first
18 sentence of Section 1B, please?
19 A The Commission may give consideration to
20 the likelihood of new environmental regulation and the
21 risk of higher future cost associated with the emission
22 of greenhouse gases such as carbon dioxide when it
23 considers utility proposals to acquire resources.
24 Q Thank you. That is the only question
25 that I have about that document.
276
1 So would you agree that the Commission
2 can decide in future resource planning cases that solar
3 thermal with storage is in part justified by the risk
4 of higher future cost from carbon legislation? Would
5 you agree with that?
6 A It is possible. I think it becomes less
7 likely, especially if the 125-megawatt facility before
8 the Commission right now is pursued as a 123 resource.
9 Q I will ask you this: If carbon
10 legislation is enacted by 2014 as is currently expected
11 by Public Service that requires an abrupt decrease in
12 power plant carbon emissions, would you agree that
13 Public Service would need to increase its plan of
14 acquisition of renewable resources?
15 A Your question had an assumption in it
16 that I think is hypothetical.
17 Q It is hypothetical.
18 A The hypothetical is that it is not just
19 that there is a price for carbon, but there is a
20 requirement for Public Service to dramatically reduce
21 its carbon output.
22 Q That's right.
23 A With that caveat -- I guess, can you
24 repeat the question and I will answer it with that
25 caveat?
277
1 Q If carbon legislation is enacted by 2014
2 that requires an abrupt decrease in power plant carbon
3 emissions, would you agree that Public Service will
4 need to increase its planned acquisition of renewable
5 resources?
6 MR. DOUGLAS: Your Honor, I object as
7 vague, unspecific hypothetical. I don't know what we
8 are talking about when we say legislation that would
9 require a dramatic decrease of carbon emissions. I am
10 not sure what that means.
11 A.L.J. JENNINGS-FADER: Mr. Sopkin.
12 MR. SOPKIN: Well, Your Honor, it was
13 answered during the deposition.
14 A.L.J. JENNINGS-FADER: I am sure during
15 the deposition you-all had reached some agreement as to
16 what those terms mean, but I will sustain the
17 objection. The question is vague.
18 Q Okay. I will ask it this way: If carbon
19 legislation is enacted that requires Public Service to
20 increase its planned acquisition of renewable
21 resources, would you agree that one of the ways to plan
22 for acquisition of renewable resources is to build
23 transmission to locations where the best renewable
24 resources are located?
25 A If there is a sudden need for that, but
278
1 to speculate on that need being there, build
2 transmission to meet the speculated need, that would
3 not be reasonable.
4 Q But you do agree that Public Service
5 should plan for some type of carbon legislation within
6 the next ten years, correct?
7 A Plan for it, yes. That does not mean
8 that you are going to necessarily implement all of the
9 different possible outcomes, because we don't know what
10 the exact outcome is. We know a range of outcomes.
11 Q I believe you testified earlier today in
12 response to Mr. Douglas' questions that because the 60
13 megawatt, 90 megawatt or 185 megawatt options that are
14 before the Commission in the application of amendment
15 2007 Resource Plan case, that those options would be
16 supported by or at least the 185-megawatt option would
17 be supported by the raising of lines in the San Luis
18 Valley, and because of that you testified that no
19 second transmission line into the valley is needed in
20 your opinion, correct?
21 A I may have dropped 230KB, and I meant to
22 make it clear no second 230KB transmission line is
23 needed into the valley.
24 Q Okay. That is because you still have the
25 opinion that the only need shown by the applicant in
279
1 this case relates to the 2007 resource planning case,
2 correct?
3 A As would be amended by the application to
4 amend the plan, that's correct.
5 Q So the same opinion you had before that
6 if there is any overbuild, it would need to be a very
7 slight amount of overbuild remains for you, correct?
8 A Generally, yes.
9 Q And so if the Commission approved 60
10 megawatts and that does not require any additional
11 construction of transmission line in the San Luis
12 Valley, would you say a line is not needed at all,
13 correct?
14 A Yes, it would not be needed to support
15 exports from the valley.
16 MR. SOPKIN: Okay. May I have one
17 moment, Your Honor?
18 A.L.J. JENNINGS-FADER: You may.
19 MR. SOPKIN: No further questions.
20 A.L.J. JENNINGS-FADER: Mr. Dougherty.
21 MR. DOUGHERTY: Tri-State has no questions
22 for this witness.
23 A.L.J. JENNINGS-FADER: Mr. Douglas.
24 MR. DOUGLAS: I have no further
25 questions, Your Honor.
280
1 A.L.J. JENNINGS-FADER: I would like to
2 thank you very much, sir, for your testimony today. It
3 has been quite helpful. You are excused. I ask that
4 you leave the marked exhibits at the witness area.
5 Thank you. Thank you, sir, very much.
6 I believe that the next witness that we
7 have is not available until Friday is my understanding,
8 correct?
9 MR. DOUGLAS: That's correct, Your Honor.
10 A.L.J. JENNINGS-FADER: What I ask of
11 Public Service and Tri-State is that, you are getting
12 dailies I believe with respect to this transcript,
13 could you let me and the parties, the parties know by
14 noon on Wednesday or so, by e-mail is fine, whether you
15 intend to offer a rebuttal witness as to the testimony
16 of Mr. Dauphinais. And that is all that you need to
17 do. I don't think that you need to identify the
18 witness, although you may, if you wish to. Just to let
19 people know so we can get some sense of what we are
20 looking at for the remainder of the hearing.
21 MR. SOPKIN: Yes, Your Honor.
22 A.L.J. JENNINGS-FADER: Thank you.
23 Anything from -- anything else from anyone?
24 MR. FLANAGAN: To prove that there is a
25 viewing audience out there on the webcast, we have
281
1 received a number of inquiries and I wanted to revisit
2 with you very briefly the situation with the Huerfano
3 County Commissioners. A number of people from the
4 Valley have contacted the Commission and asked about
5 filing written comments and have been told not to do
6 so, that they would not be part of the record and would
7 not be considered.
8 First, I think that you recognized this
9 morning that the letter that you said would be
10 considered for what it is worth from the Huerfano
11 County Commissioners. One of the three signatories to
12 that letter did testify.
13 A.L.J. JENNINGS-FADER: He did, yes.
14 MR. FLANAGAN: He testified as a
15 representative of the Huerfano County Commissioners and
16 said we are okay with the northern route but not the
17 southern route because there were a lot of people from
18 the Majors Ranch. You recall all of that. But that
19 was the thrust of the testimony at that hearing where
20 he was subject to cross-examination and now the same
21 witness is one of three signatories on a letter of June
22 16, 2010 that, as I think you indicated, is not part of
23 the official record but --
24 A.L.J. JENNINGS-FADER: It is not part of
25 the evidentiary record. It is part of the
282
1 administrative record.
2 MR. FLANAGAN: We are certainly in favor
3 of the Commission getting as much information as they
4 can, but there are a number of people who have
5 contacted us from the Valley who would like to be
6 treated similarly to Huerfano County Commissioners and
7 to make written comments.
8 You might recall, and this has been a big
9 issue down there with letters to the editor, newspaper
10 articles, the gubernatorial candidates have discussed
11 this in their discussions down there, and have received
12 questions and have had to answer inquiries, and I guess
13 we would like --
14 A.L.J. JENNINGS-FADER: If I may, let me
15 back up and do a quick rewind.
16 Let me just say that I presume your
17 request is that folks who wish to do so be given an
18 opportunity to submit written comments.
19 MR. FLANAGAN: Yes, Your Honor.
20 A.L.J. JENNINGS-FADER: Excellent. Let
21 me start by saying that after the evidentiary hearing
22 was held in February there were inquiries made of the
23 Commission as to whether or not additional letters of
24 support or nonsupport could be received and considered.
25 My understanding is the response was
283
1 because the evidentiary record is closed and no one
2 would have an opportunity, no party would have an
3 opportunity to review those letters and make statements
4 about them in testimony, those letters would not be
5 considered by the Commission.
6 We have now a different circumstance than
7 was true in March or April when those inquiries were
8 received. Now we have an evidentiary record which is
9 reopened. We have parties who, if they wish to do so,
10 may review letters received by the Commission and may
11 choose to give testimony in response to those letters.
12 This is the same opportunity that folks were given in
13 the February hearing.
14 So insofar as I understand the situation,
15 so long as a letter, written correspondence is
16 received, let us set a time so folks will have a
17 reasonable opportunity to look at that correspondence
18 before the commencement of the hearing on Friday
19 morning. So long as correspondence is received by the
20 Commission by the close of business on Wednesday, which
21 would be the 28th of this month, all parties then,
22 because those are posted on the Commission's website
23 under this docket, would have an opportunity to review
24 that correspondence and could, if they wished to do so,
25 make statements with respect to that correspondence,
284
1 that will be considered as other statements to, excuse
2 me, as other letters received by the Commission that
3 are considered in the normal course. They will still
4 not be part of the evidentiary record in this case, but
5 the Commission does look at them and does give them,
6 that correspondence, some consideration.
7 What that is I am not in a position to
8 articulate, but the Commission does read those, all the
9 letters that are received, therefore, that is my
10 statement with respect to that.
11 Any correspondence received will get the
12 same consideration as any other correspondence that has
13 been received, and the Huerfano County Commissioner
14 letter, the two letters, one in March and June, to the
15 extent that they were received after the close of the
16 evidentiary record would have received no consideration
17 from the Commission because no party would have had an
18 opportunity to respond to that correspondence.
19 Now it is in this other category simply
20 because the evidentiary record has been reopened. Is
21 that of any assistance?
22 MR. FLANAGAN: I appreciate the
23 clarification. I think there will be a few more
24 letters.
25 A.L.J. JENNINGS-FADER: Somehow from the
285
1 tenure of your discussion I expect that there be. Just
2 bear in mind that we can only get so many e-mails at a
3 time. So let us not crash the server.
4 So aside from that, aside from my
5 probably inappropriate remark, does that help?
6 MR. FLANAGAN: Yes.
7 A.L.J. JENNINGS-FADER: Okay.
8 Also, I understood Mr. Bode of the
9 Commission Staff made an appearance after we came in
10 from the afternoon break and indicated that the webcast
11 was not on.
12 I want to apologize to anyone who may
13 have attempted to access the webcast. The light did
14 not come on. There is a camera light that did not come
15 on, but the control panel showed that the webcast was
16 on. I did not know that we were not broadcasting. So
17 my apologies to everyone out there who may have been
18 inconvenienced by that.
19 So with those matters, anything else from
20 any of the parties?
21 Mr. Nelson.
22 MR. NELSON: Just a procedural question.
23 I was curious, depending on the response that Public
24 Service Company and Tri-State make with respect to
25 rebuttal witnesses, I wondered if there was any chance
286
1 that the hearing start time on Friday might be adjusted
2 or if that is set in stone? I am only asking because I
3 am out of the state on Friday and Mr. Davidson will be
4 covering for me. I wanted to make sure whether he
5 should watch for a potential change in the start time.
6 A.L.J. JENNINGS-FADER: I wish I could
7 say that is the case. I am going to hold to 8:00
8 because I just want to be 100 percent sure that we get
9 through this hearing in the combined time that is left,
10 which is Friday starting at 8:00 and Saturday starting
11 at 9:00.
12 MR. NELSON: Very good. I appreciate
13 that clarification.
14 A.L.J. JENNINGS-FADER: I too would like
15 to make that later time. I don't see it in the cards.
16 Anything else from any of the parties?
17 Thank you all very much. We are in
18 recess until 8 a.m. on Friday. I will look for the
19 e-mail from Tri-State and Public Service.
20 Thank you all very much.
21 (The hearing adjourned at 4:39 p.m., July
22 26, 2010.)
23

24

25
287
1

2 CERTIFICATION

3 STATE OF COLORADO )

4 CITY AND COUNTY OF DENVER )

6 We, Michele Koss, James Midyett and Harriet

7 Weisenthal, do hereby certify that we were present and

8 reported in stenotype the proceedings in the foregoing

9 matter; that we thereafter reduced our stenotype notes

10 to typewritten form, with the aid of a computer,

11 composing the foregoing transcript; further, that the

12 foregoing official transcript is a full and accurate

13 record of the proceedings in this matter held at

14 Denver, Colorado on July 26, 2010.

15 FILED at Denver, Colorado _________________.

16

17 __________________________
Michele Koss
18

19

20 ___________________________
Harriet Weisenthal
21

22

23

24 ___________________________
James Midyett
25

Das könnte Ihnen auch gefallen